CN103993828B CN201410094327.XA CN201410094327A CN103993828B CN 103993828 B CN103993828 B CN 103993828B CN 201410094327 A CN201410094327 A CN 201410094327A CN 103993828 B CN103993828 B CN 103993828B
Authority
CN
China
Prior art keywords
angle
section
increasing
transition
orientation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410094327.XA
Other languages
Chinese (zh)
Other versions
CN103993828A (en
Inventor
张良万
谢学明
游云武
宋金初
杨海平
王伟
吴雪平
方琴
黄军辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petrochemical Corp
Sinopec Oilfield Service Corp
Sinopec Jianghan Petroleum Engineering Co Ltd
Original Assignee
DRILLING WELL NO1 Co OF SINOPEC JIANGHAN PETROLEUM ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DRILLING WELL NO1 Co OF SINOPEC JIANGHAN PETROLEUM ENGINEERING Co Ltd filed Critical DRILLING WELL NO1 Co OF SINOPEC JIANGHAN PETROLEUM ENGINEERING Co Ltd
Priority to CN201410094327.XA priority Critical patent/CN103993828B/en
Publication of CN103993828A publication Critical patent/CN103993828A/en
Application granted granted Critical
Publication of CN103993828B publication Critical patent/CN103993828B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention provides a method of constructing a gradually-increased type transition circular curve well track. The method includes the steps of designing the well drilling track, wherein the small angle increasing rate is adopted between a transition section from a straight well section to an angle increasing section and a transition section from the angle increasing section to a horizontal section, the angle is gradually increased, and transition is smooth; then constructing a transition arc from the straight well section to the angle increasing section with a device angle compensation method, and gradually increasing the well deviation at the 5-8 degree/100 m angle increasing rate through a 30 m-50 m combination drill to form a smooth circular curve to enable the angle increasing section to be transited to the horizontal section. The method is applied to the gradually-increased type well drilling track, well drilling friction and torque can be reduced to the maximum degree, the sliding capacity of the drill can be improved, drill blocking and breaking accidents can be reduced, and the service life of the drill can be prolonged.

Description

Slow increasing formula excessive circular curve well track construction method
Technical field
The present invention relates to petroleum drilling engineering technical field, more particularly, to a kind of slow increasing formula excessive circular curve well rail Mark construction method.
Background technology
The production of oil gas, for example oily gentle, have been carried out many years.For producing these oil gas, in oil field, flatly or many Mouth well is generally drilled to underground position, and it is commonly referred to as subterranean strata or underground basin.Produce the side of oil gas from underground position Method generally includes each development phase from Scheme Choice stage to production phase.One of development phase includes drillng operation, its Form underground position to the fluid path of earth's surface.Drillng operation may include using different equipment, for example Hydraulic Power System, drill bit, Motor etc., it is used for being drilled into target depth.
At present, conventional horizontal well mostly presses " straight-increasing-horizontal segment " three sections of section constructions processed, in straight well section and increasing hole angle section, There is obvious flex point, rate of over-all angle change is larger, and well track is unsmooth, and drag and torque is larger between increasing hole angle section and horizontal segment, Enter difficulty under sleeve pipe and completion tool, drill string is susceptible to Helical Buckling, lead to bit freezing drillling tool twisting off accident to occur, make casing deformation Or damage.
Content of the invention
The technical problem to be solved is just to above-mentioned technical deficiency, provides one kind to be applied to slow increasing formula Wellbore trace, can reduce drilling well frictional resistance and moment of torsion to greatest extent, increase the slip ability of drilling tool, can reduce the bit freezing breaking of rod again Tool accident occurs, and improves the slow increasing formula excessive circular curve well track construction method of the service life of drilling tool.
The technical solution adopted for the present invention to solve the technical problems is:
Slow increasing formula excessive circular curve well track construction method, includes following process:
Carry out the design of wellbore trace first, in " straight well section to increasing hole angle section, increasing hole angle section are to horizontal segment " this two transitions Between, using less rate of increase of angle, slow increasing hole angle is gently excessive, and the hole deviation before changeover portion and orientation are continuously adjusted To in designed path, define the oblique of " vertical curve and circular arc line smooth tangent " and " circular arc line is tangent with horizontal line " Face circular curve well track.
For first vertical curve and circular arc line smooth tangent in excessive circular line, from straight well section excessively to increasing hole angle section, Strictly control tool face angle, adopt " tool face angle penalty method ", 90-110m before initial orientation, to make less than design (less) Slope orientation construction, takes slip directional drilling 5-10m, rotates composite drill 10-20m, slowly cumulative mode, to reduce hole deviation side Position rate of change, makes transition well track smooth.After hole deviation reaches 15~20 °, then return to original design build angle rate construction.
For the Article 2 circular arc line and horizontal line excessive circular line in tangent, from increasing hole angle section excessively to horizontal segment, due to Hole angle now is general to take the composite drill of 30~50m all at 70~75 ° about, is delayed with 5-8 °/100m rate of increase of angle and increases hole deviation Form a smooth arc curved transition to horizontal segment.
In such scheme, described tool face angle increases orientation in i quadrant increasing hole angle, increases orientation in quadrant drop angle, as Limit drop angle subtracts orientation, subtracts orientation in iv quadrant increasing hole angle, with the change of tool face angle, reaches increasing hole angle, drop angle, increasing hole angle variable-azimuth, fall The tiltedly purpose of variable-azimuth.Deflecting in three-dimensional horizontal well, from straight well section excessively to increasing hole angle section, when Borehole Azimuth off-design, Increasing hole angle is carried out with turning round orientation simultaneously, and because hole angle and azimuth are all being continually changing at any time, the tool face angle being previously set also exists It is continually changing.
The construction method of above 2 transition curves, can make transition well track smooth, reduce drag and torque, reduce Side force, improves the handling capacity of tubing string and survey tool, avoids to greatest extent and be susceptible to Helical Buckling at 2 flex points Lead to drillling tool twisting off and tubing string to damage, enter to create favorable conditions under the safety being later stage completion tubular column.
The main beneficial effect of the present invention is:
The inventive method can reduce drilling well frictional resistance and moment of torsion to greatest extent, increase the slip ability of drilling tool, can subtract again Few bit freezing drillling tool twisting off accident occurs, and improves the service life of drilling tool.
Brief description
Fig. 1 is embodiment of the present invention wellbore trace profile;
In figure: 1 straight well section, 2 increasing hole angle sections, 3 horizontal segments, 4 first excessive circular lines, 5 second excessive circular lines.
Specific embodiment
With reference to specific embodiment, the embodiment of the present invention is further described:
Slow increasing formula excessive circular curve well track construction method, includes following process:
Carry out the design of wellbore trace first, as shown in Figure 1 " straight well section 1 arrives increasing hole angle section 2, increasing hole angle section 2 arrives horizontal segment 3 " Between this two transitions, using less rate of increase of angle, slow increasing hole angle is gently excessive, and the hole deviation before changeover portion and orientation are connected Continue and be constantly adjusted in designed path, define one " vertical curve and circular arc line smooth tangent " and " circular arc line and a water Horizontal line is tangent " the circular arc with inclined plane well track.
For vertical curve and circular arc line smooth tangent in the first excessive circular line 4, from straight well section excessively to increasing hole angle section, sternly Lattice control tool face angle, according to the tool face angle w of any point on the inclined-plane circular arc that professor Han Zhiyong derivesiComputing formula:
Increase orientation in formula and take " " number, subtract orientation and take " ten " number.
Can be seen that from formula, the tool face angle of inclined-plane circular arc is as hole angle and azimuthal change and changes, and wants Holding meanss angle constant it is necessary at any time adjust tool-face, adopt " tool face angle penalty method ", 100m before initial orientation, to be less than Design (less) build angle rate orientation construction, takes slip directional drilling 10m, rotates composite drill 20m, slowly cumulative mode, with Reduce direction of deflection rate of change, so that transition well track is smoothed.After hole deviation reaches 20 °, then return to original design deflecting Rate is constructed.
For circular arc line and horizontal line the second excessive circular line 5 in tangent, from increasing hole angle section excessively to horizontal segment, due to this When hole angle general take the composite drill of 40m all at 70~75 ° about, delayed with 8 °/100m rate of increase of angle and increase hole deviation and form one Smooth arc curved transition is to horizontal segment.
In the present embodiment, described tool face angle i quadrant increasing hole angle increase orientation, quadrant drop angle increase orientation, as Limit drop angle subtracts orientation, subtracts orientation in iv quadrant increasing hole angle, with the change of tool face angle, reaches increasing hole angle, drop angle, increasing hole angle variable-azimuth, fall The tiltedly purpose of variable-azimuth.Deflecting in three-dimensional horizontal well, from straight well section excessively to increasing hole angle section, when Borehole Azimuth off-design, Increasing hole angle is carried out with turning round orientation simultaneously, and because hole angle and azimuth are all being continually changing at any time, the tool face angle being previously set also exists It is continually changing.
The construction method of above 2 transition curves, can make transition well track smooth, reduce drag and torque, reduce Side force, improves the handling capacity of tubing string and survey tool, avoids to greatest extent and be susceptible to Helical Buckling at 2 flex points Lead to drillling tool twisting off and tubing string to damage, enter to create favorable conditions under the safety being later stage completion tubular column.
Protection scope of the present invention is not limited to the above embodiments it is clear that those skilled in the art can be to this Bright carry out various change and deformation without deviating from scope and spirit of the present invention.If these are changed and deformation belongs to present invention power In the range of profit requirement and its equivalent technologies, then the intent of the present invention also comprises these changes and deforms.

Claims (2)

1. delay increasing formula transition arc curve well track construction method, include following process:
Carry out the design of wellbore trace first, between straight well section to increasing hole angle section, this two changeover portions of increasing hole angle section to horizontal segment, adopt Use less rate of increase of angle, slow increasing hole angle gentle transition, the hole deviation before changeover portion and orientation are continuously adjusted to design In track, form vertical curve and circular arc line smooths tangent, and the circular arc with inclined plane that a circular arc line is tangent with horizontal line Well track;
For first vertical curve and circular arc line smooth tangent in transition circle camber line, be transitioned into increasing hole angle section from straight well section, strictly Control tool face angle, using tool face angle penalty method, 90-110m before initial orientation, less than design build angle rate orientation construction, to adopt Take slip directional drilling 5-10m, rotate composite drill 10-20m, slowly cumulative mode, to reduce direction of deflection rate of change, make transition Section well track smooths, and after hole deviation reaches 15~20 °, then returns to original design build angle rate construction;
For the Article 2 circular arc line and horizontal line transition circle camber line in tangent, it is transitioned into horizontal segment from increasing hole angle section, take 30~ The composite drill of 50m, delays increasing hole deviation one smooth arc of formation with 5-8 °/100m rate of increase of angle and curves into horizontal segment.
2. as claimed in claim 1 delay increasing formula transition arc curve well track construction method it is characterised in that: described dress Angle setting increases orientation in i quadrant increasing hole angle, increases orientation in quadrant drop angle, subtracts orientation in quadrant drop angle, in the iv quadrant increasing hole angle side of subtracting Position.
CN201410094327.XA 2014-03-14 2014-03-14 Method of constructing gradually-increased type transition circular curve well track Active CN103993828B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410094327.XA CN103993828B (en) 2014-03-14 2014-03-14 Method of constructing gradually-increased type transition circular curve well track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410094327.XA CN103993828B (en) 2014-03-14 2014-03-14 Method of constructing gradually-increased type transition circular curve well track

Publications (2)

Publication Number Publication Date
CN103993828A CN103993828A (en) 2014-08-20
CN103993828B true CN103993828B (en) 2017-01-25

Family

ID=51308136

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410094327.XA Active CN103993828B (en) 2014-03-14 2014-03-14 Method of constructing gradually-increased type transition circular curve well track

Country Status (1)

Country Link
CN (1) CN103993828B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104747165B (en) * 2015-01-27 2017-06-13 中国石油天然气股份有限公司 Three-dimensional horizontal well body profile design method
CN107882505B (en) * 2016-09-28 2019-08-20 中国石油化工股份有限公司 Track control method based on steering drilling tool working characteristics
CN109138985B (en) * 2017-06-26 2021-11-02 中国石油天然气股份有限公司 Method and device for determining full-angle change rate of pipeline directional drilling crossing track
CN107762411B (en) * 2017-12-05 2019-03-01 重庆科技学院 Continuous pipe well drilling rail method for correcting error
CN112100796B (en) * 2019-06-18 2024-05-28 中国石油天然气集团有限公司 Drilling track determination method and device for preventing casing in shale gas well from being damaged

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101832105A (en) * 2010-04-28 2010-09-15 李孝勇 Method for well drilling and cementing of radial horizontal well with ultra-short radius and equipment thereof
RU2421586C1 (en) * 2009-12-14 2011-06-20 Общество с ограниченной ответственностью "УПРАВЛЯЮЩАЯ КОМПАНИЯ "Татбурнефть" ООО "УК "Татбурнефть" Procedure for construction of horizontal well in devonian strata

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2270907C1 (en) * 2004-07-26 2006-02-27 ОАО НПО "Буровая техника" Method for directed well drilling along smooth path

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2421586C1 (en) * 2009-12-14 2011-06-20 Общество с ограниченной ответственностью "УПРАВЛЯЮЩАЯ КОМПАНИЯ "Татбурнефть" ООО "УК "Татбурнефть" Procedure for construction of horizontal well in devonian strata
CN101832105A (en) * 2010-04-28 2010-09-15 李孝勇 Method for well drilling and cementing of radial horizontal well with ultra-short radius and equipment thereof

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
三维Z形斜面圆弧井眼轨迹控制技术;王伟;《石油钻采工艺》;20070815;第29卷(第4期);第10-12页 *
开口等边三角形内切圆弧水平井的轨迹控制;谢学明等;《江汉石油科技》;20101225;第20卷(第4期);第36-39页 *
斜面圆弧形井眼的轨迹控制新模式;韩志勇;《石油钻探技术》;20040325;第32卷(第2期);第1-3页 *
浅层大位移水平井轨迹控制技术;王伟;《钻采工艺》;20130125;第36卷(第1期);第15-17、21页 *

Also Published As

Publication number Publication date
CN103993828A (en) 2014-08-20

Similar Documents

Publication Publication Date Title
CN103993828B (en) Method of constructing gradually-increased type transition circular curve well track
CN104481398B (en) A kind of three-dimensional horizontal well drilling construction method
CN104265270B (en) A kind of carbonate rock fractured cave wellbore trace design and control method
CN102691477B (en) Rock debris cleaning device for drilling tool
CN104790918B (en) Method for mining coal bed gas from cluster well and horizontal well combined ground under complex terrain condition
CN104747165B (en) Three-dimensional horizontal well body profile design method
CN103437704A (en) Backup directional rotary steering drilling device
CN103867180B (en) A kind of coal bed gas horizontal well method for controlling trajectory
CN203335054U (en) Multi-branch horizontal well system suitable for coalbed methane of syncline structure
CN103899349A (en) Coal seam gas extraction method and extraction hole radial drilling guide device
CN112081528A (en) Horizontal section efficient support-free oscillating drilling tool combination and method
CN103422813B (en) Individual well eye multi-lateral horizontal well system for coal bed gas and boring method
CN107060642B (en) Wellbore trajectory control method for natural alkali deep thin layer multi-connected horizontal well
CN104343424A (en) Coalbed-methane horizontal-well PE (poly ethylene) screen pipe well completion application process method
CN203383731U (en) Push pointing type rotary guide well drilling device
CN203822156U (en) Deviation-adjustable rotary drilling device
CN103510855B (en) A kind of horizontal well logging guide track optimization method
CN103993829B (en) Apart from the middle major radius track of horizontal well before the little target of a kind of two dimension
CN103924958A (en) Coal bed gas multi-branch horizontal well applicable to syncline structures
CN105625944B (en) Drilling method for sidetracking horizontal well with same diameter as original well shaft
CN103485719B (en) A kind of gas water horizontal well drilling rig structure
CN105201436B (en) The method of high-pressure hose is sent into using narrow gap high-velocity fluid drag
CN107178356A (en) A kind of multi-branched horizontal well bores completion method and multi-branched horizontal well
CN204126612U (en) For horizontal well bottom cycle gravel pack pressure of return water control tool
CN104818977A (en) Single-well parallel crack water injection and oil extraction method of offshore low-permeability reservoir

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200710

Address after: 100027 Beijing, Chaoyangmen, North Street, No. 22, No.

Co-patentee after: SINOPEC OILFIELD SERVICE Corp.

Patentee after: SINOPEC Group

Co-patentee after: SINOPEC JIANGHAN OILFIELD SERVICE Corp.

Address before: 433121 No. 57 Xianfeng Road, Guanghua office, Qianjiang, Hubei 1

Patentee before: NO.1 DRILLING WELL COMPANY OF SINOPEC JIANGHAN PETROLEUM ENGINEERING Co.,Ltd.

TR01 Transfer of patent right