CN103898908A - Method for planting piles in seabed bare rock or shallow overburden area through balancing weights - Google Patents

Method for planting piles in seabed bare rock or shallow overburden area through balancing weights Download PDF

Info

Publication number
CN103898908A
CN103898908A CN201410083926.1A CN201410083926A CN103898908A CN 103898908 A CN103898908 A CN 103898908A CN 201410083926 A CN201410083926 A CN 201410083926A CN 103898908 A CN103898908 A CN 103898908A
Authority
CN
China
Prior art keywords
balancing weight
ship
seabed
planted
shallow overburden
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410083926.1A
Other languages
Chinese (zh)
Inventor
李新强
刘开来
明小华
孙海舰
吴永强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, CCCC Third Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201410083926.1A priority Critical patent/CN103898908A/en
Publication of CN103898908A publication Critical patent/CN103898908A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a method for planting piles in a seabed bare rock or shallow overburden area through balancing weights. The method includes the following steps that first, foundation riprapping is performed; second, the balancing weights are hoisted; third, a gondola is lifted and carried; fourth, the balancing weights are installed. The method for planting piles in the seabed bare rock or shallow overburden area through the balancing weights solves the problem that it is difficult to plant piles in the seabed bare rock or shallow overburden area, avoids the influence factors of poor geological conditions making the piles difficult to plant and guarantees construction efficiency. A construction machine used in the installing process is simple and easy to operate.

Description

The naked rock in seabed or shallow overburden region balancing weight are planted piling method
Technical field
The present invention relates to the naked rock in a kind of seabed or shallow overburden region balancing weight is planted piling method.
Background technology
In prior art, in trestle construction steel pipe pile plant stake all take vibrating hammer pile-sinking method as main, but naked rock or shallow overburden region cannot be implemented in seabed.
Summary of the invention
The object of this invention is to provide a kind of naked rock in the seabed of planting a problem or shallow overburden region balancing weight that has solved in seabed naked rock or shallow overburden region and plant piling method.
The technical scheme that the present invention adopted is for achieving the above object: the naked rock in a kind of seabed or shallow overburden region balancing weight are planted piling method, comprise the following steps:
A, basic jackstone: refuted and added backacter and carry out jackstone operation by haul side, after the lower guide rail of diving, commander's backacter carries out jackstone in formulation position, and Divers Yong Gua road strikes off;
B, balancing weight lifting: crane ship is ready, crane ship puts down main hook, by snap ring, wire rope and balancing weight block are connected, hang on the main hook of crane ship with wire rope again, after wire rope all hangs up properly, check the suspension situation of wire rope and eave tile and snap ring, confirm errorless after, commander's crane ship plays hook, then makes to hang ship and rises and hook and stranded cable, move ship balancing weight block is moved to and hung on ship;
Ship is hung in C, delivery: tugboat haul is hung ship and stayed position to installation region, hang on ship survey crew by GPS locate hang ship to corresponding balancing weight infield in;
D, balancing weight are installed: while hanging the installation of ship lifting balancing weight, ship's staff regulates balancing weight direction, and diver contacts by setting-out baseline and liaison man, and the full-time commanding of commander's loop wheel machine, regulates balancing weight to be in place.
The height minimum of the basic jackstone in described steps A is 0.5m.
In balancing weight in described step B, be prefabricated with steel pipe pile, and in steel pipe pile fluid concrete.
In described step B, every wire rope is connected in a certain order with each suspension centre.
While hanging the installation of ship lifting balancing weight in described step D, first on two steel pipe piles, install respectively two cable wind ropes, ship's staff regulates balancing weight direction by cable wind rope.
In described step D, in balancing weight installation process He after installation, to carry out underwater photography, carry out underwater camera and take pictures completing the counterweight block bottom of installation and the rubble leveling basis at edge, retain image data.
After in described step D, balancing weight is in place, survey crew uses coordinate to carry out repetition measurement by GPS to two steel pipe piles, and use guiding ruler to measure steel pipe pile verticality, after meeting the demands, diver unloads snap ring, is reinstalled on wire rope, by suspension hook, suspender is carried back, hang ship and adjust position, carry out next fast balancing weight and install.
A kind of naked rock in seabed of the present invention or shallow overburden region balancing weight are planted piling method, have solved the naked rock in seabed or shallow overburden region and have planted a difficult problem; Avoid planting because of features as poor geologic condition the influence factor of stake difficulty, guaranteed efficiency of construction; In installation process, construction equipment used is simple, easy to operate.
Accompanying drawing explanation
Fig. 1 is the pierre-perdue floor map that the naked rock in a kind of seabed of the present invention or shallow overburden region balancing weight are planted piling method.
Fig. 2 is that a kind of naked rock in seabed of the present invention or shallow overburden region balancing weight are planted piling method pierre-perdue schematic cross-section.
Fig. 3 is that a kind of naked rock in seabed of the present invention or shallow overburden region balancing weight are planted piling method balancing weight floor map.
Fig. 4 is that a kind of naked rock in seabed of the present invention or shallow overburden region balancing weight are planted piling method balancing weight schematic cross-section.
The specific embodiment
As shown in Figures 1 to 4, the naked rock in seabed or shallow overburden region balancing weight are planted piling method, the height minimum thickness of pierre-perdue is 0.5m, leg wire of slope is not less than 1.0m apart from balancing weight edge, steel pipe pile 1 is in advance in balancing weight, and at the interior fluid concrete of steel pipe pile 1, its concrete installation steps are: A, basic jackstone: the construction technology that base bed flattening adopts guide rail to scrape, refute and add backacter and carry out jackstone operation 300T haul side, diving has descended after guide rail, commander's backacter carries out jackstone in formulation position, and Divers Yong Gua road strikes off, B, balancing weight lifting: after crane ship is ready, crane ship slowly puts down main hook, lifting librarian use snap ring connects wire rope and block, again two wire rope are hung on the eave tile of crane ship, the connection of every wire rope and each suspension centre is according to a definite sequence, after wire rope all hangs up properly, lifting personnel carefully check suspension situation and eave tile and the snap ring of wire rope, avoid the situation that occurs that wire rope laminates mutually, confirm errorless after, commander's crane ship slowly plays hook, after wire rope is energetic, stop hooking, again check every wire rope, the situation of snap ring, then continue commander's crane ship and slowly play hook, when block hangs ground 10cm, crane ship has stopped hooking again, again conscientiously checked the situation of block and Current Collector Sleave by lifting personnel, check whether wire rope has fracture of wire, necking down, wearing and tearing, corrosion, the situations such as distortion, in work progress, to note strengthening the maintaining to wire rope, after guaranteeing that the service behaviour of wire rope is normal, notice is hung ship and is played hook stranded cable, moving ship moves to block stably and hangs on ship, ship is hung in C, delivery: tugboat haul is hung ship and stayed position to installation region, hang on ship survey crew by GPS locate hang ship to corresponding balancing weight infield in, D, balancing weight is installed: while hanging the installation of ship lifting balancing weight, two steel pipe piles 1 on install respectively and pull two cable ropes, ship's staff regulates balancing weight direction by cable rope, diver contacts by setting-out baseline and liaison man, the full-time commanding of commander's loop wheel machine, adjusting balancing weight is in place, survey crew uses GPS to use coordinate to carry out repetition measurement to two steel pipe piles 1 and meets the demands, and after using guiding ruler measurement steel pipe pile verticality to meet the demands, diver unloads snap ring, be reinstalled on wire rope, by suspension hook, suspender is carried back, hang ship and adjust position, carrying out next fast balancing weight installs.The naked rock in seabed of the present invention or shallow overburden region balancing weight are planted piling method, have solved the naked rock in seabed or shallow overburden region and have planted a difficult problem; Avoid planting because of features as poor geologic condition the influence factor of stake difficulty, guaranteed efficiency of construction; In installation process, construction equipment used is simple, easy to operate.

Claims (7)

1. the naked rock in seabed or shallow overburden region balancing weight are planted a piling method, it is characterized in that: comprise the following steps:
A, basic jackstone: refuted and added backacter and carry out jackstone operation by haul side, after the lower guide rail of diving, commander's backacter carries out jackstone in formulation position, and Divers Yong Gua road strikes off;
B, balancing weight lifting: crane ship is ready, crane ship puts down main hook, by snap ring, wire rope and balancing weight block are connected, hang on the main hook of crane ship with wire rope again, after wire rope all hangs up properly, check the suspension situation of wire rope and eave tile and snap ring, confirm errorless after, commander's crane ship plays hook, then makes to hang ship and rises and hook and stranded cable, move ship balancing weight block is moved to and hung on ship;
Ship is hung in C, delivery: tugboat haul is hung ship and stayed position to installation region, hang on ship survey crew by GPS locate hang ship to corresponding balancing weight infield in;
D, balancing weight are installed: while hanging the installation of ship lifting balancing weight, ship's staff regulates balancing weight direction, and diver contacts by setting-out baseline and liaison man, and the full-time commanding of commander's loop wheel machine, regulates balancing weight to be in place.
2. the naked rock in a kind of seabed according to claim 1 or shallow overburden region balancing weight are planted piling method, it is characterized in that: the height minimum of the basic jackstone in described steps A is 0.5m.
3. the naked rock in a kind of seabed according to claim 1 or shallow overburden region balancing weight are planted piling method, it is characterized in that: in the balancing weight in described step B, be prefabricated with steel pipe pile, and in steel pipe pile fluid concrete.
4. the naked rock in a kind of seabed according to claim 1 or shallow overburden region balancing weight are planted piling method, it is characterized in that: in described step B, every wire rope is connected in a certain order with each suspension centre.
5. the naked rock in a kind of seabed according to claim 1 or shallow overburden region balancing weight are planted piling method, it is characterized in that: while hanging the installation of ship lifting balancing weight in described step D, first on two steel pipe piles, install respectively two cable wind ropes, ship's staff regulates balancing weight direction by cable wind rope.
6. the naked rock in a kind of seabed according to claim 1 or shallow overburden region balancing weight are planted piling method, it is characterized in that: in described step D, in balancing weight installation process He after installation, will carry out underwater photography, carry out underwater camera and take pictures completing the counterweight block bottom of installation and the rubble leveling basis at edge, retaining image data.
7. the naked rock in a kind of seabed according to claim 1 or shallow overburden region balancing weight are planted piling method, it is characterized in that: after in described step D, balancing weight is in place, survey crew uses coordinate to carry out repetition measurement by GPS to two steel pipe piles, and use guiding ruler to measure steel pipe pile verticality, after meeting the demands, diver unloads snap ring, be reinstalled on wire rope, by suspension hook, suspender is carried back, hung ship and adjust position, carry out next piece balancing weight and install.
CN201410083926.1A 2014-03-10 2014-03-10 Method for planting piles in seabed bare rock or shallow overburden area through balancing weights Pending CN103898908A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410083926.1A CN103898908A (en) 2014-03-10 2014-03-10 Method for planting piles in seabed bare rock or shallow overburden area through balancing weights

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410083926.1A CN103898908A (en) 2014-03-10 2014-03-10 Method for planting piles in seabed bare rock or shallow overburden area through balancing weights

Publications (1)

Publication Number Publication Date
CN103898908A true CN103898908A (en) 2014-07-02

Family

ID=50990461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410083926.1A Pending CN103898908A (en) 2014-03-10 2014-03-10 Method for planting piles in seabed bare rock or shallow overburden area through balancing weights

Country Status (1)

Country Link
CN (1) CN103898908A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09111764A (en) * 1995-10-19 1997-04-28 Hotta Kensetsu Kk Special catch fork for pile-driving for ocean working ship
CN101666081A (en) * 2009-09-23 2010-03-10 中交二公局第六工程有限公司 Abrupt slope bare rock drilling platform and technology in huge reservoir
CN102312442A (en) * 2011-07-01 2012-01-11 中铁大桥局股份有限公司 Construction method of trestle steel pipe pile foundation
CN102677592A (en) * 2012-05-24 2012-09-19 中国水电建设集团十五工程局有限公司 Method for erecting deepwater steel trestle and platform on exposed bedrock in shallow sea
CN203049443U (en) * 2012-12-14 2013-07-10 中铁上海工程局有限公司 High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09111764A (en) * 1995-10-19 1997-04-28 Hotta Kensetsu Kk Special catch fork for pile-driving for ocean working ship
CN101666081A (en) * 2009-09-23 2010-03-10 中交二公局第六工程有限公司 Abrupt slope bare rock drilling platform and technology in huge reservoir
CN102312442A (en) * 2011-07-01 2012-01-11 中铁大桥局股份有限公司 Construction method of trestle steel pipe pile foundation
CN102677592A (en) * 2012-05-24 2012-09-19 中国水电建设集团十五工程局有限公司 Method for erecting deepwater steel trestle and platform on exposed bedrock in shallow sea
CN203049443U (en) * 2012-12-14 2013-07-10 中铁上海工程局有限公司 High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
姚杰等: "配重块植桩施工工艺", 《中国房地产业》 *

Similar Documents

Publication Publication Date Title
CN103924597B (en) Platform-type jackstone leveling ship and construction method thereof
CN109629568A (en) The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating
CN106703420B (en) Large span ball node Reticulated dome group's dead man lifting construction engineering method
CN104480865B (en) A kind of Large Steel open caisson accurate positioning method
CN104929044A (en) Construction method for offshore steel trestle
CN109853567A (en) A kind of pile sinking process of offshore wind farm steel tube pile embeded in rock
CN106801431B (en) A kind of three rise gantry type wind power foundation structure and its construction method certainly
JP2013221285A (en) Upper surface leveling method, seafloor foundation construction method and upper surface leveling system
CN102720222A (en) Tail-end deviation rectifying process for immersed pipe
CN105507325A (en) Pile stabilizing and positioning platform
CN107034931A (en) Steel-pipe pile testing apparatus for verticality and deep water steel pipe pile construction method
CN107386453B (en) High-rise House on stilts construction method
CN113897959A (en) Underwater positioning guide frame for offshore wind power foundation pile sinking and pile sinking construction method
CN104404888B (en) A kind of large-scale aerial gradient adjustment Lift-on/Lift-off System and application
CN204780836U (en) Fixed drilling platform of adjustable floating
CN102704512B (en) Immersed tube bottom jack type deviation rectifying fine adjusting system and adjusting technology
CN110656890B (en) Deepwater geological drilling casing, casing hoisting system and casing hoisting method
CN103898908A (en) Method for planting piles in seabed bare rock or shallow overburden area through balancing weights
CN104234636A (en) Installation method for self-elevating platform derrick
CN106939613B (en) A kind of four rise gantry type wind power foundation structure and its construction method certainly
CN105155427A (en) Construction method for laying suspension bridge catwalk
CN105256847B (en) A kind of submerged structure positioning transfer measurement apparatus and method
CN202913431U (en) Immersed tube bottom end jack type deviation-rectifying accurate adjustment system
CN205077529U (en) Measuring device is shifted to submerged structure location
CN103352598A (en) Positioning tower used for mounting multilayer cubic blocks in deep water

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140702