- CN103716894B CN103716894B CN201310752971.7A CN201310752971A CN103716894B CN 103716894 B CN103716894 B CN 103716894B CN 201310752971 A CN201310752971 A CN 201310752971A CN 103716894 B CN103716894 B CN 103716894B
- Authority
- CN
- China
- Prior art keywords
- base station
- station enb
- evolution base
- carrying
- user equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The invention provides a method and a device for processing service data during bearing and preemption in LTE. The method comprises the steps: an evolved nodeb (ENB) inquires whether a third bearer of a first user device (UE) 1 exists or not when the second allocation retention priority (ARP) 2 of a second bearer of a second user device (UE) 2 newly accessed to the ENB is higher than the first allocation retention priority (ARP) 1; the ENB uses the third bearer to transmit the service data to the first UE1 if the third bearer exists; the ENB judges whether the access time of the second bearer exceeds the preset time or not; the ENB stops transmitting the service data to the first UE1 through the third bearer and releases the first bearer if the access time of the second bearer exceeds the preset time. The method and the device for processing the service data during bearing and preemption in the LTE are used for ensuring the continuous transmission capacity of the service data with preempted and borne resources.
Description
Technical field
The present invention relates to mobile communication technology field, carries business data processing when seizing in more particularly to a kind of LTE
Method, and, the device of business data processing when seizing is carried in a kind of LTE.
Background technology
In order to ensure 3GPP (The 3rd Generation Partnership Project, third generation affiliate meter
Draw) competitive advantage, 3GPP starts LTE (Long Term Evolution, Long Term Evolution) and SAE (System
Architecture Evolution, System Architecture Evolution) project, designs the LTE/SAE system architecture (SAE for proposing full IP
After be renamed as EPC (Evolved Packet Core, evolution block core net)), and to its wireless key technology, interface protocol,
Signaling process, system safety, and its with UMTS (Universal Mobile Telecommunications System, it is general
Mobile communication system) between interoperability etc. carried out standardization.LTE/EPC is referred to as EPS (Evolved Package
System, the grouping system of evolution), EPC include MME (Mobility Management Entity, mobile management entity),
SGW (Serving Gateway, gateway), and, the network element such as PGW (PDN Gataway, packet data gateway), in LTE
Including ENB (Evolved Node Base, evolved base station) and UE (User Equipment, user equipment)
ENB in LTE can carry the GBR (Guaranteed Bit Rate, it is ensured that bit rate) of (Bearer) according to UE
Eat dishes without rice or wine with UE-AMBR (Maximum Bit Rate) distribution, bandwidth and frequency spectrum resource, but these resources are limited, when UE has height
These resources can be seized when accessing by the carrying of priority, and the carrying of lower priority is then released due to inadequate resource,
If ENB directly deletes the context of the carrying and notifies MME release EPC (Evolved Package during release
Core, the packet-based core networks of evolution) in corresponding carrying, but the delay of message signalling interactive process and process may then cause
Network element in EPC is sent to the ENB at the carrying place before local downlink bearing is deleted, still by business datum, but due to
The resource of the carrying is discharged in ENB, therefore business datum is dropped when ENB is reached, on the one hand affect user's body
Test, cause the transfer rate of the business datum of UE to decline or interrupt, on the other hand for connection-oriented certain customers' agreement, example
Such as TCP (Transmission Control Protocol, transmission control protocol) etc., business datum re-transmission can be carried out, be increased
Transmission burden and ENB eat dishes without rice or wine pressure.
Therefore, when one of those skilled in the art's problem in the urgent need to address is to carry to seize in a kind of LTE of proposition
The method and device of business data processing, is preempted the ability of the business datum continuous transmission of carrying to Support Resource, while
Degrading or interrupt and reduce Consumer's Experience due to business datum is avoided, and avoids what is brought due to the scheduling of radio bearer
Extra pressure.
The content of the invention
A kind of the technical problem to be solved carries business data processing when seizing method in being to provide LTE,
And, the device of business data processing when seizing is carried in a kind of LTE, the business datum for being preempted carrying to Support Resource is held
Resume defeated ability, while avoid degrading or interrupt and reduce Consumer's Experience due to business datum, and avoid without due to
The extra pressure that the scheduling that line is carried brings.
In order to solve the above problems, the invention discloses a kind of method that business data processing when seizing is carried in LTE, institute
Stating Long Term Evolution LTE includes that evolution base station ENB, the evolution base station ENB include that the first of first user equipment UE 1 is held
Carry, first carrying includes the first allocation retention priority ARP1, and described method includes:
When the second carrying of the new second user equipment UE 2 for accessing evolution base station ENB, its second allocation retention priority
When ARP2 is higher than first allocation retention priority ARP1, the evolution base station ENB inquiries are with the presence or absence of the first user
3rd carrying of equipment UE 1;
If have the 3rd carrying, the evolution base station ENB carries transmission services data to described the using the described 3rd
One user equipment (UE) 1;The business datum by evolution block core net EPC send to described first carry, the EPC with it is described
LTE intercommunication;
The evolution base station ENB judges that described second carries whether the time accessed exceedes the default time;
If described second carries the time accessed and exceed Preset Time, the evolution base station ENB stops using described the
Three carry the transmission business datum to first user equipment UE 1, and discharge first carrying.
Preferably, described method also includes:
The evolution base station ENB starts preemption delay intervalometer.
Preferably, the evolution base station ENB judges that described second carries whether the time accessed exceedes the default time
Step is:
When the time default more than the preemption delay intervalometer, the evolution base station ENB judges that described second carries
The time of access exceedes the default time.
Preferably, the evolution base station ENB stops carrying the transmission business datum to first user using the described 3rd
Equipment UE 1, and discharge it is described first carry the step of include:
The evolution base station ENB stops carrying the transmission business datum to first user equipment UE 1 using the described 3rd;
The evolution base station ENB deletes described first and carries corresponding contextual information.
Preferably, the described 3rd non-ensured bit rate non-GBR carryings are carried as.
The embodiment of the present invention carries the device of business data processing when seizing in additionally providing a kind of LTE, described to drill for a long time
Entering LTE includes that evolution base station ENB, the evolution base station ENB include the first carrying of first user equipment UE 1, described the
One carrying includes the first allocation retention priority ARP1, and described device includes:
Positioned at the enquiry module of evolution base station ENB, for ought newly access the second user equipment UE 2 of evolution base station ENB
Second carries, and when its second allocation retention priority ARP2 is higher than first allocation retention priority ARP1, whether inquiry deposits
In the first user equipment UE 1 the 3rd carries;
Positioned at the transport module of evolution base station ENB, if carrying for having the 3rd, carry using the described 3rd and transmit industry
Business data are to the first user equipment UE 1;The business datum is sent to described first by evolution block core net EPC and is held
Load, the EPC and the LTE intercommunication;
Positioned at the judge module of evolution base station ENB, for judging that whether described second carry the time accessed more than default
Time;
Positioned at the release module of evolution base station ENB, if the time accessed is carried for described second exceedes Preset Time,
Stop the transmission business datum being carried to first user equipment UE 1 using the described 3rd, and discharge described first carry.
Preferably, described device also includes:
Positioned at the starting module of evolution base station ENB, for starting preemption delay intervalometer.
Preferably, the judge module positioned at evolution base station ENB includes:
Positioned at the overtime decision sub-module of evolution base station ENB, for when default more than the preemption delay intervalometer
Between when, judge it is described second carry access time exceed the default time.
Preferably, the release module positioned at evolution base station ENB includes:
Transmission positioned at evolution base station ENB stops submodule, for stopping carrying the transmission business using the described 3rd
Data are to first user equipment UE 1;
Positioned at the deletion submodule of evolution base station ENB, corresponding contextual information is carried for deleting described first.
Preferably, the described 3rd non-ensured bit rate non-GBR carryings are carried as.
Compared with prior art, the present invention includes advantages below:
In embodiments of the present invention, when the resource of the carrying in UE is by the carrying with higher allocation retention priority ARP
When seizing, can be realized using other the transmission services data for carrying temporarily to substitute the carrying for being preempted resource in ENB
The succession relation of short period service data, it is ensured that be preempted the ability of the business datum continuous transmission of the carrying of resource, while keeping away
Exempt from degrading or interrupt and reduce Consumer's Experience due to business datum, and avoid the volume brought due to the scheduling of radio bearer
External pressure.
Description of the drawings
Fig. 1 is a kind of process schematic of bearing resource release of prior art;
Fig. 2 be the present invention a kind of LTE in flow chart the step of carry the embodiment of the method for business data processing when seizing;
Fig. 3 is the business data flow direction schematic diagram before a kind of bearing resource of the present invention is preempted;
Fig. 4 is the business data flow direction schematic diagram after a kind of bearing resource of the present invention is preempted;
Fig. 5 be the present invention a kind of LTE in carry the structured flowchart of the device embodiment of business data processing when seizing.
Specific embodiment
It is understandable to enable the above objects, features and advantages of the present invention to become apparent from, it is below in conjunction with the accompanying drawings and concrete real
The present invention is further detailed explanation to apply mode.
In order that those skilled in the art further appreciate that the embodiment of the present invention, bearing resource is realized to current LTE below
The scheme of release is illustrated.
ENB be carried on access or renewal process in can obtain interface-free resources, it is if now interface-free resources are not enough, right
Priority is relatively low, and the resource of the carrying that can be preempted is seized, and the resource of the carrying being preempted will be released, specifically
Process is referred to a kind of process schematic of bearing resource release of the prior art shown in Fig. 1, is presented as on S1 interfaces
E-RAB RELEASE (RAB release) process, MME is according to E-RAB RELEASE INDICATION (wireless access
Carry release and indicate message) in the corresponding core-network sides of E-RAB that indicate of radio bearer resources list E-RAB list carry, to
SGW sends RELEASE ACCESS BEARERS REQUEST (carrying right to use releasing request message), request release S1 interfaces
Carrying, if SGW agree to discharge the carrying, return RELEASE ACCESS BEARERS RESPONS (carry the right to use release
Put response message).
However, the following problem of problem that the scheme of the bearing resource release is present:
1, ENB sends E-RAB RELEASE to MME while release local carrying, by each EPC network element processing difference
With the impact of time delay, the release of the carrying in EPC network elements relatively lags behind, and now the descending business datum in part can still be sent to
In the carrying of release, cause user data loss, produce business datum and retransmit.
2, carry under release conditions in ENB, descending business datum still reaches the carrying of the ENB, causes S1 interfaces
ERR INDICATION (miscue message) are generated, into failure flow process is carried, is runed counter to program design original meaning itself.
As current release flow process may cause the transfer rate of UE to decline, serious conditions may cause user's application connection
Interrupt, simultaneously because the reason such as part EPC network elements release delay and service surface caching, causes UE partial services data to retransmit, plus
The pressure that acute ENB eats dishes without rice or wine.
Exactly inventor herein has found the seriousness of this problem, creatively proposes the core structure of the embodiment of the present invention
One of think of is that, when the carrying that power is seized with higher resource is accessed, using other carryings, temporarily replacement is preempted resource
Carry forwarding service data, it is to avoid business data transmission is interrupted, improve Consumer's Experience effect.
With reference to Fig. 2, the step of carry the embodiment of the method for business data processing when seizing in showing a kind of LTE of the invention
Flow chart, the Long Term Evolution LTE include to include first user in the evolution base station ENB with evolution base station ENB
First carrying of equipment UE 1, described first carries and can specifically may be used including the first allocation retention priority ARP1, described method
To comprise the steps:
Step 101, when the second carrying of the new second user equipment UE 2 for accessing evolution base station ENB, its second distribution retains
When priority ARP2 is higher than first allocation retention priority ARP1, evolution base station ENB inquiry is with the presence or absence of described the
3rd carrying of one user equipment (UE) 1;If having the 3rd to carry, execution step 102;
In EPS, the basic granularity that QoS (Quality of Service, service quality) is controlled is to carry, i.e., identical to hold
All business datums in load will obtain identical QoS and ensure (such as scheduling strategy, buffering queue management, link layer configuration etc.),
Different QoS is ensured to be needed different types of carrying to provide.In implementing, according to the difference of QoS, carrying can be divided
For two big class:GBR (Guranteed Bit Rate, it is ensured that bit rate) is carried and Non-GBR (Non-Guranteed Bit
Rate, non-ensured bit rate) carry.GBR refers to the bit rate of bearing requirements by the constant distribution of network " permanent ", even if
In the case of Internet resources anxiety, corresponding bit rate can also keep.MBR (Maximum Bit Rate) parameter is defined
Under conditions of GBR is carried on resource abundance, the upper limit of the service data transmission rate that can be reached.The value of MBR is possible to be more than
Or equal to the value of GBR.Contrary, Non-GBR is referred in the case of network congestion, and carrying to need to bear reduces wanting for speed
Ask, fixed Internet resources need not be taken as Non-GBR is carried, thus can be set up for a long time.And GBR carries general
Simply just set up when needed.
In embodiments of the present invention, if the resource of second carrying of the new UE2 for accessing is seized power and held higher than the first of UE1
Carry, i.e., the second ARP for carrying (Allocation/Retention Priority, distribution keep priority), higher than in ENB
First carries, then second carry the resource that will seize the first carrying, and first carries and will be released, and now ENB will inquire about this
Ground is carried with the presence or absence of the 3rd, wherein, the described 3rd carries and can carry for non-ensured bit rate non-GBR.
Specifically, ENB inquiry be preempted carry belonging to UE under with the presence or absence of except be preempted carry in addition to non-GBR, such as
Fruit is not present, then can directly discharge the carrying and its Radio Resource being preempted, illustrate now to illustrate that the carrying being preempted is UE1
The last item default bearing.After the carrying is preempted, all bearer contexts of the UE1 in ENB can be deleted, now
ENB will not provide business data transmission service for UE1.
Step 102, the evolution base station ENB carry transmission services data to the first user equipment using the described 3rd
UE1;The business datum is sent to described first by evolution block core net EPC and is carried, and the EPC is mutually communicated with the LTE
Letter;
In embodiments of the present invention, if there is other carryings in ENB, such as non-GBR then can arbitrarily choose which
In a descending carrying that continues as UE1 business datums, form descending succession relation, i.e. industry with first carrying to be released
Business data downstream direction is every to be sent to the 3rd carrying to be released, by the 3rd carry by business datum transfer to it is selected under
This partial data is sent to UE1, and shared UE-AMBR by the Radio Resource of the descending carrying that continues by the capable carrying that continues, ENB.
In one preferred embodiment of the invention, described method can also comprise the steps:
The evolution base station ENB starts preemption delay intervalometer.
Wherein, when release is preempted the Radio Resource of carrying, can start and seize delay timer T, need explanation
It is to seize delay timer T to be restricted this according to network design situation flexible configuration, the embodiment of the present invention.
Step 103, the evolution base station ENB judge that described second carries whether the time accessed exceedes the default time;
If described second carries the time accessed more than Preset Time, the step 104 is performed;
In one preferred embodiment of the invention, the sub-step of the step 103 can be:
When the time default more than the preemption delay intervalometer, the evolution base station ENB judges that described second carries
The time of access exceedes the default time.
In a kind of preferred exemplary of the present invention, after start delay intervalometer T exceedes its default time, ENB can be with
Judge that the time that the second carrying is accessed exceedes the default time.
Step 104, the evolution base station ENB stop carrying the transmission business datum to first user using the described 3rd
Equipment UE 1, and discharge first carrying.
In one preferred embodiment of the invention, the step 104 can include following sub-step:
Sub-step S11, the evolution base station ENB stop carrying the transmission business datum to the first use using the described 3rd
Family equipment UE 1;
Sub-step S12, the evolution base station ENB are deleted described first and carry corresponding contextual information.
In embodiments of the present invention, when second carries the time accessed more than the default time, it is believed that in EPC network elements
First carrying related resource be released, will not again to first carry send business datum, now ENB can discharge
Treat the resource of the first carrying.It is erased entirely to the now first related context for carrying, in addition, the 3rd carries this in LTE
Up-downgoing succession relation in network remains unchanged.
In order that those skilled in the art better understood when the embodiment of the present invention, below by way of a specific example
The embodiment of the present invention is illustrated:
A kind of bearing resource of the present invention with reference to shown in Fig. 3 be preempted before business data flow direction schematic diagram, wherein, UE
It is air wireless interface (UU interfaces) between ENB, is S1U interfaces between ENB and SGW, is S5 interfaces between SGW and PGW,
It is SGI interfaces between PGW and APN (Access Point Name, access network title).In actual applications, UE is carried on A
Downlink service data, by PGW and SGW network element of APN (Access Point Name, the access network title) network by network side
Carrying relaying after be sent to the carrying A of ENB, business datum is sent to UE by the interface-free resources of carrying A by ENB again.
A kind of bearing resource of the present invention with reference to shown in Fig. 4 be preempted after business data flow direction schematic diagram, when in ENB
After the resource of carrying A is preempted, choose non-GBR and B is carried as the carrying that continues of the downlink service data for carrying A, then carry A
Downlink data flow direction be changed to:Still by carrying A to ENB transmission services data in PGW and SGW, now UE is in carrying B
UU interfaces on still can receive from the business datum for carrying A, but the business datum of A is carried in the ENB by holding
Data are sent to UE by the Radio Resource for carrying B.When seize delay timer T it is overtime after, that is, more than seizing delay timer T
The EPC sides network element estimated discharges the time of carrying A related contexts to be released, can be with the contextual information of deleting bearing A.Seize
The time of back off timer T was could be arranged to more than EPC deenergized periods.Certainly, preemption delay intervalometer T can be according to different
Network design situation flexible configuration.
It should be noted that described in such scheme being, except the UE is in addition to carrying to be released (carry of A), still exist
The scene that non-GBR is carried, should be divided into following two situations in practice:
1st, carrying to be released (carrying A) is not the default bearing under UE certain PDN, and the UE still has which under the PDN
His default bearing.After A releases are carried, the downlink service data on A is carried in EPS by by carrying the silent of the PDN belonging to A
Recognize carrying transmission, i.e., after A releases are carried, the default bearing (for example carrying B) in EPS temporarily alternative bearer A will continue to pass
Defeated business datum;
2nd, the UE has multiple APN connections, and carries the default bearing that A is PDN under certain APN.But under others APN
Still there is default bearing in PDN connections.After A releases are carried, the downlink service data carried on A will be refused on SGI interfaces
Absolutely, business datum stops transmission.
For situation 1, the embodiment of the present invention ensure that the data for carrying A are not interrupted during being preempted.For feelings
Condition 2, the embodiment of the present invention do not affect the characteristic that business data transmission stops.
Carry in existing ENB and seize under scene, specific algorithm is not quite similar when being realized due to each manufacturer, causes different EPC
There is larger difference in the release time that network element is carried, thus possible caused business datum disconnection, and the speed experience to user is made
Into considerable influence.Secondly, in the process, the continuous transmission of data, the ERR of possible initiating system due to the release that carries
INDICATION flow processs, so as to affect the KPI (Key Performance Indicator, critical sales index) of grid.
And apply the embodiment of the present invention, it can be ensured that be carried on be preempted be carried on release during business datum service the guarantor that continues
Hold.Specifically, before the carrying that ENB releases are preempted, if the UE has non-GBR carryings, from current ENB
Non-GBR chooses a descending carrying that continues as carrying to be released in carrying, and generates the short-term of the local carryings to be released of ENB
Descending succession relation, the business datum of carrying to be released can be sent to by selected non-GBR carryings in handoff procedure
UE, guarantee are preempted the ability of the business continuous transmission of carrying.Wherein, the time that the handoff procedure succession relation keeps can be by
One Timer Controlling, starts intervalometer when seizing beginning, after the timer expiry, can delete succession relation, and thoroughly
Deletion is preempted the contextual information of carrying.
It should be noted that for embodiment of the method, in order to be briefly described, therefore which to be all expressed as a series of action group
Close, but those skilled in the art should know, the application is not limited by described sequence of movement, because according to this Shen
Please, some steps can adopt other orders or while carry out.Secondly, those skilled in the art should also know, description
Described in embodiment belong to preferred embodiment, necessary to involved action not necessarily the application.
With reference to Fig. 5, the structure of the device embodiment of business data processing when seizing in showing a kind of LTE of the invention, is carried
Block diagram, the Long Term Evolution LTE include to set including first user in the evolution base station ENB with evolution base station ENB
First carrying of standby UE1, described first carries and can include the first allocation retention priority ARP1, and described device specifically can be with
Including such as lower module:
Positioned at the enquiry module 201 of evolution base station ENB, for ought newly access the second user equipment UE 2 of evolution base station ENB
The second carrying, when its second allocation retention priority ARP2 is higher than first allocation retention priority ARP1, whether inquiry
There is the 3rd carrying of the first user equipment UE 1;
Positioned at the transport module 202 of evolution base station ENB, if carrying for having the 3rd, carry using the described 3rd and pass
Defeated business datum is to the first user equipment UE 1;The business datum can be sent to described by evolution block core net EPC
First carries, and the EPC can be with the LTE intercommunication;
In one preferred embodiment of the invention, described device can also include:
Positioned at the starting module of evolution base station ENB, for starting preemption delay intervalometer.
Positioned at the judge module 203 of evolution base station ENB, for judging that described second carries whether the time accessed exceedes in advance
If time;
In one preferred embodiment of the invention, the judge module 203 positioned at evolution base station ENB can include:
Positioned at the overtime decision sub-module of evolution base station ENB, for when default more than the preemption delay intervalometer
Between when, judge it is described second carry access time exceed the default time.
Positioned at the release module 204 of evolution base station ENB, if carry the time accessed more than presetting for described second
Between, then stop the transmission business datum being carried to first user equipment UE 1 using the described 3rd, and discharge described first hold
Carry.
In one preferred embodiment of the invention, the release module 204 positioned at evolution base station ENB can include:
Transmission positioned at evolution base station ENB stops submodule, for stopping carrying the transmission business using the described 3rd
Data are to first user equipment UE 1;
Positioned at the deletion submodule of evolution base station ENB, corresponding contextual information is carried for deleting described first.
In one preferred embodiment of the invention, the described 3rd carry and can carry for non-ensured bit rate non-GBR.
For device embodiment, due to itself and embodiment of the method basic simlarity, so description is fairly simple, it is related
Part is illustrated referring to the part of embodiment of the method.
Each embodiment in this specification is described by the way of progressive, what each embodiment was stressed be with
The difference of other embodiment, between each embodiment identical similar part mutually referring to.
Those skilled in the art are it should be appreciated that embodiments herein can be provided as method, device or computer program
Product.Therefore, the application can adopt complete hardware embodiment, complete software embodiment or with reference to the reality in terms of software and hardware
Apply the form of example.And, the application can be using the computer for wherein including computer usable program code at one or more
The computer program implemented in usable storage medium (including but not limited to disk memory, CD-ROM, optical memory etc.) is produced
The form of product.
The application be with reference to according to the method for the embodiment of the present application, equipment (system), and computer program flow process
Figure and/or block diagram are describing.It should be understood that can by computer program instructions flowchart and/or block diagram in it is each
The combination of flow process and/or square frame and flow chart and/or flow process and/or square frame in block diagram.These computer journeys can be provided
Sequence instruction to general purpose computer, special-purpose computer, Embedded Processor or other programmable data processing devices processor with
Produce a machine so that being produced by the instruction of computer or the computing device of other programmable data processing devices is used for
The dress of the function that realization is specified in one flow process of flow chart or one square frame of multiple flow processs and/or block diagram or multiple square frames
Put.
These computer program instructions may be alternatively stored in and can guide computer or other programmable data processing devices with spy
Determine in the computer-readable memory that mode works so that the instruction being stored in the computer-readable memory is produced to be included referring to
Make the manufacture of device, the command device realize in one flow process of flow chart or one square frame of multiple flow processs and/or block diagram or
The function of specifying in multiple square frames.
These computer program instructions can be also loaded in computer or other programmable data processing devices so that in meter
Series of operation steps is performed on calculation machine or other programmable devices to produce computer implemented process, so as in computer or
The instruction performed on other programmable devices is provided for realizing in one flow process of flow chart or multiple flow processs and/or block diagram one
The step of function of specifying in individual square frame or multiple square frames.
Although having been described for the preferred embodiment of the application, those skilled in the art once know basic creation
Property concept, then can make other change and modification to these embodiments.So, claims are intended to be construed to include excellent
Select embodiment and fall into the had altered of the application scope and change.
Finally, in addition it is also necessary to explanation, herein, term " including ", "comprising" or its any other variant are intended to
Cover including for nonexcludability, so that a series of process, method, article or equipment including key elements not only includes those
Key element, but also including other key elements being not expressly set out, or also include for this process, method, article or set
Standby intrinsic key element.In the absence of more restrictions, the key element for being limited by sentence "including a ...", it is not excluded that
Also there is other identical element in the process including the key element, method, article or equipment.
Above to carry in a kind of LTE provided by the present invention seize when business data processing method, and, it is a kind of
The device of business data processing when seizing is carried in LTE, is described in detail, specific case used herein is to this
Bright principle and embodiment are set forth, the explanation of above example be only intended to help understand the method for the present invention and its
Core concept;Simultaneously for one of ordinary skill in the art, according to the thought of the present invention, in specific embodiment and application
Will change in scope, in sum, this specification content should not be construed as limiting the invention.
Claims (10)
1. a kind of method that business data processing when seizing is carried in LTE, it is characterised in that Long Term Evolution LTE includes evolution
Base station ENB, the evolution base station ENB include the first carrying of first user equipment UE 1, and first carrying includes first point
With priority ARP1 is retained, described method includes:
When the new second user equipment UE 2 for accessing evolution base station ENB second carries, and the second of the second user equipment UE 2
When the second allocation retention priority ARP2 for carrying is higher than first allocation retention priority ARP1, the evolution base station ENB
Threeth carrying of the inquiry with the presence or absence of the first user equipment UE 1;
If having the 3rd to carry, the evolution base station ENB carries transmission services data using the described 3rd and uses to described first
Family equipment UE 1;The business datum is sent to described first by evolution block core net EPC and is carried, the EPC and LTE
Intercommunication;
The evolution base station ENB judges that described second carries whether the time accessed exceedes the default time;
If described second carries the time accessed more than Preset Time, the evolution base station ENB stops holding using the described 3rd
The transmission business datum is carried to first user equipment UE 1, and discharges described first and carried.
2. method according to claim 1, it is characterised in that also include:
The evolution base station ENB starts preemption delay intervalometer.
3. method according to claim 1 and 2, it is characterised in that the evolution base station ENB judges that described second carries and connect
The step of whether time for entering exceed the default time be:
When the time default more than the preemption delay intervalometer, the evolution base station ENB judges that described second carries access
Time exceed the default time.
4. method according to claim 1, it is characterised in that the evolution base station ENB stops using the described 3rd carrying
The step of business datum being transmitted to first user equipment UE 1, and discharges first carrying includes:
The evolution base station ENB stops carrying the transmission business datum to first user equipment UE 1 using the described 3rd;
The evolution base station ENB deletes described first and carries corresponding contextual information.
5. the method according to claim 1 or 4, it is characterised in that the described 3rd is carried as non-ensured bit rate non-GBR
Carry.
6. the device of business data processing when seizing is carried in a kind of LTE, it is characterised in that Long Term Evolution LTE includes evolution
Base station ENB, the evolution base station ENB include the first carrying of first user equipment UE 1, and first carrying includes first point
With priority ARP1 is retained, described device includes:
Positioned at the enquiry module of evolution base station ENB, for ought newly access the second of the second user equipment UE 2 of evolution base station ENB
Carry, the second allocation retention priority ARP2 of the second carrying of the second user equipment UE 2 is protected higher than the described first distribution
When staying priority ARP1, threeth carrying of the inquiry with the presence or absence of the first user equipment UE 1;
Positioned at the transport module of evolution base station ENB, if carrying for having the 3rd, transmission services number is carried using the described 3rd
According to the first user equipment UE 1;The business datum is sent to described first by evolution block core net EPC and is carried, institute
EPC is stated with the LTE intercommunication;
Positioned at the judge module of evolution base station ENB, during for judging whether the described second time for carrying access exceeded default
Between;
Positioned at the release module of evolution base station ENB, if the time accessed is carried for described second exceedes Preset Time, stop
Carry using the described 3rd and the business datum is transmitted to first user equipment UE 1, and discharge described first carry.
7. device according to claim 6, it is characterised in that also include:
Positioned at the starting module of evolution base station ENB, for starting preemption delay intervalometer.
8. the device according to claim 6 or 7, it is characterised in that the judge module bag positioned at evolution base station ENB
Include:
Positioned at the overtime decision sub-module of evolution base station ENB, for when the time default more than the preemption delay intervalometer,
Judge that described second carries the time accessed more than the default time.
9. device according to claim 8, it is characterised in that the release module positioned at evolution base station ENB includes:
Transmission positioned at evolution base station ENB stops submodule, for stopping carrying the transmission business datum using the described 3rd
To first user equipment UE 1;
Positioned at the deletion submodule of evolution base station ENB, corresponding contextual information is carried for deleting described first.
10. the device according to claim 6 or 9, it is characterised in that the described 3rd is carried as non-ensured bit rate non-
GBR is carried.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310752971.7A CN103716894B (en) | 2013-12-31 | 2013-12-31 | Method and device for processing service data during bearing and preemption in LTE |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310752971.7A CN103716894B (en) | 2013-12-31 | 2013-12-31 | Method and device for processing service data during bearing and preemption in LTE |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103716894A CN103716894A (en) | 2014-04-09 |
CN103716894B true CN103716894B (en) | 2017-05-03 |
Family
ID=50409341
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310752971.7A Active CN103716894B (en) | 2013-12-31 | 2013-12-31 | Method and device for processing service data during bearing and preemption in LTE |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103716894B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110022619B (en) * | 2018-01-09 | 2021-02-02 | 维沃移动通信有限公司 | Bearer identifier control method, terminal equipment and network equipment |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102056225A (en) * | 2009-11-05 | 2011-05-11 | 中兴通讯股份有限公司 | Distribution method and device for quick feedback channel |
CN102118871A (en) * | 2010-01-06 | 2011-07-06 | 鼎桥通信技术有限公司 | Method for dynamically adjusting bearer channel accessed by wireless resource |
-
2013
- 2013-12-31 CN CN201310752971.7A patent/CN103716894B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102056225A (en) * | 2009-11-05 | 2011-05-11 | 中兴通讯股份有限公司 | Distribution method and device for quick feedback channel |
CN102118871A (en) * | 2010-01-06 | 2011-07-06 | 鼎桥通信技术有限公司 | Method for dynamically adjusting bearer channel accessed by wireless resource |
Also Published As
Publication number | Publication date |
---|---|
CN103716894A (en) | 2014-04-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111885642B (en) | Switching method and device | |
CN109155762B (en) | Data transmission method and device | |
TWI504303B (en) | Handling apn based congestion control and related communication device | |
US9060294B2 (en) | System and method for throttling downlink data notifications in a network environment | |
JP6053837B2 (en) | Overload control in packet mobile communication systems | |
US8630202B2 (en) | Method and apparatus for controlling buffer status report messaging | |
US20110222406A1 (en) | Method And Device For Enabling Indication Of Congestion In A Telecommunications Network | |
CN108702240A (en) | System, method and apparatus for the data rate for managing control plane optimization | |
CN107637122B (en) | Communication terminal and method for handling upload traffic congestion | |
JP7239006B2 (en) | Base station and method | |
KR20120094106A (en) | Quality of service control in a relay | |
CN111213403B (en) | Method and device for scheduling QoS (quality of service) flow in wireless communication system | |
CN107135521B (en) | Flow control method, device and system | |
EP2437445B1 (en) | Dynamic control of air interface throughput | |
CN104702535A (en) | Data transmission method, data transmission device, data transmission system and related equipment | |
EP3304972B1 (en) | Adapting qos for a radio bearer having two associated qos by means of a ue indication | |
EP3193537A1 (en) | Operating a communications device in a mobile communications network | |
CN102427598A (en) | Method and device for limiting loading service in wireless communication | |
CN105471763A (en) | Control message transmission method and device | |
JPWO2017169064A1 (en) | Radio access network node, radio terminal, network node, and methods thereof | |
US11647419B2 (en) | Adjusting window size based on quality of experience | |
CN103716894B (en) | Method and device for processing service data during bearing and preemption in LTE | |
CN110740472B (en) | Control method and system for downlink data transmission | |
CN109802893B (en) | Data transmission method, device and system | |
JP2016046669A (en) | Packet processing device, program and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |