CN104045031A - Offshore wind generating set wharf split hoisting scheme - Google Patents

Offshore wind generating set wharf split hoisting scheme Download PDF

Info

Publication number
CN104045031A
CN104045031A CN201310082508.6A CN201310082508A CN104045031A CN 104045031 A CN104045031 A CN 104045031A CN 201310082508 A CN201310082508 A CN 201310082508A CN 104045031 A CN104045031 A CN 104045031A
Authority
CN
China
Prior art keywords
wharf
hoisting
harbour
carrier
offshore wind
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310082508.6A
Other languages
Chinese (zh)
Inventor
孙振军
王力雨
张克
李红梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI ELECTRICAL WINDPOWER CO Ltd
Original Assignee
SHANGHAI ELECTRICAL WINDPOWER CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI ELECTRICAL WINDPOWER CO Ltd filed Critical SHANGHAI ELECTRICAL WINDPOWER CO Ltd
Priority to CN201310082508.6A priority Critical patent/CN104045031A/en
Publication of CN104045031A publication Critical patent/CN104045031A/en
Pending legal-status Critical Current

Links

Abstract

The invention provides an offshore wind generating set wharf split hoisting scheme for offshore blower wharf hoisting. The offshore wind generating set wharf split hoisting scheme is used for solving the defects of multiple hoisting working procedures and high cost of an existing blower wharf hoisting scheme. According to the wharf split hoisting scheme provided by the invention, by virtue of a mode of reconstructing a port or adopting a special transport ship, the transport ship is stably berthed at a wharf, a mounting environment similar to an onshore environment is formed, and a tower drum, an engine room, a wheel hub and a blade are hoisted and mounted on the transport ship in batches. A tool tower drum is not needed to be arranged at the wharf, so that the hoisting frequency is reduced, and meanwhile demands on large hoisting equipment are reduced; the hoisting capacity is only needed to meet the weight of the greatest part sleeve, so that the wharf hoisting cost is greatly lowered, and meanwhile the wharf hoisting construction period also can be shortened.

Description

Offshore wind turbine harbour split Hoisting Program
Technical field
The present invention relates to the harbour Hoisting Program of offshore wind turbine.
Background technology
During offshore wind turbine wind field installation at sea at present, all adopt integral hoisting scheme, this just requires carrier when harbour sets out, and need complete the assembling of wind wheel, cabin and tower cylinder, is transported to together as a whole marine wind field.
Existing wind power generating set harbour lifting is generally helped lifting by mounting tool tower cylinder on harbour, concrete scheme is: first tower cylinder is contained on carrier in advance, then cabin, wheel hub, blade are arranged on successively on the frock tower cylinder of harbour, then by cabin, wheel hub, blade as a whole together handling to carrier, assemble with tower cylinder.
Along with the lengthening of wind power generation unit blade, frock pylon is more and more higher, and expense is considerable.There is repeatedly lifting in simultaneously whole harbour lifting, extra lifting number of times, has increased expense, has extended the duration.Simultaneously to lifting appliance require highly, crane capacity need meet the total weight of cabin, wheel hub, blade.
Summary of the invention
For fear of the deficiency of existing harbour Hoisting Program, the invention provides a kind of offshore wind turbine harbour split Hoisting Program.This Hoisting Program is by transformation harbour or adopt the mode of special carrier, makes carrier pulsation-free be docked in harbour place, forms and is similar to land installation environment, directly tower cylinder, cabin, wheel hub, blade gradation handling is arranged on carrier.
Wherein, the mode that described transformation harbour can adopt cofferdam is carried out separation to the carrier sea of berthing, and also can arrange and block water shutter, to block the impact on carrier of current and wave.
Described special carrier can be half latent barge or support leg ship, to realize the function in contact seabed.Guarantee the steady of carrier.
By adopting the described offshore wind turbine harbour split Hoisting Program of this explanation, need to be at harbour mounting tool tower cylinder, reduced lifting times, reduced the demand of large-scale lifting appliance simultaneously, crane capacity only need meet the weight of maximum portion cover, reduce greatly the cost of harbour lifting, also can shorten the duration of harbour lifting simultaneously.
The specific embodiment
Below in conjunction with embodiment, the present invention is described in further detail.
Adopt the mode in cofferdam, separation is carried out in the carrier sea of berthing, block the impact on carrier of current and wave, to guarantee that carrier pulsation-free is docked in harbour place, form and be similar to land installation environment.Adopt afterwards similar land separable assembled scheme, tower cylinder is arranged on carrier, then cabin, wheel hub, impeller are lifted to carrier and assembled with tower cylinder.
By adopting this offshore wind turbine harbour split Hoisting Program, need to be at harbour mounting tool tower cylinder, reduced lifting times, the crane capacity of large-scale lifting appliance only need meet the weight of maximum portion cover, reduce greatly the cost of harbour lifting, also can shorten the duration of harbour lifting simultaneously.
Although through the present invention is described in conjunction with specific embodiments, for the skilled personage of the art, substituting, revising with variation of making according to narration above will be apparent.Therefore, such, substitute, when modifications and variations fall in the spirit and scope of claim of the present invention, should be included in the present invention.

Claims (3)

1. offshore wind turbine harbour split Hoisting Program, it is characterized in that: by transformation harbour or adopt the mode of special carrier, make carrier pulsation-free be docked in harbour place, formation is similar to land installation environment, directly tower cylinder, cabin, wheel hub, blade gradation handling is arranged on carrier.
2. offshore wind turbine harbour split Hoisting Program according to claim 1, it is characterized in that: the mode that described transformation harbour can adopt cofferdam is carried out separation to the carrier sea of berthing, also can arrange and block water shutter, to block the impact on carrier of current and wave.
3. offshore wind turbine harbour split Hoisting Program according to claim 1, is characterized in that: described special carrier can be partly dive barge or support leg ship, to realize the function in contact seabed, guarantees the steady of carrier.
CN201310082508.6A 2013-03-15 2013-03-15 Offshore wind generating set wharf split hoisting scheme Pending CN104045031A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310082508.6A CN104045031A (en) 2013-03-15 2013-03-15 Offshore wind generating set wharf split hoisting scheme

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310082508.6A CN104045031A (en) 2013-03-15 2013-03-15 Offshore wind generating set wharf split hoisting scheme

Publications (1)

Publication Number Publication Date
CN104045031A true CN104045031A (en) 2014-09-17

Family

ID=51498490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310082508.6A Pending CN104045031A (en) 2013-03-15 2013-03-15 Offshore wind generating set wharf split hoisting scheme

Country Status (1)

Country Link
CN (1) CN104045031A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107237722A (en) * 2017-05-26 2017-10-10 江苏华西村海洋工程服务有限公司 A kind of offshore wind farm construction technology
CN110469458A (en) * 2019-07-19 2019-11-19 中国能源建设集团广东火电工程有限公司 A kind of marine wind turbine whole machine harbour assembling method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004001750A (en) * 2003-06-25 2004-01-08 Penta Ocean Constr Co Ltd Special working ship and execution method for offshore structure
CN101985917A (en) * 2010-10-08 2011-03-16 中交第一航务工程局有限公司 Splitting installation and construction method of marine wind generating set and equipment thereof
CN102050198A (en) * 2009-11-10 2011-05-11 中交第三航务工程局有限公司 Split installation process of submerged barge seat of wind driven generator in shallow water
CN102425530A (en) * 2011-11-17 2012-04-25 中国十七冶集团有限公司 Split high-altitude butt-joint installation method of offshore wind generating set
CN102616338A (en) * 2011-01-30 2012-08-01 华锐风电科技(集团)股份有限公司 Ship for transporting wind turbines and transporting method for wind turbines

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004001750A (en) * 2003-06-25 2004-01-08 Penta Ocean Constr Co Ltd Special working ship and execution method for offshore structure
CN102050198A (en) * 2009-11-10 2011-05-11 中交第三航务工程局有限公司 Split installation process of submerged barge seat of wind driven generator in shallow water
CN101985917A (en) * 2010-10-08 2011-03-16 中交第一航务工程局有限公司 Splitting installation and construction method of marine wind generating set and equipment thereof
CN102616338A (en) * 2011-01-30 2012-08-01 华锐风电科技(集团)股份有限公司 Ship for transporting wind turbines and transporting method for wind turbines
CN102425530A (en) * 2011-11-17 2012-04-25 中国十七冶集团有限公司 Split high-altitude butt-joint installation method of offshore wind generating set

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107237722A (en) * 2017-05-26 2017-10-10 江苏华西村海洋工程服务有限公司 A kind of offshore wind farm construction technology
CN107237722B (en) * 2017-05-26 2019-08-16 江苏华西村海洋工程服务有限公司 A kind of offshore wind farm construction technology
CN110469458A (en) * 2019-07-19 2019-11-19 中国能源建设集团广东火电工程有限公司 A kind of marine wind turbine whole machine harbour assembling method
CN110469458B (en) * 2019-07-19 2021-01-12 中国能源建设集团广东火电工程有限公司 Offshore wind turbine whole machine wharf assembly method

Similar Documents

Publication Publication Date Title
Castro-Santos et al. Methodology to calculate the installation costs of offshore wind farms located in deep waters
CN103015445B (en) Neritic zone wind energy turbine set is without changeover portion single-pile foundation construction and Fan Equipment mounting process
CN202040026U (en) Comprehensive utilization system for sea energy
KR101013789B1 (en) Method of establishing Sea wind power generator and apparatus thereof
CN103758705B (en) A kind of binary floating offshore wind turbine system
CN104948380B (en) A kind of wave energy photovoltaic and offshore wind turbine combined generating system
CN102464088B (en) Method for installing thruster at bottom of drilling platform
Asgarpour Assembly, transportation, installation and commissioning of offshore wind farms
Athanasia et al. The offshore wind market deployment: forecasts for 2020, 2030 and impacts on the European supply chain development
CN102400862B (en) Method for assembling impeller of wind power generator unit
CN203186548U (en) Self-elevating heavy installation boat
Dewan et al. Commercial proof of innovative offshore wind installation concepts using ECN Install Tool
CN103010413A (en) Working method for hoisting draught fan by barge
PH12018501431A1 (en) Offshore wind power generation facility and construction method therefor
CN104045031A (en) Offshore wind generating set wharf split hoisting scheme
KR20120139931A (en) Method and system of attaching and detaching spud can to the jack-up platform
CN104554639A (en) Installation equipment for large offshore wind power equipment
CN105239572A (en) Offshore construction method for large-diameter single pile fan foundation structure
CN204642060U (en) A kind of large-scale coastal waters wind power equipment installs equipment
CN102787988A (en) Method for installing offshore wind generating set
KR20150023182A (en) Dock used for carry for barge offshore platform building method
CN204551513U (en) A kind of large-diameter pile fan foundation structure
CN203958557U (en) Marine half latent floating type wind power generation platform
CN202414121U (en) Marine wind-powered installation vessel
CN202414126U (en) Marine wind and electricity installing platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140917

WD01 Invention patent application deemed withdrawn after publication