CN104153536A CN201410443386.3A CN201410443386A CN104153536A CN 104153536 A CN104153536 A CN 104153536A CN 201410443386 A CN201410443386 A CN 201410443386A CN 104153536 A CN104153536 A CN 104153536A
Authority
CN
China
Prior art keywords
pottery
cube
wall surface
vertical main
main joist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410443386.3A
Other languages
Chinese (zh)
Other versions
CN104153536B (en
Inventor
刘振永
梁涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Bureau Decoration Engineering Co Ltd
Original Assignee
China Construction Eighth Engineering Division Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Decoration Co Ltd filed Critical China Construction Eighth Engineering Division Decoration Co Ltd
Priority to CN201410443386.3A priority Critical patent/CN104153536B/en
Publication of CN104153536A publication Critical patent/CN104153536A/en
Application granted granted Critical
Publication of CN104153536B publication Critical patent/CN104153536B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a cubic pottery decorative wall surface structure. The cubic pottery decorative wall surface structure comprises rear embedded pieces, vertical main keels, transverse auxiliary keels, glass wool, hanging pieces, cubic pottery and back bolts, wherein each rear embedded piece is fixed to a preset position on the surface of a building, each vertical main keel is welded to the corresponding rear embedded piece through an adapter, each transverse auxiliary keel is in an L shape, one side of each transverse auxiliary keel is welded to the corresponding vertical main keel, the glass wool is arranged in the vertical main keels, each hanging piece is in an L shape, one side of each hanging piece is fixed to the other side of the corresponding L-shaped transverse auxiliary keel through a bolt, the cubic pottery is provided with an installation hole, the back bolts are fixed to the installation holes, and the other side of each hanging piece is connected with the corresponding back bolt in a fastened mode. The cubic pottery decorative wall surface structure has the advantages that the hanging pieces are small, the L-shaped transverse auxiliary keels and the cubic pottery are connected through the hanging pieces, so that the hidden performance is better, and therefore the overall attractiveness is improved; in addition, the cubic pottery does not need making of complicated shaping moulds, after the cubic pottery is produced in batches, the installation holes are formed at the installation positions, and then the L-shaped hanging pieces can be fixed; it is avoided that the positions of the hanging pieces are determined before production, and the production efficiency is improved.

Description

Cube pottery decorated wall surface structure and mounting method thereof
Technical field
The present invention relates to a kind of building wall structure and mounting method, particularly a kind of cube of make pottery decorated wall surface structure and mounting method thereof.
Background technology
Commonly using now cube suspension member that pottery installation adopts is all the die sinking of complex model mould, and suspension member volume is larger, and cube pottery design pitch is unfavorable for the hidden of suspension member when large, affects attractive in appearance; Dismounting is also cumbersome, is unfavorable for the replacement of monolithic pottery plate.
In addition, a cube pottery decorated wall surface need to be arranged in keel frame structure.Keel frame structure can be seen in gap between decorated wall surface, affects overall appearance.
Summary of the invention
Object of the present invention aims to provide a kind of cube of pottery decorated wall surface structure and mounting method thereof, to overcome the defect that exists of above-mentioned prior art.
The invention provides a kind of cube of pottery decorated wall surface structure, comprising: post-install, is fixed on the predeterminated position of building surface; Vertical main joist, is welded on post-install by adaptor; Laterally rider keel, is " L " type, and a side is welded on vertical main joist; Glass wool, arranges in vertical main joist; Suspension member, is " L " type, and the opposite side bolt of a side and the horizontal rider keel of " L " type is fixed; Cube pottery, has installing hole; Back of the body bolt, is fixed on installing hole; The opposite side of suspension member is fastenedly connected with back of the body bolt.
Further, the invention provides a kind of cube of pottery decorated wall surface structure, can also there is such feature: also comprise shutter, be fixed on vertical main joist; On shutter, there are several holes.
Further, the invention provides a kind of cube of pottery decorated wall surface structure, can also there is such feature: post-install and building surface adopt chemical anchor bolts to fix.
Further, the invention provides a kind of cube of pottery decorated wall surface structure, can also there is such feature: vertical main joist arranges shrinkage joint every preset distance.
Further, the invention provides a kind of cube of pottery decorated wall surface structure, can also there is such feature: suspension member and laterally rider keel junction arrange rubber pad.
In addition, the invention provides a kind of cube of pottery decorated wall surface mounting method, there are following steps:
Steps A. measure unwrapping wire;
Step B., at the fixing post-install of building surface predeterminated position, welds vertical main joist by adaptor, then a side of the horizontal rider keel of " L " type is welded on vertical main joist on post-install:
Step C. embeds glass wool between vertical main joist;
Step e. the opposite side of a side of " L " type suspension member and horizontal rider keel is fixed with bolt;
Step F. cube Tao Kaishe installing hole, back of the body bolt is arranged on installing hole, is fastenedly connected with the opposite side of " L " type suspension member carrying on the back bolt.
Further, the invention provides a kind of cube of pottery decorated wall surface mounting method, can also there is such feature: also comprise step D, on vertical main joist, fix shutter, on shutter, there is several holes.
Further, the invention provides a kind of cube of pottery decorated wall surface mounting method, can also there is such feature: the fixing post-install of mode that adopts chemical anchor bolts.
Further, the invention provides a kind of cube of pottery decorated wall surface mounting method, can also there is such feature: vertical main joist arranges shrinkage joint every preset distance.
Further, the invention provides a kind of cube of pottery decorated wall surface mounting method, can also there is such feature: " L " type suspension member and the horizontal rider keel of " L " type junction arrange rubber pad.
The beneficial effect of the invention
One provided by the invention cube pottery decorated wall surface structure and mounting method thereof, because the suspension member suspension member of L-type is small and exquisite, connect the horizontal rider keel of L-type and cube pottery, has more disguise, thereby improve overall appearance.And cube pottery do not need to adopt the die sinking of complex model mould, after batch production, offering installing hole in installation site can fixed L type suspension member, before not needing to produce, just determines suspension member position, and production efficiency is provided.
One provided by the invention cube pottery decorated wall surface structure and mounting method thereof, adopt cube pottery and sound insulating material glass wool to be combined with the acoustical behavior that has improved the interior space, has significant defening effect.
One provided by the invention cube pottery decorated wall surface structure and mounting method thereof, increase shutter on horizontal main joist surface, and metope installing component is covered up, and when cube pottery design pitch is large, is beneficial to hiddenly, improves aesthetics.
One provided by the invention cube pottery decorated wall surface structure and mounting method thereof, adopt screw type back of the body bolt to fix, and regulates freely, can realize monolithic and change, make to install more fast and simple in the situation that cube pottery is damaged.
Brief description of the drawings
Fig. 1 is the front view of the keel structure of of the present invention cube of pottery decorated wall surface structure.
Fig. 2 is the lateral view of of the present invention cube of pottery decorated wall surface structure.
Fig. 3 is the top view of of the present invention cube of pottery decorated wall surface structure.
The structural representation of Fig. 4 shutter of the present invention.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention will be further described.
Cube pottery decorated wall surface structure comprises: post-install 10, chemical anchor bolts 11, adaptor 12, vertical main joist 20, laterally rider keel 30, glass wool 40, suspension member 50, cube pottery 60, back of the body bolt 61, bolt 51, shutter 70 and rubber pad 52.
Post-install 10 is selected the steel plate of 200*150*8mm, adopts M12*140 chemical anchor bolts 11 to be fixed on the predeterminated position of building surface.
Adaptor 12 is selected 8# channel-section steel.After post-install 10 fixes, 8# channel-section steel full weld is used as the adaptor 12 fixing with vertical main joist 20 on post-install 10.Vertical main joist 20 is selected galvanizing 80*60*5 square tube, with adaptor 12 full welds.Vertical main joist arranges shrinkage joint every preset distance.In the present embodiment, vertical main joist arranges the shrinkage joint of 20mm every 6m, make steel have certain displacement capacity.Laterally rider keel 30 is " L " type, selects galvanizing L63*40*5 steel.Laterally a side of rider keel 30 is welded on vertical main joist on 20, and opposite side and suspension member 50 use bolts 51 are fastenedly connected.
Glass wool 40 is 50 heavy sheet glass cottons, 32kg/m 3unit weight, wraps up with black flame-retardant nonwoven, embeds between vertical steel keel, and excessive position, vertical keel distance structure body of wall space will be used 25# iron wire to fix, and prevents that glass wool from dropping.Glass wool is installed smooth, tight, stands upright.
Shutter 70 is selected the thick black steel sheet of 1.5mm, 20% punching rate.Shutter 70 has bar hole 71, and with M7 self tapping self-drilling screw, on vertical main joist 20, laterally rider keel 30 exposes from bar hole 71.
Suspension member 50 is that L-type aluminium alloys suspension member adopts 6063-T5 material, customization processing.One side of suspension member 50 is fixedly connected with bolt 51 with a side of horizontal rider keel 30; Opposite side is fastenedly connected with back of the body bolt 61.Suspension member and laterally rider keel junction arrange chlorine heavy stone used as an anchor rubber pad, prevent the oxidation of aluminium alloys suspension member.
Cube pottery 60 is hollow, has installing hole on installed surface.Back of the body bolt 61, for screw type back of the body bolt, is fixed on installing hole.The opposite side of suspension member 50 is fastenedly connected with back of the body bolt 61.
Cube pottery decorated wall surface mounting method is as follows:
Steps A. measure unwrapping wire.
According to datum axis, will cube pottery finished surface location.The structure wall side of overlapping of cube pottery construction is determined to error between building structure body of wall is whether within specification control range.
Eject a cube pottery on ground and survive control line, first carry out the vertical lattice of facade, plate seam and plate position are ejected, carry out horizontal unwrapping wire with level gauge, determine transverse dividing position, finally Measurement results and drawing compared search whether there is deviation, final spotting, is then testing line by supervisor.
Step B., at the fixing post-install of building surface predeterminated position, welds vertical main joist by adaptor, then a side of the horizontal rider keel of " L " type is welded on to (Fig. 1) on vertical main joist on post-install.
Anyhow determine the top position of 200*150*8mm post-install 10 steel plates to frame bar according to facade, use M12*140 chemical anchor bolts 11 to fix post-install, fixing chemical anchor bolts 11 places open bar hole, while making crab-bolt perforate meet structure wall reinforcing bar, have excursion capability, every post-install 11 arranges 4 chemical anchor bolts fixed points again.
After post-install 11 fixes, vertical main joist 20 is installed, is first used 8# channel-section steel full weld on post-install 11, to be used as the adaptor 12 fixing with vertical main joist 20.Vertical main joist 20 adopts galvanizing 80*60*5 square tube, and according to the position of the vertical main joist 20 of finished surface line traffic control, with adaptor 12 full welds, weld seam does antirust processing.When vertical main joist 20 welding, to draw logical line, guarantee vertical main joist 20 point-blank, within error is controlled at specification permission.Vertical main joist 20 arranges 20mm shrinkage joint every 6m, makes steel have certain displacement capacity.
The transverse dividing line of dividing during according to measurement unwrapping wire is determined the position of horizontal rider keel 30, adopts galvanizing L63*40*5 " L " shaped steel as horizontal rider keel 30, beats bar hole in a cube pottery installation site.Laterally rider keel 30 use black lusterless paint sprayings.
After steelframe welding, carry out secondary and test line, check welding quality, carry out hidden examination after passed examination, what relate to dynamo-electric concealed work will do hidden examination.
Step C. embeds glass wool between vertical main joist.
By 50 heavy sheet glass cottons, 32kg/m 3unit weight, wraps up with black flame-retardant nonwoven, embeds between vertical main joist, and excessive position, vertical main joist distance structure body of wall space will be used 25# iron wire to fix, and prevents that glass wool from dropping.Glass wool is installed smooth, tight, stands upright.
Step D. fixes shutter on vertical main joist.
Shutter is the thick black steel sheet of 1.5mm, and 20% punching rate is fixed on vertical main joist with M7 self tapping self-drilling screw, and seam must be smooth.
Step e. the opposite side of a side of " L " type suspension member and horizontal rider keel is fixed with bolt.
L-type aluminium alloys suspension member adopts 6063-T5 material, customization processing.The horizontal rider keel contact surface of suspension member and galvanizing arranges chlorine heavy stone used as an anchor rubber pad, prevents the oxidation of aluminium alloys suspension member.Suspension member is installed on horizontal rider keel with bolt.
Step F. a cube pottery is installed.
Cube pottery producer the product processing is good with wooden-box package, be transported to Xie Zhi appointed place, job site stack.M7 screw type back of the body bolt is installed into respectively in the installing hole setting in advance, and center, hole is to a cube pottery edges of boards 50mm, then according to a cube pottery plate location, by screw type carry on the back the bolt other end fastening with L-type aluminium alloys suspension member on.On L-type aluminium alloys suspension member, open longitudinal bar hole, draw logical line or use infrared instrument to adjust the installation site on L-type aluminium alloys suspension member, ensure that it is concordant with finished surface control line, horizontal gap adopts mode of the same race, 12mm gap between cube pottery of row up and down of design, is used 12 hassock wood limit mounting edge detection level degree.
Step G. is clean, examination
After installation, soak clear water with towel and incite somebody to action cube surperficial wiped clean of pottery, high with 1.8 meters at door opening place, use 12 lis of plank covering protections, wait for and checking and accepting.

Claims (10)

1. a cube pottery decorated wall surface structure, is characterized in that comprising:
Post-install, is fixed on the predeterminated position of building surface;
Vertical main joist, is welded on described post-install by adaptor;
Laterally rider keel, is " L " type, and a side is welded on described vertical main joist;
Glass wool, arranges in described vertical main joist;
Suspension member, is " L " type, and the opposite side bolt of a side and the horizontal rider keel of described " L " type is fixed;
Cube pottery, has installing hole;
Back of the body bolt, is fixed on described installing hole;
Wherein, the opposite side of described suspension member and described back of the body bolt are fastenedly connected.
2. according to claim 1 cube of pottery decorated wall surface structure, is characterized in that:
Also comprise shutter, be fixed on described vertical main joist; On described shutter, there is several holes.
3. according to claim 1 cube of pottery decorated wall surface structure, is characterized in that:
Wherein, described post-install and building surface adopt chemical anchor bolts to fix.
4. according to claim 1 cube of pottery decorated wall surface structure, is characterized in that:
Wherein, described vertical main joist arranges shrinkage joint every preset distance.
5. according to claim 1 cube of pottery decorated wall surface structure, is characterized in that:
Wherein, described suspension member and described horizontal rider keel junction arrange rubber pad.
6. a cube pottery decorated wall surface mounting method, is characterized in that having following steps:
Steps A. measure unwrapping wire;
Step B., at the fixing post-install of building surface predeterminated position, welds vertical main joist by adaptor, then a side of the horizontal rider keel of " L " type is welded on described vertical main joist on described post-install;
Step C. embeds glass wool between described vertical main joist;
Step e. a side of " L " type suspension member and the opposite side of described horizontal rider keel are fixed with bolt;
Step F. cube Tao Kaishe installing hole, back of the body bolt is arranged on described installing hole, and the opposite side of described back of the body bolt and described " L " type suspension member is fastenedly connected.
7. according to cube pottery decorated wall surface mounting method described in claim 6, it is characterized in that:
Also comprise step D, on described vertical main joist, fix shutter, on described shutter, there is several holes.
8. according to claim 6 cube of pottery decorated wall surface mounting method, is characterized in that:
Wherein, adopt the fixing described post-install of mode of chemical anchor bolts.
9. according to claim 6 cube of pottery decorated wall surface mounting method, is characterized in that:
Wherein, described vertical main joist arranges shrinkage joint every preset distance.
10. according to claim 6 cube of pottery decorated wall surface mounting method, is characterized in that:
Wherein, described " L " type suspension member and the horizontal rider keel of described " L " type junction arrange rubber pad.
CN201410443386.3A 2014-09-02 2014-09-02 Cube pottery decorated wall surface structure and installation method thereof Active CN104153536B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410443386.3A CN104153536B (en) 2014-09-02 2014-09-02 Cube pottery decorated wall surface structure and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410443386.3A CN104153536B (en) 2014-09-02 2014-09-02 Cube pottery decorated wall surface structure and installation method thereof

Publications (2)

Publication Number Publication Date
CN104153536A true CN104153536A (en) 2014-11-19
CN104153536B CN104153536B (en) 2016-08-17

Family

ID=51879150

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410443386.3A Active CN104153536B (en) 2014-09-02 2014-09-02 Cube pottery decorated wall surface structure and installation method thereof

Country Status (1)

Country Link
CN (1) CN104153536B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000297515A (en) * 1999-04-16 2000-10-24 Ig Tech Res Inc Structure for repairing alc outer wall
CN101956438A (en) * 2010-10-22 2011-01-26 泛华建设集团有限公司 Three-dimensionally adjustable disconnectable curtain wall connecting device and construction method thereof
CN203361505U (en) * 2013-06-05 2013-12-25 郑念标 Thermal insulation type wall facing material
CN204040377U (en) * 2014-09-02 2014-12-24 上海中建八局装饰有限责任公司 Cube pottery decorated wall surface structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000297515A (en) * 1999-04-16 2000-10-24 Ig Tech Res Inc Structure for repairing alc outer wall
CN101956438A (en) * 2010-10-22 2011-01-26 泛华建设集团有限公司 Three-dimensionally adjustable disconnectable curtain wall connecting device and construction method thereof
CN203361505U (en) * 2013-06-05 2013-12-25 郑念标 Thermal insulation type wall facing material
CN204040377U (en) * 2014-09-02 2014-12-24 上海中建八局装饰有限责任公司 Cube pottery decorated wall surface structure

Also Published As

Publication number Publication date
CN104153536B (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN106869380A (en) A kind of dry-hang stone keel
CN201232357Y (en) Adjustable retention hole mould of building floor pipeline
CN106245821A (en) A kind of lightweight steel construction lightweight concrete prefabrication and assembly construction body of wall and construction method thereof
CN201420317Y (en) Three-dimensional adjustable curtain wall installation connecting piece
CN203863813U (en) Die special for housing industrialization pre-cast concrete component stair
CN204040377U (en) Cube pottery decorated wall surface structure
CN207092469U (en) For the finished product construction joint in floor construction
CN104153536A (en) Cubic pottery decorative wall surface structure and installation method thereof
CN204040795U (en) Deformation-preventing wooden door
CN205591472U (en) Wall aluminum plate system
CN101983826B (en) Welding method of steel plate case of freezer
CN103161311B (en) Large diameter reinforced concrete pipe road crosses the construction method of abutment
CN203547123U (en) Supporting device for deformation joint template
CN207727982U (en) A kind of building wall corner Constructional Col-umn Construction template
CN102953498A (en) Plastic grid ceiling system
CN203547052U (en) Novel outer wall modeling pilaster structure used for building
CN102561728B (en) Recyclable steel-skeleton model-house system
CN202787964U (en) Concrete structure drop plate angle steel tool type combined template
CN105971275A (en) Combined type stair formwork
CN206673326U (en) A kind of low pressure cabinet frame work
CN206319587U (en) The making mould of concrete floor
CN210798262U (en) Wall connecting piece
CN209891481U (en) Prefabricated steelframe partition wall of assembled
CN205012559U (en) Stable form distortion combination steel -pipe column
CN203967672U (en) Concrete wall can positioning wires box

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 200120 unit 06, 07, No. 28, No. 1568, Century Avenue, free trade test area, Pudong New Area, Shanghai, China (Shanghai)

Patentee after: Zhongjian eight bureau Decoration Engineering Co., Ltd.

Address before: 200122 Pudong New Area Century Avenue, No. 28, building 06, unit 1568, 07