CN104029139A - Special clamp for threaded rebar and assembling method - Google Patents

Special clamp for threaded rebar and assembling method Download PDF

Info

Publication number
CN104029139A
CN104029139A CN201310325668.9A CN201310325668A CN104029139A CN 104029139 A CN104029139 A CN 104029139A CN 201310325668 A CN201310325668 A CN 201310325668A CN 104029139 A CN104029139 A CN 104029139A
Authority
CN
China
Prior art keywords
lock core
lock
spiral
lining
lock tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310325668.9A
Other languages
Chinese (zh)
Other versions
CN104029139B (en
Inventor
谢帮鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201310325668.9A priority Critical patent/CN104029139B/en
Publication of CN104029139A publication Critical patent/CN104029139A/en
Application granted granted Critical
Publication of CN104029139B publication Critical patent/CN104029139B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21FWORKING OR PROCESSING OF METAL WIRE
    • B21F31/00Making meshed-ring network from wire

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Winding, Rewinding, Material Storage Devices (AREA)

Abstract

The invention provides a special clamp for threaded rebar and an assembling method. The special clamp comprises a barrel-shaped rotatable lock sleeve, an opening is formed in a lateral side of the lock sleeve, a fixed lock cylinder is mounted inside the lock sleeve, an opening is formed in a lateral side of the lock cylinder, a lock cylinder lining is mounted in the opening of the lock cylinder, a section of the lock cylinder lining is in a recessed semi-circular structure which is proper for clamping the threaded rebar in size and provided with a plurality of grooves, the groove structures correspond to the position of a thread in the surface of the threaded rebar, and a locking screw rod is mounted in a surface of the lock sleeve in an inserted manner and can tightly compress the lock cylinder after penetrating the lock sleeve. The assembling method is used for assembling the threaded rebar by the special clamp. By the special clamp and the assembling method, abrasion to the threaded rebar is reduced, quick clamping of the threaded rebar can be realized by hand operation without other force applying tools, and labor saving, time saving, economy and reliability are achieved.

Description

Spiral special fixture and assembly method
Technical field
The present invention relates to fabrication of reinforcing cage technical field, refer more particularly to a kind of spiral special fixture.
Background technology
At present common steel reinforcement cage forming machine spiral fixture used is as Fig. 1, that spiral is put in to sleeve, hold out against with the bolt on sleeve again, puller bolt termination acts directly on spiral surface, because spiral outer surface has two symmetrical straightedges and asymmetrical, the multiple crescent moon corner angle that are evenly arranged, puller bolt termination usually acts on corner angle or above straightedge, puller bolt, it between spiral and sleeve fixture, is some contact, easily producing relative sliding or spiral rotates, use boosting-rod to tight a bolt, forming machine can cause spiral twisting while rotation, very easily loosening, directly affect steel reinforcement cage Forming Quality, cause spiral location inaccurate, steel reinforcement cage is in aperture docking difficulty.And the easy loss of puller bolt, often change, operate time-consumingly, reliability, the economy of this fixture are all undesirable.
Summary of the invention
Technical problem to be solved by this invention is the technical deficiency to above-mentioned existence just, provide one to alleviate spiral wearing and tearing, need be by the only object that just can realize Quick-clamped spiral hand-manipulated of other force-multiplier tool, saving of work and time, economical spiral special fixture and assembly method reliably.
The technical solution adopted for the present invention to solve the technical problems is:
Spiral special fixture, it is characterized in that: the rotatable lock tube that includes a tubular, lock tube side is with opening, lock tube inside is provided with fixing lock core, and the side of lock core is also with opening, and at the opening part of lock core, lock core lining is installed, wherein the cross section of lock core lining is indent semi-circular structure, its size can be blocked spiral, and with multiple grooves, its groove structure is corresponding with spiral thread surface position; Described lock tube surface is inserted tie down screw is installed, and tie down screw can compress lock core through lock tube.
In such scheme, described lock core lining is embedded on lock core, with lock core be separable structure.
In such scheme, described plug face is provided with a circle chute along circumference, and the position of chute is just to tie down screw, for tie down screw clamping location.
In such scheme, the concave surface area of described lock core lining, is less than 1/2nd of spiral exterior surface area.
While using this fixture to carry out spiral assembling, carry out in accordance with the following steps:
The special fixture of making is fixed by bolts on reinforcing bar shaper pallet, replaces former fixture;
Select the lock core lining of corresponding fixture and be arranged on fixed lock core according to spiral diameter; The shape of working surface of fixture lock core lining is consistent with spiral external surface shape, when installation, only need to by the working face of lock core lining outwardly and aim at the corresponding indentation, there of lock core, when replacing, outwards choose from the joint portion of lock core lining and lock core with flat mouth screwdriver.
Rotatable opening lock tube is installed; By lock tube, Open Side Down, make tie down screw on lock tube face the direction of lock core lining working face, be stuck in from outside to inside the outer surface of lock core, and make tie down screw termination aim at the chute on lock core, rotate counterclockwise lock tube, make the termination of tie down screw enter the chute of lock core.Need to change opening lock tube time, only need to rotate lock tube, by it, Open Side Down, makes tie down screw face the working face direction of lock core lining, outwards extracts lock tube simultaneously.
Rotate lock tube, make its opening direction consistent with the opening direction of lock core lining, now the working face of lock core lining is outwardly open;
Put into spiral from the opening part of lock tube, make it have angle faceted pebble and lock core lining working face to be close to, rotate counterclockwise lock tube approximately 90 degree simultaneously, make lock tube and lock core lining wrap spiral completely, now turn clockwise, tighten tie down screw, eliminate as possible the gap between lock core lining, spiral and lock tube, reach the object that clamps spiral, reverse operating is detachably by folder spiral.
The operation principle of this special fixture is to make full use of spiral resemblance, make special, stressed working face and spiral have a consistent fixture lining of corner angle facial contour, make the working face area of lining be slightly less than the external surface area of 1/2 spiral, allow lining working face can and spiral outer surface two straightedges between, there is one side of something of angle rib to be close together, again the lock core lining being close together and spiral are put in sizeable lock tube, now two of spiral straightedges lean against lining outer ledge, its angle rib of being close to lining can enter in working face corresponding recesses, it between lock core lining and spiral, is face contact, just can not there is relative motion, reach the object of Quick-clamped spiral.Not only improve effect, and significantly promote steel reinforcement cage Forming Quality.
The present invention compared with similar products, has advantages of following main:
Apparatus of the present invention can alleviate spiral wearing and tearing, need be by the only objects that just can realize Quick-clamped spiral hand-manipulated of other force-multiplier tool, and saving of work and time, economical reliable.
Brief description of the drawings
Fig. 1 is embodiment of the present invention front view;
Fig. 2 is embodiment of the present invention left view;
Fig. 3 is embodiment of the present invention lock tube surface texture figure;
In figure: 1-tie down screw, 2-lock core erection support, 3-lock core lining, 4-lock core, 5-lock tube, 6-chute.
Detailed description of the invention
Below in conjunction with detailed description of the invention, the embodiment of the present invention is further described:
Referring to Fig. 1 to Fig. 3:
Spiral special fixture, include the rotatable lock tube 5 of a tubular, lock tube 5 sides are with opening, and lock tube 5 inside are provided with lock core 4, and lock core 4 is fixedly mounted on lock core erection support 2, the side of lock core 4 is also with opening, and at the opening part of lock core 4, lock core lining 3 is installed, and wherein the cross section of lock core lining 3 is indent semi-circular structure, its size can be blocked spiral, and with multiple grooves, its groove structure is corresponding with spiral thread surface position; Described lock tube 5 surfaces are inserted tie down screw 1 are installed, and tie down screw 1 can compress lock core 4 through lock tube 5.
In the present embodiment, described lock core lining 3 is embedded on lock core 4, with lock core 4 be separable structure.
In the present embodiment, described lock core 4 surfaces are provided with a circle chute 6 along circumference, and the position of chute 6 is just to tie down screw 1, for tie down screw 1 clamping location.
In the present embodiment, the indent semicircle surface area of described lock core lining 3, is less than 1/2nd of spiral exterior surface area.
While using this fixture to carry out spiral assembling, carry out in accordance with the following steps:
The special fixture of making is fixed by bolts on reinforcing bar shaper pallet, replaces former fixture;
Select the lock core lining of corresponding fixture and be arranged on fixed lock core according to spiral diameter; The shape of working surface of fixture lock core lining is consistent with spiral external surface shape, when installation, only need to by the working face of lock core lining outwardly and aim at the corresponding indentation, there of lock core, when replacing, outwards choose from the joint portion of lock core lining and lock core with flat mouth screwdriver.
Rotatable opening lock tube is installed; By lock tube, Open Side Down, make tie down screw on lock tube face the direction of lock core lining working face, be stuck in from outside to inside the outer surface of lock core, and make tie down screw termination aim at the chute on lock core, rotate counterclockwise lock tube, make the termination of tie down screw enter the chute of lock core.Need to change opening lock tube time, only need to rotate lock tube, by it, Open Side Down, makes tie down screw face the working face direction of lock core lining, outwards extracts lock tube simultaneously.
Rotate lock tube, make its opening direction consistent with the opening direction of lock core lining, now the working face of lock core lining is outwardly open;
Put into spiral from the opening part of lock tube, make it have angle faceted pebble and lock core lining working face to be close to, rotate counterclockwise lock tube approximately 90 degree simultaneously, make lock tube and lock core lining wrap spiral completely, now turn clockwise, tighten tie down screw, eliminate as possible the gap between lock core lining, spiral and lock tube, reach the object that clamps spiral, reverse operating is detachably by folder spiral.
Protection scope of the present invention is not limited to the above embodiments, and obviously, those skilled in the art can carry out various changes and distortion and not depart from the scope of the present invention and spirit the present invention.If these changes and distortion belong to the scope of the claims in the present invention and equivalent technologies thereof, the intent of the present invention also comprises these changes and is out of shape interior.

Claims (5)

1. spiral special fixture, it is characterized in that: the rotatable lock tube that includes a tubular, lock tube side is with opening, lock tube inside is provided with fixing lock core, and the side of lock core is also with opening, and at the opening part of lock core, lock core lining is installed, wherein the cross section of lock core lining is indent semi-circular structure, its size can be blocked spiral, and with multiple grooves, its groove structure is corresponding with spiral thread surface position; Described lock tube surface is inserted tie down screw is installed, and tie down screw can compress lock core through lock tube.
2. spiral special fixture as claimed in claim 1, is characterized in that: described lock core lining is embedded on lock core, with lock core be separable structure.
3. spiral special fixture as claimed in claim 1, is characterized in that: described plug face is provided with a circle chute along circumference, and the position of chute is just to tie down screw, for tie down screw clamping location.
4. spiral special fixture as claimed in claim 1 or 2, is characterized in that: the concave surface area of described lock core lining, is less than 1/2nd of spiral exterior surface area.
5. spiral special fixture assembly method, carry out in accordance with the following steps:
The special fixture of making is fixed by bolts on reinforcing bar shaper pallet, replaces former fixture;
Select the lock core lining of corresponding fixture and be arranged on fixed lock core according to spiral diameter; The shape of working surface of fixture lock core lining is consistent with spiral external surface shape, when installation, only need to by the working face of lock core lining outwardly and aim at the corresponding indentation, there of lock core, when replacing, outwards choose from the joint portion of lock core lining and lock core with flat mouth screwdriver;
Rotatable opening lock tube is installed; By lock tube, Open Side Down, make tie down screw on lock tube face the direction of lock core lining working face, be stuck in from outside to inside the outer surface of lock core, and make tie down screw termination aim at the chute on lock core, rotate counterclockwise lock tube, make the termination of tie down screw enter the chute of lock core.Need to change opening lock tube time, only need to rotate lock tube, by it, Open Side Down, makes tie down screw face the working face direction of lock core lining, outwards extracts lock tube simultaneously;
Rotate lock tube, make its opening direction consistent with the opening direction of lock core lining, now the working face of lock core lining is outwardly open;
Put into spiral from the opening part of lock tube, make it have angle faceted pebble and lock core lining working face to be close to, rotate counterclockwise lock tube approximately 90 degree simultaneously, make lock tube and lock core lining wrap spiral completely, now turn clockwise, tighten tie down screw, eliminate as possible the gap between lock core lining, spiral and lock tube, reach the object that clamps spiral, reverse operating is detachably by folder spiral.
CN201310325668.9A 2013-07-30 2013-07-30 Spiral special fixture and assembly method Active CN104029139B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310325668.9A CN104029139B (en) 2013-07-30 2013-07-30 Spiral special fixture and assembly method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310325668.9A CN104029139B (en) 2013-07-30 2013-07-30 Spiral special fixture and assembly method

Publications (2)

Publication Number Publication Date
CN104029139A true CN104029139A (en) 2014-09-10
CN104029139B CN104029139B (en) 2016-02-17

Family

ID=51460252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310325668.9A Active CN104029139B (en) 2013-07-30 2013-07-30 Spiral special fixture and assembly method

Country Status (1)

Country Link
CN (1) CN104029139B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106626052A (en) * 2017-02-24 2017-05-10 中民筑友科技投资有限公司 Pulling trolley for prestressed reinforcing steel bars and production line for prestressed prefabricated members
CN107639188A (en) * 2017-10-24 2018-01-30 成都明杰科技有限公司 A kind of clamp assemblies prefabricated for stake holes ground steel reinforcement cage
CN112524251A (en) * 2019-09-18 2021-03-19 上海善得新材料科技有限公司 Sealing strip with locking device and mounting method thereof
CN113510648A (en) * 2021-07-14 2021-10-19 本田动力(中国)有限公司 Jig for assembling and disassembling centrifugal gear of engine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2034496U (en) * 1988-01-29 1989-03-22 陕西省建筑科学研究所 Slide block damping type connecting jig for reinforcment pneumatic welding machine
US5138912A (en) * 1991-07-31 1992-08-18 Dyke Harold J Locking pipe wrench
US5542319A (en) * 1994-04-15 1996-08-06 Wei; Chen Adjustable rachet-style self-tightening wrench
CN2287654Y (en) * 1997-06-05 1998-08-12 中国建筑科学研究院建筑机械化研究所 Steel reinforcement looping connection joint with rib
US5832974A (en) * 1997-02-19 1998-11-10 Jou; Wuu-Cheau Versatile air blow-gun
CN203426894U (en) * 2013-07-30 2014-02-12 中国一冶集团有限公司 Special fixture for rebar

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2034496U (en) * 1988-01-29 1989-03-22 陕西省建筑科学研究所 Slide block damping type connecting jig for reinforcment pneumatic welding machine
US5138912A (en) * 1991-07-31 1992-08-18 Dyke Harold J Locking pipe wrench
US5542319A (en) * 1994-04-15 1996-08-06 Wei; Chen Adjustable rachet-style self-tightening wrench
US5832974A (en) * 1997-02-19 1998-11-10 Jou; Wuu-Cheau Versatile air blow-gun
CN2287654Y (en) * 1997-06-05 1998-08-12 中国建筑科学研究院建筑机械化研究所 Steel reinforcement looping connection joint with rib
CN203426894U (en) * 2013-07-30 2014-02-12 中国一冶集团有限公司 Special fixture for rebar

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106626052A (en) * 2017-02-24 2017-05-10 中民筑友科技投资有限公司 Pulling trolley for prestressed reinforcing steel bars and production line for prestressed prefabricated members
CN107639188A (en) * 2017-10-24 2018-01-30 成都明杰科技有限公司 A kind of clamp assemblies prefabricated for stake holes ground steel reinforcement cage
CN112524251A (en) * 2019-09-18 2021-03-19 上海善得新材料科技有限公司 Sealing strip with locking device and mounting method thereof
CN112524251B (en) * 2019-09-18 2022-10-25 上海善得新材料科技有限公司 Sealing strip with locking device and mounting method thereof
CN113510648A (en) * 2021-07-14 2021-10-19 本田动力(中国)有限公司 Jig for assembling and disassembling centrifugal gear of engine

Also Published As

Publication number Publication date
CN104029139B (en) 2016-02-17

Similar Documents

Publication Publication Date Title
CN104029139A (en) Special clamp for threaded rebar and assembling method
US20190176310A1 (en) Extractor socket with bidirectional driving capability and corresponding extraction set with intermediate sizes
CN203426894U (en) Special fixture for rebar
CN105945103A (en) Linkage forming mechanism for thin-wall pipe
CN105150149A (en) Adjustable type internal and external hexagonal wrench
CN105171672B (en) Steel wire threaded sleeve installation tool free of installation handles
CN205968834U (en) Mould end cap extracting tool
CN106112886A (en) A kind of little space screw thread pair Quick fastening device
CN205763145U (en) A kind of light-wall pipe linkage shaping mechanism
CN208409733U (en) A kind of hose screw cap sleeve
CN205734664U (en) Cementing concrete truck plunger installation special tool
CN206839975U (en) Expansion nut
CN107283152A (en) The pull bar and its assembly method of axle sleeve based on interference fit
CN205799319U (en) A kind of stopcock installs clamp structure
CN204976455U (en) Opening V type spanner
TWM543139U (en) Workbench locking tool
CN204258526U (en) Double-wing righting device of slide rail motor
CN107443280A (en) A kind of Multifunctional demountable spanner
CN203583785U (en) Connecting member
TWI579111B (en) Star screwdriver system
CN204094662U (en) Bolt jointing part
CN211103672U (en) Combined wrench for gas storage well mouth
CN204209000U (en) The curved mould adapter of a kind of bending machine
CN106272052A (en) A kind of grinding head
CN202659674U (en) Socket head cap screw

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant