CN103795075A - Phase sequence arrangement adjustment method for three-phase current unbalanced wires of transmission lines in transformer substation - Google Patents

Phase sequence arrangement adjustment method for three-phase current unbalanced wires of transmission lines in transformer substation Download PDF

Info

Publication number
CN103795075A
CN103795075A CN201410022007.3A CN201410022007A CN103795075A CN 103795075 A CN103795075 A CN 103795075A CN 201410022007 A CN201410022007 A CN 201410022007A CN 103795075 A CN103795075 A CN 103795075A
Authority
CN
China
Prior art keywords
transmission line
loop transmission
sequence
unbalance
phase
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410022007.3A
Other languages
Chinese (zh)
Other versions
CN103795075B (en
Inventor
唐震
张军六
朱良肄
马振国
张悦
武春雷
李�瑞
刘新元
郑惠萍
姚以沛
黄宗泽
石继勇
张慧兵
张岚
吕巍
武中
张友富
张来福
张健
刘永鑫
王欣伟
芦山
信可嘉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Taiyuan Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Taiyuan Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd, Taiyuan Power Supply Co of State Grid Shanxi Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410022007.3A priority Critical patent/CN103795075B/en
Publication of CN103795075A publication Critical patent/CN103795075A/en
Application granted granted Critical
Publication of CN103795075B publication Critical patent/CN103795075B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/50Arrangements for eliminating or reducing asymmetry in polyphase networks

Abstract

The invention discloses a phase sequence arrangement adjustment method for three-phase current unbalanced wires of transmission lines in a transformer substation to solve the problem that the three-phase current unbalance degree of existing transmission lines is increased, and therefore misoperation frequently occurs during zero-sequence protection for buses and the transmission lines of the transformer substation. The method include the steps of firstly, setting up an unbalance current simulating calculation model of all the connected transmission lines according to the types of towers used for all the transmission lines of the whole transformer substation, the phase sequence arrangement of all the transmission lines and the actual lengths of the transmission lines; secondly, calculating a positive-sequence current, a negative-sequence current and a zero-sequence current of each transmission line of the whole transformer substation and the zero-sequence current unbalance degree and the negative-sequence current unbalance degree of each transmission line. By changing the phase sequence arrangement of the wires of the transmission lines, the zero-sequence current unbalance degree and the negative-sequence current unbalance degree of each transmission line are controlled below 5% until the zero-sequence current unbalance degrees and the negative-sequence current unbalance degrees of all the transmission lines of the transformer substation are calculated to be lower than 5%. The simple and practical adjustment method is provided for the optimal phase sequence arrangement of the wires of all the transmission lines of the transformer substation.

Description

Transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in transformer station
Technical field
The present invention relates to the method for adjustment of the Traverse phase-order arrangement of transmission line three-phase current unbalance in a kind of transformer station, be applicable to the transmission pressure of the many back transmission lines of transformer station to carry out rational phase sequence arrangement, make entirely the stand degree of unbalance of electric current of transformer station drop to minimum.
Background technology
Along with the rapid growth of power load; in electrical network, there is a large amount of short-range single back transmission line and same tower double back transmission line; these short-range transmission lines generally adopt the mode that does not replace and set up; make the aggravation of three-phase current unbalance degree; cause the bus of transformer station and the misoperation of power transmission line zero-sequence protection frequently to occur, had influence on the safe operation of electrical network.Entangle its reason: the one, according to the designing requirement of transmission line, in the time that being less than 100 kilometers completely, transmission line do not replace, and short (or ultrashort) circuit that these do not replace increases too many; The 2nd, many lists return and the common-tower double-return impact that the construction of line puts into operation in succession that do not replace; These two reasons directly cause part transmission line electric parameter asymmetric, and then cause three-phase current unbalance degree to increase.
Summary of the invention
The invention provides transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in a kind of transformer station; solve the three-phase current unbalance degree aggravation due to existing transmission line, caused the bus protection of transformer station and the frequent technical problem occurring of misoperation of power transmission line zero-sequence protection.
The present invention solves above technical problem by the following technical programs:
Transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in a kind of transformer station, comprises the following steps:
The first step, the N loop transmission line that full transformer station station is connected sort, the electric current of the first loop transmission line is represented with subscript I, the electric current of second servo loop transmission line is represented with subscript II, and by that analogy, the electric current of the N loop transmission line at the full station of transformer station represents with subscript N;
The phase sequence of actual track length, the tower using and the transmission line of second step, each loop transmission line of connecting for the full station of transformer station is arranged, and sets up respectively the unsymmetrical current Simulation Calculation of loop transmission line separately;
The unsymmetrical current Simulation Calculation of the 3rd step, the first loop transmission line of setting up according to second step, utilizes electro-magnetic transient computing method, calculates the forward-order current of the first loop transmission line
Figure 67715DEST_PATH_IMAGE002
, negative-sequence current
Figure 453697DEST_PATH_IMAGE004
, zero-sequence current
Figure 233434DEST_PATH_IMAGE006
;
The 4th step, the following formula of utilization calculate the zero-sequence current degree of unbalance of the first loop transmission line and the negative-sequence current degree of unbalance of the first loop transmission line:
Figure 222119DEST_PATH_IMAGE008
Figure 36491DEST_PATH_IMAGE010
If the zero-sequence current degree of unbalance of the 5th step the first loop transmission line
Figure 327795DEST_PATH_IMAGE012
negative-sequence current degree of unbalance with the first loop transmission line have one to exceed 5%, the phase sequence that changes the first loop transmission line is arranged, and repeats the step of above-mentioned second step to the four steps, if the zero-sequence current degree of unbalance of the first loop transmission line newly calculating
Figure 387204DEST_PATH_IMAGE012
negative-sequence current degree of unbalance with the first loop transmission line
Figure 56082DEST_PATH_IMAGE014
still have one to exceed 5%, then change the phase sequence arrangement of the first loop transmission line, repeat the step of above-mentioned second step to the four steps, until the zero-sequence current degree of unbalance of the first loop transmission line calculating
Figure 518288DEST_PATH_IMAGE012
negative-sequence current degree of unbalance with the first loop transmission line
Figure 272617DEST_PATH_IMAGE014
all be less than till 5%, the phase sequence of the first loop transmission line is now arranged as adjusts to the right place;
The 6th step, successively second servo loop transmission line is repeated the step of second step to the five steps to N loop transmission line, the phase sequence that the phase sequence of second servo loop transmission line is aligned to N loop transmission line is arranged and is all adjusted to the right place.
The invention solves the transmission system three-phase current unbalance that the full station of existing transformer station causes due to Traverse phase-order unreasonable structure and arrangement due to single back transmission line and double back transmission line; for the optimal arrangement of the Traverse phase-order of transformer station's all transmission lines in full station provides a kind of simple and practical method of adjustment; overcome the bus protection of transformer station and the misoperation of power transmission line zero-sequence protection, ensured the safe operation of electrical network.
Embodiment
The present invention is described in detail below:
Transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in a kind of transformer station, comprises the following steps:
The first step, the N loop transmission line that full transformer station station is connected sort, the electric current of the first loop transmission line is represented with subscript I, the electric current of second servo loop transmission line is represented with subscript II, and by that analogy, the electric current of the N loop transmission line at the full station of transformer station represents with subscript N;
The phase sequence of actual track length, the tower using and the transmission line of second step, each loop transmission line of connecting for the full station of transformer station is arranged, and sets up respectively the unsymmetrical current Simulation Calculation of loop transmission line separately;
The unsymmetrical current Simulation Calculation of the 3rd step, the first loop transmission line of setting up according to second step, utilizes electro-magnetic transient computing method, calculates the forward-order current of the first loop transmission line , negative-sequence current
Figure 126490DEST_PATH_IMAGE004
, zero-sequence current ;
The 4th step, the following formula of utilization calculate the zero-sequence current degree of unbalance of the first loop transmission line and the negative-sequence current degree of unbalance of the first loop transmission line:
Figure 266801DEST_PATH_IMAGE008
Figure 633935DEST_PATH_IMAGE010
If the zero-sequence current degree of unbalance of the 5th step the first loop transmission line
Figure 277406DEST_PATH_IMAGE012
negative-sequence current degree of unbalance with the first loop transmission line
Figure 81414DEST_PATH_IMAGE014
have one to exceed 5%, the phase sequence that changes the first loop transmission line is arranged, and repeats the step of above-mentioned second step to the four steps, if the zero-sequence current degree of unbalance of the first loop transmission line newly calculating
Figure 810335DEST_PATH_IMAGE012
negative-sequence current degree of unbalance with the first loop transmission line
Figure 482625DEST_PATH_IMAGE014
still have one to exceed 5%, then change the phase sequence arrangement of the first loop transmission line, repeat the step of above-mentioned second step to the four steps, until the zero-sequence current degree of unbalance of the first loop transmission line calculating
Figure 449444DEST_PATH_IMAGE012
negative-sequence current degree of unbalance with the first loop transmission line
Figure 221091DEST_PATH_IMAGE014
all be less than till 5%, the phase sequence of the first loop transmission line is now arranged as adjusts to the right place;
The 6th step, successively second servo loop transmission line is repeated the step of second step to the five steps to N loop transmission line, the phase sequence that the phase sequence of second servo loop transmission line is aligned to N loop transmission line is arranged and is all adjusted to the right place.
The present invention uses tower and phase sequence to arrange and actual track length according to transformer station's all transmission lines in full station, set up the unsymmetrical current Simulation Calculation of the each loop transmission line connecting, then, calculate positive and negative, the zero-sequence current of transformer station's every transmission line in full station and zero sequence, negative-sequence current degree of unbalance.Be arranged with 6 kinds because same tower double back transmission line Traverse phase-order is arranged with 36 kinds, single back transmission line phase sequence, arrange by the phase sequence that changes transmission line wire, the zero sequence of this loop transmission line and negative-sequence current degree of unbalance are controlled at below 5%.Constantly repeat above-mentioned computational methods, until calculate all transmission lines of transformer station zero, negative-sequence current degree of unbalance is all less than 5%, the conducting wire phase sequence of so just having determined all transmission lines in full station is arranged as best phase sequence and arranges.
The computational methods of current unbalance factor, are to have utilized electro-magnetic transient computing method, every transmission line positive and negative, zero-sequence current computational methods are as follows:
Figure DEST_PATH_IMAGE015
Figure 765205DEST_PATH_IMAGE016
……
Figure DEST_PATH_IMAGE017
Wherein:
Figure DEST_PATH_IMAGE019
for the vector calculus factor;
Zero-sequence current degree of unbalance computing formula is:
Zero-sequence current degree of unbalance=(zero-sequence current/forward-order current) × 100%;
Negative-sequence current degree of unbalance computing formula is:
Negative-sequence current degree of unbalance=(negative-sequence current/forward-order current) × 100%.

Claims (1)

1. a transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in transformer station, comprises the following steps:
The first step, the N loop transmission line that full transformer station station is connected sort, the electric current of the first loop transmission line is represented with subscript I, the electric current of second servo loop transmission line is represented with subscript II, and by that analogy, the electric current of the N loop transmission line at the full station of transformer station represents with subscript N;
The phase sequence of actual track length, the tower using and the transmission line of second step, each loop transmission line of connecting for the full station of transformer station is arranged, and sets up respectively the unsymmetrical current Simulation Calculation of loop transmission line separately;
The unsymmetrical current Simulation Calculation of the 3rd step, the first loop transmission line of setting up according to second step, utilizes electro-magnetic transient computing method, calculates the forward-order current of the first loop transmission line
Figure 2014100220073100001DEST_PATH_IMAGE002
, negative-sequence current
Figure 2014100220073100001DEST_PATH_IMAGE004
, zero-sequence current ;
The 4th step, the following formula of utilization calculate the zero-sequence current degree of unbalance of the first loop transmission line and the negative-sequence current degree of unbalance of the first loop transmission line:
Figure 2014100220073100001DEST_PATH_IMAGE008
Figure 2014100220073100001DEST_PATH_IMAGE010
If the zero-sequence current degree of unbalance of the 5th step the first loop transmission line
Figure DEST_PATH_IMAGE012
negative-sequence current degree of unbalance with the first loop transmission line have one to exceed 5%, the phase sequence that changes the first loop transmission line is arranged, and repeats the step of above-mentioned second step to the four steps, if the zero-sequence current degree of unbalance of the first loop transmission line newly calculating
Figure DEST_PATH_IMAGE012A
negative-sequence current degree of unbalance with the first loop transmission line
Figure DEST_PATH_IMAGE014A
still have one to exceed 5%, then change the phase sequence arrangement of the first loop transmission line, repeat the step of above-mentioned second step to the four steps, until the zero-sequence current degree of unbalance of the first loop transmission line calculating
Figure DEST_PATH_IMAGE012AA
negative-sequence current degree of unbalance with the first loop transmission line
Figure DEST_PATH_IMAGE014AA
all be less than till 5%, the phase sequence of the first loop transmission line is now arranged as adjusts to the right place;
The 6th step, successively second servo loop transmission line is repeated the step of second step to the five steps to N loop transmission line, the phase sequence that the phase sequence of second servo loop transmission line is aligned to N loop transmission line is arranged and is all adjusted to the right place.
CN201410022007.3A 2014-01-18 2014-01-18 Transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in transformer station Active CN103795075B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410022007.3A CN103795075B (en) 2014-01-18 2014-01-18 Transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in transformer station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410022007.3A CN103795075B (en) 2014-01-18 2014-01-18 Transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in transformer station

Publications (2)

Publication Number Publication Date
CN103795075A true CN103795075A (en) 2014-05-14
CN103795075B CN103795075B (en) 2015-09-09

Family

ID=50670514

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410022007.3A Active CN103795075B (en) 2014-01-18 2014-01-18 Transmission line three-phase current unbalance Traverse phase-order arrangement adjusting method in transformer station

Country Status (1)

Country Link
CN (1) CN103795075B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106097143A (en) * 2016-06-15 2016-11-09 国网江西省电力科学研究院 A kind of method choosing the optimum phase sequence arrangement mode of multiple-circuit on same tower
CN108631341A (en) * 2018-05-17 2018-10-09 福建奥通迈胜电力科技有限公司 Distribution low-voltage side current three-phase imbalance appraisal procedure based on zero-sequence current
CN113752921A (en) * 2021-10-20 2021-12-07 西南交通大学 Method for erecting special power transmission line for electrified railway

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030055585A1 (en) * 2001-09-13 2003-03-20 Stoupis James D. Crossover fault classification for power lines with parallel circuits
CN102916427A (en) * 2012-09-25 2013-02-06 广东电网公司电力科学研究院 Method for calculating integrated three-phase imbalance degree of multi-circuit transmission lines
CN102938010A (en) * 2012-12-10 2013-02-20 上海市电力公司 Parallel circuit unbalance degree analysis method
CN103235198A (en) * 2013-04-14 2013-08-07 国家电网公司 Method for determining phase sequence arrangement modes of conducting wires of same-tower double-circuit transmission lines
CN103412199A (en) * 2013-08-12 2013-11-27 上海电力学院 Computing method of unbalancedness of multi-circuit power transmission lines on same tower

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030055585A1 (en) * 2001-09-13 2003-03-20 Stoupis James D. Crossover fault classification for power lines with parallel circuits
CN102916427A (en) * 2012-09-25 2013-02-06 广东电网公司电力科学研究院 Method for calculating integrated three-phase imbalance degree of multi-circuit transmission lines
CN102938010A (en) * 2012-12-10 2013-02-20 上海市电力公司 Parallel circuit unbalance degree analysis method
CN103235198A (en) * 2013-04-14 2013-08-07 国家电网公司 Method for determining phase sequence arrangement modes of conducting wires of same-tower double-circuit transmission lines
CN103412199A (en) * 2013-08-12 2013-11-27 上海电力学院 Computing method of unbalancedness of multi-circuit power transmission lines on same tower

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106097143A (en) * 2016-06-15 2016-11-09 国网江西省电力科学研究院 A kind of method choosing the optimum phase sequence arrangement mode of multiple-circuit on same tower
CN108631341A (en) * 2018-05-17 2018-10-09 福建奥通迈胜电力科技有限公司 Distribution low-voltage side current three-phase imbalance appraisal procedure based on zero-sequence current
CN108631341B (en) * 2018-05-17 2021-12-21 福建奥通迈胜电力科技有限公司 Zero-sequence current-based three-phase unbalance evaluation method for distribution transformer low-voltage side current
CN113752921A (en) * 2021-10-20 2021-12-07 西南交通大学 Method for erecting special power transmission line for electrified railway

Also Published As

Publication number Publication date
CN103795075B (en) 2015-09-09

Similar Documents

Publication Publication Date Title
CN103207352B (en) Route selection impedance magnitude characteristic is utilized to realize wire selection method for power distribution network single phase earthing failure
US20170085076A1 (en) Setting and coordination calculation method for protection setting value of dc system
CN106803153A (en) A kind of appraisal procedure and system of many feed-in ac and dc systemses commutation failure risks
CN105391050B (en) Cut the check method and system of machine allocation plan high week
CN103954885B (en) The single-ended alignment system of double line down and localization method based on distributed constant
CN103746401A (en) Method for improving capacity of multi-feed-in direct current power transmission system against phase commutation failure
CN109256970B (en) MMC-MTDC transmission system monopolar grounding fault current calculation method
CN102916450A (en) Hybrid real-time simulation method for three-phase asymmetrical alternating-current/direct-current power system
CN204230896U (en) A kind of for suppressing the grid-connected additional controller devices of sub-synchronous oscillation
CN108075476A (en) A kind of security constraint optimal load flow method based on power flow transfer relation
CN106711968B (en) Setting method and system for inverse time limit zero sequence current protection
CN102508098A (en) Quick distinguishing method for zero-sequence directional elements of alternating-current and direct-current serial-parallel power grid
CN103795074B (en) According to the method that current phase angle and range-adjusting transmission line wire phase sequence arrange
CN108233408B (en) A kind of MMC-MTDC system self-adaption droop control method
CN103412199A (en) Computing method of unbalancedness of multi-circuit power transmission lines on same tower
CN106655234A (en) Method for analyzing influence of line impedance and call wire power on generalized short-circuit ratio
CN103795075A (en) Phase sequence arrangement adjustment method for three-phase current unbalanced wires of transmission lines in transformer substation
CN108008251A (en) The fault distance-finding method of mixed power transmission line unknown parameters
CN103235198B (en) Method for determining phase sequence arrangement modes of conducting wires of same-tower double-circuit transmission lines
CN103560497A (en) Short-circuit current limiting method based on power grid topological adjustment
CN103810329A (en) Method for adjusting phase sequence arrangement of electric transmission line wire according to electric transmission line power
CN106528944A (en) Analysis method for obtaining maximum transient overvoltage of single feeder line of offshore wind power plant under asymmetric short circuit fault
CN108551178B (en) Electromechanical transient simulation model of flexible direct-current power transmission system
CN105738751A (en) Setting calculation method for bus differential protection current loop line disconnection alarm fixed value
CN104915520A (en) Tripping logic simulating method for alternating current filters of direct-current converting station

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant