CN103879884B - Charging crane - Google Patents

Charging crane Download PDF

Info

Publication number
CN103879884B
CN103879884B CN201410054013.7A CN201410054013A CN103879884B CN 103879884 B CN103879884 B CN 103879884B CN 201410054013 A CN201410054013 A CN 201410054013A CN 103879884 B CN103879884 B CN 103879884B
Authority
CN
China
Prior art keywords
pulley
underarm
forelimb
crane
upper arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410054013.7A
Other languages
Chinese (zh)
Other versions
CN103879884A (en
Inventor
张松范
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410054013.7A priority Critical patent/CN103879884B/en
Publication of CN103879884A publication Critical patent/CN103879884A/en
Application granted granted Critical
Publication of CN103879884B publication Critical patent/CN103879884B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The present invention relates to a kind of charging cranes.Operation principle and step:Brick to be installed must be sling charging crane idle loop by traditional method discharge neat (every layer 20 pieces 10 layers) and then crane before dress to rise, alignment brick part decline to be installed meets top limit and lower idle loop is gone to hang lifting annular rising.At this moment under the action of steel wire rope, upper underarm closes up two forelimbs and holds brick part to be installed rise slowly in the month.Crane turning is unloaded to place to be put.It starts operation back and forth in this way, can so complete handling task, model machine has been trial-produceed successfully.

Description

Charging crane
Charging crane is a kind of specific purpose tool for building brick handling design.It is slightly changed, and can be used in more areas. Charging crane is simple for process, reasonable for structure, and low cost is easy to operate, adaptable, with extensive.Brick has been filled up in its appearance Not mechanical blank is loaded and unloaded, the history of not mechanical handling is finished;A large amount of labour has been saved in its appearance, subtracts significantly The light labor intensity of people;Its appearance is the primary great revolution of construction industry and unprecedented leap.Economic benefit can cause The sensation of construction industry!
Technical field:Construction industry.
Background technology:Using artificial.
Invention content:Using mechanical handling.
Description of the drawings:Fig. 1 is front elevation, and Fig. 2 is side view, and Fig. 3 is combination thick stick.Charging crane slings running by lifting equipment 's.Point can be divided into from type single machine, half single machine and with the series of products such as combination machine.
Specific implementation mode:Single machine is as shown in Figure 1 and Figure 2, including upper arm, underarm, forelimb 1, forelimb 2, weight ring, idle loop, top Limit, steel wire rope, pulley, shaft.Operation principle and step:Brick to be installed must be discharged neatly by traditional method before dress (every layer 20 pieces, 10 layers) and then crane sling the rising of charging crane idle loop, and alignment brick part to be installed, which declines, meets top limit, removes lower idle loop Hang lifting annular rising.At this moment under the action of steel wire rope, upper underarm closes up two forelimbs and holds brick part to be installed rise slowly in the month.Lifting Machine turning is unloaded to place to be put.It starts operation back and forth in this way, can so complete handling task, model machine has been trial-produceed successfully.Combination Machine is that single machine adds combination thick stick (weight thick stick and empty thick stick) composition as shown in figure 3, combination machine can fill imperial two pieces or more every time.Half single machine is single The half of machine height.

Claims (1)

1. a kind of charging crane, including upper arm, underarm, forelimb one, forelimb two, weight ring, idle loop, top limit, steel wire rope, pulley, shaft, The middle part of the upper arm is connect with the forelimb two, and the left part of the underarm is connect with the forelimb one, a left side for the upper arm With the left end of the underarm by including that the connector of shaft is connect, the left end of the underarm can be rotated around the shaft at end, The upper arm is equipped with pulley one, pulley two, and pulley three is connected between the pulley one and pulley two, and the pulley three is equipped with Weight ring, the right part of the upper arm are equipped with pulley four, and the right part of the underarm is equipped with pulley five, described in the steel wire rope connection Pulley one to five, at work, the idle loop that crane slings the charging crane rise, and are directed at brick part to be loaded and unloaded and decline conflict It is limited to the top, then unloads idle loop and hang lifting annular rising, under the action of the steel wire rope, the upper arm and the underarm close Hold together, so that the forelimb one and the forelimb two is clamped the brick part to be loaded and unloaded and rise.
CN201410054013.7A 2014-02-18 2014-02-18 Charging crane Expired - Fee Related CN103879884B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410054013.7A CN103879884B (en) 2014-02-18 2014-02-18 Charging crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410054013.7A CN103879884B (en) 2014-02-18 2014-02-18 Charging crane

Publications (2)

Publication Number Publication Date
CN103879884A CN103879884A (en) 2014-06-25
CN103879884B true CN103879884B (en) 2018-10-09

Family

ID=50949064

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410054013.7A Expired - Fee Related CN103879884B (en) 2014-02-18 2014-02-18 Charging crane

Country Status (1)

Country Link
CN (1) CN103879884B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87209077U (en) * 1987-06-12 1988-06-08 李忠孝 Adjustable labour-saving brick clip
CN2937348Y (en) * 2006-08-16 2007-08-22 翟丕江 Block hoisting basket for building
CN201321344Y (en) * 2008-12-29 2009-10-07 丁显彬 Mechanical brick clip clamping unit device and mechanical brick clip
CN201390633Y (en) * 2009-04-03 2010-01-27 襄樊凡氏佳机械设备厂 Brick pile clamping and transporting device
CN202988567U (en) * 2012-12-06 2013-06-12 速昌海 Gravitational gripper
CN103569849A (en) * 2012-07-25 2014-02-12 刘郑杰 Brick loading and unloading hanging basket

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87209077U (en) * 1987-06-12 1988-06-08 李忠孝 Adjustable labour-saving brick clip
CN2937348Y (en) * 2006-08-16 2007-08-22 翟丕江 Block hoisting basket for building
CN201321344Y (en) * 2008-12-29 2009-10-07 丁显彬 Mechanical brick clip clamping unit device and mechanical brick clip
CN201390633Y (en) * 2009-04-03 2010-01-27 襄樊凡氏佳机械设备厂 Brick pile clamping and transporting device
CN103569849A (en) * 2012-07-25 2014-02-12 刘郑杰 Brick loading and unloading hanging basket
CN202988567U (en) * 2012-12-06 2013-06-12 速昌海 Gravitational gripper

Also Published As

Publication number Publication date
CN103879884A (en) 2014-06-25

Similar Documents

Publication Publication Date Title
CN205381872U (en) Aircraft fuselage turning device
CN204057659U (en) The prefabricated superimposed panel lifting appliance of super large
CN103879884B (en) Charging crane
CN204711168U (en) A kind of feeding casting machine hand
CN204013141U (en) A kind of motor bearings hanger for assembling
CN205713165U (en) A kind of automatic wall building machine
CN204938918U (en) Large-scale water turbine runner stands up instrument
CN203033660U (en) Portable lifting appliance
CN204416920U (en) A kind of self-locking type automatic hanging hook
CN102942137A (en) Hydraulic winch
CN203959664U (en) Drum type inner hole part hoisting device
CN208545014U (en) A kind of large scale equipment switching hanging apparatus
CN207258998U (en) A kind of driving hanger
CN202321955U (en) Multifunctional lifting basket
CN201990375U (en) Hanging tool for hanging electrolytic copper plate
CN205257758U (en) Dipper shovel special lifting device device
CN204022268U (en) Large Precast Members hanging apparatus
CN206692202U (en) One kind lifting transporting device
CN206047067U (en) Multiaxis sandbox overturns structure
CN203833462U (en) Crane lifting tool of steel plate
CN204916918U (en) Novel brick and tile conveying machine
CN204138136U (en) Main frame crosshead hoisting fixture
CN204310686U (en) A kind of charging tray suspender for drying of Chinese wolfberry equipment
CN204297905U (en) A kind of lifting device of precast concrete
CN203977836U (en) A kind of tool-type escalator building formwork platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181009

Termination date: 20210218

CF01 Termination of patent right due to non-payment of annual fee