CN104166391A - Cooperative multipoint industrial control acquisition fault monitoring system and method - Google Patents
Cooperative multipoint industrial control acquisition fault monitoring system and method Download PDFInfo
- Publication number
- CN104166391A CN104166391A CN201410400956.0A CN201410400956A CN104166391A CN 104166391 A CN104166391 A CN 104166391A CN 201410400956 A CN201410400956 A CN 201410400956A CN 104166391 A CN104166391 A CN 104166391A
- Authority
- CN
- China
- Prior art keywords
- link
- node
- fault
- data
- node group
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Landscapes
- Hardware Redundancy (AREA)
Abstract
The invention provides a cooperative multipoint industrial control acquisition fault monitoring system and method which aim to solve the problems that a great amount of time is cost for finding out fault positions in an industrial control acquisition network with a great number of nodes and faults cannot be removed in time. According to the cooperative multipoint industrial control acquisition fault monitoring system and method, in hundreds of or even thousands of multilevel measurement cable links, measurement points and fault points of lines are determined rapidly and effectively, effective measures are taken, and therefore breakdown time is shortened and production efficiency is improved.
Description
Technical field
The present invention relates to industry control and gather field, relate in particular to a kind of coordinate multipoint industry control and gather fault monitoring system and method.
Background technology
Traditional industry control collection is that corresponding industry control collecting device is installed on Industrial Control Computer or PC, carries out on the spot industry control collection and Measurement and analysis, is a kind of measuring system of unit localization.Progress along with social technology, the acquisition node that industry control collection need to be faced is more and more, data are also more and more huger, and the appearance of industrial local network and internet, make the control of carrying out industry control collection by network system become possibility, meanwhile, the appearance of coordinate multipoint (CoMP) technology is also for the transmission of data between great deal of nodes or gather solution is provided.
But, industry control based on coordinate multipoint gathers not large-scale promotion, one of its reason is exactly when carrying out the number of nodes of industry control collection when too huge, the efficiency of the node breaking down in system being carried out to Real-Time Monitoring and judgement is too low, cause system fluctuation of service, and then affected the popularization of the industry control acquisition system based on coordinate multipoint.
Therefore, be necessary to propose a kind of intelligentized malfunction monitoring scheme for above-mentioned defect of the prior art.
Summary of the invention
The object of the invention is to be achieved through the following technical solutions.
According to an embodiment of the invention, propose a kind of coordinate multipoint industry control and gather fault monitoring system, described monitoring system comprises industry control collecting unit, industry control transmission unit and CPU (central processing unit); Described industry control collecting unit comprises acquisition node, multichannel industry control collection plate and the Industrial Control Computer that distributes and manage according to coordinate multipoint; Described industry control transmission unit adopts multiplexing switch cascade to form, and comprises top layer switch and bottom switch; CPU (central processing unit) is a high-performance computer; Each Industrial Control Computer is all installed expansion redundant transmission module;
Wherein, on industry control collecting unit, be responsible for image data from industry control collection plate, and carry out pre-service, encapsulation of data, and send to CPU (central processing unit) by Ethernet; In CPU (central processing unit), be responsible for collecting also analytic message, recombination data, and generate exploded view and analysis result; Industry control collecting unit judges, monitors for node and node group two class faults, and this information is sent to CPU (central processing unit); CPU (central processing unit) judges and monitors the fault of different links, for all kinds of faults of whole system, staff is pointed out simultaneously.
According to the coordinate multipoint industry control of embodiment of the present invention, gather fault monitoring method and be divided into industry control collecting unit malfunction monitoring stage and CPU (central processing unit) to two stages of whole system malfunction monitoring stage; Described industry control collecting unit is responsible for decision node fault and two kinds of malfunction monitorings of node group fault; CPU (central processing unit) is responsible for judging link failure, link group fault and whole three kinds of malfunction monitorings of link failure, and type and the position of being responsible for the whole five kinds of faults of prompting staff, and described method specifically comprises:
1. in the industry control collecting unit malfunction monitoring stage, comprising:
Step 1-1, first by being connected to acquisition node group on Industrial Control Computer and the AD acquisition channel in acquisition node group, be numbered, if Industrial Control Computer can be identified acquisition node group, the deposit data acquisition node group being collected, in Industrial Control Computer, otherwise goes to step 1-4;
Step 1-2, identification acquisition node form after merit, analyze each channel data collecting acquisition node group, if the range of acquisition node group be-5V to 5V that 5V is called ultimate value with-5V; Judge that whether these data exist for the data of the ultimate value of range, if not, go to step 1-5;
If it is the data of ultimate value that step 1-3 exists range, show to occur malfunctioning node, next judge that this fault type is that wiring disconnects, or connector lug generation virtual connection phenomenon; Suppose to occur that k node breaks down, if the corresponding acquisition channel data of this node are all the time in ultimate value state, occur that wiring disconnects phenomenon, if the corresponding acquisition channel data of this node fluctuate between ultimate value and normal value, occurs virtual connection phenomenon; Record this node generation node failure, and under record, gather AD acquisition channel and acquisition node group # simultaneously, then go to step 5;
If certain acquisition node group of step 1-4 Industrial Control Computer None-identified, the data that gather in acquisition node group so cannot normally be sent in Industrial Control Computer, record this acquisition node group and occur node group phenomenon of the failure, and record the numbering of this malfunctioning node group simultaneously;
Step 1-5, first check and whether occur acquisition node group fault, if do not had, go to step 1-6, otherwise encapsulate the numbering to Ethernet message of this malfunctioning node group, indicate node group fault occurs, go to step 1-7, be ready for sending;
Step 1-6, node group fault do not occur, normally reading out data of this node group is described, check and whether have node failure, if do not exist, direct data message are encapsulated as to Ethernet message together with the numbering unification of node group; Otherwise gather, data, malfunctioning node numbering and fault type are encapsulated as to Ethernet message;
After step 1-7, Ethernet have encapsulated, preparation is sent to CPU (central processing unit) by industry control transmission unit, first detect whether can be connected to CPU (central processing unit) by normal link, if can carry out message transmission, and prepare to receive the data that next acquisition node group is sent to Industrial Control Computer; Otherwise whether monitoring can be connected to CPU (central processing unit) normally by redundant transmission equipment, if can send by redundant link, and the group link failure feedback of monitoring CPU (central processing unit), if receive this feedback information, there is link group fault, need to change acquisition strategies; If redundant link can not normally be worked, data are carried out to this locality storage.
2. CPU (central processing unit), to the whole system malfunction monitoring stage, comprising:
Step 2-1, CPU (central processing unit) monitor the data that industry control collecting unit sends over, and in 5000ms, without any data receiver, think that industry control collecting unit is not activated or occurs whole link failures; Go to step 2-5;
If step 2-2 can receive data, analyze the data message that industry control collecting unit sends over, first read the type of error encapsulating in message, analyze and whether occur node failure or node group fault, if do not broken down, go to step 2-3, if there is node failure, record node serial number, node group # under this node; If there is node group fault, record this node group #;
If step 2-3 node failure is other and node group fault does not all occur, analyze the stem of this message, extract message source address, with this, analyzing this message is to transmit by normal link or redundant link, if transmitted by normal link, the link at this industrial computer place occurs without any fault, and goes to step 2-6, if transmitted by redundant link, think that this normal transmission link breaks down;
The source address that step 2-4, extraction normal link break down, find all addresses that belong to a switch with this address together, whether inquiry has at least one link can access normal transmission, in all Industrial Control Computers of a switch of common connection, as long as there is a link transmission normally, illustrate and do not occur link group fault, if connect all Industrial Control Computers of a switch, all by redundant link, transmit, illustrate and occurred link group fault;
Step 2-5, CPU (central processing unit) check and occur link failure type, if industry control collecting unit is not activated or occurs whole link failures, CPU (central processing unit) gives the alarm, the link connection situation of notifying staff to check in time top switch; If there is link group fault, CPU (central processing unit) is according to receiving the message that redundant link transmits, obtain the occurrence positions of this group link failure, and notify staff to check in time this bottom switch link connection situation, meanwhile, CPU (central processing unit) feeds back to Industrial Control Computer by link group fault, and Industrial Control Computer is received after the feedback that redundant link passes back, industry control acquisition strategies is adjusted; If there is link failure, will extract the information of this Industrial Control Computer, and the link connection situation of notifying staff to check this Industrial Control Computer; After prompting link failure, go to step 2-1, wait for next data that industry control collecting unit sends over;
If the equal no-failure operation of the normal link of step 2-6 system, system judges whether to occur node failure or node group fault, and according to malfunctioning node numbering or malfunctioning node group #, to occur that node and node group location of fault notify staff, then record and show normal data, if whole system non-fault, goes to step 2-1, wait for next data that industry control collecting unit sends over.
The present invention's advantage is compared with prior art; Time-consuming for looking up the fault location comparison in the coordinate multipoint network measure of great deal of nodes; the problem that can not fix a breakdown in time; the present invention proposes a kind of coordinate multipoint industry control and gather fault monitoring system and method; at hundreds of even in the multistage measurement cable link of thousands of; realized and determined quickly and effectively the trouble spot of measurement point and circuit; and adopt an effective measure, thereby reduce the downtime, enhance productivity.
Accompanying drawing explanation
By reading below detailed description of the preferred embodiment, various other advantage and benefits will become cheer and bright for those of ordinary skills.Accompanying drawing is only for the object of preferred implementation is shown, and do not think limitation of the present invention.And in whole accompanying drawing, by identical reference symbol, represent identical parts.In the accompanying drawings:
Accompanying drawing 1 shows according to the coordinate multipoint industry control of embodiment of the present invention and gathers fault monitoring system structural representation;
Accompanying drawing 2 shows the industry control collecting unit malfunction monitoring process flow diagram according to an embodiment of the invention;
Accompanying drawing 3 shows according to the CPU (central processing unit) of an embodiment of the invention whole system malfunction monitoring process flow diagram.
Embodiment
Illustrative embodiments of the present disclosure is described below with reference to accompanying drawings in more detail.Although shown illustrative embodiments of the present disclosure in accompanying drawing, yet should be appreciated that and can realize the disclosure and the embodiment that should do not set forth limits here with various forms.On the contrary, it is in order more thoroughly to understand the disclosure that these embodiments are provided, and can by the scope of the present disclosure complete convey to those skilled in the art.
According to definition of the present invention, the fault type of coordinate multipoint industry control acquisition system is divided into following five classes: node failure, node group fault, link failure, link group fault and whole link failure.Fault for each class has respectively corresponding fault judgment method and tracer technique.
According to the embodiment of the present invention, proposed a kind of coordinate multipoint industry control and gathered fault monitoring system, as shown in Figure 1, described monitoring system comprises industry control collecting unit, industry control transmission unit and CPU (central processing unit); Described industry control collecting unit comprises acquisition node, multichannel industry control collection plate and the Industrial Control Computer that distributes and manage according to coordinate multipoint; Described industry control transmission unit adopts multiplexing switch cascade to form, and comprises top layer switch and bottom switch; CPU (central processing unit) is that a computing machine that performance is high, computing power is strong forms.For guaranteeing the reliable of industry control transmission, the transport module that increases redundancy is arranged on Industrial Control Computer, each Industrial Control Computer all needs to expand redundant transmission module, while guaranteeing that the affiliated normal link of this Industrial Control Computer breaks down, data can be sent to CPU (central processing unit) place by redundant link.
Wherein, on industry control collecting unit, be responsible for image data from industry control collection plate, and carry out pre-service, encapsulation of data, and send to CPU (central processing unit) by Ethernet; In CPU (central processing unit), be responsible for collecting also analytic message, recombination data, and generate exploded view and analysis result; The intelligent fault monitoring that industry control collecting unit is carried out judges, monitors mainly for node and node group two class faults, and this information is sent to CPU (central processing unit); The intelligent fault monitoring that CPU (central processing unit) is carried out is mainly that the fault of different links is judged and monitored, and for all kinds of faults of whole system, staff is pointed out simultaneously.
For the determination methods of all kinds of faults, will describe one by one below.
(1) determination methods of node failure
On certain acquisition node, break down and be divided into two types, a kind of is that connection line between acquisition node and acquisition node group disconnects, now the data in acquisition node group are that (be now equivalent to link opens a way continuous ultimate value, the electric signal collecting is infinite, and changing into digital quantity is the ultimate value of range); Another is the phenomenon that virtual connection appears in acquisition node place, and the data that show as in acquisition node group are that normal data is to the continuous jump of ultimate value.Obtain after the abnormal data of this acquisition node, the acquisition node group that gathers this node data can be delivered to misdata in Industrial Control Computer, Industrial Control Computer carries out pre-service, analysis node fault type, and the information exchange of malfunctioning node is crossed to industry control transmission unit be delivered to CPU (central processing unit).
(2) determination methods of node group fault
When certain acquisition node group breaks down, data in this acquisition node group can not pass to normally and on Industrial Control Computer, do further processing, Industrial Control Computer does not collect this node group data, because each acquisition node group has numbering, therefore Industrial Control Computer can obtain the information of node group, and the information exchange of malfunctioning node group is crossed to industry control transmission unit is delivered to CPU (central processing unit).
(3) determination methods of link failure
When certain link occurs fault, Industrial Control Computer can not send to CPU (central processing unit) by gathering also packaged data message by industry control transmission equipment, shown in Fig. 1, have redundant link, so Industrial Control Computer can send data message by redundant transmission equipment; For CPU (central processing unit), what while there is link failure, receive is that redundant link passes the message information of coming, and by the analysis to data heading, CPU (central processing unit) is judged fault type.
(4) determination methods of link group fault
Link group fault refers on a plurality of links that belong to a switch and breaks down simultaneously.When one group of link occurs fault, all Industrial Control Computers that this group link connects all can not be sent to CPU (central processing unit) by data message by normal link, and the redundant link that at this moment CPU (central processing unit) receives this group Industrial Control Computer transmission passes the message information come.Now, because the quantity by message that redundant link transmits is more, in order to guarantee reliable industry control collection, while there is link group fault, each Industrial Control Computer need to be adjusted industry control acquisition strategies, as reduce sampling rate, implement the measures such as local storage, thereby avoid because of problems such as the caused industry control bust this of redundant link, resource contentions.
(5) determination methods of whole link failures
All link failure refers to that CPU (central processing unit) does not receive any data, and now fault is divided into two types: the one, and whole industry control acquisition system not yet starts, and only CPU (central processing unit) starts, and now in system, without any data, produces; Another kind of situation is that top layer switch place breaks down, no matter adopt normal transmission equipment or redundant transmission equipment, the data message that gathers and encapsulate on Industrial Control Computer all cannot send normally, at this moment, the data of whole system are all deposited on Industrial Control Computer, cause whole measuring system collapse.So, when whole link failures break down, the second situation especially, CPU (central processing unit) is not only sent five-star warning message, and in industry control collecting unit, carry out local datastore, and reduce the sampling rate of data, make as far as possible the extent of damage of data be down to minimum.
According to the coordinate multipoint industry control of embodiment of the present invention, gather fault monitoring method and be divided into industry control collecting unit malfunction monitoring stage and CPU (central processing unit) to two stages of whole system malfunction monitoring stage; Industry control collecting unit is responsible for decision node fault and two kinds of malfunction monitorings of node group fault; CPU (central processing unit) is responsible for judging link failure, link group fault and whole three kinds of malfunction monitorings of link failure, and type and the position of being responsible for the whole five kinds of faults of prompting staff, and described method specifically comprises:
1. industry control collecting unit malfunction monitoring stage, as shown in Figure 2:
First by being connected to acquisition node group on Industrial Control Computer and the AD acquisition channel in acquisition node group, be numbered, if Industrial Control Computer can be identified acquisition node group, the deposit data acquisition node group being collected is in Industrial Control Computer.
Identification acquisition node forms after merit, analyzes each channel data collecting acquisition node group, if the range of acquisition node group be-5V to 5V that 5V is called ultimate value with-5V; Judging whether these data exist for the data of the ultimate value of range, is the data of ultimate value if there is range, shows to occur malfunctioning node, next judges that this fault type is that wiring disconnects, or connector lug generation virtual connection phenomenon; Suppose to occur that k node breaks down, if the corresponding acquisition channel data of this node are all the time in ultimate value state, occur that wiring disconnects phenomenon, if the corresponding acquisition channel data of this node fluctuate between ultimate value and normal value, occurs virtual connection phenomenon; Record this node generation node failure, and under record, gather AD acquisition channel and acquisition node group # simultaneously.
Node group fault does not occur, normally reading out data of this node group is described, checks and whether has node failure, if do not exist, direct data message is encapsulated as to Ethernet message together with the numbering unification of node group; Otherwise gather, data, malfunctioning node numbering and fault type are encapsulated as to Ethernet message;
If certain acquisition node group of Industrial Control Computer None-identified, the data that gather in acquisition node group so cannot normally be sent in Industrial Control Computer, record this acquisition node group and occur node group phenomenon of the failure, and record the numbering of this malfunctioning node group simultaneously.And encapsulate numbering to Ethernet message of this malfunctioning node group, indicate node group fault occurs, be ready for sending;
After Ethernet has encapsulated, preparation is sent to CPU (central processing unit) by industry control transmission unit, first detect whether can be connected to CPU (central processing unit) by normal link, if can carry out message transmission, and prepare to receive the data that next acquisition node group is sent to Industrial Control Computer; Otherwise whether monitoring can be connected to CPU (central processing unit) normally by redundant transmission equipment, if can send by redundant link, and the group link failure feedback of monitoring CPU (central processing unit), if receive this feedback information, there is link group fault, need to change acquisition strategies; If redundant link can not normally be worked, data are carried out to this locality storage.
2. CPU (central processing unit) is to the whole system malfunction monitoring stage, as shown in Figure 3:
First CPU (central processing unit) is monitored the data that industry control collecting unit sends over, and in 5000ms, without any data receiver, thinks that industry control collecting unit is not activated or occurs whole link failures.
If can receive data, analyze the data message that industry control collecting unit sends over, first read the type of error encapsulating in message, analyze and whether occur node failure or node group fault, if there is node failure, record node serial number, node group # under this node; If there is node group fault, record this node group #.
If node failure is other and node group fault does not all occur, analyze the stem of this message, extract message source address, with this, analyzing this message is to transmit by normal link or redundant link, if transmitted by normal link, the link at this industrial computer place occurs without any fault, if transmitted by redundant link, thinks that this normal transmission link breaks down; Extract the source address that normal link breaks down, find all addresses that belong to a switch with this address together, whether inquiry has at least one link can access normal transmission, in all Industrial Control Computers of a switch of common connection, as long as there is a link transmission normally, illustrate and do not occur link group fault, if connect all Industrial Control Computers of a switch, all by redundant link, transmit, illustrate and occurred link group fault.
CPU (central processing unit) checks and occurs link failure type, if industry control collecting unit is not activated or occurs whole link failures, CPU (central processing unit) gives the alarm, the link connection situation of notifying staff to check in time top switch; If there is link group fault, CPU (central processing unit) is according to receiving the message that redundant link transmits, obtain the occurrence positions of this group link failure, and notify staff to check in time this bottom switch link connection situation, meanwhile, CPU (central processing unit) feeds back to Industrial Control Computer by link group fault, and Industrial Control Computer is received after the feedback that redundant link passes back, industry control acquisition strategies is adjusted; If there is link failure, will extract the information of this Industrial Control Computer, and the link connection situation of notifying staff to check this Industrial Control Computer.
If the equal no-failure operation of the normal link of system, system judges whether to occur node failure or node group fault, and according to malfunctioning node numbering or malfunctioning node group #, will occur that node and node group location of fault notify staff, and then record and show normal data.
After above-mentioned work completes, CPU (central processing unit) is waited for next data that industry control collecting unit sends over.
The above; be only the present invention's embodiment preferably, but protection scope of the present invention is not limited to this, is anyly familiar with in technical scope that those skilled in the art disclose in the present invention; the variation that can expect easily or replacement, within all should being encompassed in protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion by the described protection domain with claim.
Claims (2)
1. coordinate multipoint industry control gathers a fault monitoring system, and described monitoring system comprises industry control collecting unit, industry control transmission unit and CPU (central processing unit); Described industry control collecting unit comprises acquisition node, multichannel industry control collection plate and the Industrial Control Computer that distributes and manage according to coordinate multipoint; Described industry control transmission unit adopts multiplexing switch cascade to form, and comprises top layer switch and bottom switch; CPU (central processing unit) is a high-performance computer; Each Industrial Control Computer is all installed expansion redundant transmission module;
Wherein, on industry control collecting unit, be responsible for image data from industry control collection plate, and carry out pre-service, encapsulation of data, and send to CPU (central processing unit) by Ethernet; In CPU (central processing unit), be responsible for collecting also analytic message, recombination data, and generate exploded view and analysis result; Industry control collecting unit judges, monitors for node and node group two class faults, and this information is sent to CPU (central processing unit); CPU (central processing unit) judges and monitors the fault of different links, for all kinds of faults of whole system, staff is pointed out simultaneously.
2. coordinate multipoint industry control gathers the method that fault monitoring system carries out malfunction monitoring as claimed in claim 1, is divided into industry control collecting unit malfunction monitoring stage and CPU (central processing unit) to two stages of whole system malfunction monitoring stage; Described industry control collecting unit is responsible for decision node fault and two kinds of malfunction monitorings of node group fault; CPU (central processing unit) is responsible for judging link failure, link group fault and whole three kinds of malfunction monitorings of link failure, and type and the position of being responsible for the whole five kinds of faults of prompting staff, and described method specifically comprises:
(1) in the industry control collecting unit malfunction monitoring stage, comprising:
Step 1-1, first by being connected to acquisition node group on Industrial Control Computer and the AD acquisition channel in acquisition node group, be numbered, if Industrial Control Computer can be identified acquisition node group, the deposit data acquisition node group being collected, in Industrial Control Computer, otherwise goes to step 1-4;
Step 1-2, identification acquisition node form after merit, analyze each channel data collecting acquisition node group, if the range of acquisition node group be-5V to 5V that 5V is called ultimate value with-5V; Judge that whether these data exist for the data of the ultimate value of range, if not, go to step 1-5;
If it is the data of ultimate value that step 1-3 exists range, show to occur malfunctioning node, next judge that this fault type is that wiring disconnects, or connector lug generation virtual connection phenomenon; Suppose to occur that k node breaks down, if the corresponding acquisition channel data of this node are all the time in ultimate value state, occur that wiring disconnects phenomenon, if the corresponding acquisition channel data of this node fluctuate between ultimate value and normal value, occurs virtual connection phenomenon; Record this node generation node failure, and under record, gather AD acquisition channel and acquisition node group # simultaneously, then go to step 1-5;
If certain acquisition node group of step 1-4 Industrial Control Computer None-identified, the data that gather in acquisition node group so cannot normally be sent in Industrial Control Computer, record this acquisition node group and occur node group phenomenon of the failure, and record the numbering of this malfunctioning node group simultaneously;
Step 1-5, first check and whether occur acquisition node group fault, if do not had, go to step 1-6, otherwise encapsulate the numbering to Ethernet message of this malfunctioning node group, indicate node group fault occurs, go to step 1-7, be ready for sending;
Step 1-6, node group fault do not occur, normally reading out data of this node group is described, check and whether have node failure, if do not exist, direct data message are encapsulated as to Ethernet message together with the numbering unification of node group; Otherwise gather, data, malfunctioning node numbering and fault type are encapsulated as to Ethernet message;
After step 1-7, Ethernet have encapsulated, preparation is sent to CPU (central processing unit) by industry control transmission unit, first detect whether can be connected to CPU (central processing unit) by normal link, if can carry out message transmission, and prepare to receive the data that next acquisition node group is sent to Industrial Control Computer; Otherwise whether monitoring can be connected to CPU (central processing unit) normally by redundant transmission equipment, if can send by redundant link, and the group link failure feedback of monitoring CPU (central processing unit), if receive this feedback information, there is link group fault, need to change acquisition strategies; If redundant link can not normally be worked, data are carried out to this locality storage.
(2) CPU (central processing unit), to the whole system malfunction monitoring stage, comprising:
Step 2-1, CPU (central processing unit) monitor the data that industry control collecting unit sends over, and in 5000ms, without any data receiver, think that industry control collecting unit is not activated or occurs whole link failures; Go to step 2-5;
If step 2-2 can receive data, analyze the data message that industry control collecting unit sends over, first read the type of error encapsulating in message, analyze and whether occur node failure or node group fault, if do not broken down, go to step 2-3, if there is node failure, record node serial number, node group # under this node; If there is node group fault, record this node group #;
If step 2-3 node failure is other and node group fault does not all occur, analyze the stem of this message, extract message source address, with this, analyzing this message is to transmit by normal link or redundant link, if transmitted by normal link, the link at this industrial computer place occurs without any fault, and goes to step 2-6, if transmitted by redundant link, think that this normal transmission link breaks down;
The source address that step 2-4, extraction normal link break down, find all addresses that belong to a switch with this address together, whether inquiry has at least one link can access normal transmission, in all Industrial Control Computers of a switch of common connection, as long as there is a link transmission normally, illustrate and do not occur link group fault, if connect all Industrial Control Computers of a switch, all by redundant link, transmit, illustrate and occurred link group fault;
Step 2-5, CPU (central processing unit) check and occur link failure type, if industry control collecting unit is not activated or occurs whole link failures, CPU (central processing unit) gives the alarm, the link connection situation of notifying staff to check in time top switch; If there is link group fault, CPU (central processing unit) is according to receiving the message that redundant link transmits, obtain the occurrence positions of this group link failure, and notify staff to check in time this bottom switch link connection situation, meanwhile, CPU (central processing unit) feeds back to Industrial Control Computer by link group fault, and Industrial Control Computer is received after the feedback that redundant link passes back, industry control acquisition strategies is adjusted; If there is link failure, will extract the information of this Industrial Control Computer, and the link connection situation of notifying staff to check this Industrial Control Computer; After prompting link failure, go to step 2-1, wait for next data that industry control collecting unit sends over;
If the equal no-failure operation of the normal link of step 2-6 system, system judges whether to occur node failure or node group fault, and according to malfunctioning node numbering or malfunctioning node group #, to occur that node and node group location of fault notify staff, then record and show normal data, if whole system non-fault, goes to step 2-1, wait for next data that industry control collecting unit sends over.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410400956.0A CN104166391A (en) | 2014-08-14 | 2014-08-14 | Cooperative multipoint industrial control acquisition fault monitoring system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410400956.0A CN104166391A (en) | 2014-08-14 | 2014-08-14 | Cooperative multipoint industrial control acquisition fault monitoring system and method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104166391A true CN104166391A (en) | 2014-11-26 |
Family
ID=51910252
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410400956.0A Pending CN104166391A (en) | 2014-08-14 | 2014-08-14 | Cooperative multipoint industrial control acquisition fault monitoring system and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104166391A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111614716A (en) * | 2020-04-10 | 2020-09-01 | 厦门网宿有限公司 | Method and system for collecting remote equipment data |
CN116700197A (en) * | 2023-08-03 | 2023-09-05 | 中国电子信息产业集团有限公司第六研究所 | Industrial control monitoring, analyzing and early warning system and analyzing and early warning processing method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102170368A (en) * | 2011-04-18 | 2011-08-31 | 北京航空航天大学 | Intelligent fault locating method of distributed measuring system facing heavy gauge member |
CN202049376U (en) * | 2011-03-25 | 2011-11-23 | 舟山市定海区巨洋技术开发有限公司 | Universal ship monitoring and alarming system |
CN202404422U (en) * | 2011-11-23 | 2012-08-29 | 陕西特恩电子科技有限公司 | Fault diagnosis system based on remote control and acquisition |
CN103023715A (en) * | 2012-11-23 | 2013-04-03 | 北京广利核系统工程有限公司 | Fault monitoring method based on RS485 bus communication link |
CN103353893A (en) * | 2013-07-18 | 2013-10-16 | 国家电网公司 | Intelligent diagnosis method for distributed data acquisition fault of dispatching automation system |
-
2014
- 2014-08-14 CN CN201410400956.0A patent/CN104166391A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202049376U (en) * | 2011-03-25 | 2011-11-23 | 舟山市定海区巨洋技术开发有限公司 | Universal ship monitoring and alarming system |
CN102170368A (en) * | 2011-04-18 | 2011-08-31 | 北京航空航天大学 | Intelligent fault locating method of distributed measuring system facing heavy gauge member |
CN202404422U (en) * | 2011-11-23 | 2012-08-29 | 陕西特恩电子科技有限公司 | Fault diagnosis system based on remote control and acquisition |
CN103023715A (en) * | 2012-11-23 | 2013-04-03 | 北京广利核系统工程有限公司 | Fault monitoring method based on RS485 bus communication link |
CN103353893A (en) * | 2013-07-18 | 2013-10-16 | 国家电网公司 | Intelligent diagnosis method for distributed data acquisition fault of dispatching automation system |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111614716A (en) * | 2020-04-10 | 2020-09-01 | 厦门网宿有限公司 | Method and system for collecting remote equipment data |
CN111614716B (en) * | 2020-04-10 | 2022-12-16 | 厦门网宿有限公司 | Method and system for collecting remote equipment data |
CN116700197A (en) * | 2023-08-03 | 2023-09-05 | 中国电子信息产业集团有限公司第六研究所 | Industrial control monitoring, analyzing and early warning system and analyzing and early warning processing method |
CN116700197B (en) * | 2023-08-03 | 2023-10-10 | 中国电子信息产业集团有限公司第六研究所 | Industrial control monitoring, analyzing and early warning system and analyzing and early warning processing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102111310B (en) | Method and system for monitoring content delivery network (CDN) equipment status | |
TWI741505B (en) | Topology processing method, device and system | |
CN104796273A (en) | Method and device for diagnosing root of network faults | |
CN103699063B (en) | The harvester of off-line data and method in a kind of Manufacturing Executive System MES | |
CN105807722B (en) | Possesses the numerical control system of internal register runback bit function | |
CN104252401B (en) | Weight based device status judgment method and system thereof | |
CN103699111A (en) | Failure detection method and device for distributed monitoring system | |
CN104678912A (en) | Measurement system consisting of a plurality of sensors | |
CN105450292A (en) | Fault diagnosis analysis method, fault diagnosis device, fault analysis device and fault diagnosis analysis system | |
CN105527910A (en) | Remote monitoring system based on OPC UA (OLE for Process Control Unified Architecture) and fault removal method | |
CN107528630A (en) | With Backup lightpath and failure can self-healing double mode optic-fiber monitoring system and method | |
CN103905219A (en) | System and method for monitoring and storing communication information in service platform | |
CN105007294A (en) | System for quickly receiving and distributing power transmission and transformation equipment state monitoring big data | |
CN105049253A (en) | Method for obtaining mobile network fault location and fault early warning | |
CN102832794B (en) | Frequency converter system and fault processing method thereof | |
CN102170368B (en) | Intelligent fault locating method of distributed measuring system facing heavy gauge member | |
CN102694692A (en) | Fault detecting method and device of distributed equipment | |
CN103455464A (en) | Relay device, connection management method, and information communication system | |
CN104166391A (en) | Cooperative multipoint industrial control acquisition fault monitoring system and method | |
CN102195342A (en) | Photovoltaic power station assembly state real-time monitoring system | |
CN202735418U (en) | Power quality monitoring system | |
CN106571955A (en) | Optical power monitoring system cooperation intelligence optical fiber management system and fault processing method | |
CN102984013A (en) | Alarm analysis method for communication transmission network | |
CN103997126A (en) | Fault diagnosis grading method and system based on on-off state | |
CN108123752B (en) | EPON precise loop detection method based on geographic information positioning |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20141126 |
|
RJ01 | Rejection of invention patent application after publication |