CN103986165B - Refining load control method and system in electric system - Google Patents

Refining load control method and system in electric system Download PDF

Info

Publication number
CN103986165B
CN103986165B CN201410232513.5A CN201410232513A CN103986165B CN 103986165 B CN103986165 B CN 103986165B CN 201410232513 A CN201410232513 A CN 201410232513A CN 103986165 B CN103986165 B CN 103986165B
Authority
CN
China
Prior art keywords
load
control
rank
regulation
signal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410232513.5A
Other languages
Chinese (zh)
Other versions
CN103986165A (en
Inventor
莫光玲
苏伟
刘智勇
王文银
何勃兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Energy-Conservation Science And Technology Ltd Is Passed Through In Shanghai Thousand
Guangzhou electric power design institute
Original Assignee
Energy-Conservation Science And Technology Ltd Is Passed Through In Shanghai Thousand
Guangzhou electric power design institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Energy-Conservation Science And Technology Ltd Is Passed Through In Shanghai Thousand, Guangzhou electric power design institute filed Critical Energy-Conservation Science And Technology Ltd Is Passed Through In Shanghai Thousand
Priority to CN201410232513.5A priority Critical patent/CN103986165B/en
Publication of CN103986165A publication Critical patent/CN103986165A/en
Application granted granted Critical
Publication of CN103986165B publication Critical patent/CN103986165B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention provides a refining load control method in an electric system. The method comprises the steps that a control center detects a load capacity needing to be adjusted by a user group at present; the control center obtains the standby capacity of a power utilization device in a user terminal and the preset load regulating and controlling level; the control center calculates the adjustable and controllable load of different load regulating and controlling levels in the user group according to the standby capacity of the power utilization device and the preset load regulating and controlling level; the control center generates and sends a load regulating and controlling signal to the user terminal according to the load capacity needing to be adjusted by the user group at present and the adjustable and controllable loads of the different load regulating and controlling levels of the user group, wherein the load regulating and controlling comprises the current regulating and controlling level and the regulating and controlling proportion; the user terminal receives the load regulating and controlling signal, and the load of the power utilization device is adjusted according to the current load regulating and controlling level and the regulating and controlling proportion. The invention further provides a corresponding system. The processing burden of the electric system can be greatly reduced, and the load regulating and controlling speed is improved.

Description

Load Precise control method and system in power system
Technical field
The present invention relates to power system computation field, particularly relate to a kind of load Precise control method in power system, and load Precise control system in a kind of power system.
Background technology
When wholesale power market price raises or system reliability is compromised, after power consumer receives the direct compensation notice or power price rising signals that inductivity that supplier of electricity sends reduces load, the custom power mode that it is intrinsic need be changed, reach and reduce or pass the power load of certain period and respond supply of electric power, thus the guarantee stabilization of power grids, and electricity price is suppressed to rise.
It is predicted, about the year two thousand twenty Analyzing Total Electricity Consumption will reach 7.7 trillion kilowatt hours, peak load will reach 12.7 hundred million kilowatts.If power supply can implement the load control of effect, then at least can realize economize on electricity 5% and reduce peak load 5%, at least can reduce electric power to the year two thousand twenty and install 1.3 hundred million kilowatts, Generation Side average load rate at least improves about 4 percentage points, gross coal consumption rate 8.4 grams/kilowatt hour can be reduced, thus standard coal can be saved every year be about fifty-five million ton; Electricity consumption side power consumption efficiency improves 5 percentage points, then generated energy about 4,000 hundred million kilowatt hour can be lacked in the whole nation when the time comes, is equivalent to reduce by about 1.3 hundred million tons of standard coal consumption in.Therefore visible, supplier of electricity implements load control by the very considerable energy-saving and emission-reduction of generation and social benefit to power consumer.
Conventional art can divide incident classification the ratio causing electrical network to subtract for load usually.Such as, for the province of load more than 2,000 ten thousand kilowatts, autonomous region's electrical network, subtract for load less than more than 13% 30%, then form major accident; Subtract for load more than 30%, then form special major accident.At present, China's single extra-high voltage alternating current-direct current power transmission engineering transmission capacity is comparatively large, and such as, the specified transmission power of bright and beautiful Su Zhiliu reaches 7,200,000 kilowatts, and Changzhi-Nanyang-Jingmen specified transmission power of extra-high-voltage alternating current demonstration project reaches 5,000,000 kilowatts.Before extra-high voltage alternating current-direct current transmission of electricity forms network structure, after single UHV transmission channel failure, amphidromic stream transfering channel, causes greater impact to two ends electrical network, unavoidably causes the machine of cutting of larger proportion, the consequence of cutting load.
At present, because power consumer quantity is very huge, amount of calculation and the processing load of power system load regulation and control are very large, and processing speed is slow, the cutting load device of electric power system stability control system is generally arranged on 110kV and above transformer station, draws and stop outlet switch during cutting load, has the feature of " a black a slice ", the mode of load control belongs to extensive, cannot satisfy the demands.
Summary of the invention
Based on this, the invention provides load Precise control method and system in a kind of power system, significantly can reduce the processing load of power system, improve load control speed.
A kind of load Precise control method in power system, comprises the steps:
The load that active user group need adjust detects in control centre; Wherein, described customer group comprises multiple user side, and described user side comprises multiple stage electrical appliance;
The spare capacity that control centre obtains electrical appliance described in described user side and the load control rank preset;
Control centre, according to the spare capacity of described electrical appliance and described load control rank, calculates the controllable load of different load regulation and control rank in described customer group;
In the load that control centre need adjust according to described active user group and described customer group, the controllable load of different load regulation and control rank, generates load control signal and also sends to described user side; Wherein, described load control signal comprises this regulation and control rank and regulation and control ratio;
Described user side receives described load control signal, adjusts the load of described electrical appliance according to this load control rank described and regulation and control ratio.
Load Precise control system in a kind of power system, comprise control centre and customer group, described customer group comprises multiple user side, and described user side comprises multiple stage electrical appliance:
Described control centre comprises detection module, for detecting the load that active user group need adjust;
Described control centre comprises acquisition module, for obtaining the spare capacity of electrical appliance described in described user side and default load control rank;
Described control centre comprises computing module, for according to the spare capacity of electrical appliance described in described user side and the load control rank preset, calculates the controllable load of described customer group different load regulation and control rank;
Described control centre comprises sending module, for the controllable load according to different load regulation and control rank in the load needing in described active user group to adjust and described customer group, generates load control signal and sends to described user side; Wherein, described load control signal comprises this regulation and control rank and regulation and control ratio;
Described user side, for receiving described load control signal, adjusts the load of described electrical appliance according to this load control rank described and regulation and control ratio.
Load Precise control method and system in above-mentioned power system, the load that active user group need adjust detects in control centre, and the spare capacity obtaining electrical appliance described in user side and the load control rank preset, calculate the controllable load of different load regulation and control rank in customer group, then regeneration load control signal is broadcast to each user side; User side then adjusts the load of described electrical appliance according to this load control rank in load control signal and regulation and control ratio; Thus significantly reducing the amount of calculation of control centre, the present invention is easy to expansion, is a kind of load control method of non-intrusion type, and the compatible multiple electrical appliance of energy, can realize the regulation and control that become more meticulous of load.
Accompanying drawing explanation
Fig. 1 is load Precise control method schematic flow sheet in one embodiment in power system of the present invention.
Fig. 2 is the schematic diagram of load Precise control method load control signal in one embodiment in power system of the present invention.
Fig. 3 is the load Precise control method schematic diagram of the electrical appliance that different load regulation and control rank is corresponding in user side in one embodiment in power system of the present invention.
Fig. 4 is load Precise control system structural representation in one embodiment in power system of the present invention.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing, the present invention is described in further detail, but embodiments of the present invention are not limited thereto.
As shown in Figure 1, be the schematic flow sheet of load Precise control method in power system of the present invention, comprise the steps:
S11, control centre detect the load that active user group need adjust; Wherein, described customer group comprises multiple user side, and described user side comprises multiple stage electrical appliance;
S12, control centre obtain the spare capacity of electrical appliance described in described user side and default load control rank;
S13, control centre, according to the spare capacity of described electrical appliance and described load control rank, calculate the controllable load of different load regulation and control rank in described customer group;
In the load that S14, control centre need adjust according to described active user group and described customer group, the controllable load of different load regulation and control rank, generates load control signal and also sends to described user side; Wherein, described load control signal comprises this regulation and control rank and regulation and control ratio;
S15, described user side receive described load control signal, adjust the load of described electrical appliance according to this load control rank described and regulation and control ratio;
In the present embodiment, first control centre obtains the load that active user group need regulate and control; Described customer group comprises the multiple user sides be connected with control centre, and each user side connects multiple stage electrical appliance, and electrical appliance can comprise air-conditioning, desk lamp, water dispenser, TV, charger etc.
Control centre also from each user side obtain connect each user side each described in the spare capacity of electrical appliance and the load control rank preset corresponding to described electrical appliance;
The load control rank of the present embodiment can be used for distinguishing the state of current electric grid and the participation of electrical equipment participation load control, thus makes: the electrical equipment 1) being applicable to participating in load control, first participates in load control, run with making the less energy consumption of electrical network; 2) be not suitable for long-term but can the short time, a small amount of electrical equipment participating in load control, only participate in response when electrical network is badly in need of reducing load, thus ensure power grid security, stable operation.The load control rank of user side by presetting, allows electrical equipment to participate in load control with the different degree of depth, makes participation form more flexible.
Such as, load control rank can comprise 4 ranks as shown in the table, also can expand on this basis according to actual needs:
The hierarchical relationship of relative size is there is between load control rank, the relation of 4 ranks described in upper table never participates in for the < of participation < peak load participation at any time promptly participates in <, each rank has corresponding level identification, be followed successively by 0,1,2, N/A; " never participate in " rank owing to not participating in load control, therefore the present embodiment is follow-up can not consider when adding up load.
Next, control centre is according to the spare capacity of described electrical appliance and described load control rank, the controllable load of different load regulation and control rank in customer group described in statistical computation, afterwards again in conjunction with the load that described active user group need adjust, generate load control signal and send to described user side;
Control centre receives the spare capacity of its each electrical appliance prestored that each user side sends and load control rank corresponding to this default electrical appliance and adds up, thus obtain total spare capacity corresponding to whole customer group different load regulation and control rank, then generate load control signal according to following methods:
Make l=l 0, Q = Q d ( 1 ) ;
Wherein, l 0for minimum load control rank, for the controllable load that load control rank l is corresponding;
If Q>=Δ Q t, then determine that this regulation and control rank described is l;
If Q < Δ Q t, then make l=l+1, if l is rank maximum in load control rank, then determine that this regulation and control rank described is l;
Wherein, l=l+1 represents increases a rank by current load control rank; Δ Q tfor the load that described active user group need adjust;
After determining this regulation and control rank, regulation and control ratio can be calculated further; In the load that need be able to adjust according to described active user group, described customer group, different load regulates and controls the controllable load of rank and this regulation and control rank described, is calculated by following formula:
r signal = &Delta;Q t - &Sigma; l = 1 l signal - 1 Q d ( l ) Q d ( l signal ) ;
Wherein, r signalfor described regulation and control ratio, l signalfor this regulation and control rank described, l signalcurrent load control rank is reduced by a rank by-1 expression.
Load control signal comprises this load control rank and regulation and control ratio two data; The generation of load control signal, by reasonable distribution, can reduce the size of load control signal, thus improves the efficiency issuing load control signal, reduces the workload to a large number of users end broadcast load control signal.
In the present embodiment, load control signal can use this load control rank of 2 byte representations and regulation and control ratio, and in the present embodiment, load control rank can comprise 3 grades, utilizes 4 binary systems to represent [0,7] integer in interval, is enough to represent load control rank; Remaining 12 for recording regulation and control ratio, expression scope is the regulation and control ratio of 0 ~ 212-1; Therefore, regulation and control ratio also needs to carry out sliding-model control, is calculated by following formula:
k=round((2 n-1)×r signal);
Wherein, k is the regulation and control ratio after described sliding-model control, and n is default number of bits.
Such as, when control centre is according to the instruction of supplier of electricity, detect when need reduce 10000W load, according to statistical computation, obtain 3 load control ranks in customer group: participation level (0) corresponding spare capacity is 8502W at any time, peak load participation level (1) corresponding spare capacity is 10220W, and urgent participation level (2) corresponding spare capacity is 7018W;
Then this regulation and control rank is determined:
(1) l=0 is established,
(2) if Q>=Δ Q t, then perform step (4), otherwise continue to perform step (3).
(3) l=l+1, return step (2); If l overloads, the maximum of regulation and control rank, then direct by l signal=l exports.
(4) these regulation and control rank l is determined signal=l;
After determining this regulation and control rank, calculate regulation and control ratio further; Calculate by following formula:
r signal = &Delta;Q t - &Sigma; l = 1 l signal - 1 Q d ( l ) Q d ( l signal ) ;
According to above-mentioned steps, this regulation and control rank in the present embodiment is:
l signal=1
r signal = &Delta; Q t - Q d ( 0 ) Q d ( 1 ) = 10000 - 8502 10220 = 0.1465753425
After will regulating and controlling inverse discrete, can obtain:
k = round ( ( 2 n - 1 ) &times; 10000 - 8502 10220 ) = 600
According to the load control signal format of the present embodiment, the load control signal of generation can be as shown in Figure 2.
User side receives described load control signal, reads out this regulation and control rank and regulation and control ratio, carry out load control to each electrical appliance from described load control signal; As shown in Figure 3, be the schematic diagram that in user side, different load regulates and controls electrical appliance corresponding to rank;
Because regulation and control ratio is through sliding-model control, the regulation and control ratio of sliding-model control need be normalized by user side:
r signal = k 2 n - 1 = k 2 12 - 1 = 2.441 &times; 10 - 4 k , k = 0,1 , . . . , 4095 .
Concrete, the step how user side regulates and controls each electrical appliance according to described load control signal is as follows:
User side receives load control signal (l signal, r signal) after, all default regulating strategies being superior to this load control rank all can not perform, and all default regulating strategies lower than this load control rank all can perform, the strategy that grade is just equal with this load control rank, can according to r signalwith specific strategy consequence, optionally perform, load control signal is a positive integer, r signal∈ [0,4095].
User side carries out load control according to load control signal, and load control process is specific as follows:
Each user side obtains the spare capacity of each electrical equipment under each load control rank:
Q id ( l ) = Q is ( l ) , l = 0 max { Q is ( l ) - Q is ( l - 1 ) , 0 } , l > 0 ;
Wherein, l is described load control rank, and i is described electrical appliance, for the actual spare capacity of electrical appliance i under load control rank l, for the maximum spare capacity of electrical appliance i under load control rank l;
Each user side obtains the summation of the spare capacity of each electrical appliance under each load control rank, generates total spare capacity of each load control rank; Each user side receives load control signal, and according to the total spare capacity under the load control signal received and each load control rank, obtains the load control strategy of the power consumption of electrical appliance corresponding to each user side of regulation and control; According to described load control strategy, what regulate and control electrical equipment corresponding to each user side uses electricity condition;
User side receives load control signal, and electricity condition of using corresponding for the load control rank lower than described load class is used electricity condition as pending; According to total spare capacity of described regulation and control ratio and the load control rank identical with described load class, generate the load control strategy corresponding with described load class, concrete according to the spare capacity in load control signal, regulation and control ratio and can to solve as drag, obtain the xj of each electricity condition, generate the load control strategy corresponding with described load class:
max &Delta;Q d ( l signal ) = &Sigma; j = 1 m &Delta;Q js ( l signal ) x j
s . t . &Delta;Q d ( l signal ) &le; r signal &CenterDot; Q d ( l signal ) &Sigma; j &Element; S i x j &Element; { 0,1 } x j &Element; { 0,1 }
Wherein, j is for using electricity condition, l signalfor this load control rank described, γ signalfor the regulation and control ratio in described load control signal, for the total amount of the spare capacity of each electrical appliance after regulation and control, for with electricity condition j at described load class l signalunder spare capacity, for the total spare capacity under the load control rank identical with described load class, x jfor performing mark, S for identifying whether with electricity condition j ifor the electricity consumption state set of electrical appliance i.
As shown in Figure 4, be the structural representation of load Precise control system in a kind of power system of the present invention, comprise control centre 41 and customer group 42, described customer group comprises multiple user side 421, and described user side comprises multiple stage electrical appliance:
Described control centre comprises detection module 411, for detecting the load that active user group need adjust;
Described control centre comprises acquisition module 412, for obtaining the spare capacity of electrical appliance described in described user side and default load control rank;
Described control centre comprises computing module 413, for according to the spare capacity of electrical appliance described in described user side and the load control rank preset, calculates the controllable load of different load regulation and control rank in described customer group;
Described control centre comprises sending module 414, for the controllable load of the load that need adjust according to described active user group and described customer group different load regulation and control rank, generates load control signal and also sends to described user side; Wherein, described load control signal comprises this regulation and control rank and regulation and control ratio;
Described user side 421, for receiving described load control signal, adjusts the load of described electrical appliance according to this load control rank described and regulation and control ratio;
In the present embodiment, first control centre obtains the load that active user group need regulate and control; Described customer group comprises the multiple user sides be connected with control centre, and each user side connects multiple stage electrical appliance, and electrical appliance can comprise air-conditioning, desk lamp, water dispenser, TV, charger etc.
Control centre also from each user side obtain connect each user side each described in the spare capacity of electrical appliance and the load control rank preset corresponding to described electrical appliance;
The load control rank of the present embodiment can be used for distinguishing the state of current electric grid and the participation of electrical equipment participation load control, thus makes: the electrical equipment 1) being applicable to participating in load control, first participates in load control, run with making the less energy consumption of electrical network; 2) be not suitable for long-term but can the short time, a small amount of electrical equipment participating in load control, only participate in response when electrical network is badly in need of reducing load, thus ensure power grid security, stable operation.The load control rank of user side by presetting, allows electrical equipment to participate in load control with the different degree of depth, makes participation form more flexible.
Such as, load control rank can comprise 4 ranks as shown in the table, also can expand on this basis according to actual needs:
There is the hierarchical relationship of relative size between load control rank, the relation of 4 ranks described in upper table never participates in for the < of participation < peak load participation at any time promptly participates in <; Never participation level is not owing to participating in load control, and therefore the present embodiment can follow-uply can not considered when adding up load.
Next, control centre is according to the spare capacity of described electrical appliance and described load control rank, the controllable load of customer group different load regulation and control rank described in statistical computation, afterwards again in conjunction with the load that described active user group need adjust, generate load control signal and send to described user side;
Control centre receives the spare capacity of its each electrical appliance prestored that each user side sends and load control rank corresponding to this default electrical appliance and adds up, thus obtain total spare capacity corresponding to whole customer group different load regulation and control rank, generate load control signal:
Make l=l 0, Q = Q d ( 1 ) ;
Wherein, l 0for minimum load control rank, for the controllable load that load control rank l is corresponding;
If Q>=Δ Q t, then determine that this regulation and control rank described is l;
If Q < Δ Q t, then make l=l+1, if l is rank maximum in load control rank, then determine that this regulation and control rank described is l;
Wherein, l=l+1 represents increases a rank by current load control rank; Δ Q tfor the load that described active user group need adjust;
After determining this regulation and control rank, calculate regulation and control ratio further; Calculate by following formula:
r signal = &Delta;Q t - &Sigma; l = 1 l signal - 1 Q d ( l ) Q d ( l signal ) ;
Wherein, r signalfor described regulation and control ratio, l signalfor this regulation and control rank described, l signalcurrent load control rank is reduced by a rank by-1 expression.
Load control signal comprises this load control rank and regulation and control ratio two data; The generation of load control signal, by reasonable distribution, can reduce the size of load control signal, thus improves the efficiency issuing load control signal, reduces the workload to a large number of users end broadcast load control signal.
Load control signal can use this load control rank of 2 byte representations and regulation and control ratio, and in the present embodiment, load control rank can comprise 3 grades, utilizes 4 binary systems can represent integer in [0,7] interval, is enough to represent load control rank; Remaining 12 for recording regulation and control ratio, expression scope is the regulation and control ratio of 0 ~ 212-1; Therefore, regulation and control ratio also needs to carry out sliding-model control, is calculated by following formula:
k=round((2 n-1)×r signal);
Wherein, k is the regulation and control ratio after described sliding-model control, and n is default number of bits.
User side receives described load control signal, reads out this regulation and control rank and regulation and control ratio, carry out load control to each electrical appliance from described load control signal.
Because regulation and control ratio is through sliding-model control, the regulation and control ratio of sliding-model control need be normalized by user side:
r signal = k 2 n - 1 = k 2 12 - 1 = 2.441 &times; 10 - 4 k , k = 0,1 , . . . , 4095 .
Concrete, user side also can be used for:
User side receives load control signal (l signal, r signal) after, all default regulating strategies being superior to this load control rank all can not perform, and all default regulating strategies lower than this load control rank all can perform, the strategy that grade is just equal with this load control rank, can according to r signalwith specific strategy consequence, optionally perform, load control signal is a positive integer, r signal∈ [0,4095].User side carries out load control according to load control signal.
Load Precise control method and system in power system of the present invention, the load that active user group need adjust detects in control centre, and the spare capacity obtaining electrical appliance described in user side and the load control rank preset, calculate the controllable load of different load regulation and control rank in customer group, then regeneration load control signal is broadcast to each user side; User side then adjusts the load of described electrical appliance according to this load control rank in load control signal and regulation and control ratio; Thus significantly reducing the amount of calculation of control centre, the present invention is easy to expansion, is a kind of load control method of non-intrusion type, and the compatible multiple electrical appliance of energy, can realize the regulation and control that become more meticulous of load.
The above embodiment only have expressed several embodiment of the present invention, and it describes comparatively concrete and detailed, but therefore can not be interpreted as the restriction to the scope of the claims of the present invention.It should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.

Claims (4)

1. a load Precise control method in power system, is characterized in that, comprise the steps:
The load that active user group need adjust detects in control centre; Wherein, described customer group comprises multiple user side, and described user side comprises multiple stage electrical appliance;
The spare capacity that control centre obtains electrical appliance described in described user side and the load control rank preset;
Control centre, according to the spare capacity of described electrical appliance and described load control rank, calculates the controllable load of different load regulation and control rank in described customer group;
In the load that control centre need adjust according to described active user group and described customer group, the controllable load of different load regulation and control rank, generates load control signal and also sends to described user side; Wherein, described load control signal comprises this regulation and control rank and regulation and control ratio;
Described user side receives described load control signal, adjusts the load of described electrical appliance according to this regulation and control rank described and regulation and control ratio;
Wherein, the controllable load of different load regulation and control rank in the load that described control centre need adjust according to described active user group and described customer group, generates load control signal and also sends to the step of described user side to comprise:
Make l=l 0, Q = Q d ( l ) ;
Wherein, l 0for minimum load control rank, for the controllable load that load control rank l is corresponding;
If Q>=Δ Q t, then determine that this regulation and control rank described is l;
If Q < Δ Q t, then make l=l+1, if l is rank maximum in load control rank, then determine that this regulation and control rank described is l;
Wherein, l=l+1 represents increases a rank by current load control rank; Δ Q tfor the load that described active user group need adjust.
2. load Precise control method in power system according to claim 1, it is characterized in that, the controllable load of different load regulation and control rank in the load that described control centre need adjust according to described active user group and described customer group, generates load control signal and also sends to the step of described user side to comprise:
The controllable load of different load regulation and control rank and this regulation and control rank described in the load that need adjust according to described active user group, described customer group, calculate described regulation and control ratio by following formula:
r signal = &Delta; Q t - &Sigma; l = 1 l signal - 1 Q d ( l ) Q d ( l signal )
Wherein, r signalfor described regulation and control ratio, l signalfor this regulation and control rank described, l signalcurrent load control rank is reduced by a rank by-1 expression.
3. a load Precise control system in power system, is characterized in that, comprise control centre and customer group, described customer group comprises multiple user side, and described user side comprises multiple stage electrical appliance:
Described control centre comprises detection module, for detecting the load that active user group need adjust;
Described control centre comprises acquisition module, for obtaining the spare capacity of electrical appliance described in described user side and default load control rank;
Described control centre comprises computing module, for according to the spare capacity of electrical appliance described in described user side and the load control rank preset, calculates the controllable load of described customer group different load regulation and control rank;
Described control centre comprises sending module, for the controllable load according to different load regulation and control rank in the load needing in described active user group to adjust and described customer group, generates load control signal and sends to described user side; Wherein, described load control signal comprises this regulation and control rank and regulation and control ratio;
Described user side, for receiving described load control signal, adjusts the load of described electrical appliance according to this regulation and control rank described and regulation and control ratio;
Wherein, described sending module also for:
Make l=l 0, Q = Q d ( l ) ;
Wherein, l 0for minimum load control rank, for the controllable load that load control rank l is corresponding;
If Q < Δ Q t, then make l=l+1, if Q>=Δ Q t, then determine that this regulation and control rank described is l;
Wherein, l=l+1 represents increases a grade by load control rank; Δ Q tfor the load that described active user group need adjust.
4. load Precise control system in power system according to claim 3, is characterized in that, described sending module also for:
The controllable load of different load regulation and control rank and this regulation and control rank described in the load that need adjust according to described active user group, described customer group, calculate described regulation and control ratio by following formula:
r signal = &Delta; Q t - &Sigma; l = 1 l signal - 1 Q d ( l ) Q d ( l signal )
Wherein, r signalfor described regulation and control ratio, l signalfor this regulation and control rank described.
CN201410232513.5A 2014-05-28 2014-05-28 Refining load control method and system in electric system Active CN103986165B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410232513.5A CN103986165B (en) 2014-05-28 2014-05-28 Refining load control method and system in electric system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410232513.5A CN103986165B (en) 2014-05-28 2014-05-28 Refining load control method and system in electric system

Publications (2)

Publication Number Publication Date
CN103986165A CN103986165A (en) 2014-08-13
CN103986165B true CN103986165B (en) 2015-03-25

Family

ID=51278033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410232513.5A Active CN103986165B (en) 2014-05-28 2014-05-28 Refining load control method and system in electric system

Country Status (1)

Country Link
CN (1) CN103986165B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104331849B (en) * 2014-11-13 2017-05-17 重庆大学 Electrical power system risk ranking method and application
CN106877343A (en) * 2017-04-27 2017-06-20 相舆科技(上海)有限公司 Without node type real-time electric power management configuration method and system
CN107104331B (en) * 2017-06-06 2019-07-09 山东大学 Intelligent socket and its working method with cutting load function
CN107679694B (en) * 2017-09-04 2021-06-04 佛山佳牧乐科技有限公司 Electric power regulation and control method and device
CN110233480B (en) * 2019-06-14 2023-03-31 国网山东省电力公司平阴县供电公司 Load regulation and control method and system for power system
CN113437748A (en) * 2021-06-21 2021-09-24 国网山东省电力公司泗水县供电公司 Load regulation and control method and system for power system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102522783A (en) * 2012-01-17 2012-06-27 刘忠菁 Multi-user automatic-negotiation non-synchronization micro-grid scheduling system and method
CN202856352U (en) * 2012-10-15 2013-04-03 武汉大学 Intelligent cell dynamic-alternation load shedding control system
CN103532142A (en) * 2013-10-24 2014-01-22 广州电力设计院 Refined and stable control method and system of electric system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102522783A (en) * 2012-01-17 2012-06-27 刘忠菁 Multi-user automatic-negotiation non-synchronization micro-grid scheduling system and method
CN202856352U (en) * 2012-10-15 2013-04-03 武汉大学 Intelligent cell dynamic-alternation load shedding control system
CN103532142A (en) * 2013-10-24 2014-01-22 广州电力设计院 Refined and stable control method and system of electric system

Also Published As

Publication number Publication date
CN103986165A (en) 2014-08-13

Similar Documents

Publication Publication Date Title
CN103986165B (en) Refining load control method and system in electric system
Ding et al. Control of hybrid AC/DC microgrid under islanding operational conditions
CN103545814B (en) Coordinated voltage control method for alternating-current and direct-current hybrid power system
CN110198030B (en) Direct-current emergency coordination control method considering photovoltaic power generation power rapid regulation and control
CN103647283A (en) Solar power grid and municipal power grid no-countercurrent combination power supply control system and method thereof
CN205011850U (en) Hot balance control device of aluminium cell
CN103997035A (en) Power transformer and line economic operation closed loop control system and method
CN102638037A (en) Power supply control method and power supply control system of communication equipment as well as power supply system
Wang et al. Voltage prevention and emergency coordinated control strategy for photovoltaic power plants considering reactive power allocation
CN103543678B (en) A kind of controller of configurable demand on power demand side
CN103746377B (en) Based on the detection method of the voltage power-less sensitivity that integration maps
CN103023041A (en) Active/reactive power control system of intelligent wind power station
CN103683267B (en) Different DC line power support capacity distribution method in a kind of many direct current systems
CN204144950U (en) A kind of compensation program control circuit on-load voltage regulation system
CN208508526U (en) A kind of electricity supply and use equipment behavior management system
Zhibing et al. Coordinated control strategy of reactive power for large‐scale wind power transmission by LCC‐HVDC links
CN104158194A (en) Voltage stability control method using direct current inverter station as dynamic reactive power source
CN103997037B (en) For the load control method and system of electric power system
CN104882903B (en) A kind of duty control method for stabilizing distributed power source fluctuation
Khederzadeh Frequency control of microgrids by demand response
CN204334379U (en) The V/f-with hysteretic characteristic falls down vertical microgrid inverter power supply
Pollock et al. Overcoming the issues associated with operating a distribution system in reverse power flow
CN104882892A (en) Demand side response method based on voltage regulation
CN106099959A (en) A kind of three-phase imbalance based on cloud platform regulation system
CN110661268B (en) Dynamic reactive power compensation requirement determining method and system for new energy collection station

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant