Prior art keywords
secondary beam
girder
plate
junction plate
long girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410105171.0A
Other languages
Chinese (zh)
Other versions
CN103898971B (en
Inventor
张爱林
赵亮
刘学春
马林
王艺蒙
张庆芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongling Xiangyu Commerce And Trade Co ltd
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201410105171.0A priority Critical patent/CN103898971B/en
Publication of CN103898971A publication Critical patent/CN103898971A/en
Application granted granted Critical
Publication of CN103898971B publication Critical patent/CN103898971B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a modularized assembly type steel structure system for achieving joint rigid connection, and belongs to the technical field of structural engineering. The structure system is formed by assembling assembly type floor slabs and assembly type flange columns through bolts. The assembly type floor slabs can be spliced into the required scale and are spliced through bolts to form the whole layer floor of a building. The steel structure system is suitable for industrialized production and can be quickly assembled on the site, the structure system is assembled on the site completely through the high-strength bolts, environmental pollution caused by concrete pouring and rolled steel welding is avoided, after being demounted, structure components can be efficiently recycled, the environment friendliness concept is truly achieved, and the structure system is environmentally friendly.

Description

A kind of how high-rise assembling type steel structure system of modularization that realizes rigid joint connection
Technical field
The present invention relates to a kind of how high-rise assembling type steel structure system of modularization that rigid joint connects that realizes, belong to technical field of structural engineering.
Background technology
2,000,000,000 square metres of China's annual town and country newly constructed house areas, more than 80% are wherein high energy consumption building, and China unit's building area energy consumption is the more than 2 times of developed country.Join in a common effort meter according to Chinese steel, announce according to State Statistics Bureau, within 2013, China's output of steel is broken through 1,000,000,000 tons of high pointes first, reach 10.6762 hundred million tons, occupy output of steel first place, countries in the world, U.S.'s steel building area accounts for overall floorage more than 50%, Japan accounts for 80%, and China is less than 4%.Conduct steel output big country in the world of China, the development of steel house seriously lags behind.
On January 1st, 2013, " the green building action scheme " that forward National Development and Reform Commission, the formulation of house town and country construction portion for (2013) No. 1 sent out by the General Office of the State Council with the Office of the State Council.In the vital task of its regulation, clearly propose: greatly develop green building material, promote industrialization of construction industry.Require the departments such as house town and country construction to want Speed-up Establishment to promote the standards system of the link such as design, construction, component production of industrialization of construction industry, the standardization of pushing structure part, component, parts, enriches the kind of standard component, raising versatility and substitutability.Popularization is applicable to the building systems such as the Prefabricated steel construction of suitability for industrialized production, accelerates development the prefabricated and mounting technology of construction project, improves industrialization of construction industry technology integrated horizontal.The industrialization construction of base that support integrates design, produces, constructs, carries out industrialized building demonstration pilot project.Prefabricated assembled steel house can better embody the essence of green building, and " green building action " provides major opportunity for the corresponding system innovation of China's light-duty steel construction house and industrialization.
The problem of the how high-rise assembling type steel structure system of the existing modularization of China is the node that floor and beam column connect, and only relying on a limited number of high-strength bolt is to realize being rigidly connected of node, is unfavorable for the stressed of structure.The splicing form that the present invention adopts can effectively realize being rigidly connected of node, overcomes the deficiency of existing system.
Summary of the invention
The present invention proposes a kind of how high-rise assembling type steel structure system of modularization that belongs to technical field of structural engineering.
Technical scheme of the present invention is as follows:
The how high-rise assembling type steel structure system of described modularization adopts bolts assemblies to form by assembling floor and assembling flange post; The bean column node of described steel structure system is to be welded in factory with being connected of framework, can realize and being rigidly connected; Described assembling floor is by A plate, B plate, C plate, D plate, E plate and 6 kinds of combined and spliced forming of assembling floor of F plate;
Described A plate is made up of short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, secondary beam III 5, long girder I 6, column base 7, junction plate I 15, junction plate II 16 and floor 17, all members of described A plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor A by welding, short girder II 2 is vertical with secondary beam I 3 puts, short girder II 2 is connected with secondary beam I 3 with junction plate I 15 by column base 7, short girder II 2 and secondary beam I 3 are connected in the square steel pipe I (12) of column base 7, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam I 3 with short girder II 2 respectively, two junction plate I 15 are connected on short girder II 2 and secondary beam I 3 top flanges and bottom flange, and all connecting portions are welding, short girder I 1 and short girder II 2 are placed on same straight line, are connected by column base 7, and short girder I 1 and short girder II 2 are connected in the square steel pipe I (12) of column base 7, and all connecting portions are all adopted as welding, secondary beam II 4 is parallel with secondary beam I 3, vertical with short girder II 2 with short girder I 1, be connected with short girder II 2 with short girder I 1 with junction plate I 15 by column base 7, be connected in the square steel pipe I (12) of column base 7, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam II 4 with short girder I 1, short girder II 2 respectively, two junction plate I 15 are connected on the top flange and bottom flange of short girder I 1, short girder II 2 and secondary beam II 4, and all connecting portions are all adopted as welding, secondary beam III 5 is parallel with secondary beam II 4, vertical with short girder II 2 with short girder I 1, be connected with short girder I 1 by junction plate I 15, three sides of the plate stretching out in short girder I 1 are connected with upper bottom flange and the web of secondary beam III 5, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam III 5 with short girder I 1 respectively, two junction plate I 15 are connected on top flange and bottom flange, and all connecting portions are all adopted as welding, long girder I 6 is parallel to short girder I 1 and short girder II 2, perpendicular to secondary beam I 3, by junction plate I 15 and junction plate II 16 and secondary beam I 3, secondary beam II 4 is connected with secondary beam III 5, described junction plate II 16 is positioned at the end of secondary beam I 3 and secondary beam II 4, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam II 4 with secondary beam I 3, a side is connected with the web of secondary beam I 3, another side connects with the web of long girder I 6, two sides of described junction plate I 15 connect long girder I 6, secondary beam I 3, the edge of a wing of secondary beam II 4 and secondary beam III 5, junction plate I 15 is connected to long girder I 6, secondary beam I 3, on the top flange and bottom flange of secondary beam II 4 and secondary beam III 5, all connecting portions are all adopted as welding, floor 17 adopts shear key to splice in the plane being surrounded by short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, secondary beam III 5, long girder I 6,
Described B plate is made up of secondary beam II 4, long girder I 6, long girder II 8, secondary beam IV 9, secondary beam V 10, junction plate I 15, junction plate II 16 and floor 17, all members of described B plate all complete in factory process, be then connected with shear key each component assembly is become to described assembling floor B by welding, long girder I 6 and secondary beam IV 9, secondary beam V 10 is vertically put, by junction plate I 15 and junction plate II 16 by two long girder I 6 and secondary beam IV 9, secondary beam V 10 connects in beam end, form rectangular frame, described junction plate II 16 is positioned at the end of secondary beam IV 9, the upper and lower side of junction plate II 16 and secondary beam IV 9, the edge of a wing of secondary beam V 10 is connected, a side is connected with the web of secondary beam V 10 with secondary beam IV 9, another side is connected with long girder I 6 webs, two sides of described junction plate I 15 respectively with long girder I 6 and secondary beam IV 9, long girder I 6 is connected with the edge of a wing of secondary beam V 10, two junction plate I 15 that arrange are connected to long girder I 6 and secondary beam IV 9, on long girder I 6 and secondary beam V 10 top flanges and bottom flange, all connecting portions are welding, described long girder II 8 is parallel with long girder I 6, placement vertical with secondary beam V 10, long girder II 8 is positioned at the middle of two long girder I 6, two ends of long girder II 8 are connected in secondary beam IV 9 by junction plate I 15 respectively, the middle part of secondary beam V 10, two sides of described junction plate I 15 respectively with long girder II 8 and secondary beam IV 9, long girder II 8 is connected with the edge of a wing of secondary beam V 10, two end extensions of long girder II 8 are respectively with secondary beam IV 9, the central-web of secondary beam V 10 is connected, two junction plate I 15 that arrange are connected to long girder II 8, on the top flange and bottom flange of secondary beam IV 9 and secondary beam V 10, all connecting portions are welding, described secondary beam II 4 is parallel with secondary beam V 10, with the placement vertical with long girder II 8 of long girder I 6, by junction plate I 15, the beam-ends of secondary beam II 4 is connected in to the middle part of long girder I 6 and long girder II 8, be connected with long girder I 6 two sides of junction plate I 15 of one end of secondary beam II 4 are connected with the edge of a wing of long girder I 6 with secondary beam II 4 respectively, two junction plate I 15 that arrange are connected on the top flange and bottom flange of secondary beam II 4 and long girder I 6, be connected with long girder II 8 two sides of junction plate I 15 of one end of secondary beam II 4 are connected with the edge of a wing of long girder II 8 with secondary beam II 4 respectively, two junction plate I 15 that arrange are connected on the top flange and bottom flange of secondary beam II 4 and long girder II 8, secondary beam II 4 two ends extensions are connected with the central-web of long girder II 8 with long girder I 6, all connecting portions are welding, floor 17 adopts shear key to splice on the framework being surrounded by secondary beam II 4, long girder I 6, long girder II 8, secondary beam IV 9, secondary beam V 10,
Described C plate is made up of short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, long girder I 6, column base 7, secondary beam V 10, junction plate I 15, junction plate II 16 and floor 17, all members of described C plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor C by welding, described two secondary beam I 3 are placed on same straight line, connect by column base 7, and the square steel pipe I (12) that is connected to column base 7 is upper, and as two opposite side of rectangle assembling floor C plate, all connections are welding, the placement vertical with secondary beam I 3 of described long girder I 6, as the two other opposite side of rectangle assembling floor C plate, all connections are welding, the four edges of C plate is connected with junction plate II 16 by junction plate I 15, form rectangular frame, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam I 3 with long girder I 6 respectively, two junction plate I 15 are connected on long girder I 6 and secondary beam I 3 top flanges and bottom flange, all connecting portions are welding, described junction plate II 16 is positioned at one end that secondary beam I 3 is connected with long girder I 6, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam I 3, a side is connected with the web of secondary beam I 3, and all connecting portions are welding, short girder I 1, one end of short girder II 2 and two secondary beam II 4 is connected on four sides of column base 7, short girder I 1, short girder II 2 and two secondary beam II 4 are connected in the square steel pipe I 12 of column base 7, two short girders point-blank, two secondary beams point-blank, column base 7 is positioned at C Ban center, between adjacent short girder and secondary beam, connect by junction plate I 15, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam II 4 with short girder I 1 respectively, junction plate I 15 is connected on short girder I 1 and secondary beam II 4 top flanges and bottom flange, the other end of described short girder I 1 is connected to secondary beam V 10 middle parts, three sides of extension of short girder I 1 are connected with the edge of a wing and the web of secondary beam V 10 respectively, short girder I 1 is passed through junction plate I 15 and is connected on secondary beam V 10 limits, two sides of junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with short girder I 1 respectively, junction plate I 15 is connected on short girder I 1 and secondary beam V 10 top flanges and bottom flange, all connecting portions are welding, the other end of described short girder II 2 is connected with two secondary beam I 3 with junction plate I 15 by column base 7, be connected in the square steel pipe I (12) of column base 7, two sides of junction plate I 15 are connected with the edge of a wing of secondary beam I 3 with short girder II 2 respectively, junction plate I 15 is connected on short girder II 2 and secondary beam I 3 top flanges and bottom flange, all connecting portions are welding, the other end of described secondary beam II 4 is connected to the middle part of long girder I 6, adopt junction plate I 15 to connect, three sides of extension of secondary beam II 4 are connected with the edge of a wing and the web of long girder I 6 respectively, two sides of junction plate I 15 are connected with the edge of a wing of long girder I 6 with secondary beam II 4 respectively, junction plate I 15 is connected on secondary beam II 4 and long girder I 6 top flanges and bottom flange, all connecting portions are welding, floor 17 adopts shear key to splice on the framework surrounding in short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, long girder I 6,
Described D plate is made up of short girder I 1, secondary beam II 4, secondary beam III 5, long girder I 6, column base 7, junction plate I 15, junction plate II 16 and floor 17, all members of described D plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor D by welding, short girder I 1 is vertical with secondary beam III 5 puts, by junction plate I 15, short girder I 1 is connected with secondary beam III 5, the extension of short girder I 1 is connected with the end web of secondary beam III 5, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam III 5 with short girder I 1 respectively, two junction plate I 15 are connected on top flange and bottom flange, and all connecting portions are welding, two short girder I 1 are placed on same straight line, are connected by column base 7, and two short girder I 1 are connected in the square steel pipe I 12 of column base 7, and all connecting portions are all adopted as welding, secondary beam II 4 is parallel with secondary beam III 5, vertical with two short girder I 1, be connected with two short girder I 1 with junction plate I 15 by column base 7, be connected in the square steel pipe I 12 of column base 7, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam II 4 with two short girder I 1 respectively, junction plate I 15 is connected on the top flange and bottom flange of two short girder I 1 and secondary beam II 4, and all connecting portions are all adopted as welding, long girder I 6 is parallel to two short girder I 1, perpendicular to secondary beam II 4, be connected with secondary beam II 4 and the secondary beam III 5 at two ends with junction plate II 16 by junction plate I 15, described junction plate II 16 is positioned at the end of secondary beam II 4 and secondary beam III 5, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam III 5 with secondary beam II 4, a side is connected with the web of secondary beam III 5 with secondary beam II 4, another side connects with the web of long girder I 6, two sides of described junction plate I 15 connect the edge of a wing of long girder I 6 and secondary beam II 4 and secondary beam III 5, junction plate I 15 is connected to long girder I 6, on secondary beam II 4 and secondary beam III 5 top flanges and bottom flange, the central-web of long girder I 6 is connected with the extension of secondary beam II 4, all connecting portions are all adopted as welding, floor 17 adopts shear key to splice on the framework surrounding in short girder I 1, secondary beam II 4, secondary beam III 5, long girder I 6,
Described E plate is made up of secondary beam II 4, long girder I 6, long girder II 8, secondary beam V 10, junction plate I 15, junction plate II 16 and floor 17, all members of described E plate all complete in factory process, be then connected with shear key each component assembly is become to assembling floor E by welding, long girder I 6 is vertical with secondary beam V 10 puts, long girder I 6 is connected in beam end with secondary beam V 10 with junction plate II 16 by junction plate I 15, form rectangular frame, described junction plate II 16 is positioned at the end of secondary beam, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam V 10, a side is connected with the web of secondary beam V 10, another side is connected with long girder I 6 webs, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with long girder I 6 respectively, the junction plate I 15 arranging is connected on the top flange and bottom flange of long girder I 6 and secondary beam V 10, all connecting portions are welding, described long girder II 8 is parallel with long girder I 6, placement vertical with secondary beam V 10, long girder II 8 is positioned at the middle of two long girder I 6, two ends of long girder II 8 are connected in respectively the middle part of secondary beam V 10 by junction plate I 15, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with long girder II 8 respectively, the central-web of extension two ends, two ends secondary beam V 10 of long girder II 8 is connected, the junction plate I 15 arranging is connected on the top flange and bottom flange of long girder II 8 and secondary beam V 10, all connecting portions are welding, described secondary beam II 4 is parallel with secondary beam V 10, with the placement vertical with long girder II 8 of long girder I 6, by junction plate I 15, the beam-ends of secondary beam II 4 is connected in to the middle part of long girder I 6 and long girder II 8, be connected with long girder I 6 two sides of junction plate I 15 of one end of secondary beam II 4 are connected with the edge of a wing of long girder I 6 with secondary beam II 4 respectively, the junction plate I 15 arranging is connected on secondary beam II 4 and long girder I 6 top flanges and bottom flange, be connected with long girder II 8 two sides of junction plate I 15 of one end of secondary beam II 4 are connected with the edge of a wing of long girder II 8 with secondary beam II 4 respectively, two junction plate I 15 that arrange are connected on secondary beam II 4 and long girder II 8 top flanges and bottom flange, secondary beam II 4 two ends extensions are connected with the central-web of long girder II 8 with the long girder I 6 in both sides, all connecting portions are welding, floor 17 adopts shear key to splice on the framework surrounding in secondary beam II 4, long girder I 6, long girder II 8, secondary beam V 10,
Described F plate is made up of short girder I 1, secondary beam II 4, long girder I 6, column base 7, secondary beam V 10, junction plate I 15, junction plate II 16 and floor 17, all members of described F plate all complete in factory process, be then connected with shear key each component assembly is become to assembling floor F by welding, long girder I 6 is vertical with secondary beam V 10 puts, long girder I 6 is connected in beam end with secondary beam V 10 with junction plate II 16 by junction plate I 15, form rectangular frame, described junction plate II 16 is positioned at the end of secondary beam, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam V 10, a side is connected with the web of secondary beam V 10, another side is connected with long girder I 6 webs, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with long girder I 6 respectively, the junction plate I 15 arranging is connected on long girder I 6 and secondary beam V 10 top flanges and bottom flange, all connecting portions are welding, one end of two short girder I 1 and two secondary beam II 4 is connected on four sides of column base 7, two short girder I 1 and two secondary beam II 4 are connected in the square steel pipe I 12 of column base 7, two short girders point-blank, two secondary beams point-blank, column base 7 is positioned at F Ban center, between adjacent short girder and secondary beam, connect by junction plate I 15, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam II 4 with short girder I 1 respectively, junction plate I 15 is connected on short girder I 1 and secondary beam II 4 top flanges and bottom flange, the other end of described short girder I 1 is connected to secondary beam V 10 middle parts, three sides of the extension of short girder I 1 are connected with the edge of a wing and the web at secondary beam V 10 middle parts respectively, short girder I 1 is connected with secondary beam V 10 by junction plate I 15, two sides of junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with short girder I 1 respectively, junction plate I 15 is connected on top flange and bottom flange, the other end of described secondary beam II 4 is connected to the middle part of long girder I 6, adopt junction plate I 15 to connect, three sides of extension of secondary beam II 4 are connected with the edge of a wing and the web at long girder I 6 middle parts respectively, two sides of junction plate I 15 are connected with the edge of a wing of long girder I 6 with secondary beam II 4 respectively, junction plate I 15 is connected on the top flange and bottom flange of secondary beam II 4 and long girder I 6, all connecting portions are welding, floor 17 adopts shear key to splice on the framework surrounding in short girder I 1, secondary beam II 4, long girder I 6, column base 7, secondary beam V 10,
Described assembling floor A plate and described assembling floor B plate splice, and connecting method is that the long girder I 6 of the long girder I 6 of A plate and B plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor B plate and described assembling floor C plate splice, and connecting method is that the long girder I 6 of the long girder I 6 of B plate and C plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor D plate and described assembling floor E plate splice, connecting method is that the long girder I 6 of the long girder I 6 of D plate and E plate is spliced, described assembling floor E plate and described assembling floor F plate splice, and connecting method is the long girder I 6 of the long girder I 6 of E plate and F plate to be spliced to all splicings all adopt bolt to carry out scene splicing; Described assembling floor A plate and described assembling floor D plate splice, and connecting method is that the secondary beam V 10 of the secondary beam V 10 of A plate and D plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor B plate and described assembling floor E plate splice, connecting method is that the secondary beam V 10 of the secondary beam V 10 of B plate and E plate is spliced, described assembling floor C plate and described assembling floor F plate splice, connecting method is that the secondary beam V 10 of the secondary beam V 10 of C plate and F plate is spliced, and all splicings all adopt bolt to carry out scene splicing;
The basic composition unit of described assembling floor system is A plate, B plate, C plate, D plate, E plate and F plate; The two ends of assembling floor system are A plate and D plate in the horizontal, and B plate and C plate stitch together and can form a module, and this module can be spliced mutually, according to the area of building requirements, increase quantity and the splicing of A plate of this module; E plate and F plate stitch together and can form another module, and this module can be spliced mutually, according to the area of building requirements, increase quantity and the splicing of D plate of this module; The two ends of longitudinally upper assembling floor system are A plate, B plate and C plate, by increasing the intermediate module of D plate, E plate and F plate composition, splice to increase building area; Realize Modularized splice;
Described column base 7 is made up of two flanged plates 11 and a square steel pipe I 12, and two flanged plates 11 lay respectively on two ends of square steel pipe I 12, and all connections all adopt welding; Described flange post 13 is made up of a square steel pipe II 14 and two flanged plates 11, and two flanged plates 11 lay respectively on two ends of square steel pipe II 14, and all connections all adopt welding; Described flange post 13 is connected with column base 7, forms steel frame structural system, and all connections are all with bolts.
Described short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, long girder II 8, secondary beam IV 9 are H shaped steel, or two back-to-back equivalent H shaped steel that are spliced of channel-section steel, or two equivalent H shaped steel that T-steel is spliced, or four equivalent H shaped steel that angle splice joint forms; Described secondary beam III 5, long girder I 6, secondary beam V 10 are channel-section steels, or two equivalent channel-section steels that angle splice joint forms.
All beams are section steel beams, or in the Steel Castellated Beams of the web place of beam opening holes, are convenient to various pipelines and pass.
In the how high-rise assembling type steel structure system of modularization that the present invention proposes, described assembling flange post and assembling column base all complete in factory process, are then bolted each component assembly and become described assembling floor.
All beams are section steel beams, or in the Steel Castellated Beams of the web place of beam opening holes, are convenient to various pipelines and pass, and have both saved steel, effectively improve again the clear height in house.
Beneficial effect: the how high-rise assembling type steel structure system of modularization that realizes rigid joint connection of the present invention's proposition is the structural system of the innovation in assembling high-rise building steel structure system.It is by modularization, and batch production and assemblingization combine, and have realized batch production production, and assemble fast at scene, improve speed of application, shorten the construction period, reduce construction costs, reduce environment pollution, steel recoverable after removing, is a kind of structural system of environmental protection.
Accompanying drawing explanation
Fig. 1 is assembling floor splicing layout plan of the present invention
Fig. 2 is the schematic diagram of assembling floor A plate of the present invention
Fig. 3 is the unit decomposition figure of assembling floor A plate of the present invention
Fig. 4 is the schematic diagram of assembling floor B plate of the present invention
Fig. 5 is the unit decomposition figure of assembling floor B plate of the present invention
Fig. 6 is the schematic diagram of assembling floor C plate of the present invention
Fig. 7 is the unit decomposition figure of assembling floor C plate of the present invention
Fig. 8 is the schematic diagram of assembling floor D plate of the present invention
Fig. 9 is the unit decomposition figure of assembling floor D plate of the present invention
Figure 10 is the schematic diagram of assembling floor E plate of the present invention
Figure 11 is the unit decomposition figure of assembling floor E plate of the present invention
Figure 12 is the schematic diagram of assembling floor F plate of the present invention
Figure 13 is the unit decomposition figure of assembling floor F plate of the present invention
Figure 14 is Assembled Building sheet-pile seat unit decomposition figure of the present invention
Figure 15 is assembling flange pole unit exploded view of the present invention
Figure 16 is the schematic diagram that punches of the beam in assembling floor of the present invention
Figure 17 is the assembling design sketch of the how high-rise assembling type steel structure system of modularization of the present invention
Wherein: 1-short girder I, 2-short girder II, 3-secondary beam I, 4-secondary beam II, 5-secondary beam III, 6-long girder I, 7-column base, 8-long girder II, 9-secondary beam IV, 10-secondary beam V, 11-flanged plate, 12-square steel pipe I, 13-flange post, 14-square steel pipe II, 15-junction plate I, 16-junction plate II, 17-floor
The specific embodiment
Below in conjunction with accompanying drawing, the present invention is described in detail:
As shown in Figure 1, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, and the how high-rise assembling type steel structure system of described modularization adopts bolts assemblies to form by assembling floor and assembling flange post; The basic composition unit of described assembling floor system is A plate, B plate, C plate, D plate, E plate and F plate.
As shown in accompanying drawing 2 and accompanying drawing 3, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, and described A plate is made up of short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, secondary beam III 5, long girder I 6, column base 7, junction plate I 15, junction plate II 16 and floor 17; All members of described A plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor A by welding.Short girder II 2 is vertical with secondary beam I 3 puts, short girder II 2 is connected with secondary beam I 3 with junction plate I 15 by column base 7, short girder II 2 and secondary beam I 3 are connected in the square steel pipe I 12 of column base 7, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam I 3 with short girder II 2 respectively, two junction plate I 15 are connected on short girder II 2 and secondary beam I 3 top flanges and bottom flange, and all connecting portions are welding, short girder I 1 and short girder II 2 are placed on same straight line, are connected by column base 7, and short girder I 1 and short girder II 2 are connected in the square steel pipe I 12 of column base 7, and all connecting portions are all adopted as welding, secondary beam II 4 is parallel with secondary beam I 3, vertical with short girder II 2 with short girder I 1, be connected with short girder II 2 with short girder I 1 with junction plate I 15 by column base 7, be connected in the square steel pipe I 12 of column base 7, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam II 4 with short girder I 1, short girder II 2 respectively, two junction plate I 15 are connected on the top flange and bottom flange of short girder I 1, short girder II 2 and secondary beam II 4, and all connecting portions are all adopted as welding, secondary beam III 5 is parallel with secondary beam II 4, vertical with short girder II 2 with short girder I 1, be connected with short girder I 1 by junction plate I 15, three sides of the plate stretching out in short girder I 1 are connected with upper bottom flange and the web of secondary beam III 5, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam III 5 with short girder I 1 respectively, two junction plate I 15 are connected on top flange and bottom flange, and all connecting portions are all adopted as welding, long girder I 6 is parallel to short girder I 1 and short girder II 2, perpendicular to secondary beam I 3, by junction plate I 15 and junction plate II 16 and secondary beam I 3, secondary beam II 4 is connected with secondary beam III 5, described junction plate II 16 is positioned at the end of secondary beam I 3 and secondary beam II 4, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam II 4 with secondary beam I 3, a side is connected with the web of secondary beam I 3, another side connects with the web of long girder I 6, two sides of described junction plate I 15 connect long girder I 6, secondary beam I 3, the edge of a wing of secondary beam II 4 and secondary beam III 5, junction plate I 15 is connected to long girder I 6, secondary beam I 3, on the top flange and bottom flange of secondary beam II 4 and secondary beam III 5, all connecting portions are all adopted as welding, floor 17 adopts shear key to splice in the plane being surrounded by short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, secondary beam III 5, long girder I 6.
As shown in accompanying drawing 4 and accompanying drawing 5, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, and described B plate is made up of secondary beam II 4, long girder I 6, long girder II 8, secondary beam IV 9, secondary beam V 10, junction plate I 15, junction plate II 16 and floor 17; All members of described B plate all complete in factory process, be then connected with shear key each component assembly is become to described assembling floor B by welding.Long girder I 6 and secondary beam IV 9, secondary beam V 10 is vertically put, by junction plate I 15 and junction plate II 16 by two long girder I 6 and secondary beam IV 9, secondary beam V 10 connects in beam end, form rectangular frame, described junction plate II 16 is positioned at the end of secondary beam IV 9, the upper and lower side of junction plate II 16 and secondary beam IV 9, the edge of a wing of secondary beam V 10 is connected, a side is connected with the web of secondary beam V 10 with secondary beam IV 9, another side is connected with long girder I 6 webs, two sides of described junction plate I 15 respectively with long girder I 6 and secondary beam IV 9, long girder I 6 is connected with the edge of a wing of secondary beam V 10, two junction plate I 15 that arrange are connected to long girder I 6 and secondary beam IV 9, on long girder I 6 and secondary beam V 10 top flanges and bottom flange, all connecting portions are welding, described long girder II 8 is parallel with long girder I 6, placement vertical with secondary beam V 10, long girder II 8 is positioned at the middle of two long girder I 6, two ends of long girder II 8 are connected in secondary beam IV 9 by junction plate I 15 respectively, the middle part of secondary beam V 10, two sides of described junction plate I 15 respectively with long girder II 8 and secondary beam IV 9, long girder II 8 is connected with the edge of a wing of secondary beam V 10, two end extensions of long girder II 8 are respectively with secondary beam IV 9, the central-web of secondary beam V 10 is connected, two junction plate I 15 that arrange are connected to long girder II 8, on the top flange and bottom flange of secondary beam IV 9 and secondary beam V 10, all connecting portions are welding, described secondary beam II 4 is parallel with secondary beam V 10, with the placement vertical with long girder II 8 of long girder I 6, by junction plate I 15, the beam-ends of secondary beam II 4 is connected in to the middle part of long girder I 6 and long girder II 8, be connected with long girder I 6 two sides of junction plate I 15 of one end of secondary beam II 4 are connected with the edge of a wing of long girder I 6 with secondary beam II 4 respectively, two junction plate I 15 that arrange are connected on the top flange and bottom flange of secondary beam II 4 and long girder I 6, be connected with long girder II 8 two sides of junction plate I 15 of one end of secondary beam II 4 are connected with the edge of a wing of long girder II 8 with secondary beam II 4 respectively, two junction plate I 15 that arrange are connected on the top flange and bottom flange of secondary beam II 4 and long girder II 8, secondary beam II 4 two ends extensions are connected with the central-web of long girder II 8 with long girder I 6, all connecting portions are welding, floor 17 adopts shear key to splice on the framework being surrounded by secondary beam II 4, long girder I 6, long girder II 8, secondary beam IV 9, secondary beam V 10.
As shown in accompanying drawing 6 and accompanying drawing 7, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, and described C plate is made up of short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, long girder I 6, column base 7, secondary beam V 10, junction plate I 15, junction plate II 16 and floor 17; All members of described C plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor C by welding.Described two secondary beam I 3 are placed on same straight line, connect by column base 7, and the square steel pipe I (12) that is connected to column base 7 is upper, and as two opposite side of rectangle assembling floor C plate, all connections are welding, the placement vertical with secondary beam I 3 of described long girder I 6, as the two other opposite side of rectangle assembling floor C plate, all connections are welding, the four edges of C plate is connected with junction plate II 16 by junction plate I 15, form rectangular frame, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam I 3 with long girder I 6 respectively, two junction plate I 15 are connected on long girder I 6 and secondary beam I 3 top flanges and bottom flange, all connecting portions are welding, described junction plate II 16 is positioned at one end that secondary beam I 3 is connected with long girder I 6, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam I 3, a side is connected with the web of secondary beam I 3, and all connecting portions are welding, short girder I 1, one end of short girder II 2 and two secondary beam II 4 is connected on four sides of column base 7, short girder I 1, short girder II 2 and two secondary beam II 4 are connected in the square steel pipe I (12) of column base 7, two short girders point-blank, two secondary beams point-blank, column base 7 is positioned at C Ban center, between adjacent short girder and secondary beam, connect by junction plate I 15, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam II 4 with short girder I 1 respectively, junction plate I 15 is connected on short girder I 1 and secondary beam II 4 top flanges and bottom flange, the other end of described short girder I 1 is connected to secondary beam V 10 middle parts, three sides of extension of short girder I 1 are connected with the edge of a wing and the web of secondary beam V 10 respectively, short girder I 1 is passed through junction plate I 15 and is connected on secondary beam V 10 limits, two sides of junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with short girder I 1 respectively, junction plate I 15 is connected on short girder I 1 and secondary beam V 10 top flanges and bottom flange, all connecting portions are welding, the other end of described short girder II 2 is connected with two secondary beam I 3 with junction plate I 15 by column base 7, be connected in the square steel pipe I 12 of column base 7, two sides of junction plate I 15 are connected with the edge of a wing of secondary beam I 3 with short girder II 2 respectively, junction plate I 15 is connected on short girder II 2 and secondary beam I 3 top flanges and bottom flange, all connecting portions are welding, the other end of described secondary beam II 4 is connected to the middle part of long girder I 6, adopt junction plate I 15 to connect, three sides of extension of secondary beam II 4 are connected with the edge of a wing and the web of long girder I 6 respectively, two sides of junction plate I 15 are connected with the edge of a wing of long girder I 6 with secondary beam II 4 respectively, junction plate I 15 is connected on secondary beam II 4 and long girder I 6 top flanges and bottom flange, all connecting portions are welding, floor 17 adopts shear key to splice on the framework surrounding in short girder I 1, short girder II 2, secondary beam I 3, secondary beam II 4, long girder I 6.
As illustrated in Figure 8 and 9 reference, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, and described D plate is made up of short girder I 1, secondary beam II 4, secondary beam III 5, long girder I 6, column base 7, junction plate I 15, junction plate II 16 and floor 17; All members of described D plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor D by welding.Short girder I 1 is vertical with secondary beam III 5 puts, by junction plate I 15, short girder I 1 is connected with secondary beam III 5, the extension of short girder I 1 is connected with the end web of secondary beam III 5, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam III 5 with short girder I 1 respectively, two junction plate I 15 are connected on top flange and bottom flange, and all connecting portions are welding, two short girder I 1 are placed on same straight line, are connected by column base 7, and two short girder I 1 are connected in the square steel pipe I 12 of column base 7, and all connecting portions are all adopted as welding, secondary beam II 4 is parallel with secondary beam III 5, vertical with two short girder I 1, be connected with two short girder I 1 with junction plate I 15 by column base 7, be connected in the square steel pipe I 12 of column base 7, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam II 4 with two short girder I 1 respectively, junction plate I 15 is connected on the top flange and bottom flange of two short girder I 1 and secondary beam II 4, and all connecting portions are all adopted as welding, long girder I 6 is parallel to two short girder I 1, perpendicular to secondary beam II 4, be connected with secondary beam II 4 and the secondary beam III 5 at two ends with junction plate II 16 by junction plate I 15, described junction plate II 16 is positioned at the end of secondary beam II 4 and secondary beam III 5, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam III 5 with secondary beam II 4, a side is connected with the web of secondary beam III 5 with secondary beam II 4, another side connects with the web of long girder I 6, two sides of described junction plate I 15 connect the edge of a wing of long girder I 6 and secondary beam II 4 and secondary beam III 5, junction plate I 15 is connected to long girder I 6, on secondary beam II 4 and secondary beam III 5 top flanges and bottom flange, the central-web of long girder I 6 is connected with the extension of secondary beam II 4, all connecting portions are all adopted as welding, floor 17 adopts shear key to splice on the framework surrounding in short girder I 1, secondary beam II 4, secondary beam III 5, long girder I 6.
As shown in accompanying drawing 10 and accompanying drawing 11, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, and described E plate is made up of secondary beam II 4, long girder I 6, long girder II 8, secondary beam V 10, junction plate I 15, junction plate II 16 and floor 17; All members of described E plate all complete in factory process, be then connected with shear key each component assembly is become to assembling floor E by welding.Long girder I 6 is vertical with secondary beam V 10 puts, long girder I 6 is connected in beam end with secondary beam V 10 with junction plate II 16 by junction plate I 15, form rectangular frame, described junction plate II 16 is positioned at the end of secondary beam, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam V 10, a side is connected with the web of secondary beam V 10, another side is connected with long girder I 6 webs, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with long girder I 6 respectively, the junction plate I 15 arranging is connected on the top flange and bottom flange of long girder I 6 and secondary beam V 10, all connecting portions are welding, described long girder II 8 is parallel with long girder I 6, placement vertical with secondary beam V 10, long girder II 8 is positioned at the middle of two long girder I 6, two ends of long girder II 8 are connected in respectively the middle part of secondary beam V 10 by junction plate I 15, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with long girder II 8 respectively, the central-web of extension two ends, two ends secondary beam V 10 of long girder II 8 is connected, the junction plate I 15 arranging is connected on the top flange and bottom flange of long girder II 8 and secondary beam V 10, all connecting portions are welding, described secondary beam II 4 is parallel with secondary beam V 10, with the placement vertical with long girder II 8 of long girder I 6, by junction plate I 15, the beam-ends of secondary beam II 4 is connected in to the middle part of long girder I 6 and long girder II 8, be connected with long girder I 6 two sides of junction plate I 15 of one end of secondary beam II 4 are connected with the edge of a wing of long girder I 6 with secondary beam II 4 respectively, the junction plate I 15 arranging is connected on secondary beam II 4 and long girder I 6 top flanges and bottom flange, be connected with long girder II 8 two sides of junction plate I 15 of one end of secondary beam II 4 are connected with the edge of a wing of long girder II 8 with secondary beam II 4 respectively, two junction plate I 15 that arrange are connected on secondary beam II 4 and long girder II 8 top flanges and bottom flange, secondary beam II 4 two ends extensions are connected with the central-web of long girder II 8 with the long girder I 6 in both sides, all connecting portions are welding, floor 17 adopts shear key to splice on the framework surrounding in secondary beam II 4, long girder I 6, long girder II 8, secondary beam V 10.
As shown in accompanying drawing 12 and accompanying drawing 13, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, and described F plate is made up of short girder I 1, secondary beam II 4, long girder I 6, column base 7, secondary beam V 10, junction plate I 15, junction plate II 16 and floor 17; All members of described F plate all complete in factory process, be then connected with shear key each component assembly is become to assembling floor F by welding.Long girder I 6 is vertical with secondary beam V 10 puts, long girder I 6 is connected in beam end with secondary beam V 10 with junction plate II 16 by junction plate I 15, form rectangular frame, described junction plate II 16 is positioned at the end of secondary beam, the upper and lower side of junction plate II 16 is connected with the edge of a wing of secondary beam V 10, a side is connected with the web of secondary beam V 10, another side is connected with long girder I 6 webs, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with long girder I 6 respectively, the junction plate I 15 arranging is connected on long girder I 6 and secondary beam V 10 top flanges and bottom flange, all connecting portions are welding, one end of two short girder I 1 and two secondary beam II 4 is connected on four sides of column base 7, two short girder I 1 and two secondary beam II 4 are connected in the square steel pipe I 12 of column base 7, two short girders point-blank, two secondary beams point-blank, column base 7 is positioned at F Ban center, between adjacent short girder and secondary beam, connect by junction plate I 15, two sides of described junction plate I 15 are connected with the edge of a wing of secondary beam II 4 with short girder I 1 respectively, junction plate I 15 is connected on short girder I 1 and secondary beam II 4 top flanges and bottom flange, the other end of described short girder I 1 is connected to secondary beam V 10 middle parts, three sides of the extension of short girder I 1 are connected with the edge of a wing and the web at secondary beam V 10 middle parts respectively, short girder I 1 is connected with secondary beam V 10 by junction plate I 15, two sides of junction plate I 15 are connected with the edge of a wing of secondary beam V 10 with short girder I 1 respectively, junction plate I 15 is connected on top flange and bottom flange, the other end of described secondary beam II 4 is connected to the middle part of long girder I 6, adopt junction plate I 15 to connect, three sides of extension of secondary beam II 4 are connected with the edge of a wing and the web at long girder I 6 middle parts respectively, two sides of junction plate I 15 are connected with the edge of a wing of long girder I 6 with secondary beam II 4 respectively, junction plate I 15 is connected on the top flange and bottom flange of secondary beam II 4 and long girder I 6, all connecting portions are welding, floor 17 adopts shear key to splice on the framework surrounding in short girder I 1, secondary beam II 4, long girder I 6, column base 7, secondary beam V 10.
What the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, described assembling floor A plate and described assembling floor B plate splice, connecting method is that the long girder I 6 of the long girder I 6 of A plate and B plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor B plate and described assembling floor C plate splice, and connecting method is that the long girder I 6 of the long girder I 6 of B plate and C plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor D plate and described assembling floor E plate splice, connecting method is that the long girder I 6 of the long girder I 6 of D plate and E plate is spliced, described assembling floor E plate and described assembling floor F plate splice, and connecting method is the long girder I 6 of the long girder I 6 of E plate and F plate to be spliced to all splicings all adopt bolt to carry out scene splicing; Described assembling floor A plate and described assembling floor D plate splice, and connecting method is that the secondary beam V 10 of the secondary beam V 10 of A plate and D plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor B plate and described assembling floor E plate splice, connecting method is that the secondary beam V 10 of the secondary beam V 10 of B plate and E plate is spliced, described assembling floor C plate and described assembling floor F plate splice, connecting method is that the secondary beam V 10 of the secondary beam V 10 of C plate and F plate is spliced, and all splicings all adopt bolt to carry out scene splicing.
As shown in accompanying drawing 14 and accompanying drawing 15, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, described column base 7 is made up of two flanged plates 11 and a square steel pipe I 12, two flanged plates 11 lay respectively on two ends of square steel pipe I 12, and all connections all adopt welding; Described flange post 13 is made up of a square steel pipe II 14 and two flanged plates 11, and two flanged plates 11 lay respectively on two ends of square steel pipe II 14, and all connections all adopt welding; Described flange post 13 is connected with column base 7, forms steel frame structural system, and all connections are all with bolts.
As shown in Figure 16, what the present invention proposed realizes in the how high-rise assembling type steel structure system of modularization of rigid joint connection, and described all beams, all can adopt the Steel Castellated Beams at the web place of beam opening holes, are convenient to various pipelines and pass.
As shown in Figure 17, assembling design sketch of the present invention.
What the present invention proposed realize, and the how high-rise assembling type steel structure system of modularization that rigid joint connects is to the overturning of traditional housing building of steel-structure, and has given full play to the advantage of steel house.

Claims (3)

1. realize the how high-rise assembling type steel structure system of modularization that rigid joint connects, it is characterized in that: the how high-rise assembling type steel structure system of described modularization adopts bolts assemblies to form by assembling floor and assembling flange post; The bean column node of described steel structure system is to be welded in factory with being connected of framework, can realize and being rigidly connected; Described assembling floor is by A plate, B plate, C plate, D plate, E plate and 6 kinds of combined and spliced forming of assembling floor of F plate;
Described A plate is made up of short girder I (1), short girder II (2), secondary beam I (3), secondary beam II (4), secondary beam III (5), long girder I (6), column base (7), junction plate I (15), junction plate II (16) and floor (17), all members of described A plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor A by welding, short girder II (2) and vertical the putting of secondary beam I (3), short girder II (2) is connected with secondary beam I (3) with junction plate I (15) by column base (7), short girder II (2) and secondary beam I (3) are connected in the square steel pipe I (12) of column base 7, two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam I (3) with short girder II (2) respectively, two junction plate I (15) are connected on short girder II (2) and secondary beam I (3) top flange and bottom flange, and all connecting portions are welding, short girder I (1) and short girder II (2) are placed on same straight line, be connected by column base (7), short girder I (1) and short girder II (2) are connected in the square steel pipe I (12) of column base (7), and all connecting portions are all adopted as welding, secondary beam II (4) is parallel with secondary beam I (3), vertical with short girder II (2) with short girder I (1), be connected with short girder II (2) with short girder I (1) with junction plate I (15) by column base (7), be connected in the square steel pipe I (12) of column base (7), two sides of described junction plate I (15) respectively with short girder I (1), short girder II (2) is connected with the edge of a wing of secondary beam II (4), two junction plate I (15) are connected to short girder I (1), on the top flange and bottom flange of short girder II (2) and secondary beam II (4), all connecting portions are all adopted as welding, secondary beam III (5) is parallel with secondary beam II (4), vertical with short girder II (2) with short girder I (1), be connected with short girder I (1) by junction plate I (15), three sides of the plate stretching out in short girder I (1) are connected with upper bottom flange and the web of secondary beam III (5), two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam III (5) with short girder I (1) respectively, two junction plate I (15) are connected on top flange and bottom flange, and all connecting portions are all adopted as welding, long girder I (6) is parallel to short girder I (1) and short girder II (2), perpendicular to secondary beam I (3), by junction plate I (15) and junction plate II (16) and secondary beam I (3), secondary beam II (4) is connected with secondary beam III (5), described junction plate II (16) is positioned at the end of secondary beam I (3) and secondary beam II (4), the upper and lower side of junction plate II (16) is connected with the edge of a wing of secondary beam II (4) with secondary beam I (3), a side is connected with the web of secondary beam I (3), another side connects with the web of long girder I (6), two sides of described junction plate I (15) connect long girder I (6), secondary beam I (3), the edge of a wing of secondary beam II (4) and secondary beam III (5), junction plate I (15) is connected to long girder I (6), secondary beam I (3), on the top flange and bottom flange of secondary beam II (4) and secondary beam III (5), all connecting portions are all adopted as welding, floor (17) adopts shear key to splice in the plane being surrounded by short girder I (1), short girder II (2), secondary beam I (3), secondary beam II (4), secondary beam III (5), long girder I (6),
Described B plate is made up of secondary beam II (4), long girder I (6), long girder II (8), secondary beam IV (9), secondary beam V (10), junction plate I (15), junction plate II (16) and floor (17), all members of described B plate all complete in factory process, be then connected with shear key each component assembly is become to described assembling floor B by welding, long girder I (6) and secondary beam IV (9), secondary beam V (10) is vertically put, by junction plate I (15) and junction plate II (16) by two long girder I (6) and secondary beam IV (9), secondary beam V (10) connects in beam end, form rectangular frame, described junction plate II (16) is positioned at the end of secondary beam IV (9), the upper and lower side of junction plate II (16) and secondary beam IV (9), the edge of a wing of secondary beam V (10) is connected, a side is connected with the web of secondary beam V (10) with secondary beam IV (9), another side is connected with long girder I (6) web, two sides of described junction plate I (15) respectively with long girder I (6) and secondary beam IV (9), long girder I (6) is connected with the edge of a wing of secondary beam V (10), the two junction plate I (15) that arrange are connected to long girder I (6) and secondary beam IV (9), on long girder I (6) and secondary beam V (10) top flange and bottom flange, all connecting portions are welding, described long girder II (8) is parallel with long girder I (6), placement vertical with secondary beam V (10), long girder II (8) is positioned at the middle of two long girder I (6), two ends of long girder II (8) are connected in secondary beam IV (9) by junction plate I (15) respectively, the middle part of secondary beam V (10), two sides of described junction plate I (15) respectively with long girder II (8) and secondary beam IV (9), long girder II (8) is connected with the edge of a wing of secondary beam V (10), two end extensions of long girder II (8) are respectively with secondary beam IV (9), the central-web of secondary beam V (10) is connected, the two junction plate I (15) that arrange are connected to long girder II (8), on the top flange and bottom flange of secondary beam IV (9) and secondary beam V (10), all connecting portions are welding, described secondary beam II (4) is parallel with secondary beam V (10), with long girder I (6) placement vertical with long girder II (8), by junction plate I (15), the beam-ends of secondary beam II (4) is connected in to the middle part of long girder I (6) and long girder II (8), be connected with long girder I (6) two sides of junction plate I (15) of one end of secondary beam II (4) are connected with the edge of a wing of long girder I (6) with secondary beam II (4) respectively, the two junction plate I (15) that arrange are connected on the top flange and bottom flange of secondary beam II (4) and long girder I (6), be connected with long girder II (8) two sides of junction plate I (15) of one end of secondary beam II (4) are connected with the edge of a wing of long girder II (8) with secondary beam II (4) respectively, the two junction plate I (15) that arrange are connected on the top flange and bottom flange of secondary beam II (4) and long girder II (8), secondary beam II (4) two ends extension is connected with the central-web of long girder II (8) with long girder I (6), all connecting portions are welding, floor (17) adopts shear key to splice on the framework being surrounded by secondary beam II (4), long girder I (6), long girder II (8), secondary beam IV (9), secondary beam V (10),
Described C plate is made up of short girder I (1), short girder II (2), secondary beam I (3), secondary beam II (4), long girder I (6), column base (7), secondary beam V (10), junction plate I (15), junction plate II (16) and floor (17), all members of described C plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor C by welding, described two secondary beam I (3) are placed on same straight line, connect by column base (7), and the square steel pipe I (12) that is connected to column base (7) is upper, and as two opposite side of rectangle assembling floor C plate, all connections are welding, described long girder I (6) placement vertical with secondary beam I (3), as the two other opposite side of rectangle assembling floor C plate, all connections are welding, the four edges of C plate is connected with junction plate II (16) by junction plate I (15), form rectangular frame, two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam I (3) with long girder I (6) respectively, two junction plate I (15) are connected on long girder I (6) and secondary beam I (3) top flange and bottom flange, all connecting portions are welding, described junction plate II (16) is positioned at one end that secondary beam I (3) is connected with long girder I (6), the upper and lower side of junction plate II (16) is connected with the edge of a wing of secondary beam I (3), a side is connected with the web of secondary beam I (3), all connecting portions are welding, short girder I (1), one end of short girder II (2) and two secondary beam II (4) is connected on four sides of column base (7), short girder I (1), short girder II (2) and two secondary beam II (4) are connected in the square steel pipe I (12) of column base 7, two short girders point-blank, two secondary beams point-blank, column base (7) is positioned at C Ban center, between adjacent short girder and secondary beam, connect by junction plate I (15), two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam II (4) with short girder I (1) respectively, junction plate I (15) is connected on short girder I (1) and secondary beam II (4) top flange and bottom flange, the other end of described short girder I (1) is connected to secondary beam V (10) middle part, three sides of extension of short girder I (1) are connected with the edge of a wing and the web of secondary beam V (10) respectively, short girder I (1) is passed through junction plate I (15) and is connected on secondary beam V (10) limit, two sides of junction plate I (15) are connected with the edge of a wing of secondary beam V (10) with short girder I (1) respectively, junction plate I (15) is connected on short girder I (1) and secondary beam V (10) top flange and bottom flange, all connecting portions are welding, the other end of described short girder II (2) is connected with two secondary beam I (3) with junction plate I (15) by column base (7), be connected in the square steel pipe I (12) of column base 7, two sides of junction plate I (15) are connected with the edge of a wing of secondary beam I (3) with short girder II (2) respectively, junction plate I (15) is connected on short girder II (2) and secondary beam I (3) top flange and bottom flange, all connecting portions are welding, the other end of described secondary beam II (4) is connected to the middle part of long girder I (6), adopt junction plate I (15) to connect, three sides of extension of secondary beam II (4) are connected with the edge of a wing and the web of long girder I (6) respectively, two sides of junction plate I (15) are connected with the edge of a wing of long girder I (6) with secondary beam II (4) respectively, junction plate I (15) is connected on secondary beam II (4) and long girder I (6) top flange and bottom flange, all connecting portions are welding, floor (17) adopts shear key to splice on the framework surrounding in short girder I (1), short girder II (2), secondary beam I (3), secondary beam II (4), long girder I (6),
Described D plate is made up of short girder I (1), secondary beam II (4), secondary beam III (5), long girder I (6), column base (7), junction plate I (15), junction plate II (16) and floor (17), all members of described D plate all complete in factory process, be then connected with shear key each component assembly is become to described novel fabricated floor D by welding, short girder I (1) and vertical the putting of secondary beam III (5), by junction plate I (15), short girder I (1) is connected with secondary beam III (5), the extension of short girder I (1) is connected with the end web of secondary beam III (5), two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam III (5) with short girder I (1) respectively, two junction plate I (15) are connected on top flange and bottom flange, and all connecting portions are welding, two short girder I (1) are placed on same straight line, are connected by column base (7), and two short girder I (1) are connected in the square steel pipe I (12) of column base (7), and all connecting portions are all adopted as welding, secondary beam II (4) is parallel with secondary beam III (5), vertical with two short girder I (1), be connected with two short girder I (1) with junction plate I (15) by column base (7), be connected in the square steel pipe I (12) of column base (7), two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam II (4) with two short girder I (1) respectively, junction plate I (15) is connected on the top flange and bottom flange of two short girder I (1) and secondary beam II (4), and all connecting portions are all adopted as welding, long girder I (6) is parallel to two short girder I (1), perpendicular to secondary beam II (4), be connected with secondary beam II (4) and the secondary beam III (5) at two ends with junction plate II (16) by junction plate I (15), described junction plate II (16) is positioned at the end of secondary beam II (4) and secondary beam III (5), the upper and lower side of junction plate II (16) is connected with the edge of a wing of secondary beam III (5) with secondary beam II (4), a side is connected with the web of secondary beam III (5) with secondary beam II (4), another side connects with the web of long girder I (6), two sides of described junction plate I (15) connect the edge of a wing of long girder I (6) and secondary beam II (4) and secondary beam III (5), junction plate I (15) is connected to long girder I (6), on secondary beam II (4) and secondary beam III (5) top flange and bottom flange, the central-web of long girder I (6) is connected with the extension of secondary beam II (4), all connecting portions are all adopted as welding, floor (17) adopts shear key to splice on the framework surrounding in short girder I (1), secondary beam II (4), secondary beam III (5), long girder I (6),
Described E plate is made up of secondary beam II (4), long girder I (6), long girder II (8), secondary beam V (10), junction plate I (15), junction plate II (16) and floor (17), all members of described E plate all complete in factory process, be then connected with shear key each component assembly is become to assembling floor E by welding, long girder I (6) and vertical the putting of secondary beam V (10), long girder I (6) is connected in beam end with secondary beam V (10) with junction plate II (16) by junction plate I (15), form rectangular frame, described junction plate II (16) is positioned at the end of secondary beam, the upper and lower side of junction plate II (16) is connected with the edge of a wing of secondary beam V (10), a side is connected with the web of secondary beam V (10), another side is connected with long girder I (6) web, two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam V (10) with long girder I (6) respectively, the junction plate I (15) arranging is connected on the top flange and bottom flange of long girder I (6) and secondary beam V (10), all connecting portions are welding, described long girder II (8) is parallel with long girder I (6), placement vertical with secondary beam V (10), long girder II (8) is positioned at the middle of two long girder I (6), two ends of long girder II (8) are connected in respectively the middle part of secondary beam V (10) by junction plate I (15), two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam V (10) with long girder II (8) respectively, the central-web of two ends extension two ends secondary beam V (10) of long girder II (8) is connected, the junction plate I (15) arranging is connected on the top flange and bottom flange of long girder II (8) and secondary beam V (10), all connecting portions are welding, described secondary beam II (4) is parallel with secondary beam V (10), with long girder I (6) placement vertical with long girder II (8), by junction plate I (15), the beam-ends of secondary beam II (4) is connected in to the middle part of long girder I (6) and long girder II (8), be connected with long girder I (6) two sides of junction plate I (15) of one end of secondary beam II (4) are connected with the edge of a wing of long girder I (6) with secondary beam II (4) respectively, the junction plate I (15) arranging is connected on secondary beam II (4) and long girder I (6) top flange and bottom flange, be connected with long girder II (8) two sides of junction plate I (15) of one end of secondary beam II (4) are connected with the edge of a wing of long girder II (8) with secondary beam II (4) respectively, the two junction plate I (15) that arrange are connected to (on secondary beam II (4) and long girder II (8) top flange and bottom flange, secondary beam II (4) two ends extension is connected with the central-web of long girder II (8) with the long girder I in both sides (6), all connecting portions are welding, floor (17) adopts shear key to splice on the framework surrounding in secondary beam II (4), long girder I (6), long girder II (8), secondary beam V (10),
Described F plate is made up of short girder I (1), secondary beam II (4), long girder I (6), column base (7), secondary beam V (10), junction plate I (15), junction plate II (16) and floor (17), all members of described F plate all complete in factory process, be then connected with shear key each component assembly is become to assembling floor F by welding, long girder I (6) and vertical the putting of secondary beam V (10), long girder I (6) is connected in beam end with secondary beam V (10) with junction plate II (16) by junction plate I (15), form rectangular frame, described junction plate II (16) is positioned at the end of secondary beam, the upper and lower side of junction plate II (16) is connected with the edge of a wing of secondary beam V (10), a side is connected with the web of secondary beam V (10), another side is connected with long girder I (6) web, two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam V (10) with long girder I (6) respectively, the junction plate I (15) arranging is connected on long girder I (6) and secondary beam V (10) top flange and bottom flange, all connecting portions are welding, one end of two short girder I (1) and two secondary beam II (4) is connected on four sides of column base (7), two short girder I (1) and two secondary beam II (4) are connected in the square steel pipe I (12) of column base 7, two short girders point-blank, two secondary beams point-blank, column base (7) is positioned at F Ban center, between adjacent short girder and secondary beam, connect by junction plate I (15), two sides of described junction plate I (15) are connected with the edge of a wing of secondary beam II (4) with short girder I (1) respectively, junction plate I (15) is connected on short girder I (1) and secondary beam II (4) top flange and bottom flange, the other end of described short girder I (1) is connected to secondary beam V (10) middle part, three sides of the extension of short girder I (1) are connected with the edge of a wing and the web at secondary beam V (10) middle part respectively, short girder I (1) is connected with secondary beam V (10) by junction plate I (15), two sides of junction plate I (15) are connected with the edge of a wing of secondary beam V (10) with short girder I (1) respectively, junction plate I (15) is connected on top flange and bottom flange, the other end of described secondary beam II (4) is connected to the middle part of long girder I (6), adopt junction plate I (15) to connect, three sides of extension of secondary beam II (4) are connected with the edge of a wing and the web at long girder I (6) middle part respectively, two sides of junction plate I (15) are connected with the edge of a wing of long girder I (6) with secondary beam II (4) respectively, junction plate I (15) is connected on the top flange and bottom flange of secondary beam II (4) and long girder I (6), all connecting portions are welding, floor (17) adopts shear key to splice on the framework surrounding in short girder I (1), secondary beam II (4), long girder I (6), column base (7), secondary beam V (10),
Described assembling floor A plate and described assembling floor B plate splice, and connecting method is that the long girder I (6) of the long girder I (6) of A plate and B plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor B plate and described assembling floor C plate splice, and connecting method is that the long girder I (6) of the long girder I (6) of B plate and C plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor D plate and described assembling floor E plate splice, connecting method is that the long girder I (6) of the long girder I (6) of D plate and E plate is spliced, described assembling floor E plate and described assembling floor F plate splice, and connecting method is the long girder I (6) of the long girder I (6) of E plate and F plate to be spliced to all splicings all adopt bolt to carry out scene splicing; Described assembling floor A plate and described assembling floor D plate splice, and connecting method is that the secondary beam V (10) of the secondary beam V (10) of A plate and D plate is spliced, and all splicings all adopt bolt to carry out scene splicing; Described assembling floor B plate and described assembling floor E plate splice, connecting method is that the secondary beam V (10) of the secondary beam V (10) of B plate and E plate is spliced, described assembling floor C plate and described assembling floor F plate splice, connecting method is that the secondary beam V (10) of the secondary beam V (10) of C plate and F plate is spliced, and all splicings all adopt bolt to carry out scene splicing;
The basic composition unit of described assembling floor system is A plate, B plate, C plate, D plate, E plate and F plate; The two ends of assembling floor system are A plate and D plate in the horizontal, and B plate and C plate stitch together and can form a module, and this module can be spliced mutually, according to the area of building requirements, increase quantity and the splicing of A plate of this module; E plate and F plate stitch together and can form another module, and this module can be spliced mutually, according to the area of building requirements, increase quantity and the splicing of D plate of this module; The two ends of longitudinally upper assembling floor system are A plate, B plate and C plate, by increasing the intermediate module of D plate, E plate and F plate composition, splice to increase building area; Realize Modularized splice;
Described column base (7) is made up of two flanged plates (11) and a square steel pipe I (12), and two flanged plates (11) lay respectively on two ends of square steel pipe I (12), and all connections all adopt welding; Described flange post (13) is made up of a square steel pipe II (14) and two flanged plates (11), and two flanged plates (11) lay respectively on two ends of square steel pipe II (14), and all connections all adopt welding; Described flange post (13) is connected with column base (7), forms steel frame structural system, and all connections are all with bolts.
2. a kind of how high-rise assembling type steel structure prestressing force support system that rigid joint connects of realizing according to claim 1, it is characterized in that: described short girder I (1), short girder II (2), secondary beam I (3), secondary beam II (4), long girder II (8), secondary beam IV (9) are H shaped steel, or two back-to-back equivalent H shaped steel that are spliced of channel-section steel, or two equivalent H shaped steel that T-steel is spliced, or four equivalent H shaped steel that angle splice joint forms; Described secondary beam III (5), long girder I (6), secondary beam V (10) are channel-section steels, or two equivalent channel-section steels that angle splice joint forms.
3. a kind of how high-rise assembling type steel structure system of modularization that rigid joint connects that realizes according to claim 1, is characterized in that: all beams are section steel beams, or in the Steel Castellated Beams of the web place of beam opening holes, is convenient to various pipelines and passes.
CN201410105171.0A 2014-03-20 2014-03-20 A kind of many high-rise assembling type steel structure systems of modularization realizing rigid joint connection Expired - Fee Related CN103898971B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410105171.0A CN103898971B (en) 2014-03-20 2014-03-20 A kind of many high-rise assembling type steel structure systems of modularization realizing rigid joint connection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410105171.0A CN103898971B (en) 2014-03-20 2014-03-20 A kind of many high-rise assembling type steel structure systems of modularization realizing rigid joint connection

Publications (2)

Publication Number Publication Date
CN103898971A true CN103898971A (en) 2014-07-02
CN103898971B CN103898971B (en) 2016-08-17

Family

ID=50990522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410105171.0A Expired - Fee Related CN103898971B (en) 2014-03-20 2014-03-20 A kind of many high-rise assembling type steel structure systems of modularization realizing rigid joint connection

Country Status (1)

Country Link
CN (1) CN103898971B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105522500A (en) * 2016-01-28 2016-04-27 中交第二航务工程局有限公司 Overall modularized finish-machined positioning device for steel components

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5333426A (en) * 1993-01-06 1994-08-02 Forintek Canada Corporation Wood frame construction system with prefabricated components
JPH06280307A (en) * 1993-03-29 1994-10-04 Sumitomo Metal Ind Ltd Column beam joint part
CN101748903A (en) * 2009-12-31 2010-06-23 宝业集团浙江建设产业研究院有限公司 Structural system of industrial low storied dwelling
CN201785865U (en) * 2010-09-28 2011-04-06 杨峰 Structure and system for house combining external prestress post tensioning method steel beam and pretensioning method prestress composite beam
CN102995743A (en) * 2012-11-26 2013-03-27 北京工业大学 Multi-high-rise assembly type steel structure system
CN103334491A (en) * 2013-06-24 2013-10-02 北京工业大学 Multi-story high-rise fabricated steel-structure special-shaped column framework supporting system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5333426A (en) * 1993-01-06 1994-08-02 Forintek Canada Corporation Wood frame construction system with prefabricated components
JPH06280307A (en) * 1993-03-29 1994-10-04 Sumitomo Metal Ind Ltd Column beam joint part
CN101748903A (en) * 2009-12-31 2010-06-23 宝业集团浙江建设产业研究院有限公司 Structural system of industrial low storied dwelling
CN201785865U (en) * 2010-09-28 2011-04-06 杨峰 Structure and system for house combining external prestress post tensioning method steel beam and pretensioning method prestress composite beam
CN102995743A (en) * 2012-11-26 2013-03-27 北京工业大学 Multi-high-rise assembly type steel structure system
CN103334491A (en) * 2013-06-24 2013-10-02 北京工业大学 Multi-story high-rise fabricated steel-structure special-shaped column framework supporting system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105522500A (en) * 2016-01-28 2016-04-27 中交第二航务工程局有限公司 Overall modularized finish-machined positioning device for steel components

Also Published As

Publication number Publication date
CN103898971B (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN103184762B (en) Multi-story/high-rise fabricated steel structural prestressed supporting system capable of realizing rigid connection of joints
CN103206014B (en) Multi-high-rise assembled steel structure frame supporting system capable of realizing rigid connection of joints
CN103195163B (en) Multiple high-level assembly steel structure system capable of realizing rigid node connections
CN103898975A (en) Modularized multi-high-layer assembly type steel-structure framework eccentric supporting system
CN103898971A (en) Modularized multi-storey and high-rise assembly type steel structure system for achieving rigid joint connection
CN103899021A (en) Assembly type steel frame meshing splicing system for rigid joint
CN103898970A (en) Assembly-type steel frame prestress center support meshed splicing system of rigid joints
CN103882944A (en) Modularized multi-story and high-rise assembly type steel structure frame system
CN103882941A (en) Modularized multi-story and high-rise assembly type steel structure frame center supporting system
CN103882954B (en) The how high-rise assembling type steel structure eccentrical braces of a kind of modularization
CN103882947A (en) Industrialized assembled type steel frame eccentric supporting meshed spliced system
CN103882946B (en) Modular how high-rise assembling type steel structure prestressing force eccentrical braces
CN103866853A (en) Industrialized modularized high-rise assembled steel structure framework system
CN103898969A (en) Assembly type steel frame eccentric supporting and meshing splicing system for rigid joint
CN103882943A (en) Pitch point rigid connection modularization assembly type steel structure central supporting system
CN103866854A (en) Assembly type steel structure prestressing force center supporting, engaging and splicing system with rigidly connected joints
CN103882983A (en) Pitch point rigid connection modularization assembly type steel structure prestressing eccentric supporting system
CN103882942A (en) Center supporting system of modularization multi-storey and high-rise assembling type steel structure
CN103866856A (en) Center support occlusion splicing system of assembly type steel structure with rigid-connection nodes
CN103866852A (en) High-rise fabricated steel structure center support system of holding-on splicing
CN103898965A (en) Meshing-spliced multi-high-layer assembled steel structural system
CN103882984A (en) Pitch point rigid connection assembly type steel structure occlusion splicing system
CN103882945B (en) A kind of modularization how high-rise assembling type steel structure prestressing force center support system
CN103882939B (en) The assembled steel frame pre-stress bias of rigidity node supports occlusion splicing system
CN103882955A (en) Eccentric supporting system of meshing spliced multi-storey and high-rise assembly type steel structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200717

Address after: 050000 room 2103, unit 2, building 17, Everest international, No.180, Zhufeng street, hi tech Zone, Shijiazhuang City, Hebei Province

Patentee after: Hebei Hao Zhen Intellectual Property Agency Service Co.,Ltd.

Address before: 100124 Chaoyang District, Beijing Ping Park, No. 100

Patentee before: Beijing University of Technology

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201012

Address after: 244000 No. 316, building A, hi tech Innovation Service Center, Anhui, Tongling

Patentee after: TONGLING XIANGYU COMMERCE AND TRADE Co.,Ltd.

Address before: 050000 room 2103, unit 2, building 17, Everest international, No.180, Zhufeng street, hi tech Zone, Shijiazhuang City, Hebei Province

Patentee before: Hebei Hao Zhen Intellectual Property Agency Service Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160817