CN103727934B - A kind of accurate construction lofting method of cantilever glider bridge construction - Google Patents

A kind of accurate construction lofting method of cantilever glider bridge construction Download PDF

Info

Publication number
CN103727934B
CN103727934B CN201410025067.0A CN201410025067A CN103727934B CN 103727934 B CN103727934 B CN 103727934B CN 201410025067 A CN201410025067 A CN 201410025067A CN 103727934 B CN103727934 B CN 103727934B
Authority
CN
China
Prior art keywords
reference mark
point
article
visual lines
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410025067.0A
Other languages
Chinese (zh)
Other versions
CN103727934A (en
Inventor
唐利民
郑健龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201410025067.0A priority Critical patent/CN103727934B/en
Publication of CN103727934A publication Critical patent/CN103727934A/en
Application granted granted Critical
Publication of CN103727934B publication Critical patent/CN103727934B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Bridges Or Land Bridges (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of cantilever glider bridge to construct accurate construction lofting method, by forced centering observation stand, in the observation steady period, setting-out goes out cantilever glider bridge and to construct two reference mark of accurate construction lofting; Then accurately layout point is determined by observing mutually at two reference mark erection total powerstations.Use the method to carry out the construction lofting of cantilever glider bridge construction, the stability of cantilever glider bridge construction lofting can be ensured, also can improve the accuracy of cantilever glider bridge construction lofting.

Description

A kind of accurate construction lofting method of cantilever glider bridge construction
Technical field
The present invention relates to the accurate construction lofting method of a kind of cantilever glider bridge construction.
Background technology
For tall and big cantilever glider bridge, the accuracy of construction lofting is the key factor determining construction quality and success or failure.The accuracy of construction lofting relates generally to plane positioning and elevation location.And the accuracy of plane positioning is the most important thing in construction lofting quality control.The large area of building of current mountainous area highway is launched, and tall and big bridge, particularly high pier bridge are more and more.Widely, and the height of pier is higher for cantilever glider bridge or the use of T steel structure beam bridge in mountain area, require basis, pier shaft, cantilever segment construction lofting quality higher.Frequent appearance causes fried pier due to the too large even appearance mistake of construction lofting error, ruins the generation of pier event, causes certain loss to national economy.And the total powerstation polar method construction lofting method that traditional construction lofting technology, particularly domestic unit in charge of construction generally adopt, there is very large risk.Such as in mountain area, the distance of lofting control point and basis, high pier and cantilever segment layout point, due to the restriction of landform, often reaches 200-300 meters far away even farther.The setting-out distance of length like this, any tiny error in measuring process is all likely amplified to the limit difference scope exceeding specification and specify.So, need the method proposing the accurate construction lofting of a kind of cantilever glider bridge.
Summary of the invention
Easily there is error to solve current cantilever glider bridge construction lofting and cause the affected technical matters of engineering, the invention provides the accurate construction lofting method of a kind of cantilever glider bridge construction.
Technical scheme of the present invention is, a kind of accurate construction lofting method of cantilever glider bridge construction, comprises the steps:
Step 1: the forced centering observation stand near cantilever glider bridge construction place sets up total powerstation observe by being arranged on, setting-out goes out cantilever glider bridge and to construct two reference mark of accurate construction lofting, and two reference mark are the firmly quality section of the end of the bridge of extended line on cantilever glider bridge two reverse directions of cantilever glider bridge bridge axis and the position that can observe mutually;
Step 2: set pre-layout point as cantilever beam section is along the mid point a of bridge axis direction length, now make one of them reference mark be A, another reference mark is B, then A in theory, a, B three point on a straight line, at A place, reference mark erection total powerstation, the aiming subtend reference mark B that faces left determines Article 1 direction of visual lines, then on Article 1 direction of visual lines, with reference mark A for starting point, with the distance between reference mark A and pre-layout point a for length, determine position 1;
Step 3: the total powerstation set up on the A of reference mark again, coils right aiming subtend reference mark B, determines Article 2 direction of visual lines, then on Article 2 direction of visual lines, with reference mark A for starting point, with the distance between reference mark A and pre-layout point a for length, determines position 2;
Step 4: the fetch bit mid point of putting line between 1 and position 2 just to be fixed a point a1 as setting-out;
Step 5: set up total powerstation again on the B of reference mark, the aiming subtend reference mark A that faces left determines Article 3 direction of visual lines, then on Article 3 direction of visual lines, with reference mark B for starting point, with the distance between reference mark B and pre-layout point a for length, determines position 3;
Step 6: set up total powerstation again on the B of reference mark, coils right aiming subtend reference mark A and determines Article 4 direction of visual lines, then on Article 4 direction of visual lines, with reference mark B for starting point, with the distance between reference mark B and pre-layout point a for length, determines position 4;
Step 7: fetch bit puts the mid point of line between 3 and position 4 as setting-out time fixed point a2;
Step 8: pick and place just fix a point a1 and setting-out time of sample and fix a point the mid point of line between a2 as the accurate layout point of a point.
Technique effect of the present invention is, can ensure the accuracy of construction lofting, also can expand the suitable time of construction lofting, solves the accuracy problem of cantilever glider bridge construction lofting, greatly reduces error probability and the risk of construction lofting.
Below in conjunction with accompanying drawing, the invention will be further described.
Accompanying drawing explanation
Fig. 1 is schematic diagram of the present invention.
Embodiment
See Fig. 1, the present invention includes following steps:
Step 1: the forced centering observation stand near cantilever glider bridge construction place sets up total powerstation observe by being arranged on, setting-out goes out cantilever glider bridge and to construct two reference mark of accurate construction lofting, and two reference mark are the firmly quality section of the end of the bridge of extended line on cantilever glider bridge two reverse directions of cantilever glider bridge bridge axis and the position that can observe mutually;
Step 2: set pre-layout point as cantilever beam section is along the mid point a of bridge axis direction length, now make one of them reference mark be A, another reference mark is B, then A in theory, a, B three point on a straight line, at A place, reference mark erection total powerstation, the aiming subtend reference mark B that faces left determines Article 1 direction of visual lines, then on Article 1 direction of visual lines, with reference mark A for starting point, with the distance between reference mark A and pre-layout point a for length, determine position 1;
Step 3: the total powerstation set up on the A of reference mark again, coils right aiming subtend reference mark B, determines Article 2 direction of visual lines, then on Article 2 direction of visual lines, with reference mark A for starting point, with the distance between reference mark A and pre-layout point a for length, determines position 2;
Step 4: the fetch bit mid point of putting line between 1 and position 2 just to be fixed a point a1 as setting-out;
Step 5: set up total powerstation again on the B of reference mark, the aiming subtend reference mark A that faces left determines Article 3 direction of visual lines, then on Article 3 direction of visual lines, with reference mark B for starting point, with the distance between reference mark B and pre-layout point a for length, determines position 3;
Step 6: set up total powerstation again on the B of reference mark, coils right aiming subtend reference mark A and determines Article 4 direction of visual lines, then on Article 4 direction of visual lines, with reference mark B for starting point, with the distance between reference mark B and pre-layout point a for length, determines position 4;
Step 7: fetch bit puts the mid point of line between 3 and position 4 as setting-out time fixed point a2;
Step 8: pick and place just fix a point a1 and setting-out time of sample and fix a point the mid point of line between a2 as the accurate layout point of a point.

Claims (1)

1. an accurate construction lofting method for cantilever glider bridge construction, is characterized in that, comprise the steps:
Step 1: the forced centering observation stand near cantilever glider bridge construction place sets up total powerstation observe by being arranged on, setting-out goes out cantilever glider bridge and to construct two reference mark of accurate construction lofting, and two reference mark are the firmly quality section of the end of the bridge of extended line on cantilever glider bridge two reverse directions of cantilever glider bridge bridge axis and the position that can observe mutually;
Step 2: set pre-layout point as cantilever beam section is along the mid point a of bridge axis direction length, now make one of them reference mark be A, another reference mark is B, then A in theory, a, B three point on a straight line, at A place, reference mark erection total powerstation, the aiming subtend reference mark B that faces left determines Article 1 direction of visual lines, then on Article 1 direction of visual lines, with reference mark A for starting point, with the distance between reference mark A and pre-layout point a for length, determine position 1;
Step 3: the total powerstation set up on the A of reference mark again, coils right aiming subtend reference mark B, determines Article 2 direction of visual lines, then on Article 2 direction of visual lines, with reference mark A for starting point, with the distance between reference mark A and pre-layout point a for length, determines position 2;
Step 4: the fetch bit mid point of putting line between 1 and position 2 just to be fixed a point a1 as setting-out;
Step 5: set up total powerstation again on the B of reference mark, the aiming subtend reference mark A that faces left determines Article 3 direction of visual lines, then on Article 3 direction of visual lines, with reference mark B for starting point, with the distance between reference mark B and pre-layout point a for length, determines position 3;
Step 6: set up total powerstation again on the B of reference mark, coils right aiming subtend reference mark A and determines Article 4 direction of visual lines, then on Article 4 direction of visual lines, with reference mark B for starting point, with the distance between reference mark B and pre-layout point a for length, determines position 4;
Step 7: fetch bit puts the mid point of line between 3 and position 4 as setting-out time fixed point a2;
Step 8: pick and place just fix a point a1 and setting-out time of sample and fix a point the mid point of line between a2 as the accurate layout point of a point.
CN201410025067.0A 2014-01-20 2014-01-20 A kind of accurate construction lofting method of cantilever glider bridge construction Expired - Fee Related CN103727934B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410025067.0A CN103727934B (en) 2014-01-20 2014-01-20 A kind of accurate construction lofting method of cantilever glider bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410025067.0A CN103727934B (en) 2014-01-20 2014-01-20 A kind of accurate construction lofting method of cantilever glider bridge construction

Publications (2)

Publication Number Publication Date
CN103727934A CN103727934A (en) 2014-04-16
CN103727934B true CN103727934B (en) 2016-03-16

Family

ID=50452114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410025067.0A Expired - Fee Related CN103727934B (en) 2014-01-20 2014-01-20 A kind of accurate construction lofting method of cantilever glider bridge construction

Country Status (1)

Country Link
CN (1) CN103727934B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110057245B (en) * 2019-03-11 2021-06-04 中国人民解放军63883部队 High-precision lofting method for shooting datum
CN110030019B (en) * 2019-05-28 2021-12-31 中国五冶集团有限公司 Rapid positioning lofting method for tunnel primary support steel arch frame

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101158146A (en) * 2007-11-20 2008-04-09 中铁大桥局集团第二工程有限公司 Cable-stayed bridge main-beam sliding form frame system and construction method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10275299A (en) * 1997-03-31 1998-10-13 Saginomiya Seisakusho Inc Vehicle position recognition device for parking lot and parking lot management system

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101158146A (en) * 2007-11-20 2008-04-09 中铁大桥局集团第二工程有限公司 Cable-stayed bridge main-beam sliding form frame system and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
测量中以2点找第三点的一些方法应用;赖海军;《科技传播》;20131010(第18期);第138页、149页 *

Also Published As

Publication number Publication date
CN103727934A (en) 2014-04-16

Similar Documents

Publication Publication Date Title
CN106524936B (en) A kind of tunneltron canopy deformation monitoring method
CN102561118B (en) Quick fine tuning method for ballastless track of high-speed rail based on track deviation
CN101798918B (en) Method for determining relative spatial position of adjacent well parallel segment
CN103706673B (en) A kind of node component radial location method of dome-like roof
EP4279896A3 (en) Optical position and/or shape sensing
CN105973141B (en) A kind of duct pieces of shield tunnel faulting of slab ends measuring device
CN102155230B (en) Tunnel curve segment lofting method based on circle coordinates
CN103115605A (en) Subway shaft orientated measurement method based on connected triangle
CN103727934B (en) A kind of accurate construction lofting method of cantilever glider bridge construction
CN103557800B (en) Multilayer floor slab layering horizontal displacement monitoring method
CN203587075U (en) Building foundation pit slope horizontal displacement monitoring device
CN105421172A (en) Measuring method for one-sided operating double track railway track control net
CN107687831B (en) Aero-engine turn, stator radial clearance calculation method
CN103741726B (en) A kind of open caisson settlement measurement metering method
CN104569355A (en) Surface soil erosion measuring device and method
CN204988223U (en) Detection apparatus for steel member preparation size precision
CN108612075B (en) Method for monitoring horizontal displacement of deep foundation pit
CN203881339U (en) Detachable monitoring pier
CN203375966U (en) Dotting device for vertical shaft connection survey
CN104153353B (en) A kind of method utilizing laser level determination bored pile absolute altitude
CN104897212B (en) Transmission route survey setting-out formula total powerstation
CN202255403U (en) Upper centering bracket for gyroscopic total station
CN103487040B (en) The measuring method that a kind of steel column is installed
CN203249583U (en) Straightness measuring instrument of deep hole
CN207936896U (en) A kind of reinforcement welding axial direction bending angle detector

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160316

Termination date: 20170120

CF01 Termination of patent right due to non-payment of annual fee