CN104196000A - Rapid construction method for strong-stormy-wave deep sea underwater connection system - Google Patents

Rapid construction method for strong-stormy-wave deep sea underwater connection system Download PDF

Info

Publication number
CN104196000A
CN104196000A CN201410379312.8A CN201410379312A CN104196000A CN 104196000 A CN104196000 A CN 104196000A CN 201410379312 A CN201410379312 A CN 201410379312A CN 104196000 A CN104196000 A CN 104196000A
Authority
CN
China
Prior art keywords
construction
platform
connection system
sleeve connection
mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410379312.8A
Other languages
Chinese (zh)
Inventor
袁长春
姜永军
孙百锋
李招明
张亚峰
蔡维栋
崔淑斌
樊立龙
王守国
李志辉
刘长辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201410379312.8A priority Critical patent/CN104196000A/en
Publication of CN104196000A publication Critical patent/CN104196000A/en
Pending legal-status Critical Current

Links

Abstract

The invention provides a rapid construction method for a strong-stormy-wave deep sea underwater connection system. The method comprises the following steps that (1) construction preparation is carried out; (2) platform steel pipe piles are constructed; (3) underwater sleeve connection systems are manufactured in factories; (4) the underwater sleeve connection systems are transported to a steel pipe pile construction platform at a pier position through a ship; (5) a floating crane enters a site and is anchored and positioned; (6) lifting points of one sleeve connection system are connected, and a lifting appliance is installed; (7) the sleeve connection system is lifted by the floating crane, and the corresponding platform steel pipe piles are sleeved with the sleeve connection system; (8) the sleeve connection system is released downwards to a design position, and a top crossbeam is installed and fixedly connected with the lifting appliance; (9) mortar is poured in interlayer walls of the sleeve connection system and the steel pipe piles; (10) after the strength of the mortar reaches design strength, the lifting appliance is dismounted; (11) construction of mortar in other sleeve interlayer walls is carried out; (12) cyclic construction of the other sleeve connection systems is carried out, and construction of the connection systems of all the platform piles is finished. The method has the advantages that problems of deepwater construction operations carried out by frogmen are solved, the construction period is shortened, and construction investment is reduced.

Description

It is rapid constructing method that a kind of high wind wave deep-sea connects under water
Technical field
The invention belongs to Offshore Bridges engineering construction technical field, especially relating to that a kind of high wind wave deep-sea connects is under water rapid constructing method.
Background technology
At present, it is that common employing frogman directly welds or bolt under water that domestic and international marine deep water construction platform connects under water, after Platform pipe pile driving construction, it is design attitude steel pipe pile spacing that frogman's subaqueous survey connects, connection system cut and assembly welding according to steel pipe pile spacing, then transfer to design attitude under water and connects and be and the Underwater Welding of steel pipe pile connecting system's entirety.The method underwater operation risk is larger, difficult quality control, and speed of application is slower.
Summary of the invention
The problem to be solved in the present invention avoids frogman to connect under water, shortens construction period, reduces construction and drops into.
For solving the problems of the technologies described above, the technical solution used in the present invention is: it is rapid constructing method that a kind of high wind wave deep-sea connects under water, comprises the following steps:
1) preparation of construction;
2) Platform pipe pile driving construction;
3) sleeve pipe connection is under water factory process;
4) Ship Transportation is to pier position steel pipe pile operation platform;
5) crane barge is marched into the arena, and the location of casting anchor;
6) sleeve pipe connection is that suspension centre connects, suspender is installed;
7) floating-crane lifting sleeve pipe connects system, is inserted in Platform pipe stake;
8) transferring sleeve pipe connection is to design attitude, head piece is installed and is also fixed with suspender;
9) build sleeve pipe and connect system and the interior mortar of steel pipe pile double wall;
10) mortar strength reaches after design strength, removes suspender;
11) mortar in other sleeve pipe double walls of constructing;
12) other sleeve pipes of circulation construction connect system, complete the connection system construction of whole platform stakes.
Advantage and good effect that the present invention has are:
Owing to adopting technique scheme, it is the conventional method of construction that change high wind wave deep-sea connects under water, solve a difficult problem for frogman's deep water construction operation, ensure to connect the quality and the platform and integrally that are under water stable, shorten construction period, reduce construction and drop into, ensure to complete safely and fast the construction that connects system under water.
Brief description of the drawings
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only embodiments of the invention, for those of ordinary skill in the art, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is the present invention's schematic diagram under completion status of constructing;
Fig. 2 is the present invention's top view under completion status of constructing;
Fig. 3 is the present invention's partial schematic diagram under completion status of constructing.
Wherein:
The stake of 1-Platform pipe; 2-sleeve pipe connects system; 3-mortar
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, obviously, described embodiment is only the present invention's part embodiment, instead of whole embodiment.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtaining under creative work prerequisite, belong to the scope of protection of the invention.
A lot of details are set forth in the following description so that fully understand the present invention, but the present invention can also adopt other to be different from alternate manner described here and implement, those skilled in the art can do similar popularization under the condition without prejudice to intension of the present invention, and therefore the present invention is not subject to the restriction of following public specific embodiment.
As shown in Figure 1 to Figure 3, the present invention includes following steps:
1) preparation of construction;
2) Platform pipe stake 1 is constructed;
3) according to design conditions and the actual perpendicularity deviation of steel pipe, connecting at bank entirety process water setting of casing is 2, and connection is that sleeve pipe 2 diameters are than the Platform pipe stake large 60cm of 1 diameter left and right;
4) with barge will be under water sleeve pipe to connect be 2 to be transported to pier position steel pipe pile operation platform, location barge casts anchor;
5) crane barge is marched into the arena, and the location of casting anchor;
6) sleeve pipe connection is that 2 suspension centres connect, suspender is installed;
7) connection of floating-crane lifting sleeve pipe is 2, is inserted in Platform pipe stake 1;
8) under water sleeve pipe to connect be 2 to transfer to after design attitude at corresponding platform steel pipe pile 1 welded top crossbeam, wire rope is connected with crossbeam, hang to connect temporarily and be;
9) build sleeve pipe and connect system and the interior mortar of steel pipe pile double wall;
10) mortar 3 intensity reach after design strength, remove suspender;
11) mortar in other sleeve pipe double walls of constructing;
12) other sleeve pipes of circulation construction connect system, complete the connection system construction of whole platform stakes.
The present invention has solved frogman's Underwater Welding quality problems effectively, has shortened construction period simultaneously, has reduced difficulty of construction and cost, ensures to complete safely and fast the construction that connects system under water.This invention has higher application value, and social benefit is good.For the construction of conditions of similarity Offshore Bridges has accumulated invaluable experience.
Above one embodiment of the present of invention are had been described in detail, but described content is only preferred embodiment of the present invention, can not be considered to for limiting practical range of the present invention.All equalization variation and improvement etc. of doing according to the present patent application scope, within all should still belonging to patent covering scope of the present invention.

Claims (1)

1. to connect be under water a rapid constructing method at high wind wave deep-sea, it is characterized in that: comprise the following steps:
1) preparation of construction;
2) Platform pipe pile driving construction;
3) sleeve pipe connection is under water factory process;
4) Ship Transportation is to pier position steel pipe pile operation platform;
5) crane barge is marched into the arena, and the location of casting anchor;
6) sleeve pipe connection is that suspension centre connects, suspender is installed;
7) floating-crane lifting sleeve pipe connects system, is inserted in Platform pipe stake;
8) transferring sleeve pipe connection is to design attitude, head piece is installed and is also fixed with suspender;
9) build sleeve pipe and connect system and the interior mortar of steel pipe pile double wall;
10) mortar strength reaches after design strength, removes suspender;
11) mortar in other sleeve pipe double walls of constructing;
12) other sleeve pipes of circulation construction connect system, complete the connection system construction of whole platform stakes.
CN201410379312.8A 2014-08-01 2014-08-01 Rapid construction method for strong-stormy-wave deep sea underwater connection system Pending CN104196000A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410379312.8A CN104196000A (en) 2014-08-01 2014-08-01 Rapid construction method for strong-stormy-wave deep sea underwater connection system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410379312.8A CN104196000A (en) 2014-08-01 2014-08-01 Rapid construction method for strong-stormy-wave deep sea underwater connection system

Publications (1)

Publication Number Publication Date
CN104196000A true CN104196000A (en) 2014-12-10

Family

ID=52081353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410379312.8A Pending CN104196000A (en) 2014-08-01 2014-08-01 Rapid construction method for strong-stormy-wave deep sea underwater connection system

Country Status (1)

Country Link
CN (1) CN104196000A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106429888A (en) * 2016-12-02 2017-02-22 中交第二航务工程勘察设计院有限公司 Equipment for precise installation of underwater component and operation method
CN107190735A (en) * 2017-07-13 2017-09-22 中交武汉港湾工程设计研究院有限公司 Based on steel-pipe pile under deep water conditions lateral constructing device and construction method under water
CN109267492A (en) * 2018-10-17 2019-01-25 中铁大桥局集团有限公司 A kind of operation platform connection structure mounting device and method
CN110241812A (en) * 2019-06-03 2019-09-17 中铁大桥局集团有限公司 A kind of drilling platform steel-pipe pile inserting piling method and leading truck component
CN110924307A (en) * 2019-11-28 2020-03-27 中铁广州工程局集团桥梁工程有限公司 Trestle construction method for bare rock geology
CN111622211A (en) * 2020-05-29 2020-09-04 中铁大桥局第七工程有限公司 Underwater pipe pile connecting system and installation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004278148A (en) * 2003-03-17 2004-10-07 Sumitomo Mitsui Construction Co Ltd Construction method of bridge
CN1818225A (en) * 2006-03-10 2006-08-16 刘晓东 Base construction and its facilities at rapid stream of deep water
CN101429761A (en) * 2008-11-18 2009-05-13 中铁大桥局集团第二工程有限公司 Deep sea bare rock pier protection barrel, positioning pile, underwater cofferdam integrated platform and construction method
CN101694093A (en) * 2009-10-12 2010-04-14 中铁大桥局集团第四工程有限公司 Quick positioning and connecting system in inserting and driving steel pipe supporting pile and construction method thereof
CN102619206A (en) * 2012-04-06 2012-08-01 中铁二十二局集团第三工程有限公司 Foundation platform structure of bare rock and karst pile in deep water
CN103452087A (en) * 2013-08-21 2013-12-18 浙江江南春建设集团有限公司 Construction method for erecting steel frame platform by utilizing eccentric vibrator

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004278148A (en) * 2003-03-17 2004-10-07 Sumitomo Mitsui Construction Co Ltd Construction method of bridge
CN1818225A (en) * 2006-03-10 2006-08-16 刘晓东 Base construction and its facilities at rapid stream of deep water
CN101429761A (en) * 2008-11-18 2009-05-13 中铁大桥局集团第二工程有限公司 Deep sea bare rock pier protection barrel, positioning pile, underwater cofferdam integrated platform and construction method
CN101694093A (en) * 2009-10-12 2010-04-14 中铁大桥局集团第四工程有限公司 Quick positioning and connecting system in inserting and driving steel pipe supporting pile and construction method thereof
CN102619206A (en) * 2012-04-06 2012-08-01 中铁二十二局集团第三工程有限公司 Foundation platform structure of bare rock and karst pile in deep water
CN103452087A (en) * 2013-08-21 2013-12-18 浙江江南春建设集团有限公司 Construction method for erecting steel frame platform by utilizing eccentric vibrator

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106429888A (en) * 2016-12-02 2017-02-22 中交第二航务工程勘察设计院有限公司 Equipment for precise installation of underwater component and operation method
CN106429888B (en) * 2016-12-02 2018-01-12 中交第二航务工程勘察设计院有限公司 One kind precisely installs equipment and operating method for underwater components
CN107190735A (en) * 2017-07-13 2017-09-22 中交武汉港湾工程设计研究院有限公司 Based on steel-pipe pile under deep water conditions lateral constructing device and construction method under water
CN109267492A (en) * 2018-10-17 2019-01-25 中铁大桥局集团有限公司 A kind of operation platform connection structure mounting device and method
CN109267492B (en) * 2018-10-17 2021-04-06 中铁大桥局集团有限公司 Construction platform connection system installation device and method
CN110241812A (en) * 2019-06-03 2019-09-17 中铁大桥局集团有限公司 A kind of drilling platform steel-pipe pile inserting piling method and leading truck component
CN110924307A (en) * 2019-11-28 2020-03-27 中铁广州工程局集团桥梁工程有限公司 Trestle construction method for bare rock geology
CN111622211A (en) * 2020-05-29 2020-09-04 中铁大桥局第七工程有限公司 Underwater pipe pile connecting system and installation method thereof

Similar Documents

Publication Publication Date Title
CN104196000A (en) Rapid construction method for strong-stormy-wave deep sea underwater connection system
CN106516021A (en) Self-propelled carrying and installing all-in-one ship for underwater tunnel immersed tubes
CN201756173U (en) Water surface hoisting construction ship with buoyant boxes
CN102852147B (en) Method for righting jacket by using single cantilever gin pole and double hooks
CN101881148B (en) Jacket riser mounting method and special riser component thereof
CN103741657A (en) Construction method of large multifunctional over-water construction platform
CN104153384A (en) On-sea sandwich steel pipe pile foundation and construction method
CN102644290A (en) Steel cofferdam construction method suitable for deep silt-layer bridge construction in shallow sea area
CN103123017A (en) Shallow sea long-distance submarine pipeline tension-free laying construction technology
CN110965804A (en) Method for dismantling offshore wind power jacket foundation
CN106522275A (en) Construction process for shipping large sinking pipes by self-propelled semi-submerged ship
CN104805857A (en) Detachable cyclic utilization bottomless steel jacket box and construction method thereof
CN102409613A (en) Construction method for installing steel beam of plank road built along mountain and near river
CN101962946A (en) Method for arranging hoisting points and floating-supported conduit frame with skirt pile sleeves
CN110185057B (en) Tool and construction method for lifting and erecting steel pipe piles of offshore wind power single pile foundation
CN202733172U (en) Integral hoisting and immersed tube construction device for large-diameter ultra-long steel tube
CN104153366B (en) The method of a kind of marine high wind wave high strength naked rock steel pipe pile foundation
CN102991646B (en) Manufacturing methods for gravity anchor
CN110106904B (en) Steel pipe pile structure and jacket foundation construction process
CN204608812U (en) One detachably recycles bottomless steel jacket box
CN201649080U (en) Steel casing favorable for stable submerging on underwater bare rock surface
CN204151835U (en) The vertical piece structure of connection of the basement wall and cast-in-place buttress
CN102661444B (en) Installation method of deepwater double piping system of offshore platform
CN109518710A (en) A kind of polygonal jacket basis and its construction method for ocean engineering
CN104627326A (en) Special lifting and vibration-driving ship for integrated driving of cell type steel sheet pile large cylinders and vice cells

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20141210

RJ01 Rejection of invention patent application after publication