CN103866810B - Hydraulic engineering remove contamination grab bucket locking means - Google Patents

Hydraulic engineering remove contamination grab bucket locking means Download PDF

Info

Publication number
CN103866810B
CN103866810B CN201410109930.0A CN201410109930A CN103866810B CN 103866810 B CN103866810 B CN 103866810B CN 201410109930 A CN201410109930 A CN 201410109930A CN 103866810 B CN103866810 B CN 103866810B
Authority
CN
China
Prior art keywords
grab bucket
moved cross
cross beam
handle
contamination
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410109930.0A
Other languages
Chinese (zh)
Other versions
CN103866810A (en
Inventor
姚宏超
陈丽晔
周伟
陈松伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Engineering Consulting Co Ltd
Original Assignee
Yellow River Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Engineering Consulting Co Ltd filed Critical Yellow River Engineering Consulting Co Ltd
Priority to CN201410109930.0A priority Critical patent/CN103866810B/en
Publication of CN103866810A publication Critical patent/CN103866810A/en
Application granted granted Critical
Publication of CN103866810B publication Critical patent/CN103866810B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The invention discloses a kind of hydraulic engineering remove contamination grab bucket locking means, one, on the grab bucket handle top end face of grab bucket of removing contamination, be symmetrical in its longitudinal midline both sides fixing font of falling door holder respectively, the aperture of door then running through each font of falling door holder slides respectively and arranges a moved cross beam; Two, on dam body dam facing, be positioned at grab bucket groove both sides fixedly locked seat respectively; Three, on each moved cross beam, postive stop baffle and retraction postive stop baffle are fixedly stretched out in equal interval; Four, non-remove contamination period, by the door machine on dam facing will remove contamination grab bucket be placed in grab bucket groove in, by two moved cross beams respectively to grab bucket handle outside stretch out be mounted in correspondence locking seat on, then grab bucket handle and door machine are departed from; Five, when needs carry out removing contamination operation, door machine is connected with grab bucket handle, then two moved cross beams is retracted into the inside in grab bucket handle top end face and can carries out operation of removing contamination.The invention has the advantages that easy and simple to handle, grab bucket locking characteristics of compact layout of removing contamination.

Description

Hydraulic engineering remove contamination grab bucket locking means
Technical field
The present invention relates to the grab bucket of removing contamination used in hydraulic engineering, especially relate to hydraulic engineering remove contamination grab bucket locking means.
Background technology
In farmland water conservancy works and Hydraulic and Hydro-Power Engineering, adopt the mode that grab bucket 12 coordinates door machine 13 pairs of trashracks 14 to remove contamination of removing contamination to be widely used, as shown in Figure 3, this mode of operation has the advantages such as remove contamination effective, efficiency is high, a tractor serves several purposes.But at present in Hydraulic and Hydro-Power Engineering, grab bucket 12 of removing contamination connects with door machine 13 all the time and plays walking with one.Because the volume of grab bucket 12 of removing contamination and quality are all comparatively large, such mode of operation not only visual effect is not good, the more important thing is and can have a negative impact to other routine works carried out on dam body 5, there is unsafe factor.In view of removing contamination, grab bucket 12 only need use when trashrack 14 is removed contamination, frequency of utilization is lower, therefore grab bucket 12 of removing contamination during non-removing contamination is thrown off with door machine 13, the dam body 5 being locked in grab bucket groove 4 top then be can yet be regarded as a kind of desirable arrangement, but due to the design feature of grab bucket 12 self of removing contamination, yet there are no all reports about this respect.
Summary of the invention
The locking means that the object of the invention is to provide a kind of hydraulic engineering to remove contamination grab bucket.
For achieving the above object, the present invention takes following technical proposals:
The locking means that grab bucket is removed contamination in hydraulic engineering of the present invention, carries out according to following step:
One, be symmetrical in its longitudinal midline both sides and fix the font of falling a door holder respectively on the grab bucket handle top end face of grab bucket of removing contamination, the aperture of door then running through the described each font of falling door holder respectively horizontal slip arranges a moved cross beam;
Two, on the dam facing of dam body, be positioned at grab bucket groove both sides fix a locking seat respectively;
Three, on described each moved cross beam, equal interval is fixed one and is stretched out postive stop baffle and retraction postive stop baffle, described in the distance of stretching out between postive stop baffle and retraction postive stop baffle be: a, when moved cross beam stretches out outside described grab bucket handle, the outer end of moved cross beam should be able to reach the top of described locking seat; B, when moved cross beam is retracted, the outer end of moved cross beam should be able to be retracted in grab bucket handle top end face;
Four, remove contamination period non-, be placed in described grab bucket groove by the grab bucket of removing contamination of the door machine on dam facing, after the top end face of grab bucket handle is flushed with the locking seat end face of described grab bucket groove both sides, two moved cross beams being mounted on corresponding locking seat respectively to stretching out outside grab bucket handle, then grab bucket handle and door machine being departed from;
Five, when needs carry out removing contamination operation, first door machine is connected with grab bucket handle, then two moved cross beams is retracted into the inside in grab bucket handle top end face and can carries out operation of removing contamination.
The invention has the advantages that and realize being locked in after grab bucket of removing contamination is thrown off with door machine by non-period of removing contamination grabbing bucket on the dam body at groove top, walking without the need to linking together with door machine all the time.Grab bucket of removing contamination is locked in the top of grab bucket groove, saves the operating space of dam body, decrease the adverse effect to other routine works of dam facing and unsafe factor, reach the object of safety in production.Meanwhile, the inventive method is easy and simple to handle, removing contamination to grab bucket locks characteristics of compact layout.
Accompanying drawing explanation
Grab bucket of removing contamination is locked in the schematic diagram of grabbing bucket on the dam body of groove top according to the inventive method by Fig. 1.
Fig. 2 is the schematic diagram of grabbing bucket removing contamination when departing from grab bucket groove top dam body according to the inventive method.
Fig. 3 is that existing employing is removed contamination the layout schematic diagram that grab bucket coordinates door machine to remove contamination to trashrack.
Detailed description of the invention
As shown in Figure 1, 2, the locking means that grab bucket is removed contamination in hydraulic engineering of the present invention, carries out according to following step:
One, be symmetrical in its longitudinal midline both sides and fix the font of falling a door holder 2 respectively on grab bucket handle 1 top end face of grab bucket of removing contamination, the aperture of door then running through the described each font of falling door holder 2 respectively horizontal slip arranges a moved cross beam 3;
Two, on the dam facing of dam body 4, be positioned at grab bucket groove 5 both sides fix a locking seat 6 respectively;
Three, on described each moved cross beam 3, equal interval is fixed one and is stretched out postive stop baffle 7 and retraction postive stop baffle 8, described distance of stretching out between postive stop baffle 7 and retraction postive stop baffle 8 is: a, as shown in Figure 1, when moved cross beam 3 stretches out outside described grab bucket handle 1, the outer end of moved cross beam 3 should be able to reach the top of described locking seat 6; B, as shown in Figure 2, when moved cross beam 3 is retracted, the outer end of moved cross beam 3 should be able to be retracted in grab bucket handle 1 top end face;
Four, remove contamination period non-, be placed in described grab bucket groove 5 by the grab bucket of removing contamination of the door machine on dam facing, after the top end face of grab bucket handle 1 is flushed with locking seat 6 end face of described grab bucket groove 5 both sides, two moved cross beams 3 being mounted on corresponding locking seat 6 respectively to stretching out outside grab bucket handle 1, then grab bucket handle 1 and door machine being departed from;
Five, when needs carry out removing contamination operation, first door machine is connected with grab bucket handle 1, within then two moved cross beams 3 being retracted into the inside grab bucket handle 1 top end face, can operation of removing contamination be carried out.
Conveniently the stretching of moved cross beam 3, contract, the outer end of each two moved cross beams 3 arranges a push-and-pull earrings 9 respectively, and like this, namely staff carries out the stretching of moved cross beam 3, operation of contracting by rod member.
When the outer end of moved cross beam 3 is retracted into after in grab bucket handle 1 top end face, for improving the stability of moved cross beam 3, a pin-and-hole 10 and bolt hole 11 can be offered respectively with the sidewall corresponding position of moved cross beam 3 on the sidewall of holder 2, bolt is spirally connected fixing through the pin-and-hole 10 on holder 2 sidewall with the bolt hole 11 on moved cross beam 3 sidewall, like this, when carrying out removing contamination operation, moved cross beam 3 is more firm with the connection of grab bucket handle 1.

Claims (1)

1. hydraulic engineering remove contamination grab bucket a locking means, it is characterized in that: carry out according to following step:
One, be symmetrical in its longitudinal midline both sides and fix the font of falling a door holder respectively on the grab bucket handle top end face of grab bucket of removing contamination, the aperture of door then running through each font of falling door holder respectively horizontal slip arranges a moved cross beam;
Two, on the dam facing of dam body, be positioned at grab bucket groove both sides fix a locking seat respectively;
Three, on each moved cross beam, equal interval is fixed one and is stretched out postive stop baffle and retraction postive stop baffle, described in the distance of stretching out between postive stop baffle and retraction postive stop baffle be: a, when moved cross beam stretches out outside described grab bucket handle, the outer end of moved cross beam should be able to reach the top of described locking seat; B, when moved cross beam is retracted, the outer end of moved cross beam should be able to be retracted in grab bucket handle top end face;
Four, remove contamination period non-, be placed in described grab bucket groove by the grab bucket of removing contamination of the door machine on dam facing, after the top end face of grab bucket handle is flushed with the locking seat end face of described grab bucket groove both sides, two moved cross beams being mounted on corresponding locking seat respectively to stretching out outside grab bucket handle, then grab bucket handle and door machine being departed from;
Five, when needs carry out removing contamination operation, first door machine is connected with grab bucket handle, then two moved cross beams is retracted into the inside in grab bucket handle top end face and can carries out operation of removing contamination.
CN201410109930.0A 2014-03-24 2014-03-24 Hydraulic engineering remove contamination grab bucket locking means Active CN103866810B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410109930.0A CN103866810B (en) 2014-03-24 2014-03-24 Hydraulic engineering remove contamination grab bucket locking means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410109930.0A CN103866810B (en) 2014-03-24 2014-03-24 Hydraulic engineering remove contamination grab bucket locking means

Publications (2)

Publication Number Publication Date
CN103866810A CN103866810A (en) 2014-06-18
CN103866810B true CN103866810B (en) 2016-01-20

Family

ID=50905791

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410109930.0A Active CN103866810B (en) 2014-03-24 2014-03-24 Hydraulic engineering remove contamination grab bucket locking means

Country Status (1)

Country Link
CN (1) CN103866810B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0180642B1 (en) * 1996-06-29 1999-04-01 김정남 Burying prevention type sand excavating and conveying equipment
CN201843159U (en) * 2010-10-15 2011-05-25 江苏兆盛环保集团有限公司 Movable grab sewage disposal apparatus
CN202273257U (en) * 2011-10-21 2012-06-13 安徽省六安恒源机械有限公司 Door type hydraulic grab bucket trash remover
CN202544005U (en) * 2012-04-09 2012-11-21 吕燕林 Trash cleaning grab bucket taking vertical trash rack face and trash rack hole sidewall as guide rails
CN202543997U (en) * 2012-03-21 2012-11-21 张建 Novel full-open hydraulic grab type trash removal machine

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07197433A (en) * 1993-12-28 1995-08-01 Marsima Aqua Syst Corp Dust remover

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0180642B1 (en) * 1996-06-29 1999-04-01 김정남 Burying prevention type sand excavating and conveying equipment
CN201843159U (en) * 2010-10-15 2011-05-25 江苏兆盛环保集团有限公司 Movable grab sewage disposal apparatus
CN202273257U (en) * 2011-10-21 2012-06-13 安徽省六安恒源机械有限公司 Door type hydraulic grab bucket trash remover
CN202543997U (en) * 2012-03-21 2012-11-21 张建 Novel full-open hydraulic grab type trash removal machine
CN202544005U (en) * 2012-04-09 2012-11-21 吕燕林 Trash cleaning grab bucket taking vertical trash rack face and trash rack hole sidewall as guide rails

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
柘溪扩机工程拦污栅及其清污设计;左长新;《全国水利水电金属结构专业信息网2007年大会论文集》;20070901;第167-171页 *
高沙电站坝顶门机及液压清污抓斗的使用情况;刘书昌等;《水利电力机械》;20050228;第27卷(第1期);第20-23页 *

Also Published As

Publication number Publication date
CN103866810A (en) 2014-06-18

Similar Documents

Publication Publication Date Title
CN204868757U (en) Little latus rectum cone valve disk seat dismounting device
CN103866810B (en) Hydraulic engineering remove contamination grab bucket locking means
CN203961871U (en) Oil recovery fishing device
CN202596150U (en) Scaffold pedal
CN204355943U (en) Jack-up platform truss leg main chord tube stands up hoisting tooling
CN103674689A (en) Internal-expanded hydraulic pressure tool for minor-caliber pipe
CN204608833U (en) Municipal administration manhole
CN204471583U (en) The stretch-draw tool of a kind of prestressed concrete pipe pile single pile one end end-plate-free
CN206417791U (en) A kind of hanging apparatus for being used to install single ended bolt stretching-machine in groups
CN204640052U (en) A kind of Novel bolt spanner
CN203545529U (en) Crane of hydraulic jacking device
CN206296846U (en) A kind of wireless drilling inclinometers circulating sleeve withdrawing device
CN203755277U (en) Locking device of trash removal grab bucket for water conservancy project
CN203891819U (en) Drill rod salvaging device
CN204265361U (en) Workover rig winch steel rope live line head locker
CN106284634A (en) A kind of pipe dredging instrument
CN204935548U (en) A kind of specific purpose tool removing guide vanes of water turbine sleeve
CN204371887U (en) Apical ring hydraulic nut
CN205012381U (en) Power shovel and tup exchange dismounting device
CN204152174U (en) A kind of scaffold being convenient to dismounting and expansion
CN205025864U (en) Long and thin flexible hydro -cylinder of loop wheel machine
CN203587433U (en) Inner expanding water pressure tool of small-bore pipe
CN204199283U (en) Construction work micro hydraulic hammer stake machine
CN204060748U (en) A kind of anchor pole perfusion winding apparatus
CN204163375U (en) Builder's jack external corner bracing or strutting arrangement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 450003 Jinshui Road 109, Zhengzhou City, Henan Province

Patentee after: Yellow River Survey Planning and Design Research Institute Co., Ltd.

Address before: 450003 Jinshui Road 109, Zhengzhou City, Henan Province

Patentee before: Yellow River Engineering Consulting Co., Ltd.

CP01 Change in the name or title of a patent holder