CN103825758A - Fault processing method for electric power communication network operation monitoring system - Google Patents

Fault processing method for electric power communication network operation monitoring system Download PDF

Info

Publication number
CN103825758A
CN103825758A CN201410009708.3A CN201410009708A CN103825758A CN 103825758 A CN103825758 A CN 103825758A CN 201410009708 A CN201410009708 A CN 201410009708A CN 103825758 A CN103825758 A CN 103825758A
Authority
CN
China
Prior art keywords
client
server
fault
fault handling
task
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410009708.3A
Other languages
Chinese (zh)
Other versions
CN103825758B (en
Inventor
詹辉红
卢黎明
楼平
黄立
张国平
张韡
盛建雄
陈军
樊栽根
钱振兴
张伟刚
宗丽英
孙卫庆
董科
张云峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410009708.3A priority Critical patent/CN103825758B/en
Publication of CN103825758A publication Critical patent/CN103825758A/en
Application granted granted Critical
Publication of CN103825758B publication Critical patent/CN103825758B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Computer And Data Communications (AREA)

Abstract

The invention provides a fault processing method for an electric power communication network operation monitoring system. The method comprises: a detection terminal notifying detected fault information to a client, and the client, according to the fault information, forming a fault alarm signal for uploading to a server group for storage; the client responding to the detection terminal, and the client, according to a fault processing process, forming fault processing information and maintaining the fault processing information, the fault processing information being stored in the client in a form of a batch task; and the client uploading the fault processing information which is stored in the form of the batch task to the server group. The method provided by the invention can enable the server group to obtain the concrete information of the fault processing process, facilitates fault processing management and monitoring by operation and maintenance workers, and guarantees fault processing completeness and reliability.

Description

A kind of fault handling method for power telecom network O&M supervisory control system
Technical field
The present invention relates to power telecom network O&M monitoring technique, particularly a kind of fault handling method for power telecom network O&M supervisory control system.
Background technology
In the work of existing power information communication O&M, in the time that client gets the fault message of sense terminals, client is by this fault message group that uploads onto the server, related personnel is after completing Failure elimination, notice client failure is eliminated, client is Failure elimination completion status according to obtained information by sense terminals status indication, and group uploads onto the server Failure elimination completion status simultaneously.
In existing information communication O&M troubleshooting technology, because client sends the effect of only having played notice in the Failure elimination completion status of server group to, staff can not be known the specifying information of Failure elimination in server group, can not carry out comprehensive analysis to fault treating procedure, to O&M, work brings greater inconvenience.Again due to after Failure elimination, eliminated by client announcement server group fault, server group can only be accepted prompting passively, can not guarantee integrality and the validity of Failure elimination, process centralized management and the monitoring that cannot get rid of fault detect by server group.
In sum, at present in the urgent need to a kind of fault handling method for power telecom network O&M supervisory control system, can solve the above problems.
Summary of the invention
The object of the invention is to solve the problems of the technologies described above, a kind of fault handling method for power telecom network O&M supervisory control system is provided, can know the batch task information in fault treating procedure in server group, for O&M worker, fault treating procedure is analyzed, and, by server group, the progress of batch task is judged, guarantee the integrality of Failure elimination process.For solving the problems of the technologies described above, the invention provides a kind of fault handling method for power telecom network O&M supervisory control system, O&M supervisory control system comprises several clients and at least one server group, each client and described server group communication, and the method comprises the following steps:
Sense terminals notifies the fault message detecting to client, and described client forms the failure alarm signal group that uploads onto the server according to described fault message and stores;
Described client is replied described sense terminals, and client forms fault handling information according to fault treating procedure, and described fault handling information is stored in described client with batch task form, fault handling information described in client maintenance;
The described fault handling information with batch task form storage is uploaded to described server group by described client.
Preferably, the method is further comprising the steps of: by server group, fault handling information is judged, if when all tasks all complete, server group is eliminated described failure alarm signal, and notify this fault of described client processed completing, otherwise this troubleshooting of notice client does not complete.
Preferably, in batches the dividing with the pressing degree of task of the fault handling information of described batch of task form, the most urgent first task that is labeled as, next is labeled as second batch task, and by that analogy, pressing degree is artificially set in described client.
Preferably, when fault handling information judgement by server group, in the time that completing, a collection of task could judge next group task.
Preferably, in the fault handling information of described batch of task form, every batch of task includes: abort situation information, fault type information, troubleshooting required time and fault handling method.
Preferably, described server group is the integrated equipment that is integrated with database server and WEB server and apps server; Or the equipment that described server group is intercomed with apps server mutually by database server, WEB server forms; Or, described server group by the integrated equipment that is integrated with database server, WEB server and any two kinds of servers in apps server with remain the equipment that a kind of server intercoms mutually and form.The present invention has following useful effect than prior art:
The fault handling method of a kind of power telecom network O&M supervisory control system provided by the invention, client records fault handling information and with batch task form storage failure process information, and be uploaded to server group, make O&M worker obtain complete procedure and the progress of troubleshooting by server group, be convenient to the management and monitoring of O&M work, simultaneously, server group is stored fault handling information, be convenient to statistical analysis again, in the time that same case occurs again, because server group has had the trouble hunting record in old times, can judge to obtain the nidus that the is out of order problem that may exist according to the trouble hunting record in old times, thereby be convenient to the quick of O&M work, effectively carry out.
Further, by server group, the batch task information of fault handling information is judged, if when all tasks all complete, server group is eliminated described failure alarm signal, and notify this fault of described client processed completing, otherwise, this troubleshooting of notice client does not complete, overcome in prior art and to have been decided by client whether complete troubleshooting is causes troubleshooting imperfect thereby have a problem of potential safety hazard, guarantee the integrality of troubleshooting, made power telecom network safety and reliability.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described further:
Fig. 1 is the structured flowchart of the power telecom network O&M supervisory control system of the embodiment of the present invention;
Fig. 2 is the flow chart of a kind of fault handling method for power telecom network O&M supervisory control system of the embodiment of the present invention.
Embodiment
Below in conjunction with specific embodiments and the drawings, the invention will be further described, but should not limit the scope of the invention with this.
Fig. 1 shows the structured flowchart of the power telecom network O&M supervisory control system of the embodiment of the present invention, comprising: by database server, and apps server, the server group of WEB server composition, client 1, client 2.Described server group is the integrated equipment that is integrated with database server and WEB server and apps server; Or the equipment that described server group is intercomed with apps server mutually by database server, WEB server forms; Or, described server group by the integrated equipment that is integrated with database server, WEB server and any two kinds of servers in apps server with remain the equipment that a kind of server intercoms mutually and form, any one combination all can be used as execution mode.Described server group and described client communicating by letter each other realized by the networking of information Intranet, wherein server group is described in detail hereinbefore, and the general computer of customer end adopted, in electric power system, client can receive as substation controller the fault message that the sense terminals in electrical network is sent.
Fig. 2 shows the flow chart of a kind of fault handling method for power telecom network O&M supervisory control system of the present embodiment.Its step comprises:
S11: sense terminals notifies the fault message detecting to client, described client forms the failure alarm signal group that uploads onto the server according to described fault message and stores;
S12: described client is replied described sense terminals, and client forms fault handling information according to fault treating procedure, described fault handling information is stored in described client with batch task form, fault handling information described in client maintenance;
S13: the described fault handling information with batch task form storage is uploaded to described server group by described client;
S14: by server group, fault handling information is judged, if when all tasks all complete, server group is eliminated described failure alarm signal, and notify this fault of described client processed completing, otherwise this troubleshooting of notice client does not complete.
Simultaneously in conjunction with Fig. 1 and Fig. 2, sense terminals (not shown on figure) notifies the fault message detecting to client 1, client 1 forms a failure alarm signal according to fault message and is uploaded to database server and stores, in database server, generate a record, the fault handling information that will upload to store client 1; The present embodiment illustrates embodiment by the client 1 illustrating, in other embodiment, also can use client 2 or other not shown clients to describe;
Client 1 is replied described sense terminals, and client 1 forms fault handling information according to fault treating procedure, and described fault handling information is stored in described client 1 with batch task form, and client 1 is safeguarded described fault handling information; Client 1 will be uploaded to database server, apps server and WEB server with the fault handling information of batch task form storage, as the optional execution mode of one, database server is stored in fault handling information in the record having created, and apps server is processed direct demonstration to fault handling information or issued by WEB server.
In embodiments of the present invention, the task of fault handling information is to divide according to the pressing degree of task in batches, pressing degree is also to set according to artificial judgement in described client 1, the most urgent first task that is labeled as, next is labeled as second batch task, and by that analogy, the present embodiment is only as preferably a kind of, in other embodiments, also can divide according to the complexity of task; Fault handling information is stored by the form of data structure, comprises following one or several: array, queue, chained list, tree, figure, and a collection of task is as a data element storage; Client 1 is by after being uploaded to database server stores with the fault handling information of batch task form storage, apps server and WEB server can call the data in database server, O&M worker can analyze fault treating procedure, be convenient to carrying out of O&M work, in the time that this fault occurs again in the future, O&M personnel can inquire about rapidly, and troubleshooting work is carried out quickly and efficiently.
In the present embodiment, fault handling information comprises: abort situation information, fault type information, troubleshooting required time and fault handling method.
Further, continue with reference to figure 1 and Fig. 2, according to fault handling information, by server group, fault handling information is judged, in the time that all tasks all complete, server group is eliminated described failure alarm signal, and notifies described client 1 this fault is processed and complete, otherwise 1 this troubleshooting of notice client does not complete.Preferably, when fault handling information judgement by server group, in the time that completing, a collection of task could judge next group task.Whether the present embodiment decides troubleshooting to complete by server group, process centralized management and monitoring by server group to troubleshooting, and the Integrity And Reliability of assurance trouble hunting, has eliminated the incomplete potential safety hazard of troubleshooting existing.
It should be noted that, server group judges and determines whether troubleshooting completes batch task processing, in order further to deal with problems, also can not comprise in other embodiments above-mentioned steps, and still determine by client whether fault has been disposed, solved sense terminals the fault message detecting is notified to client, described client forms the failure alarm signal group that uploads onto the server according to described fault message and stores, described client is replied described sense terminals, and client forms fault handling information according to fault treating procedure, and described fault handling information is stored in described client with batch task form, fault handling information described in client maintenance, the described fault handling information with batch task form storage is uploaded to described server group by described client, make O&M worker obtain complete procedure and the progress of troubleshooting by server group, be convenient to the management and monitoring of O&M work, simultaneously, server group is stored fault handling information, be convenient to statistical analysis again, in the time that same case occurs again, because server group has had the trouble hunting record in old times, can judge to obtain the nidus that the is out of order problem that may exist according to the trouble hunting record in old times, thereby be convenient to the quick of O&M work, effectively carry out.
Although the present invention with preferred embodiment openly as above; but it is not for limiting the present invention; any those skilled in the art without departing from the spirit and scope of the present invention; can make possible variation and modification, therefore protection scope of the present invention should be as the criterion with the scope that the claims in the present invention were defined.

Claims (6)

1. for a fault handling method for power telecom network O&M supervisory control system, O&M supervisory control system comprises several clients and at least one server group, and each client and described server group communication, is characterized in that, the method comprises the following steps:
Sense terminals notifies the fault message detecting to client, and described client forms the failure alarm signal group that uploads onto the server according to described fault message and stores;
Described client is replied described sense terminals, and client forms fault handling information according to fault treating procedure, and described fault handling information is stored in described client with batch task form, fault handling information described in client maintenance;
The described fault handling information with batch task form storage is uploaded to described server group by described client.
2. a kind of fault handling method for power telecom network O&M supervisory control system as claimed in claim 1, it is characterized in that, the method is further comprising the steps of: by server group, fault handling information is judged, if when all tasks all complete, server group is eliminated described failure alarm signal, and notify this fault of described client processed completing, otherwise this troubleshooting of notice client does not complete.
3. a kind of fault handling method for power telecom network O&M supervisory control system as claimed in claim 2, it is characterized in that, in batches dividing with the pressing degree of task of the fault handling information of described batch of task form, the most urgent first task that is labeled as, next is labeled as second batch task, by that analogy, pressing degree is artificially set in described client.
4. a kind of fault handling method for power telecom network O&M supervisory control system as claimed in claim 3, is characterized in that, when fault handling information judgement by server group, in the time that a collection of task completes, could judge next group task.
5. a kind of fault handling method for power telecom network O&M supervisory control system as claimed in claim 1, it is characterized in that, in the fault handling information of described batch of task form, every batch of task includes: abort situation information, fault type information, troubleshooting required time and fault handling method.
6. a kind of fault handling method for power telecom network O&M supervisory control system as claimed in claim 1, is characterized in that, described server group is the integrated equipment that is integrated with database server and WEB server and apps server; Or the equipment that described server group is intercomed with apps server mutually by database server, WEB server forms; Or, described server group by the integrated equipment that is integrated with database server, WEB server and any two kinds of servers in apps server with remain the equipment that a kind of server intercoms mutually and form.
CN201410009708.3A 2014-01-09 2014-01-09 Fault processing method for electric power communication network operation monitoring system Active CN103825758B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410009708.3A CN103825758B (en) 2014-01-09 2014-01-09 Fault processing method for electric power communication network operation monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410009708.3A CN103825758B (en) 2014-01-09 2014-01-09 Fault processing method for electric power communication network operation monitoring system

Publications (2)

Publication Number Publication Date
CN103825758A true CN103825758A (en) 2014-05-28
CN103825758B CN103825758B (en) 2015-03-25

Family

ID=50760605

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410009708.3A Active CN103825758B (en) 2014-01-09 2014-01-09 Fault processing method for electric power communication network operation monitoring system

Country Status (1)

Country Link
CN (1) CN103825758B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104158688A (en) * 2014-08-22 2014-11-19 武汉虹翼信息有限公司 Method and system of implementing maintenance and management of communication device through information label
CN104361236A (en) * 2014-11-17 2015-02-18 国家电网公司 Evaluation method for health condition of electric power equipment
CN106228496A (en) * 2016-08-29 2016-12-14 苏州金螳螂怡和科技有限公司 Cable operation management system
CN113268479A (en) * 2021-07-02 2021-08-17 浙江万里学院 Computer database cloud debugging and maintenance system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1635802A (en) * 2003-12-26 2005-07-06 华为技术有限公司 Alarm system and method thereof
CN101179623A (en) * 2006-11-08 2008-05-14 中兴通讯股份有限公司 Equipment failure process and alarm method in communication system
CN101217591A (en) * 2008-01-18 2008-07-09 中兴通讯股份有限公司 A method and system realizing snooping data storage
CN102663537A (en) * 2012-03-13 2012-09-12 凯里供电局 Maintenance system of power equipment based on risk assessment

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1635802A (en) * 2003-12-26 2005-07-06 华为技术有限公司 Alarm system and method thereof
CN101179623A (en) * 2006-11-08 2008-05-14 中兴通讯股份有限公司 Equipment failure process and alarm method in communication system
CN101217591A (en) * 2008-01-18 2008-07-09 中兴通讯股份有限公司 A method and system realizing snooping data storage
CN102663537A (en) * 2012-03-13 2012-09-12 凯里供电局 Maintenance system of power equipment based on risk assessment

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104158688A (en) * 2014-08-22 2014-11-19 武汉虹翼信息有限公司 Method and system of implementing maintenance and management of communication device through information label
CN104361236A (en) * 2014-11-17 2015-02-18 国家电网公司 Evaluation method for health condition of electric power equipment
CN104361236B (en) * 2014-11-17 2018-02-13 国家电网公司 The appraisal procedure of power equipment health status
CN106228496A (en) * 2016-08-29 2016-12-14 苏州金螳螂怡和科技有限公司 Cable operation management system
CN113268479A (en) * 2021-07-02 2021-08-17 浙江万里学院 Computer database cloud debugging and maintenance system

Also Published As

Publication number Publication date
CN103825758B (en) 2015-03-25

Similar Documents

Publication Publication Date Title
CN105049223B (en) A kind of power telecom network defect troubleshooting decision assistant analysis method
CN111562460B (en) Power distribution network power failure event detection research and judgment method, device, computer equipment and medium
CN110650052B (en) Customer reason fault identification processing method and system based on intelligent algorithm
CN103825758B (en) Fault processing method for electric power communication network operation monitoring system
CN103544739A (en) B/S (Browser/Server) architecture-based polling method of visual subway equipment polling management system
CN109559064A (en) The operation and maintenance method of gate based on Internet of Things
KR102302395B1 (en) Mes platform for monitoring and controlling root industry equipment and operating method thereof
US11526156B2 (en) Computer-implemented method for the monitoring of a plurality of cable-processing machines, and a monitoring system
CN102566531A (en) Monitoring and early warning system for service life of equipment
CN110808856A (en) Big data operation and maintenance method and system based on data center
US20180130339A1 (en) System & methods for critical infrastructure automation
CN107809321B (en) Method for realizing safety risk evaluation and alarm generation
CN113506096B (en) Inter-system interface method based on industrial internet identification analysis system
CN104734353A (en) Intelligent substation hovering fault monitoring method based on network message
CN112737124B (en) Method and device for constructing power equipment monitoring terminal
JP2008059413A (en) Failure management support system and its information management method
CN111835583B (en) Attribute inspection method and device for products of Internet of things and computer equipment
CN107682166B (en) Implementation method for remote data acquisition of safety operation and maintenance service platform based on big data
CN114429256A (en) Data monitoring method and device, electronic equipment and storage medium
CN111404736A (en) API gateway-based government and enterprise service application integration method and gateway monitoring platform
CN116362561A (en) Centralized control station operation auxiliary decision-making method based on big data
CN115509854A (en) Inspection processing method, inspection server and inspection system
CN105550094B (en) A kind of high-availability system state automatic monitoring method
CN111146863A (en) Power safety detection method for transformer substation
CN108199482B (en) Maintenance prompting method and device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant