CN103912704B - Gas Pressure Regulating Equipment and pressure regulation method - Google Patents

Gas Pressure Regulating Equipment and pressure regulation method Download PDF

Info

Publication number
CN103912704B
CN103912704B CN201410114258.4A CN201410114258A CN103912704B CN 103912704 B CN103912704 B CN 103912704B CN 201410114258 A CN201410114258 A CN 201410114258A CN 103912704 B CN103912704 B CN 103912704B
Authority
CN
China
Prior art keywords
pressure
switch valve
valve
preset
gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410114258.4A
Other languages
Chinese (zh)
Other versions
CN103912704A (en
Inventor
张飞飞
徐箭
张瑞丽
胡石磊
童国芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI FIORENTINI GAS EQUIPMENT CO Ltd
Original Assignee
SHANGHAI FIORENTINI GAS EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI FIORENTINI GAS EQUIPMENT CO Ltd filed Critical SHANGHAI FIORENTINI GAS EQUIPMENT CO Ltd
Priority to CN201410114258.4A priority Critical patent/CN103912704B/en
Publication of CN103912704A publication Critical patent/CN103912704A/en
Application granted granted Critical
Publication of CN103912704B publication Critical patent/CN103912704B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17DPIPE-LINE SYSTEMS; PIPE-LINES
    • F17D3/00Arrangements for supervising or controlling working operations
    • F17D3/01Arrangements for supervising or controlling working operations for controlling, signalling, or supervising the conveyance of a product
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17DPIPE-LINE SYSTEMS; PIPE-LINES
    • F17D1/00Pipe-line systems
    • F17D1/02Pipe-line systems for gases or vapours

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Control Of Fluid Pressure (AREA)

Abstract

A kind of Gas Pressure Regulating Equipment, including pressure regulator, the first switch valve, preregulator and pilot valve.Pressure regulator has upper chamber, lower chamber, inlet plenum and discharge chamber.Pilot valve has epicoele, lumen and cavity of resorption.First switch valve has the first air inlet, the first gas outlet, the first ratio pressure mouth and the first setting spring, and first sets spring for setting the first preset pressure.First air inlet, the first ratio pressure mouth are communicated to inlet plenum, and the first gas outlet is communicated to preregulator, and preregulator is respectively communicated to epicoele and lumen, epicoele is communicated to downstream pipe, downstream pipe is connected with discharge chamber, and lumen is communicated to lower chamber, and upper chamber is communicated to downstream pipe.Additionally, additionally provide the pressure regulation method of a kind of Gas Pressure Regulating Equipment.Above-mentioned Gas Pressure Regulating Equipment and pressure regulation method, it is to avoid the hypertonia or too low of upstream gas ductwork, relative timing supplies, to the adjustment of upstream gas ductwork pressure relatively in time, accurately, and, the cost of relatively remote control transmission & distribution gas puts into relatively low.

Description

Gas Pressure Regulating Equipment and pressure regulation method
Technical field
The present invention relates to gas transmission and distribution field, particularly relate to a kind of gas pressure regulating for regulating distribution pressure Device and pressure regulation method.
Background technology
For the operation of urban pipe network, the pressure stability in pipe network is most important, and hypotony can affect Use makings amount, and hypertonia can cause potential safety hazard.Resident's cooking and hot water for life, and public clothes Business user etc. has a biggest lack of uniformity with gas, therefore gas-fueled vehicles, distributed combined heat and power generation and thermoelectric cold Coproduction user, in city gas is applied, more act as the role of city gas pipe network peak regulation user, with Reduce the pressure of gas-use low peak phase gas ductwork, eliminate safe hidden trouble.But, in actual applications, due to Peak regulation user is not adopted an effective measure, cause there is peak regulation user with resident and public clothes with gas peak period Business user robs the situation of gas or gas-use low peak phase peak regulation user does not use combustion gas to cause the pressure of gas ductwork Too high situation, to pipe network with makings amount with cause safely considerable influence with gas.
Gas Pressure Regulating Equipment is the important component part in gas transmission and distribution field.But, traditional gas pressure regulating dress Put, be only capable of under normal circumstances realizing the adjustment to outlet pressure, be i.e. only capable of realizing the combustion of Gas Pressure Regulating Equipment downstream The regulation of gas pipe network pressure, it is difficult to realize the adjustment to inlet pressure, Gas Pressure Regulating Equipment upstream gas ductwork Hypertonia or too low situation easily occur.Development along with gas transmission and distribution technology, although can be by right Timing supply or the long-range transmission & distribution gas that controls of peak regulation user carry out the pressure of regulating gas pipe network, but, due to combustion Gas user uses the time of combustion gas can follow without rule accurately with consumption, pressure regulation not in time, inaccurate, and remote Process control transmission & distribution gas relatively costly, is unfavorable for promoting the use of.
Summary of the invention
Based on this, it is necessary to pressure mistake easily occurs in the upstream gas ductwork for traditional Gas Pressure Regulating Equipment High or too low, regularly pressure regulation for gas supply not in time, inaccurate, and remotely control relatively costly the asking of transmission & distribution gas Topic, it is provided that upstream pipe network gaseous-pressure can be adjusted by one, pressure regulation is timely, accurate, and cost is relatively Low Gas Pressure Regulating Equipment.
A kind of Gas Pressure Regulating Equipment, including pressure regulator, the first switch valve, preregulator and pilot valve,
Described pressure regulator has upper chamber, lower chamber, epithelium, inlet plenum, discharge chamber, the described air inlet of connection The valve port of room and described discharge chamber and spool, described epithelium splits described upper chamber and described lower chamber, Described spool is connected with described epithelium, and follows described epithelium action, with valve port described on and off;
Described pilot valve has epicoele, lumen and cavity of resorption, described first switch valve have the first air inlet, first Gas outlet, the first ratio pressure mouth and first set spring, and described first setting spring is used for setting described first and opens Close the first preset pressure that valve is opened, set when the pressure of described first ratio pressure mouth sets spring more than described first During fixed first preset pressure, described first switch valve is opened, and described first air inlet is given vent to anger with described first Mouth conducting;
Described first air inlet, described first ratio pressure mouth are communicated to described inlet plenum, and described first gas outlet is even Passing to described preregulator, described preregulator is respectively communicated to described epicoele and described lumen, and described epicoele connects To downstream pipe, described downstream pipe is connected with described discharge chamber, and described lumen is communicated to described lower chamber, Described upper chamber is communicated to described downstream pipe.
Wherein in an embodiment, also include that second switch valve, described second switch valve have the second air inlet Mouth, the second gas outlet, the second ratio pressure mouth and second set spring, and described second sets spring is used for setting institute State the second preset pressure that second switch valve is opened, set more than described second than the pressure of pressure mouth when described second When determining the second preset pressure that spring sets, described second switch valve is opened, and described second air inlet is with described Second gas outlet conducting;Described second air inlet is communicated to described inlet plenum, and described second than pressing mouth with described Second gas outlet is respectively communicated to described preregulator, and described first preset pressure is more than described second preset pressure.
Wherein in an embodiment, described pressure regulator is inefficacy normally closed type pressure regulator, and described pilot valve was for losing efficacy Normally closed type pilot valve, described first switch valve and second switch valve are inefficacy closing type switch valve.
Wherein in an embodiment, described pilot valve also has the adjusting screw rod for arranging pilot valve preset pressure, Second preset pressure of described second switch valve is more than described pilot valve preset pressure.
Wherein in an embodiment, also include that manual switch valve, one end of described manual switch valve are connected to Described inlet plenum, the other end is connected to described preregulator.
Wherein in an embodiment, also include that exhaust switch valve, described first gas outlet are communicated to described row One end of exhaust switch valve, the other end of described exhaust switch valve is unsettled.
Additionally, additionally provide the pressure regulation method of a kind of Gas Pressure Regulating Equipment.
A kind of pressure regulation method according to Gas Pressure Regulating Equipment described above, comprises the following steps,
Obtain the first preset pressure of user preset;
Judge whether first be more than described first preset pressure than the pressure of pressure mouth;
The most described first switch valve is opened, and the pressure of the inlet plenum of pressure regulator is successively via described first Switch valve, preregulator enter the lower chamber of described pressure regulator with pilot valve, drive to remove on epithelium band movable valve plug and open Valve port, the inlet plenum of described pressure regulator turns on discharge chamber, supplies downstream pipe;
If it is not, the most described first switch valve cuts out.
Wherein in an embodiment, judging that described first is more than the described first default pressure than the pressure of pressure mouth Power, after described first switch valve is opened, further comprising the steps of,
Obtain the second preset pressure of user preset;
Judge whether second be more than described second preset pressure than the pressure of pressure mouth;
The most described second switch valve is opened, and the pressure of the inlet plenum of pressure regulator is respectively via described first Switch valve merges after described second switch valve, and enters described pressure regulator via preregulator after pilot valve successively Lower chamber, drive to remove on epithelium band movable valve plug and open valve port;
If it is not, the most described second switch valve cuts out, the pressure of the inlet plenum of pressure regulator is via described first switch Valve, preregulator enter the lower chamber of described pressure regulator with pilot valve, drive to remove on epithelium band movable valve plug and open valve port.
Wherein in an embodiment, judging that described first is less than the described first default pressure than the pressure of pressure mouth Power, after described first switch valve cuts out, further comprising the steps of,
Obtain the second preset pressure of user preset;
Judge whether second be more than described second preset pressure than the pressure of pressure mouth;
The most described second switch valve is opened, and the pressure of the inlet plenum of pressure regulator is successively via described second Enter the lower chamber of described pressure regulator after switch valve, preregulator and pilot valve, drive and remove on epithelium band movable valve plug Open valve port;
If it is not, the most described second switch valve cuts out, described valve port is closed, and described pressure regulator stops Downstream pipe is supplied.
Above-mentioned Gas Pressure Regulating Equipment and pressure regulation method are relatively big, i.e. in upstream at upstream gas ductwork pressure When pressure is more than the first preset pressure, the spool of pressure regulator is opened, and valve port turns on, and supplies for downstream pipe, Alleviate the pressure of upstream gas ductwork, it is to avoid the hypertonia of upstream gas ductwork;In upstream Gas Pipe The pressure of net is less, and i.e. when the pressure of upstream is less than the first preset pressure, the spool of pressure regulator keeps Close, stop supplying for downstream pipe, contribute to maintaining stablizing of upstream gas ductwork pressure, it is to avoid on The pressure of trip gas ductwork is too small.The present invention sets first by the first setting spring of the first switch valve and presets Pressure, compares than pressure and first preset pressure of pressure mouth detection pressure regulator inlet plenum by first, and Adjust the pressure of upstream gas ductwork according to comparative result, thus keep stablizing of upstream gas ductwork pressure, Relative timing supplies, and the adjustment to upstream gas ductwork pressure is relatively timely, accurate, and, relatively remote control The cost of transmission & distribution gas processed puts into relatively low.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of the Gas Pressure Regulating Equipment of an embodiment;
Fig. 2 is the flow chart of the pressure regulation method of the Gas Pressure Regulating Equipment of an embodiment;
Fig. 3 is the flow chart of the pressure regulation method of the Gas Pressure Regulating Equipment of another embodiment;
Fig. 4 is the flow chart of the pressure regulation method of the Gas Pressure Regulating Equipment of further embodiment.
Detailed description of the invention
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.
As it is shown in figure 1, in one embodiment, a kind of Gas Pressure Regulating Equipment, including pressure regulator 110, first Switch valve 120, preregulator 130 and pilot valve 140.
Pressure regulator 110 has upper chamber, lower chamber, epithelium, inlet plenum, discharge chamber, connection inlet plenum and goes out The valve port of air chamber and spool, epithelium segmentation upper chamber and lower chamber, spool is connected with epithelium, and follows Epithelium action, with on and off valve port.Pressure regulator 110 is inefficacy normally closed type pressure regulator.
Pilot valve 140 has epicoele, lumen and cavity of resorption, the first switch valve 120 have the first air inlet, first Gas outlet, the first ratio pressure mouth and first set spring, and first sets spring for setting the first switch valve 120 First preset pressure of unlatching, presets more than the first of the first setting spring setting than the pressure of pressure mouth when first During pressure, the first switch valve 120 is opened, the first air inlet and the conducting of the first gas outlet.Pilot valve 140 also has There is the adjusting screw rod for arranging pilot valve 140 preset pressure.Pilot valve 140 is inefficacy normally closed type pilot valve.First Switch valve 120 is inefficacy closing type switch valve.
First air inlet, the first ratio pressure mouth are communicated to inlet plenum, and the first gas outlet is communicated to preregulator 130, in advance Adjusting device 130 to be respectively communicated to epicoele and lumen, epicoele is communicated to downstream pipe, downstream pipe and discharge chamber phase Connection, lumen is communicated to lower chamber, and upper chamber is communicated to downstream pipe.
Above-mentioned Gas Pressure Regulating Equipment is relatively big at upstream gas ductwork pressure, i.e. at upstream pressure more than the During one preset pressure, the spool of pressure regulator 110 is opened, and valve port turns on, and supplies for downstream pipe, alleviates The pressure of upstream gas ductwork, it is to avoid the hypertonia of upstream gas ductwork;Pressure at upstream gas ductwork Power is less, and i.e. when the pressure of upstream is less than the first preset pressure, the spool of pressure regulator 110 keeps closing Close, stop supplying for downstream pipe, contribute to maintaining the stablizing of upstream gas ductwork pressure, it is to avoid upstream The pressure of gas ductwork is too small.It is pre-that the present invention sets first by the first setting spring of the first switch valve 120 If pressure, compare than pressure and first preset pressure of pressure mouth detection pressure regulator 110 inlet plenum by first Relatively, and adjust the pressure of upstream gas ductwork according to comparative result, thus keep upstream gas ductwork pressure Stable, relative timing supplies, and the adjustment to upstream gas ductwork pressure is relatively timely, accurate, and, relatively The cost remotely controlling transmission & distribution gas puts into relatively low.
In the particular embodiment, Gas Pressure Regulating Equipment also includes second switch valve 150.Second switch valve 150 Having the second air inlet, the second gas outlet, the second ratio pressure mouth and the second setting spring, second sets spring uses In setting the second preset pressure that second switch valve 150 is opened, set more than second than the pressure of pressure mouth when second When determining the second preset pressure that spring sets, second switch valve 150 is opened, and the second air inlet and second is given vent to anger Mouth conducting;Second air inlet is communicated to inlet plenum, and second is respectively communicated to presetting than pressure mouth and the second gas outlet Device 130, the first preset pressure is more than the second preset pressure.Second switch valve 150 is inefficacy closing type switch valve, Second preset pressure of second switch valve 150 is more than pilot valve 140 preset pressure.
When the pressure of upstream gas ductwork is more than the first preset pressure, first is more than first than the pressure of pressure mouth During preset pressure, the first switch valve 120 is opened, and meanwhile, second is more than second than the pressure of pressure mouth presets pressure Power, second switch valve 150 opens, and two switch valves are opened, and accelerate the tune to upstream gas ductwork pressure Whole speed.When the pressure of upstream gas ductwork drops to below the first preset pressure, first than the pressure pressing mouth Power is less than the first preset pressure, and the first switch valve 120 cuts out, but now the second ratio presses the pressure of mouth still More than the second preset pressure, therefore second switch valve 150 allows and is in opening, and single switch valve is opened, Slow down and upstream gas ductwork pressure is regulated the speed, contribute to making upstream gas ductwork pressure enter as early as possible Steady statue, avoids upstream gas ductwork pressure when the critical point of the first preset pressure simultaneously, and first opens The vibration of pressure regulator 110 spool that the open and close repeatedly of pass valve 120 causes.It addition, in upstream Gas Pipe When the pressure of net drops to below the first preset pressure and is higher than the second preset pressure, second switch valve 150 is opened Opening, the pressure of the second air inlet of second switch valve 150, the pressure of the second gas outlet and second are than pressure mouth Pressure is identical, until the pressure of upstream gas ductwork drops to below the second preset pressure, second switch valve 150 Closing, the spool slowly closing of pressure regulator 110, the second gas outlet of second switch valve 150 is pressed with the second ratio Mouthful rapid pressure drop to below the second preset pressure, the unlatching repeatedly of second switch valve 150 will not be produced Close.
In the particular embodiment, Gas Pressure Regulating Equipment also includes manual switch valve 160 and exhaust switch valve 170, One end of manual switch valve is connected to inlet plenum, and the other end is connected to preregulator 130.First gas outlet is communicated to One end of exhaust switch valve 170, the other end of exhaust switch valve 170 is unsettled.Manual switch valve 160 and row Exhaust switch valve 170 is for installing the debugging at initial stage and follow-up maintenance and repair.
Additionally, additionally provide the pressure regulation method of a kind of Gas Pressure Regulating Equipment.
As shown in Fig. 2, Fig. 3 and Fig. 4, in one embodiment, the pressure regulation method of a kind of Gas Pressure Regulating Equipment, Use above-mentioned Gas Pressure Regulating Equipment to carry out pressure regulation, comprise the following steps,
Step S210, obtains the first preset pressure of user preset.Generally, staff is by the first switch First setting spring of valve 120 carries out the setting of the first preset pressure, and it is pre-that the first switch valve 120 obtains first If after pressure, compare, subsequently into step S220 than the pressure of pressure mouth with first.
Step S220, it is judged that whether first be more than the first preset pressure than the pressure of pressure mouth.Owing to first than pressure Mouth is communicated to the inlet plenum of pressure regulator 110, and the inlet plenum of pressure regulator 110 is connected with upstream gas ductwork, Successively, the pressure of the first ratio pressure mouth is the pressure of upstream gas ductwork.If first is more than than the pressure of pressure mouth First preset pressure, then enter step S230.
Step S230, the first switch valve 120 opens, and the pressure of the inlet plenum of pressure regulator 110 is successively via One switch valve 120, preregulator 130 and pilot valve 140 enter the lower chamber of pressure regulator 110, drive epithelium to drive Removing on spool and open valve port, the inlet plenum of pressure regulator 110 turns on discharge chamber, supplies downstream pipe.If First is less than the first preset pressure than the pressure of pressure mouth, then the first switch valve 120 cuts out.
Relatively big at upstream gas ductwork pressure, when upstream pressure is more than the first preset pressure, pressure regulator 110 Spool open, supply for downstream pipe, alleviate the pressure of upstream gas ductwork, it is to avoid upstream combustion gas The hypertonia of pipe network;Less at the pressure of upstream gas ductwork, the pressure of upstream is preset less than first During pressure, the spool of pressure regulator 110 remains turned-off, and stops supplying for downstream pipe, contributes to maintaining upstream Stablizing of gas ductwork pressure, it is to avoid the pressure of upstream gas ductwork is too small.Relative timing supplies, to upper The adjustment of trip gas ductwork pressure is relatively timely, accurate, and, the cost of relatively remote control transmission & distribution gas puts into Relatively low.
In the particular embodiment, judging that first is more than the first preset pressure than the pressure of pressure mouth, first opens It is after closing valve 120 unlatching, further comprising the steps of,
Step S310, obtains the second preset pressure preset.Generally, staff passes through second switch valve 120 The second setting spring carry out the setting of the first preset pressure, second switch valve 120 obtains the second preset pressure After, compare, subsequently into step S320 than the pressure of pressure mouth with second.
Step S320, it is judged that whether second be more than the second preset pressure than the pressure of pressure mouth.The most then enter Step S330;If it is not, then enter step S340.
Step S330, second switch valve 150 opens, and the pressure of the inlet plenum of pressure regulator 110 is respectively via One switch valve 120 merges after second switch valve 150, and successively via after preregulator 130 and pilot valve 140 Enter the lower chamber of pressure regulator 110, drive to remove on epithelium band movable valve plug and open valve port, entering of pressure regulator 110 Air chamber turns on discharge chamber, supplies downstream pipe.
Step S340, second switch valve 150 cuts out, and the pressure of the inlet plenum of pressure regulator 110 is opened via first Close valve 120, preregulator 130 and pilot valve 140 and enter the lower chamber of pressure regulator 110, drive epithelium band movable valve plug On remove and open valve port, the inlet plenum of pressure regulator 110 turns on discharge chamber, supplies downstream pipe.
Certainly, in practice, if arranging the first preset pressure more than the second preset pressure, due to the One is more than the first preset pressure than the pressure of pressure mouth, after the first switch valve 120 is opened, and the pressure of the second ratio pressure mouth Power is the ratio pressure of pressure mouth equal to first, and therefore the pressure of the second specific pressure is more than the second preset pressure, therefore exists First preset pressure, more than in the case of the second preset pressure, only exists the situation that second switch valve 150 is opened.
When the pressure of upstream gas ductwork is more than the first preset pressure, first is more than first than the pressure of pressure mouth During preset pressure, the first switch valve 120 is opened, and meanwhile, second is more than second than the pressure of pressure mouth presets pressure Power, second switch valve 150 opens, and two switch valves are opened, and accelerate the tune to upstream gas ductwork pressure Whole speed.
In the particular embodiment, judging that first is less than the first preset pressure than the pressure of pressure mouth, first opens It is after closing valve 120 closedown, further comprising the steps of,
Step S410, obtains the second preset pressure preset.
Step S420, it is judged that whether second be more than the second preset pressure than the pressure of pressure mouth.The most then enter Step S430;If it is not, then enter step S440.
Step S430, second switch valve 150 opens, and the pressure of the inlet plenum of pressure regulator 110 is successively via Enter the lower chamber of pressure regulator 110 after two switch valves 150, preregulator 130 and pilot valve 140, drive epithelium band Removing on movable valve plug and open valve port, the inlet plenum of pressure regulator 110 turns on discharge chamber, supplies downstream pipe.
Step S440, then second switch valve 150 cuts out, and valve port is closed, and pressure regulator 110 stops Downstream pipe is supplied.
When the pressure of upstream gas ductwork drops to below the first preset pressure, first is less than the pressure of pressure mouth In the first preset pressure, the first switch valve 120 cuts out, but now second than pressure mouth pressure still above Second preset pressure, therefore second switch valve 150 allows and is in opening, and single switch valve is opened, and slows down Upstream gas ductwork pressure regulated the speed, contributes to making upstream gas ductwork pressure enter as early as possible stable State, avoids upstream gas ductwork pressure when the critical point of the first preset pressure, the first switch valve simultaneously The vibration of pressure regulator 110 spool that the open and close repeatedly of 120 causes.It addition, in the pressure of upstream gas ductwork When power drops to below the first preset pressure and is higher than the second preset pressure, second switch valve 150 is opened, the The pressure of the second air inlet of two switch valves 150, the pressure of the second gas outlet and second are than the pressure phase of pressure mouth With, until the pressure of upstream gas ductwork drops to below the second preset pressure, second switch valve 150 cuts out, The spool slowly closing of pressure regulator 110, the pressure of mouth is pressed with the second ratio in the second gas outlet of second switch valve 150 Power is dropped rapidly to below the second preset pressure, will not produce the open and close repeatedly of second switch valve 150.
Above-mentioned Gas Pressure Regulating Equipment and pressure regulation method, be mountable to the upstream of the gas ductwork of peak regulation user, With the pressure of gas peak period gas ductwork less time stop to peak regulation user supply, it is ensured that the supply of other users Quality;Start when the pressure of gas-use low peak phase gas ductwork is bigger, to adjusting user's supply, to contribute to alleviating The pressure of gas ductwork, it is to avoid the pressure of gas ductwork excessive.
Embodiment described above only have expressed the several embodiments of the present invention, and it describes more concrete and detailed, But therefore can not be interpreted as the restriction to the scope of the claims of the present invention.It should be pointed out that, for this area Those of ordinary skill for, without departing from the inventive concept of the premise, it is also possible to make some deformation and Improving, these broadly fall into protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be with appended Claim is as the criterion.

Claims (5)

1. a Gas Pressure Regulating Equipment, it is characterised in that include pressure regulator, the first switch valve, preregulator with Pilot valve,
Described pressure regulator has upper chamber, lower chamber, epithelium, inlet plenum, discharge chamber, the described air inlet of connection The valve port of room and described discharge chamber and spool, described epithelium splits described upper chamber and described lower chamber, Described spool is connected with described epithelium, and follows described epithelium action, with valve port described on and off;
Described pilot valve has epicoele, lumen and cavity of resorption, described first switch valve have the first air inlet, first Gas outlet, the first ratio pressure mouth and first set spring, and described first setting spring is used for setting described first and opens Close the first preset pressure that valve is opened, set when the pressure of described first ratio pressure mouth sets spring more than described first During fixed first preset pressure, described first switch valve is opened, and described first air inlet is given vent to anger with described first Mouth conducting;
Described first air inlet, described first ratio pressure mouth are communicated to described inlet plenum, and described first gas outlet is even Passing to described preregulator, described preregulator is respectively communicated to described epicoele and described lumen, and described epicoele connects To downstream pipe, described downstream pipe is connected with described discharge chamber, and described lumen is communicated to described lower chamber, Described upper chamber is communicated to described downstream pipe;
Also include second switch valve, described second switch valve have the second air inlet, the second gas outlet, second Setting spring than pressure mouth with second, described second sets spring for setting the of described second switch valve unlatching Two preset pressure, preset more than the second of described second setting spring setting than the pressure of pressure mouth when described second During pressure, described second switch valve is opened, described second air inlet and described second gas outlet conducting;Described Second air inlet is communicated to described inlet plenum, and described second is respectively communicated to described second gas outlet than pressure mouth Described preregulator, described first preset pressure is more than described second preset pressure.
Gas Pressure Regulating Equipment the most according to claim 1, it is characterised in that described pressure regulator was for losing efficacy Normally closed type pressure regulator, described pilot valve is inefficacy normally closed type pilot valve, and described first switch valve and second switch valve are Inefficacy closing type switch valve.
Gas Pressure Regulating Equipment the most according to claim 1, it is characterised in that described pilot valve also has use In arranging the adjusting screw rod of pilot valve preset pressure, the second preset pressure of described second switch valve be more than described in lead Valve preset pressure.
4. the pressure regulation method of a Gas Pressure Regulating Equipment as claimed in claim 1, it is characterised in that include Following steps,
Obtain the first preset pressure of user preset;
Judge whether first be more than described first preset pressure than the pressure of pressure mouth;
The most described first switch valve is opened, and the pressure of the inlet plenum of pressure regulator is successively via described first Switch valve, preregulator enter the lower chamber of described pressure regulator with pilot valve, drive to remove on epithelium band movable valve plug and open Valve port, the inlet plenum of described pressure regulator turns on discharge chamber, supplies downstream pipe;
If it is not, the most described first switch valve cuts out;
Judging that described first is more than described first preset pressure than the pressure of pressure mouth, described first switch valve is opened Qi Hou, further comprising the steps of,
Obtain the second preset pressure of user preset;
Judge whether second be more than described second preset pressure than the pressure of pressure mouth;
The most described second switch valve is opened, and the pressure of the inlet plenum of pressure regulator is respectively via described first Switch valve merges after described second switch valve, and enters described pressure regulator via preregulator after pilot valve successively Lower chamber, drive to remove on epithelium band movable valve plug and open valve port;
If it is not, the most described second switch valve cuts out, the pressure of the inlet plenum of pressure regulator is via described first switch Valve, preregulator enter the lower chamber of described pressure regulator with pilot valve, drive to remove on epithelium band movable valve plug and open valve port.
5. the pressure regulation method of a Gas Pressure Regulating Equipment as claimed in claim 1, it is characterised in that include Following steps,
Obtain the first preset pressure of user preset;
Judge whether first be more than described first preset pressure than the pressure of pressure mouth;
The most described first switch valve is opened, and the pressure of the inlet plenum of pressure regulator is successively via described first Switch valve, preregulator enter the lower chamber of described pressure regulator with pilot valve, drive to remove on epithelium band movable valve plug and open Valve port, the inlet plenum of described pressure regulator turns on discharge chamber, supplies downstream pipe;
If it is not, the most described first switch valve cuts out;
Judging that described first closes less than described first preset pressure, described first switch valve than the pressure of pressure mouth It is after closing, further comprising the steps of,
Obtain the second preset pressure of user preset;
Judge whether second be more than described second preset pressure than the pressure of pressure mouth;
The most described second switch valve is opened, and the pressure of the inlet plenum of pressure regulator is successively via described second Enter the lower chamber of described pressure regulator after switch valve, preregulator and pilot valve, drive and remove on epithelium band movable valve plug Open valve port;
If it is not, the most described second switch valve cuts out, described valve port is closed, and described pressure regulator stops Downstream pipe is supplied.
CN201410114258.4A 2014-03-25 2014-03-25 Gas Pressure Regulating Equipment and pressure regulation method Active CN103912704B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410114258.4A CN103912704B (en) 2014-03-25 2014-03-25 Gas Pressure Regulating Equipment and pressure regulation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410114258.4A CN103912704B (en) 2014-03-25 2014-03-25 Gas Pressure Regulating Equipment and pressure regulation method

Publications (2)

Publication Number Publication Date
CN103912704A CN103912704A (en) 2014-07-09
CN103912704B true CN103912704B (en) 2016-08-17

Family

ID=51038598

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410114258.4A Active CN103912704B (en) 2014-03-25 2014-03-25 Gas Pressure Regulating Equipment and pressure regulation method

Country Status (1)

Country Link
CN (1) CN103912704B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111963738A (en) * 2020-10-20 2020-11-20 四川九门科技股份有限公司 Remote pressure monitoring device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2934675Y (en) * 2006-03-24 2007-08-15 广州三业科技有限公司 Constant hoisting height/ check water pump dedicated valve
CN201548855U (en) * 2009-12-08 2010-08-11 上海航天能源有限公司 Pressure regulation control system
CN201739592U (en) * 2010-06-07 2011-02-09 开维喜阀门集团有限公司 Multifunctional reducing valve
CN102062242A (en) * 2010-12-23 2011-05-18 大丰市丰泰机电有限公司 Gas pressure regulator
CN103324184A (en) * 2013-06-29 2013-09-25 上海飞奥燃气设备有限公司 Fuel gas transportation and distribution monitoring system

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006285661A (en) * 2005-03-31 2006-10-19 Osaka Gas Co Ltd Pressure governing device
CN203880171U (en) * 2014-03-25 2014-10-15 上海飞奥燃气设备有限公司 Fuel gas pressure regulating device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2934675Y (en) * 2006-03-24 2007-08-15 广州三业科技有限公司 Constant hoisting height/ check water pump dedicated valve
CN201548855U (en) * 2009-12-08 2010-08-11 上海航天能源有限公司 Pressure regulation control system
CN201739592U (en) * 2010-06-07 2011-02-09 开维喜阀门集团有限公司 Multifunctional reducing valve
CN102062242A (en) * 2010-12-23 2011-05-18 大丰市丰泰机电有限公司 Gas pressure regulator
CN103324184A (en) * 2013-06-29 2013-09-25 上海飞奥燃气设备有限公司 Fuel gas transportation and distribution monitoring system

Also Published As

Publication number Publication date
CN103912704A (en) 2014-07-09

Similar Documents

Publication Publication Date Title
CN106556151B (en) A kind of fuel gas of fuel gas water heater automatic pressure unit and method
CN104296386B (en) Control method, control system and the gas heater of gas heater
CN104422141A (en) Method for controlling gas water heater adaptable to different altitudes
RU2015145845A (en) METHOD AND DEVICE FOR PROVIDING REVERSE CURRENT (FROM) THROUGH POWER SUPPLY UNIT SUPPLY FAN
CN110940094B (en) Gas water heater control method and gas water heater
CN103423190A (en) Parallel operation axial flow primary fan automatic regulating method and device
CN111365855A (en) Gas water heater capable of realizing multistage current limiting and temperature control and control method thereof
CN103912704B (en) Gas Pressure Regulating Equipment and pressure regulation method
CN203476764U (en) Parallel-running axial-flow type primary air fan automatic adjusting apparatus
CN102818117B (en) Coal gas pressurization device
CN109747673A (en) A kind of interior pressure regulating device and adjusting method
CN203880171U (en) Fuel gas pressure regulating device
CN204493196U (en) A kind of two-stage helical-lobe compressor exhaust pressure stabilizer
CN205803521U (en) A kind of blast funnace hot blast stove gas flow Optimal Control System
CN203656972U (en) Closed-loop combustion control system
CN110425581B (en) Intelligent control device for gas combustion
TW201702982A (en) Energy resource consumption management method reduces consumption of energy resource under state of no stopping supplying energy resource
CN207701225U (en) A kind of gas turbine fuel calorific value adjusting apparatus
CN101603627A (en) A kind of automatic switching and adjustment method for big and small pipes of coal gas mixing station
CN104865983A (en) Fuel gas transmission and distribution intelligent pressure regulating station and control method thereof
CN204787297U (en) Gas heater constant temperature equipment
CN206018567U (en) Steam transmission system
CN104775022B (en) Combustion-supporting fan linkage control system and method
CN104482283B (en) Upstream under-pressure automatic closing pressure regulator
US8770185B2 (en) Gas fireplace with gas controlling device and method of controlling gas consumption of the gas fireplace

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhang Feifei

Inventor after: Xu Jian

Inventor after: Zhang Ruili

Inventor after: Hu Shilei

Inventor after: Tong Guofang

Inventor before: Pan Liang

Inventor before: Zhang Feifei

Inventor before: Xu Jian

Inventor before: Hu Shilei

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant