CN103882829A - Foaming concrete retaining wall used for preventing debris flow disasters and building and maintaining method - Google Patents

Foaming concrete retaining wall used for preventing debris flow disasters and building and maintaining method Download PDF

Info

Publication number
CN103882829A
CN103882829A CN201410082335.2A CN201410082335A CN103882829A CN 103882829 A CN103882829 A CN 103882829A CN 201410082335 A CN201410082335 A CN 201410082335A CN 103882829 A CN103882829 A CN 103882829A
Authority
CN
China
Prior art keywords
cellular concrete
stone
mud
preventing
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410082335.2A
Other languages
Chinese (zh)
Inventor
陈锐
吴跃东
刘坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Graduate School Harbin Institute of Technology
Original Assignee
Shenzhen Graduate School Harbin Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Graduate School Harbin Institute of Technology filed Critical Shenzhen Graduate School Harbin Institute of Technology
Priority to CN201410082335.2A priority Critical patent/CN103882829A/en
Publication of CN103882829A publication Critical patent/CN103882829A/en
Pending legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention provides a foaming concrete retaining wall used for preventing debris flow disasters and a building and maintaining method. The retaining wall and the method are used for landslide prevention. A mountain has a slope, the foaming concrete retaining wall used for preventing the debris flow disasters comprises foaming concrete and a rock retaining wall, the rock retaining wall is provided with a front slope, the foaming concrete is poured on the front slope of the rock retaining wall and formed by mixing foam, concrete, aggregate and water, the foam is made of foaming agents, and the foaming concrete retaining wall used for preventing the debris flow disasters is arranged on a slope toe. According to the foaming concrete retaining wall, the foaming concrete serves as an energy consumption material, sources of the aggregate are wide, local materials or building wastes can be used, and the materials are low in carbon and environmentally friendly; the foaming concrete retaining wall is high in corrosion resistance, good in long-term performance and low in later maintenance cost.

Description

For preventing the cellular concrete barricade of mud-stone flow disaster and building maintaining method
Technical field
The present invention relates to a kind of cellular concrete barricade and build maintaining method, relating in particular to a kind of for preventing the cellular concrete barricade of mud-stone flow disaster and building maintaining method.
Background technology
Slope, is seen everywhere in China, distributes extremely extensive.But the natural calamity that cause on slope, as landslide and mud-rock flow etc., often sudden strong, harmfulness is large, especially in densely populated Hong Kong, Shenzhen, Chongqing etc.The disaster that cause on slope not only causes huge property loss, also can cause a tremendous loss of lives.The method of preventing and treating of the disaster that at present, cause on slope has two classes: initiatively protection and passive protection.Initiatively protection is to stop in advance slope to produce landslide, mud-stone flow disaster, as sets antislide pile etc.Passive protection is in the generation that allows disaster, but avoids disaster to work the mischief.Initiatively protection is because control area is large, and expense is huge, is often used in that slope is less and particular importance is regional.Passive control is widely used in slope treatment because cost is low and efficiency is high.In passive control, halfway sliding mass or mud-rock flow etc. being tackled is a kind of effectively safeguard procedures.The features such as motion path based on sliding mass and mud-rock flow, sliding rate, slippage scope, barricade is used to tackle sliding mass and mud-rock flow etc., to ensure property and life security in guard plot.
Gabion baffling is a kind of common passive protection barricade.Because its price is relatively cheap, in intercept process, distortion greatly, absorbs energy large, in passive protection, is widely used.But gabion baffling wire is easy to corrosion, long-term behaviour is not good, and later maintenance expense is larger.Gabion baffling needs large-scale stone, brings challenges to transport and the carrying in the mountain area of complicated condition.And for building after calamity, gabion baffling often needs to reconstruct again, the construction time is long, has increased the disaster-stricken risk in urban conservation area.
Summary of the invention
In order to overcome above-mentioned the deficiencies in the prior art, the invention provides a kind of for preventing the cellular concrete barricade of mud-stone flow disaster and building maintaining method.
A kind of for preventing the cellular concrete barricade of mud-stone flow disaster, for the control of landslide, described massif has slope, it is characterized in that: describedly comprise cellular concrete and stone cut off wall for the cellular concrete barricade that prevents mud-stone flow disaster, described stone cut off wall be provided with meet domatic, it is domatic that described cellular concrete is cast in meeting of stone cut off wall, described cellular concrete by bubble, cement, aggregate and water through mixing, wherein said bubble adopts blowing agent to make, described for preventing the cellular concrete dams setting of mud-stone flow disaster under toe of a slope.
Further, described maximum aggregate size is 5mm.
Further, described stone cut off wall is rigidity stone cut off wall, and the thickness of described stone cut off wall is 0.2m to 2m.
Further, the thickness of described cellular concrete is 0.2 to 1m, and the height of described cellular concrete is identical with stone cut off wall height.
Further, described cellular concrete is mixed by bubble, cement, aggregate and water, and the ratio of described bubble, cement, aggregate is bubble: cement: aggregate is about 700L:330kg:1200kg.
Further, described cement adopts Portland cement, and its strength grade is not less than 32.5.
Further, described aggregate adopts one or more of on-the-spot soil, building castoff or mud-rock flow relict soil/Shi Tizhong.
Further, the mobility of described cellular concrete is 160 to 190mm, and moist unit weight is 5 to 13 kN/m 3, air capacity 20 to 70%, 28 days unconfined compression strengths 0.5 to 2MPa.
For preventing the construction maintaining method of cellular concrete barricade for mud-stone flow disaster, comprise the following steps,
The first step: build stone cut off wall;
Second step: leveling stone cut off wall is met domatic ground, builds the template for building cellular concrete;
The 3rd step: mix bubble, cement, aggregate and water, prepare standard compliant cellular concrete;
The 4th step: adopt pumping equipment that the cellular concrete of new system is delivered in template;
The 5th step: maintain certain humidity, maintenance cellular concrete is after 28 days, stripping.
Compared to prior art, cellular concrete stone cut off wall of the present invention is taking cellular concrete as power consumption material, and institute's aggregate that adopts is originated extensively, can gather materials on the spot, and maybe can adopt building castoff, low-carbon environment-friendly; Cellular concrete barricade has stronger corrosion resistance, and long-term behaviour is good, and later maintenance expense is low; Cellular concrete is macrovoid material, has reduced construction price; The distortion when soil body clashes into is large, even broken, and power consumption significantly; Cellular concrete stream plasticity is good, and easy construction is especially applicable to the rugged complex conditions that waits of physical features; Stand after disaster, only need cellular concrete to repair, and aggregate can adopt landslide or the mud-rock flow soil body, convenience, simple, quick.
Brief description of the drawings
Fig. 1 is of the present invention for preventing the structural representation of cellular concrete barricade of mud-stone flow disaster.
Detailed description of the invention
Below in conjunction with brief description of the drawings and detailed description of the invention, the present invention is further described.
Refer to Fig. 1, the invention provides a kind of for preventing the cellular concrete barricade of mud-stone flow disaster and building maintaining method.Described for preventing the cellular concrete barricade of mud-stone flow disaster to build in 1 underfooting, slope near zone of protection 5 places.Specifically, for preventing the cellular concrete barricade of mud-stone flow disaster to build between 1 underfooting, slope and zone of protection 5.
Described cellular concrete barricade comprises cellular concrete 3 and stone cut off wall 4, and stone cut off wall 4 is provided with towards meeting of slope 1 one sides domatic.Described cellular concrete 3 is padded coaming, be cast in meeting of stone cut off wall 4 domatic, described cellular concrete 3 is formed through mixing and maintenance by bubble, cement, aggregate and water, bubble is produced by blowing agent, aggregate can be selected on-the-spot soil, building castoff or mud-rock flow relict soil/stone body according to field condition, as optimal way, aggregate is selected building castoff.
Described stone cut off wall 4 requires as rigidity, and thickness is 0.2m to 2m, and as optimal way, the thickness of stone cut off wall 4 is 2m.Described cellular concrete 3 is padded coaming, is cast in meeting of stone cut off wall 4 domatic, and the thickness of cellular concrete 3 is 0.2 to 1m, and height is highly consistent with stone cut off wall 4, and as optimal way, the thickness of cellular concrete is 0.5m.
Described cellular concrete 3 is formed through mixing and maintenance by bubble, cement, aggregate and water, and bubble is produced by blowing agent, and cement is Portland cement (PO), and strength grade is not less than 32.5, as optimal way, and cement selection Portland cement 32.5.Described maximum aggregate size is 5mm.Be understandable that, the generation type of described cellular concrete 3, with of the prior art concrete to make mode consistent, does not repeat them here.In the present embodiment, the ratio of described bubble, cement, aggregate is bubble: cement: aggregate is about 700L:330kg:1200kg.Be understandable that, the consumption of raw material can increase and decrease on year-on-year basis according to above ratio, to adapt to the cellular concrete barricade of different size.
The mobility of described cellular concrete 3 is 160 to 190mm, moist unit weight is 5 to 13 kN/m3, air capacity is 20 to 70%, within 28 days, unconfined compression strength 0.5 is to 2MPa, as optimal way, the mobility of described cellular concrete 3 is 180mm, and moist unit weight is 6 kN/m3, air capacity was at 60%, 28 day unconfined compression strength 0.8MPa
For preventing the construction maintaining method of cellular concrete barricade for mud-stone flow disaster, comprise the steps:
The first step: build stone cut off wall 4;
Second step: leveling stone cut off wall 4 is met domatic ground, builds the template for building cellular concrete 3;
The 3rd step: mix bubble, cement, aggregate and water, prepare standard compliant cellular concrete 3;
The 4th step: adopt pumping equipment that the cellular concrete of new system 3 is delivered in template;
The 5th step: maintain certain humidity, maintenance cellular concrete is after 28 days, stripping.
Be understandable that, above method also can be applicable to safeguard after the calamity of cellular concrete barricade.
Beneficial effect of the present invention is: cellular concrete stone cut off wall is taking cellular concrete as power consumption material, and institute's aggregate that adopts is originated extensively, can gather materials on the spot, and maybe can adopt building castoff, low-carbon environment-friendly; Cellular concrete barricade has stronger corrosion resistance, and long-term behaviour is good, and later maintenance expense is low; Cellular concrete is macrovoid material, has reduced construction price; The distortion when soil body clashes into is large, even broken, and power consumption significantly; Cellular concrete stream plasticity is good, and easy construction is especially applicable to the rugged complex conditions that waits of physical features; Stand after disaster, only need cellular concrete to repair, and aggregate can adopt landslide or the mud-rock flow soil body, convenience, simple, quick.
Above content is in conjunction with concrete preferred embodiment further description made for the present invention, can not assert that specific embodiment of the invention is confined to these explanations.For general technical staff of the technical field of the invention, without departing from the inventive concept of the premise, can also make some simple deduction or replace, all should be considered as belonging to protection scope of the present invention.

Claims (9)

1. one kind for preventing the cellular concrete barricade of mud-stone flow disaster, for the control of landslide, described massif has slope, it is characterized in that: describedly comprise cellular concrete and stone cut off wall for the cellular concrete barricade that prevents mud-stone flow disaster, described stone cut off wall be provided with meet domatic, it is domatic that described cellular concrete is cast in meeting of stone cut off wall, described cellular concrete by bubble, cement, aggregate and water through mixing, wherein said bubble adopts blowing agent to make, described for preventing the cellular concrete dams setting of mud-stone flow disaster under toe of a slope.
2. according to claim 1 for preventing the cellular concrete barricade of mud-stone flow disaster, it is characterized in that: described maximum aggregate size is 5mm.
3. according to claim 1 for preventing the cellular concrete barricade of mud-stone flow disaster, it is characterized in that: described stone cut off wall is rigidity stone cut off wall, the thickness of described stone cut off wall is 0.2m to 2m.
4. according to claim 1 for preventing the cellular concrete barricade of mud-stone flow disaster, it is characterized in that: the thickness of described cellular concrete is 0.2 to 1m, and the height of described cellular concrete is identical with stone cut off wall height.
5. according to claim 1 for preventing the cellular concrete barricade of mud-stone flow disaster, it is characterized in that: described cellular concrete is mixed by bubble, cement, aggregate and water, the ratio of described bubble, cement, aggregate is bubble: cement: aggregate is about 700L:330kg:1200kg.
6. according to claim 5 for preventing the cellular concrete barricade of mud-stone flow disaster, it is characterized in that: described cement adopts Portland cement, and its strength grade is not less than 32.5.
7. according to claim 5 for preventing the cellular concrete barricade of mud-stone flow disaster, it is characterized in that: described aggregate adopts one or more of on-the-spot soil, building castoff or mud-rock flow relict soil/Shi Tizhong.
8. according to claim 5 for preventing the cellular concrete barricade of mud-stone flow disaster, it is characterized in that: the mobility of described cellular concrete is 160 to 190mm, and moist unit weight is 5 to 13 kN/m 3, air capacity 20 to 70%, 28 days unconfined compression strengths 0.5 to 2MPa.
9. for preventing the construction maintaining method of cellular concrete barricade for mud-stone flow disaster, it is characterized in that: comprise the following steps,
The first step: build stone cut off wall;
Second step: leveling stone cut off wall is met domatic ground, builds the template for building cellular concrete;
The 3rd step: mix bubble, cement, aggregate and water, prepare standard compliant cellular concrete;
The 4th step: adopt pumping equipment that the cellular concrete of new system is delivered in template;
The 5th step: maintain certain humidity, maintenance cellular concrete is after 28 days, stripping.
CN201410082335.2A 2014-03-07 2014-03-07 Foaming concrete retaining wall used for preventing debris flow disasters and building and maintaining method Pending CN103882829A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410082335.2A CN103882829A (en) 2014-03-07 2014-03-07 Foaming concrete retaining wall used for preventing debris flow disasters and building and maintaining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410082335.2A CN103882829A (en) 2014-03-07 2014-03-07 Foaming concrete retaining wall used for preventing debris flow disasters and building and maintaining method

Publications (1)

Publication Number Publication Date
CN103882829A true CN103882829A (en) 2014-06-25

Family

ID=50951932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410082335.2A Pending CN103882829A (en) 2014-03-07 2014-03-07 Foaming concrete retaining wall used for preventing debris flow disasters and building and maintaining method

Country Status (1)

Country Link
CN (1) CN103882829A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652473A (en) * 2015-01-12 2015-05-27 哈尔滨工业大学深圳研究生院 Debris flow protective wall made of foam glass and building method thereof
CN108331013A (en) * 2018-03-21 2018-07-27 中铁第四勘察设计院集团有限公司 Gear mud wall composite structure
CN112942412A (en) * 2021-02-07 2021-06-11 中山大学 Multilayer buffering debris flow protection retaining wall and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009098736A1 (en) * 2008-02-06 2009-08-13 Protec Engineering Inc. Shock absorbing fence
CN101736707A (en) * 2009-12-15 2010-06-16 中国科学院水利部成都山地灾害与环境研究所 Novel energy consumption damping stone blocking structure
CN202031051U (en) * 2010-08-26 2011-11-09 北京道从交通科技有限公司 Guiding highway cushion pad
CN102753498A (en) * 2010-02-18 2012-10-24 拉法基公司 New foamed concrete
CN202899165U (en) * 2012-09-17 2013-04-24 浙江八咏公路工程有限公司 T-shaped wallboard type retaining wall structure of highway subgrade
CN103334385A (en) * 2013-07-09 2013-10-02 中国人民解放军后勤工程学院 Anti-stone-falling flexible stone blocking wall
CN203361033U (en) * 2013-05-27 2013-12-25 中铁工程设计咨询集团有限公司 Protective device for intercepting falling rocks of through cut

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009098736A1 (en) * 2008-02-06 2009-08-13 Protec Engineering Inc. Shock absorbing fence
CN101736707A (en) * 2009-12-15 2010-06-16 中国科学院水利部成都山地灾害与环境研究所 Novel energy consumption damping stone blocking structure
CN102753498A (en) * 2010-02-18 2012-10-24 拉法基公司 New foamed concrete
CN202031051U (en) * 2010-08-26 2011-11-09 北京道从交通科技有限公司 Guiding highway cushion pad
CN202899165U (en) * 2012-09-17 2013-04-24 浙江八咏公路工程有限公司 T-shaped wallboard type retaining wall structure of highway subgrade
CN203361033U (en) * 2013-05-27 2013-12-25 中铁工程设计咨询集团有限公司 Protective device for intercepting falling rocks of through cut
CN103334385A (en) * 2013-07-09 2013-10-02 中国人民解放军后勤工程学院 Anti-stone-falling flexible stone blocking wall

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652473A (en) * 2015-01-12 2015-05-27 哈尔滨工业大学深圳研究生院 Debris flow protective wall made of foam glass and building method thereof
CN108331013A (en) * 2018-03-21 2018-07-27 中铁第四勘察设计院集团有限公司 Gear mud wall composite structure
CN112942412A (en) * 2021-02-07 2021-06-11 中山大学 Multilayer buffering debris flow protection retaining wall and construction method thereof

Similar Documents

Publication Publication Date Title
CN104692729B (en) Harmless solid waste high performance concrete
CN107434378B (en) Low-carbon environment-friendly waste asphalt mixture composite permeable mortar for sponge city and preparation method thereof
CN104099845A (en) Highway pavement structure taking building rubbish as aggregate
CN103882829A (en) Foaming concrete retaining wall used for preventing debris flow disasters and building and maintaining method
CN103938797A (en) Heat-preserving recycled concrete rectangular column with dismantling-free high performance cement mortar mold plate and manufacturing method
CN105777020A (en) Iron tailing sand PVA fiber-reinforced-cement-based composite
CN105366969A (en) Recycled self-hardening cementing material and preparation method thereof
CN107805024A (en) A kind of C25 levels freeze thawing resistance pervious concrete
CN103242012A (en) Foamed concrete based on shale ceramic sand
CN103449776B (en) A kind of construction slurry steaming-free air-adding concrete segment and manufacture method thereof
CN107382235A (en) Utilize the air-entrained concrete building block and its processing method of blast-furnace cinder production
CN104310880A (en) Method for improving freeze-thaw resistance of concrete by using waste incineration fly ash pre-treated by washing
CN102701655A (en) Environmental-protection type regeneration brick and preparation method thereof
CN204700982U (en) A kind of building mixer supporting seat
CN102976675A (en) Mortar-enriched cemented sand and gravel and preparation method thereof
CN106277984A (en) A kind of barren rock ecological brick for mine slope revegetation and preparation method thereof
CN104652473A (en) Debris flow protective wall made of foam glass and building method thereof
CN102260066A (en) Masonry mortar prepared from tailings
CN105294003A (en) Method for preparing cement mortar with gangue particles
CN203361470U (en) Steel tube accommodating type recycled concrete column
CN202731059U (en) Recycled stone waste material concrete heat-insulating porous brick
CN103967211A (en) Dismantling-free high-performance cement mortar template heat preservation regenerative concrete T-shaped column and construction method thereof
CN104294754B (en) T-shaped section steel pipe regeneration concrete pier shaft
CN204038467U (en) A kind of conveyer of coal ash autoclaved aerated-block
CN203769410U (en) Communication tower mast device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140625