CN103726874A - Closed wall sealing method for underground coal mine - Google Patents

Closed wall sealing method for underground coal mine Download PDF

Info

Publication number
CN103726874A
CN103726874A CN201310753453.7A CN201310753453A CN103726874A CN 103726874 A CN103726874 A CN 103726874A CN 201310753453 A CN201310753453 A CN 201310753453A CN 103726874 A CN103726874 A CN 103726874A
Authority
CN
China
Prior art keywords
wall
airtight
reserved opening
stones
closing door
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310753453.7A
Other languages
Chinese (zh)
Other versions
CN103726874B (en
Inventor
李现锋
李彦灵
杨奎峰
李耀民
徐彦伟
李红恩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wang Kun
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310753453.7A priority Critical patent/CN103726874B/en
Publication of CN103726874A publication Critical patent/CN103726874A/en
Application granted granted Critical
Publication of CN103726874B publication Critical patent/CN103726874B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Specific Sealing Or Ventilating Devices For Doors And Windows (AREA)
  • Special Wing (AREA)

Abstract

The invention relates to a closed wall sealing method for an underground coal mine. The method includes the steps that a building position of a closed wall is determined, a foundation pit is dug after a reference wall line is pulled, the closed wall is built in the foundation pit, a wall reserved opening is reserved in the closed wall, a sealing door is installed on the wall reserved opening, and when building of the closed wall is completed, the sealing door arranged on the wall reserved opening is built after a door plate of the sealing door on the wall reserved opening is closed. According to the method, a notch is reserved on the built closed wall, a door structure is fixed to the inner side of the notch, the door structure is closed when the reserved notch is finally sealed, air flow is cut off through the door structure, air pressure is reduced, and fast and safe sealing is achieved. The equipment is simple in structure, practical and convenient to use, other energy is not need, and the phenomenon that body health of employees is injured under the action of high air pressure is avoided. Through application of the method, high-standard fast operation is achieved, and a safe work environment is also provided for the employees.

Description

Airtight body of wall method for blocking under a kind of coal mine
Technical field
The present invention relates to airtight body of wall method for blocking under a kind of coal mine.
Background technology
In coal production process, must have rationally, the operation of efficient, science stable, ventilation system guarantee ventilation equipment and whole system reliably, thereby guarantee safety in production.Accomplish that this point need to build a large amount of ventilation walls and fire dam by laying bricks or stones, airtight body of wall is exactly conventional ventilation equipment, after work plane reclaims, for preventing Study on Protection of Spontaneous Combustion, needs to recovery operation Mian Ji lane, air way, seal in time simultaneously.Employing machine lane, air way seal simultaneously, can cut off rapidly goaf oxygen supply condition, can reach the complete totally enclosed shortest time in goaf, eliminate in time the hidden danger of spontaneous fire.At present, in the shutoff of coal mine down-hole tunnel, be all to adopt airtight body of wall conventionally, airtight body of wall to build by laying bricks or stones be conventionally all to build by laying bricks or stones in the tunnel of the discarded tunnel of needs or breaking out of fire, when airtight building wall, first dig foundation pit, then in foundation pit, build by laying bricks or stones.And there is inconvenience in building by laying bricks or stones of body of wall of sealing, along with building by laying bricks or stones of airtight body of wall, the draught area in tunnel reduces gradually, during particularly to last sealing, because draught area is too small, exist blast large, wind speed is high, and pernicious gas constantly increases, the operation needing to the staff who builds sealing body of wall by laying bricks or stones brings very big difficulty, because blast is large, the reason that wind speed is high, staff must wear anti-goggles just can carry out operation, finally when sealing, because of the wind speed in tunnel high, the airtight body of wall of the reason top that blast is large is difficult for building by laying bricks or stones, the building materials at airtight body of wall top can be blown off by high wind, and it builds position by laying bricks or stones, often need the repetition shutoff of 5-6 time, the integral body that just can complete airtight body of wall is built by laying bricks or stones, and due to the building by laying bricks or stones of top of sealing body of wall, cannot build by laying bricks or stones according to the program of building by laying bricks or stones normally, be difficult to the masonry quality that reaches desirable.Staff is when building airtight body of wall top by laying bricks or stones, need built on stilts to carry out operation, when work high above the ground, blast is large, wind speed is high, and pernicious gas constantly increases and staff can not adopt normal work position to carry out work, bring hidden danger and increase intensity of workers to staff's safety, also can bring infringement to staff's health.
Summary of the invention
The shortcoming existing for prior art, the invention provides airtight body of wall method for blocking under a kind of coal mine, and the method can be carried out shutoff to work plane or Abandoned Tunnel fast and efficiently.
Technical scheme of the present invention is such realization: airtight body of wall method for blocking under a kind of coal mine, comprises the following steps:
(1), in the tunnel of discarded tunnel or breaking out of fire, determine the position of building by laying bricks or stones of airtight body of wall;
(2) according to the position of building by laying bricks or stones of airtight body of wall, draw after benchmark wall line, according to benchmark wall line, dig foundation pit, in foundation pit, build airtight body of wall by laying bricks or stones, when the height of airtight body of wall is built by laying bricks or stones to ground line position, tunnel, reserved body of wall reserved opening on airtight body of wall, the size of described body of wall reserved opening be airtight body of wall the gross area 1/4th to 2/5ths, the thickness of described airtight body of wall is 500-800mm;
(3) closing door body is installed in body of wall reserved opening, described closing door body is comprised of door-plate and rotating shaft part, and the rotating shaft part on described closing door body is fixed in body of wall reserved opening, makes closing door body by rotating shaft part and sealing wall connecting;
(4) open the door-plate of closing door body in body of wall reserved opening, continue to build by laying bricks or stones airtight body of wall;
(5) when airtight building wall completes, close after the door-plate of closing door body in body of wall reserved opening, then the closing door body that masonry panel reserved opening place arranges divides.
Further, 1/3rd of the gross area that the size of described body of wall reserved opening is airtight body of wall.
Further, described closing door body adopts fire proofing to make.
Further, the building materials of described airtight body of wall is stone or brick.
The invention has the beneficial effects as follows: the present invention adopts reserved breach on the airtight body of wall of building by laying bricks or stones, in breach inboard, fix a door, when breach is reserved in the end shutoff, close door, by door, cut off object distinguished and admirable, that the realization of reduction blast is fast and safely sealed.The present invention is simple in structure, practical and convenient, without using other energy, has avoided employee to damage under high Action of Wind pressure healthy.The application of the method, realizes high standard sharp work, also for employee provides safe working environment.
Accompanying drawing explanation
The structural representation of Fig. 1 airtight body of wall of the present invention;
1, airtight body of wall 2, body of wall reserved opening 3, closing door body 4, rotating shaft 5, door-plate
The specific embodiment
For making the object, technical solutions and advantages of the present invention clearer, below in conjunction with accompanying drawing, embodiment of the present invention is described in further detail.
As shown in Figure 1, airtight body of wall method for blocking under a kind of coal mine, comprises the following steps:
(1), in the tunnel of discarded tunnel or breaking out of fire, determine the position of building by laying bricks or stones of airtight body of wall;
(2) according to the position of building by laying bricks or stones of airtight body of wall, draw after benchmark wall line, according to benchmark wall line, dig foundation pit, in foundation pit, build airtight body of wall by laying bricks or stones, when the height of airtight body of wall is built by laying bricks or stones to ground line position, tunnel, reserved body of wall reserved opening on airtight body of wall, the size of described body of wall reserved opening be airtight body of wall the gross area 1/4th to 2/5ths, the thickness of described airtight body of wall is 500-800mm;
(3) closing door body is installed in body of wall reserved opening, described closing door body is comprised of door-plate and rotating shaft part, and the rotating shaft part on described closing door body is fixed in body of wall reserved opening, makes closing door body by rotating shaft part and sealing wall connecting;
(4) open the door-plate of closing door body in body of wall reserved opening, continue to build by laying bricks or stones airtight body of wall;
(5) when airtight building wall completes, close after the door-plate of closing door body in body of wall reserved opening, then the closing door body that masonry panel reserved opening place arranges divides.
Further, 1/3rd of the gross area that the size of described body of wall reserved opening is airtight body of wall.
Further, described closing door body adopts fire proofing to make.
Further, the building materials of described airtight body of wall is stone or brick.
In concrete building process, this sealing method is safely and fast under coal mine, to construct the inboard fixed gate constructional device of the reserved breach of fire dam, this device is by the door of door-plate, tumbler mix proportion, utilize the closure blocking-up of door distinguished and admirable, reduce blast, reach the object of quick sealing, on airtight body of wall, the reserved breach of institute is determined according to present position blast size, and the reserved greatly breach of blast is little, the little reserved breach of blast can be suitably large.The building materials of airtight body of wall can be sequentially according to its concrete composition: reserved breach on the fire dam of building by laying bricks or stones in coal mine return air lane, in the inboard fixed gate structure of breach, can adopt stone to build by laying bricks or stones building Abandoned Tunnel by laying bricks or stones, build building by laying bricks or stones of fire protection strip by laying bricks or stones and generally take brick masonry, during the reserved breach of in the end shutoff, close door, by door, cut off distinguished and admirable, reduction blast, for employee creates safe working environment, realize sealing safely and fast.
It should be noted that, above-described embodiment is to the explanation of technical solution of the present invention and unrestricted, other modification that is equal to replacement or makes according to prior art of person of an ordinary skill in the technical field is as long as no the thinking and the scope that exceed technical solution of the present invention, within all should being included in right of the presently claimed invention and scope.

Claims (4)

1. an airtight body of wall method for blocking under coal mine, is characterized in that: comprise the following steps:
(1), in the tunnel of discarded tunnel or breaking out of fire, determine the position of building by laying bricks or stones of airtight body of wall;
(2) according to the position of building by laying bricks or stones of airtight body of wall, draw after benchmark wall line, according to benchmark wall line, dig foundation pit, in foundation pit, build airtight body of wall by laying bricks or stones, when the height of airtight body of wall is built by laying bricks or stones to ground line position, tunnel, reserved body of wall reserved opening on airtight body of wall, the size of described body of wall reserved opening be airtight body of wall the gross area 1/4th to 2/5ths, the thickness of described airtight body of wall is 500-800mm;
(3) closing door body is installed in body of wall reserved opening, described closing door body is comprised of door-plate and rotating shaft part, and the rotating shaft part on described closing door body is fixed in body of wall reserved opening, makes closing door body by rotating shaft part and sealing wall connecting;
(4) open the door-plate of closing door body in body of wall reserved opening, continue to build by laying bricks or stones airtight body of wall;
(5) when airtight building wall completes, close after the door-plate of closing door body in body of wall reserved opening, then the closing door body that masonry panel reserved opening place arranges divides.
2. airtight body of wall method for blocking under a kind of coal mine according to claim 1, is characterized in that: 1/3rd of the gross area that the size of described body of wall reserved opening is airtight body of wall.
3. airtight body of wall method for blocking under a kind of coal mine according to claim 1, is characterized in that: described closing door body adopts fire proofing to make.
4. airtight body of wall method for blocking under a kind of coal mine according to claim 1, is characterized in that: the building materials of described airtight body of wall is stone or brick.
CN201310753453.7A 2013-12-30 2013-12-30 A kind of airtight body of wall method for blocking of underground coal mine Expired - Fee Related CN103726874B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310753453.7A CN103726874B (en) 2013-12-30 2013-12-30 A kind of airtight body of wall method for blocking of underground coal mine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310753453.7A CN103726874B (en) 2013-12-30 2013-12-30 A kind of airtight body of wall method for blocking of underground coal mine

Publications (2)

Publication Number Publication Date
CN103726874A true CN103726874A (en) 2014-04-16
CN103726874B CN103726874B (en) 2016-06-08

Family

ID=50451141

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310753453.7A Expired - Fee Related CN103726874B (en) 2013-12-30 2013-12-30 A kind of airtight body of wall method for blocking of underground coal mine

Country Status (1)

Country Link
CN (1) CN103726874B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4096702A (en) * 1975-10-17 1978-06-27 Burton Willard J Mine stopping device and method of constructing same
US20030082010A1 (en) * 1998-11-09 2003-05-01 Jack Kennedy Metal Products & Buildings, Inc. Mine stopping
CN102337906A (en) * 2011-09-09 2012-02-01 陕西开拓建筑科技有限公司 Construction method for pouring airtight partition wall between recovered roadway and reserved roadway
CN102518472A (en) * 2011-12-31 2012-06-27 大同煤矿集团有限责任公司 Mine goaf closing method
CN103244145A (en) * 2013-05-29 2013-08-14 唐山开滦广汇设备制造有限公司 Pressure resistance and pressure relief bricks for coal mine underground seal wall and construction method of seal wall
CN203347824U (en) * 2013-06-17 2013-12-18 李红恩 Coal mine no-frame air door

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4096702A (en) * 1975-10-17 1978-06-27 Burton Willard J Mine stopping device and method of constructing same
US20030082010A1 (en) * 1998-11-09 2003-05-01 Jack Kennedy Metal Products & Buildings, Inc. Mine stopping
CN102337906A (en) * 2011-09-09 2012-02-01 陕西开拓建筑科技有限公司 Construction method for pouring airtight partition wall between recovered roadway and reserved roadway
CN102518472A (en) * 2011-12-31 2012-06-27 大同煤矿集团有限责任公司 Mine goaf closing method
CN103244145A (en) * 2013-05-29 2013-08-14 唐山开滦广汇设备制造有限公司 Pressure resistance and pressure relief bricks for coal mine underground seal wall and construction method of seal wall
CN203347824U (en) * 2013-06-17 2013-12-18 李红恩 Coal mine no-frame air door

Also Published As

Publication number Publication date
CN103726874B (en) 2016-06-08

Similar Documents

Publication Publication Date Title
CN103061776B (en) Method for repairing TBM (tunnel boring machine) cutter head in intra-tunnel high-pressure environment
CN103133007B (en) Shield ground compartment opening method
CN103835723B (en) Pit shaft passes through the comprehensive pre-administering method on stratum, goaf
CN103089276B (en) Deep-shallow hole and high-low pressure coupling grouting technology
CN102061919B (en) Co-mining tunneling method of seam roadway gas
CN205445634U (en) Be used for constructing built -in toward peripheral stratum slip casting reinforcing apparatus from shield
CN208653679U (en) A kind of hydrofracturing detecting earth stress unit protection device
CN102116171A (en) Method for rapid discharge of gas in tunnel
CN108468850A (en) The closed gas pumping control device of underground coal mine
CN103726874A (en) Closed wall sealing method for underground coal mine
CN104929565A (en) Double-layered grouting guide pipe
CN205503185U (en) Quick airtight device of unsealing
CN204326960U (en) The Completion of Drilling Hole device of mine accident down-hole major diameter level rescue
CN205714091U (en) The device in analog band pressure grouting closure boring coal petrography crack
CN206410616U (en) The static medicament pressure pipe of city shallow embedding rock stratum tunnel static blasting construction intermediate hole
CN206220556U (en) Artificial digging pile underground protective platform
CN104612748A (en) Coal-mass gas extraction method and device
CN103758483A (en) Secondary hole sealing method for treating broken area after extraction of crossing hole
CN204342235U (en) A kind of roller shutter type protection door for construction elevator
CN113123720A (en) Construction process for treating grouting holes and simultaneously using grouting holes as gas extraction holes in water damage area of coal seam floor
CN209277931U (en) A kind of this coal bed gas extraction of underground coal mine drilling integrated apparatus
CN103016011A (en) Method for blocking water by grouting wall of auxiliary vertical shaft of sandstones with medium water permeability
CN208251118U (en) Slope reinforcement device
CN206816291U (en) Suitable for the high efficiency fire extinguishing system of well industrial and mineral well shaft
CN106609677A (en) A gas extraction and discharge construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Wang Kun

Inventor after: Cheng Wenjuan

Inventor after: Chen Ling

Inventor after: Zhang Chaohui

Inventor after: Gao Dawei

Inventor after: Yao Dongyang

Inventor after: Lou Yimin

Inventor after: Tang Weijie

Inventor after: Chen Qiang

Inventor after: Xue Qiangqiang

Inventor before: Li Xianfeng

Inventor before: Li Yanling

Inventor before: Yang Kuifeng

Inventor before: Li Yaomin

Inventor before: Xu Yanwei

Inventor before: Li Hongen

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160505

Address after: 467000, No. 9, No. 7, East Central, Kaiyuan Middle Road, Wei East, Pingdingshan, Henan

Applicant after: Wang Kun

Address before: 467000, No. 57, building 7, East Ring Road East, 4 East Methodist Road, Pingdingshan, Henan

Applicant before: Li Hongen

C14 Grant of patent or utility model
GR01 Patent grant