Invention content
Goal of the invention:In order to solve to face under hollow panel balloon base station, the dynamic allocation and mobile subscriber QoS of channel width need
Ask the problem of being met as far as possible.
Technical scheme of the present invention:
System includes:Balloon (relaying) base station, ground base station, mobile subscriber.System architecture is as shown in Figure 1.Fig. 1 is shown
Based on the network architecture for facing wide-band mobile communication under hollow panel balloon base station.System is illustrated below:
(1) the skyborne working power in balloon base station is supplied by solar cell.
(2) balloon base station and the interconnection of ground base station full duplex, can be used optic communication or microwave communication, microwave communications link is adopted
With Advanced Orbiting Systems (Advanced Orbiting System, AOS) link, directional aerial intercommunication is used.Ground network connects
Entering can be by wired, wireless mode to ground base station, and wired that optical fiber and Ethernet may be used, wireless mode has WiFi to connect
Mouthful, WiFi interfaces can be interconnected with other terrestrial wireless Mesh interfaces.In addition ground base station also has AOS interfaces, provides use
It is wirelessly transferred in ground base station and balloon base station.
(3) when ground base station is out of order, balloon base station can select the ground base station using relaying or with nearby backing up
It is communicated.
(4) balloon base station carries out covering communication using fan antenna to subordinate's ground region.
Although the overlay area of balloon base station is limited, but region area is relatively wide, therefore will can be somebody's turn to do in advance
Area of coverage opsition dependent is divided into multiple subregion Si, pipe can be carried out to the mobile subscriber in region in order to balloon base station in this way
Reason, is shown in attached drawing 2.When mobile subscriber enters the overlay area for facing hollow panel balloon base station, if user has data needs and balloon
Base station is communicated, then channel width change and access can occur.User i sends to balloon base station and has changed pseudo channel at this time
Data cell (Virtual Channel Data Unit, VCDU) dominates the association request frame of head, is added in association request frame
The data volume size of spatial domain position, required transmission where user, shakes the information such as required time at the delay requirement time;Balloon
Base station receives and the user is divided into affiliated subregion S according to its location information after such association request frameiIn, it counts simultaneously
Calculate the ratio a that user's number in the subregion accounts for total number of users in balloon base station coverage areai, calculate in the subregion and need to pass
Defeated total data volume accounts for the ratio beta that all users in balloon base station coverage area need the total amount of data transmittedi, analyzing and associating
The VCDU of claim frame dominates head, and the number to calculate active user in the subregion accounts for all realities in balloon base station coverage area
When number of users ratio γi;In order to preferably provide the service quality of balloon base station, three proportionality coefficients 0.3 are designed hereby,
0.5,0.2, it is then proportionately distributed to the channel width of all subregion, the channel strip of the subregion distribution as where user i
Width is Bi=(0.3 αi+0.5βi+0.2γi) B, wherein B is the total bandwidth that balloon base station can be distributed.
Space data link agreement based on existing AOS, carried out VCDU dominate head modification and association request frame,
The design of associated response broadcast frame.Wherein, VCDU dominates the modification of head, sees shown in attached drawing 3.
The reserved bit of the signal domain of head is dominated in our modification mainly for VCDU.2 bits are used for distinguishing frame type, and 01
Association request frame is represented, 10 represent associated response broadcast frame, and disassociation frame is removed in 00 representative, and 11 retain;1 bit indicates whether there is number
The not communication data with balloon base station is represented according to demand, 0,1 represents the communication data having with balloon base station;1 bit is indicated
Whether there is delay requirement, 0 represents without delay requirement, and 1 representative has delay requirement;1 bit indicates whether there is shake
Demand, 0 represents without shake demand, and 1 representative has shake demand;1 bit indicates whether to represent non-reality for real time business, 0
When business, 1 represents real time business;2 bits retain.
Secondly, the association request frame changed VCDU and dominated head is sent to the balloon base station for facing hollow panel, specific association is asked
Frame format is sought, is seen shown in attached drawing 4, wherein:
9 byte representations of location information, (9 bits represent the integer part of longitude to 3 byte representation longitudes, and 4 bits are represented
Longitude divides position, 8 bits to represent the second position of longitude, remaining bits is reserved), (9 bits represent latitude to 3 byte representation latitudes
Integer part, 4 bits represent point position of latitude, and 8 bits represent the second position of latitude, remaining bits is reserved), last 3 table of bytes
Show that (17 bits represent the vertical range of user distance earth's surface to height of the user away from earth's surface, are accurate to m);The delay requirement time is with 1
Byte representation;Shake 1 byte representation of required time;4 byte representations of data length, 232=4294967296 (KB), i.e., most
Height can indicate 4096 GB data volumes, this is enough for As-Is.
After balloon base station receives association request frame, analyzes its VCDU and dominate the flag bit that head carries, whether judge its user
With delay requirement and whether with shake demand.If balloon base station judges user i simultaneously, and there is delay requirement and shake to need
It asks, then calculates the Z for the user i for meeting this demandiSize, Zi=a (Bi+Di+Ji).Balloon base station judges that if user i has
Prolong demand without shake demand, then calculates the Z for the user i for meeting this demandiSize, Zi=b (Bi+Di).Sentence balloon base station
If disconnected user i has shake demand without delay requirement, the Z for the user i for meeting this demand is calculatediSize, Zi=c
(Bi+Ji).If balloon base station judges that user i does not have delay requirement and shake demand, the user for meeting this demand is calculated
The Z of iiSize, Zi=d × Bi。
Wherein:
ZiFor hypothesis judgement user gradation an integrated value, if ZiIt is bigger, then illustrating that the grade of the user i is got over
It is high;
BiFor the data volume sizes to be transmitted of user i, i.e. amount of bandwidth;
A, b, c, d represent the weight coefficient of distribution, a>b≥c>d.
Balloon base station integrates the Z of institute's calculated valuei, carry out the priority ranking of user i, ZiValue is bigger, and base station is by its user's
Priority setting is higher, and 0 is highest priority, and 1 secondly, successively backward.User after all subregion is lined up by balloon base station is excellent
First grade result utilizes associated response broadcast frame (note:Associated response broadcast frame be balloon base station by association response frame to broadcast
Form is sent) inform all subregion user.Specific associated response broadcasts frame format, sees shown in attached drawing 5, wherein:1 table of bytes
Show subarea number, the existing residing subregion of broadcasting user;1 byte representation channel width, the subregion institute residing for broadcasting user
The channel width being assigned to;The centre frequency of 2 byte representation channel widths;After 4 bits indicate that user sorts in the subregion
The priority size of acquisition;4 bits retain.
After the user of all subregion receives associated response broadcast frame, distributed by User Priority height to be lined up to use
Channel is communicated, and after high-priority users use, low priority user just can access channel and be communicated, same preferential
Grade user is communicated using Random Access access channel.
If have the area of coverage that user leaves balloon base station, user removes disassociation frame disassociation to balloon Base Transmitter.
In the case where facing hollow panel balloon base station user access on demand channel communication method detailed process it is as shown in Fig. 6.
Step 100:Start.
Step 110:User i, which enters, faces hollow panel balloon base station overlay area, and whether judgement user i will carry out with balloon base station
Communication, if desired then carries out step 120, otherwise jumps directly to terminate.
Step 120:Spatial domain position from user i to the balloon base station transmission carrying user for wishing to communicate, required transmission where
Data volume size, the delay requirement time, the shake information such as required time association request frame.
Step 130:Balloon base station receives the subregion S judged according to location information after association request frame where useri。
Step 140:Balloon base station calculates αi、βiAnd γiValue, while calculating the channel width for being assigned to the subregion
For Bi=(0.3 αi+0.5βi+0.2γi)B。
Step 150:Balloon base station judges whether user i has delay requirement, if so then execute step 160, conversely, redirecting
To step 190.
Step 160:Balloon base station judges whether user i has shake demand, if so then execute step 170, conversely, executing
Step 180.
Step 170:Balloon base station calculates the Z for the user i for meeting this demandiSize, Zi=a (Bi+Di+Ji)。
Step 180:Balloon base station calculates the Z for the user i for meeting this demandiSize, Zi=b (Bi+Di)。
Step 190:Balloon base station judges whether user i has shake demand, if so then execute step 200, conversely, executing
Step 210.
Step 200:Balloon base station calculates the Z for the user i for meeting this demandiSize, Zi=c (Bi+Ji)。
Step 210:Balloon base station calculates the Z for the user i for meeting this demandiSize, Zi=d × Bi。
Step 220:Comprehensive institute calculated value Zi, carry out the priority ranking of user i, ZiValue is bigger, and base station is by the excellent of its user
First grade setting is higher, and 0 is highest priority, and 1 secondly, successively backward.
Step 230:User Priority result after all subregion is lined up by balloon base station is accused using associated response broadcast frame
Know all subregion user.
Step 240:After the user of all subregion receives associated response broadcast frame, used by User Priority height to be lined up
The channel distributed is communicated, and after high-priority users use, low priority user just can access channel and be communicated,
Same priority user is communicated using Random Access access channel
Step 250:Terminate.
It is to face the method flow that multi-user under hollow panel balloon base station accesses channel on demand above, it can be ensured that channel resource
It is fully used, and ensures that the QoS demand of user is met as far as possible.
It illustrates:For convenience of description, what our aerial platforms were selected is balloon platform, this can be according in real base station
The combined factors such as rise, hovering time, recovery difficult consider other aircraft platforms, such as dirigible etc..
Specific implementation mode
2 the invention will be further described below in conjunction with the accompanying drawings.
Scene Simulation:Facing in hollow panel balloon base station overlay area, there are multiple mobile subscribers to want to communicate.It is false
If balloon base station operation, in L frequency ranges, centre frequency is 1.6 GHz, and balloon base station available bandwidth B is 320 MHz, with a byte
Channel width is divided, it is averagely divided into 28=256 parts, i.e. the minimum value of dynamic bandwidth allocation is 1.25 MHz.Assuming that
There are A (0x00000001), B (0x00000002), C (0x00000001), D in balloon base station overlay area at this time
(0x00000002)、E(0x00000001)、F(0x00000002)、G(0x00000001)、H(0x00000007)、I
Totally 10 users enter (note by (0x00000002), J (0x00000001), K (0x00000000):A(e):A indicates user's name,
E indicates that the user needs the length of transmitted data amount, is indicated using 16 systems), certain customers need to lead to balloon base station
Letter, and certain customers have no data transmission with balloon base station.Such as user K has no the communication data with balloon base station, therefore for
For user K, balloon base station does not take any action.And have and balloon base for user A, B, C, D, E, F, G, H, I, J
Channel width change and access can then occur for the communication data stood.
User A, B, C, D, E, F, G, H, I, J first send the association request frame changed VCDU and dominated head to balloon base station,
In the data volume size of position, required transmission where being added to it in association request frame, delay requirement time, shake demand
Between etc. information;Balloon base station receive after association request frame according to each user present position information by each user be divided into belonging to
Subregion SiIn, such as:A, B, C, D are divided into subregion S1, E, F, G are divided into subregion S2, H is divided into subregion
S3, I, J are divided into subregion S4。
In order to preferably provide the service quality of balloon base station, considers many-sided influence factor, give this three ratios
Distribution weight 0.3,0.5,0.2 respectively, are then divided in portion channel width, the letter of the subregion distribution as where user i
Road bandwidth is Bi=(0.3 αi+0.5βi+0.2γi) B, the subregion S for example, where user A, B, C, D1The channel width of distribution
For:
After balloon base station receives association request frame, the flag bit of its VCDU carrying is analyzed, judges whether its user has
Delay requirement and whether have shake demand.Assuming that A (1,1,0), B (1,0,0), C (1,0,1), D (1,0,0), E (1,1,1), F
(1,0,0), G (1,1,0), H (1,0,0), I (1,1,1), J (1,0,1);It notes (x, y, z):X, which is 1 representative, has communication data, is
0 represents no communication data;Y, which is 1 representative, has delay requirement, and no delay requirement is represented for 0;Z is 1 representative, and there is shake to need
It asks, being represented for 0 does not have shake demand.With S1For region, user A is with delay requirement also with shake demand, it is assumed that analysis
The delay requirement time that its association request frame carries is 1ms, shake required time is 0.1ms.User B, which had not both had time delay, to be needed
It asks, also without shake demand.User C does not have delay requirement, and has shake demand, analyzes trembling for its association request frame carrying
Dynamic required time is assumed to be 0.1ms.User D has delay requirement, without shaking demand, analyzes the carrying of its association request frame
The delay requirement time is assumed to be 1.5ms.
From hypothesis before:S1In region, the data volume that user A is carried is 0x0000001=(1)10,
The data volume that user B is carried is 0x0000002=(2)10, the data volume that user C is carried is 0x0000001=
(1)10, the data volume that user D is carried is 0x0000002=(2)10.In addition, a=4 is taken, b=3, c=2, d=1.It calculates separately
A, the Z of B, C, DiIt is worth size:
ZB=d × BB=1 × 2=2;
Balloon base station integrates the Z of institute's calculated valuei, carry out the priority ranking of user i, ZiValue is bigger, and base station is by its user's
Priority setting is higher, and 0 is highest priority, and 1 secondly, successively backward.It can obtain S1Under region, priority ranking is (by height
To low) result is A (0), D (1), C (2), B (3), wherein () inner number be the priority number of imparting.
Balloon base station is by S1User Priority result after region is lined up informs S using associated response broadcast frame1Region it is each
User.S1After the user in region receives associated response broadcast frame, come by User Priority height (A (0), D (1), C (2), B (3))
Queuing uses distributed channel to be communicated, and after high-priority users use, low priority user just can access channel
It is communicated, same priority user is communicated using Random Access access channel.
It is to face the method flow that multi-user under hollow panel balloon base station accesses channel on demand above, it can be ensured that channel resource
It is fully used, and ensures that the QoS demand of user is met as far as possible.
In this description, the present invention is described with reference to specific embodiment.But it is clear that can still make
Various modifications and alterations are without departing from the spirit and scope of the invention.Therefore, the description and the appended drawings should be considered as illustrative
And not restrictive.