CN104141601A - Technological method for making up deficiency of insufficient air inflating capacity of air compressor in summer - Google Patents

Technological method for making up deficiency of insufficient air inflating capacity of air compressor in summer Download PDF

Info

Publication number
CN104141601A
CN104141601A CN201410225501.XA CN201410225501A CN104141601A CN 104141601 A CN104141601 A CN 104141601A CN 201410225501 A CN201410225501 A CN 201410225501A CN 104141601 A CN104141601 A CN 104141601A
Authority
CN
China
Prior art keywords
air
compressor
section
separator
auxiliary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410225501.XA
Other languages
Chinese (zh)
Other versions
CN104141601B (en
Inventor
赵新岭
白金光
张丽楠
郝子健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHONG YUAN DAHUA GROUP Ltd OF HENAN PROVINCE
Original Assignee
ZHONG YUAN DAHUA GROUP Ltd OF HENAN PROVINCE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHONG YUAN DAHUA GROUP Ltd OF HENAN PROVINCE filed Critical ZHONG YUAN DAHUA GROUP Ltd OF HENAN PROVINCE
Priority to CN201410225501.XA priority Critical patent/CN104141601B/en
Publication of CN104141601A publication Critical patent/CN104141601A/en
Application granted granted Critical
Publication of CN104141601B publication Critical patent/CN104141601B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Compressors, Vaccum Pumps And Other Relevant Systems (AREA)

Abstract

A technological method for making up deficiency of insufficient air inflating capacity of an air compressor in summer is an auxiliary technology for the air compressor. A one-section separator outlet pipeline and an auxiliary separator outlet pipeline are connected onto a pipeline of a two-section compressor of a main air compressor respectively; a one-section separator is connected onto the one-section separator outlet pipeline and connected with a one-section cooler through a one-section cooler outlet pipeline, the one-section cooler is connected with a one-section compressor of the main air compressor through a one-section compression outlet pipeline, and the one-section compressor of the main air compressor is connected with an air filter through a one-section compression inlet pipeline of the main compressor; an auxiliary separator is connected onto the auxiliary separator outlet pipeline and connected with an auxiliary cooler through an auxiliary cooler outlet pipeline, and the auxiliary cooler is connected with an auxiliary air compressor through an auxiliary air compressor outlet pipeline; and the auxiliary air compressor is connected with the one-section compression inlet pipeline of the main air compressor through an auxiliary air compressor inlet pipeline.

Description

A kind of technological method that makes up air compressor inflate quantity in summer deficiency
Technical field: the present invention relates to the ancillary technique in air compressor, especially a kind of technological method that makes up air compressor inflate quantity in summer deficiency.
Background technique: the problem of ubiquitous air compressor inflate quantity in summer deficiency in the industry production processes such as chemical industry, petrochemical industry, iron and steel, air separation, often using air compressor is air compressor, provides pressurized air for producing.Under air compressor normal operation, exhaust pressure is certain, the inflate quantity of air compressor depends on ambient temperature and rotating speed, because the design load of air compressor one-level inlet temperature is the intermediate value of winter temperature and summer temperature, therefore when air compressor is in the winter time with summer, along with the variation of temperature, inflate quantity also changes thereupon.Summer airborne water content higher than winter, this be cause air compressor inflate quantity reduce Another reason.Along with the rising inflate quantity of temperature is obviously not enough, can not meet process units needs in summer, device must load shedding move, and causes a large amount of wastes.Temperature is irresistible with the variation in season, thereby air compressor inflate quantity is ubiquitous with the problem changing season.
Summary of the invention: the object of this invention is to provide a kind of technological method that makes up air compressor inflate quantity in summer deficiency, it has overcome the shortcoming of prior art, the object of the present invention is achieved like this, connecting respectively one section of separator outlet pipeline and auxiliary air separator outlet conduit on the pipeline of two sections of compressors of main air compressor; On one section of separator outlet pipeline, connecting one section of separator, one section of separator is connected by one section of cooler outlet pipeline with in the middle of one section of cooler, in the middle of one section of compressor of one section of cooler and main air compressor, be connected by one section of compression outlet conduit, one section of compressor of main air compressor is connected by one section of compression inlet pipe of main air compressor with air filter is middle; On auxiliary air separator outlet conduit, connecting auxiliary air separator, auxiliary air separator is connected by auxiliary cooler outlet conduit with auxiliary cooler, auxiliary cooler is connected by air-boost compressor outlet conduit with air-boost compressor, and air-boost compressor outlet valve and air-boost compressor outlet check valve are installed on air-boost compressor outlet conduit; Air-boost compressor is connected by one section of compression inlet pipe of air-boost compressor inlet pipe and main air compressor, and air-boost compressor inlet valve is installed in the middle of it.
One section of compressor of main air compressor, one section of cooler, one section of separator and air-boost compressor, auxiliary cooler, auxiliary air separator are to be connected in parallel.
When the present invention works, be divided into two-way from air filter air out, the first via enters in one section of compressor of main empty compressor and compresses from one section of compression inlet pipe of main air compressor, air after compression enters one section of cooler from one section of compression outlet conduit and carries out cooling, then enter one section of separator from one section of cooler out, compress through one section of laggard two sections of compressor of air compressor of becoming owner of of separator separating and condensing water; Secondary route air-boost compressor inlet pipe, after air-boost compressor inlet valve, entering air-boost compressor compresses, air after compression enters auxiliary cooler and carries out cooling after air-boost compressor outlet conduit, air-boost compressor outlet check valve, air-boost compressor outlet valve, cooled air is after auxiliary air separator separating and condensing water, through auxiliary air separator outlet conduit and mix from one section of separator air out, and then enter in two sections of compressors of main air compressor and compress.
The inflate quantity of air-boost compressor is the 3%-15% of one section of discharge gas Qty of compressor of main air compressor.
In the time of summer operation, this device is to increase main air compressor inflate quantity by operation air-boost compressor, makes the sum total of the inflate quantity of one section of compression of main air compressor and the inflate quantity of air-boost compressor meet need of production, the stable high load running of assurance device.
Meaning of the present invention is: 1, overcome the air compressor causing due to the rising of temperature and looked not enough shortcoming up and down, realized the high load running of device, reduced waste, reduced cost of production; 2, solved the bottleneck problem of air compressor in Chemical Manufacture; 3, by increasing air-boost compressor, auxiliary cooler, met the need of production at varying environment temperature; 4, it had both been applicable to Multistage centrifugal compressor and had also been applicable to multistage reciprocal compressor; 5, the compression that it had both been applicable to air is also applicable to the compression of other gas that has analogue; 6, the design that it both can directly apply to new equipment also can be applicable to the technical innovation of old device; 7, the air-boost compressor one increasing is that inflate quantity is little, the 2nd, and outlet pressure is lower, so energy consumption is lower; 8, one section of inlet temperature of the rising major effect air compressor of temperature, impact on two sections of inlet temperatures is less, it has solved targetedly because of the raise problem of the one section of entrance gettering quantity deficiency of air compressor causing of temperature, make the ability of the follow-up machine of main air compressor and the driving machine of main air compressor obtain maximum performance, thereby it is a kind of best approach little and that energy consumption is low of investing.
Brief description of the drawings: Fig. 1 is a kind of tooling schematic diagram that makes up air compressor inflate quantity in summer deficiency, in figure 1, air filter 2, one section of compression inlet pipe 3 of main air compressor, one section of compressor 4 of main air compressor, main air compressor one section outlet pipeline 5, one section of cooler 6, one section of cooler outlet pipeline 7, one section of separator 8, one section of separator outlet pipeline 9, air-boost compressor inlet pipe 10, air-boost compressor inlet valve 11, air-boost compressor 12, air-boost compressor outlet conduit 13, air-boost compressor outlet check valve 14, air-boost compressor outlet valve 15, auxiliary cooler 16, auxiliary cooler outlet conduit 17, auxiliary air separator 18, auxiliary air separator outlet conduit 19, two sections of compressors of main air compressor.
Embodiment: embodiment 1, connecting respectively one section of separator outlet pipeline 8 and auxiliary air separator outlet conduit 18 on the pipeline of two sections of compressors 19 of main air compressor; On one section of separator outlet pipeline 8, connecting one section of separator 7, one section of separator 7 is connected by one section of cooler outlet pipeline 6 with in the middle of one section of cooler 5, in the middle of one section of compressor of one section of cooler 5 and main air compressor 3, be connected by one section of compression outlet conduit 4, one section of compressor 3 of main air compressor is connected by one section of compression inlet pipe 2 of main air compressor with air filter 1 is middle; On auxiliary air separator outlet conduit 18, connecting auxiliary air separator 17, auxiliary air separator 17 is connected by auxiliary cooler outlet conduit 16 with auxiliary cooler 15, auxiliary cooler 15 is connected by air-boost compressor outlet conduit 12 with air-boost compressor 11, and air-boost compressor outlet valve 14 and air-boost compressor outlet check valve 13 are installed on air-boost compressor outlet conduit 12; Air-boost compressor 11 is connected by one section of compression inlet pipe 2 of air-boost compressor inlet pipe 9 and main air compressor, and air-boost compressor inlet valve 10 is installed in the middle of it.
Embodiment 2, one section of compressor of main air compressor 3, one section of cooler 5, one section of separator 7 are to be connected in parallel with air-boost compressor 11, auxiliary cooler 15, auxiliary air separator 17.
Embodiment 3, method of work of the present invention are: be divided into two-way from air filter 1 air out, the first via enters in one section of compressor 3 of main empty compressor and compresses from one section of compression inlet pipe 2 of main air compressor, air after compression enters one section of cooler 5 from one section of compression outlet conduit 4 and carries out cooling, then enter one section of separator 7 from one section of cooler 5 out, compress through the laggard two sections of compressors 19 of air compressor of becoming owner of of one section of separator, 7 separating and condensing water; Secondary route air-boost compressor inlet pipe 9, after air-boost compressor inlet valve 10, entering air-boost compressor 11 compresses, air after compression enters auxiliary cooler 15 and carries out cooling after air-boost compressor outlet conduit 12, air-boost compressor outlet check valve 13, air-boost compressor outlet valve 14, cooled air is after auxiliary air separator 17 separating and condensing water, through auxiliary air separator outlet conduit 18 and mix from one section of separator air out, and then enter in two sections of compressors 19 of main air compressor and compress.
The inflate quantity of embodiment 4, air-boost compressor 11 is 3%-15% of one section of compressor 3 inflate quantity of main air compressor.
Embodiment 5, in the time of summer operation, this device is to increase main air compressor inflate quantity by operation air-boost compressor, make the sum total of the inflate quantity of one section of compression of main air compressor and the inflate quantity of air-boost compressor meet need of production, the stable high load running of assurance device.
   

Claims (5)

1. a tooling that makes up air compressor inflate quantity in summer deficiency, is characterized in that: on the pipeline of two sections of compressors of main air compressor (19), connecting respectively one section of separator outlet pipeline (8) and auxiliary air separator outlet conduit (18), on one section of separator outlet pipeline (8), connecting one section of separator (7), one section of separator (7) is connected by one section of cooler outlet pipeline (6) with in the middle of one section of cooler (5), one section of cooler (5) is connected by one section of compression outlet conduit (4) with in the middle of one section of compressor of main air compressor (3), and one section of compressor of main air compressor (3) is connected by one section of compression inlet pipe of main air compressor (2) with air filter (1) is middle, on auxiliary air separator outlet conduit (18), connecting auxiliary air separator (17), auxiliary air separator (17) is connected by auxiliary cooler outlet conduit (16) with auxiliary cooler (15), auxiliary cooler (15) is connected by air-boost compressor outlet conduit (12) with air-boost compressor (11), and air-boost compressor outlet valve (14) is installed on air-boost compressor outlet conduit (12) to be connected by one section of compression inlet pipe of air-boost compressor inlet pipe (9) and main air compressor (2) with air-boost compressor outlet check valve (13) air-boost compressor (11), air-boost compressor inlet valve (10) is installed in the middle of it.
2. a kind of tooling that makes up air compressor inflate quantity in summer deficiency according to claim 1, is characterized in that: one section of compressor of main air compressor (3), one section of cooler (5), one section of separator (7) are to be connected in parallel with air-boost compressor (11), auxiliary cooler (15), auxiliary air separator (17).
3. a kind of method of work that makes up the not enough tooling of air compressor inflate quantity in summer claimed in claim 1, it is characterized in that: be divided into two-way from air filter (1) air out, the first via enters in one section of compressor of main empty compressor (3) and compresses from one section of compression inlet pipe of main air compressor (2), air after compression enters one section of cooler (5) from one section of compression outlet conduit (4) and carries out cooling, then enter one section of separator (7) from one section of cooler (5) out, compress through the laggard two sections of compressors of air compressor (19) of becoming owner of of one section of separator (7) separating and condensing water, secondary route air-boost compressor inlet pipe (9), after air-boost compressor inlet valve (10), entering air-boost compressor (11) compresses, air after compression is through air-boost compressor outlet conduit (12), air-boost compressor outlet check valve (13), after air-boost compressor outlet valve (14), entering auxiliary cooler (15) carries out cooling, cooled air is after auxiliary air separator (17) separating and condensing water, pass through auxiliary air separator outlet conduit (18) and mix from one section of separator air out, and then enter in two sections of compressors of main air compressor (19) and compress.
4. a kind of method of work that makes up the not enough tooling of air compressor inflate quantity in summer described in claim 1 or 2, is characterized in that: the inflate quantity of air-boost compressor (11) is the 3%-15% of one section of compressor of main air compressor (3) inflate quantity.
5. a kind of method of work that makes up the not enough tooling of air compressor inflate quantity in summer described in claim 1 or 2, it is characterized in that: in the time of summer operation, to increase main air compressor inflate quantity by operation air-boost compressor, make the sum total of the inflate quantity of one section of compression of main air compressor and the inflate quantity of air-boost compressor meet need of production, the stable high load running of assurance device.
CN201410225501.XA 2014-05-27 2014-05-27 A kind of process that makes up air compressor inflate quantity in summer deficiency Expired - Fee Related CN104141601B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410225501.XA CN104141601B (en) 2014-05-27 2014-05-27 A kind of process that makes up air compressor inflate quantity in summer deficiency

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410225501.XA CN104141601B (en) 2014-05-27 2014-05-27 A kind of process that makes up air compressor inflate quantity in summer deficiency

Publications (2)

Publication Number Publication Date
CN104141601A true CN104141601A (en) 2014-11-12
CN104141601B CN104141601B (en) 2016-05-04

Family

ID=51850886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410225501.XA Expired - Fee Related CN104141601B (en) 2014-05-27 2014-05-27 A kind of process that makes up air compressor inflate quantity in summer deficiency

Country Status (1)

Country Link
CN (1) CN104141601B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060293816A1 (en) * 2005-06-23 2006-12-28 Yunjun Li Series arranged air compressors system
US20070214963A1 (en) * 2006-03-15 2007-09-20 Bendix Commercial Vehicle Systems Llc Charging system
CN101403377A (en) * 2008-11-10 2009-04-08 周文三 Inflating apparatus
CN202056040U (en) * 2011-04-29 2011-11-30 江门汇海饲料厂有限公司 Control system for multiple air compressors
CN203892160U (en) * 2014-05-27 2014-10-22 河南省中原大化集团有限责任公司 Process device for making up shortage of inflation quantity of air compressors in summer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060293816A1 (en) * 2005-06-23 2006-12-28 Yunjun Li Series arranged air compressors system
US20070214963A1 (en) * 2006-03-15 2007-09-20 Bendix Commercial Vehicle Systems Llc Charging system
CN101403377A (en) * 2008-11-10 2009-04-08 周文三 Inflating apparatus
CN202056040U (en) * 2011-04-29 2011-11-30 江门汇海饲料厂有限公司 Control system for multiple air compressors
CN203892160U (en) * 2014-05-27 2014-10-22 河南省中原大化集团有限责任公司 Process device for making up shortage of inflation quantity of air compressors in summer

Also Published As

Publication number Publication date
CN104141601B (en) 2016-05-04

Similar Documents

Publication Publication Date Title
CN103883287A (en) Low-pressure natural gas recovering system for offshore gas field
CN204611345U (en) A kind of synchronous revolving oil gas combined transportation device
CN205618328U (en) A combination equipment for preparing it is dry, clean gaseous
CN203892160U (en) Process device for making up shortage of inflation quantity of air compressors in summer
CN105457329A (en) Cyclohexane oxidation tail gas recycling device
CN103759499A (en) Ultralow-energy-consumption nitrogen making device
CN203796236U (en) Low-pressure natural gas recovery system of offshore gas field
CN104482396B (en) BOG recovery system with cold storage function
CN104141601A (en) Technological method for making up deficiency of insufficient air inflating capacity of air compressor in summer
CN205908465U (en) Air compressor machine with comdenstion water is collected and discharging equipment
CN205779572U (en) Air compressor machine oil circuit circulating device
CN205370892U (en) Integrated form air compressor
CN104481849A (en) Air source system of barrel making device
CN104179657A (en) Passive pneumatic pressurizing device for underground coal mine
CN206377462U (en) A kind of compressed air air supply system
CN204051046U (en) A kind of cyclohexane oxidation off-gas recycle device
CN204220007U (en) Compressed air drier
CN204532781U (en) A kind of membrane compressor automatic cycle start-stop control system
CN204327446U (en) compressor oil recovering device
CN203731092U (en) Device for pressurizing raw natural gas by using natural gas pipeline network pressure energy
CN207406465U (en) It is a kind of using air compressor as empty nitrogen mutually for the nitrogen supply system of compressor standby host
CN202494246U (en) Heat-recyclable refrigeration compressor parallel-connection unit
CN205663618U (en) Air compressor system with novel waste fitting discharging
CN103712062B (en) Method and device for pressurizing raw natural gas through natural gas pipeline network pressure energy
CN207036659U (en) Infra-red inspection air compressor machine nitrogen gas handling system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160504

Termination date: 20210527

CF01 Termination of patent right due to non-payment of annual fee