CN103605814A - Information processing method and information processing system in substation transformation process - Google Patents

Information processing method and information processing system in substation transformation process Download PDF

Info

Publication number
CN103605814A
CN103605814A CN201310670691.1A CN201310670691A CN103605814A CN 103605814 A CN103605814 A CN 103605814A CN 201310670691 A CN201310670691 A CN 201310670691A CN 103605814 A CN103605814 A CN 103605814A
Authority
CN
China
Prior art keywords
file
icd
former
amended
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310670691.1A
Other languages
Chinese (zh)
Other versions
CN103605814B (en
Inventor
邹晖
吴劲晖
檀庭芳
王巍巍
纪陵
毛海波
陈彩霞
吴建伟
刘威
柯梦晗
祝碧贤
杜浩良
徐峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Guodiannanzi Software Engineering Co Ltd
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Maintenance Branch of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Nanjing Guodiannanzi Software Engineering Co Ltd
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Maintenance Branch of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Guodiannanzi Software Engineering Co Ltd, State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, Maintenance Branch of State Grid Zhejiang Electric Power Co Ltd filed Critical Nanjing Guodiannanzi Software Engineering Co Ltd
Priority to CN201310670691.1A priority Critical patent/CN103605814B/en
Publication of CN103605814A publication Critical patent/CN103605814A/en
Application granted granted Critical
Publication of CN103605814B publication Critical patent/CN103605814B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/10File systems; File servers
    • G06F16/16File or folder operations, e.g. details of user interfaces specifically adapted to file systems
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Human Resources & Organizations (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Public Health (AREA)
  • Human Computer Interaction (AREA)
  • Data Mining & Analysis (AREA)
  • Databases & Information Systems (AREA)
  • General Engineering & Computer Science (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses an information processing method and an information processing system in a substation transformation process. The information processing method comprises the following steps that after the original ICD (IED Capability Description) document of target power equipment is modified, the obtained original ICD document of the target power equipment is compared with the modified ICD, first modified information which is modified previously in the modified ICD is confirmed, and then, the modification part in the modified ICD is directly imported into the corresponding part of an original SCD (Substation Configuration Description) document without importing the non-modified part, so that the problems of the increase of difficulty and workload of the field adjustment work, the reduction of efficiency of the field adjustment work and influence on the working efficiency of the substation transformation works as in the substation transformation process, when the original ICD document of the target power equipment needs to be modified a plurality of times, the corresponding part of the original SCD document is replaced with the modified ICD document a plurality of times and the original configuration of the target power equipment is correspondingly adjusted according to the ICD document modified each time in the prior art can be solved.

Description

Information processing method and system in a kind of Transfomer Substation Reconstruction process
Technical field
The present invention relates to Transfomer Substation Reconstruction technical field, relate in particular information processing method and system in a kind of Transfomer Substation Reconstruction process.
Background technology
Along with the fast development of electrical network, intelligent grid has become the Developing mainstream of electric system, in order to adapt to the development of intelligent grid, old-fashioned Transfomer Substation Reconstruction need be become to intelligent substation.In change process; conventionally can need the ICD(IED Capability Description to intelligent power equipment; intelligent power equipment ability description) file is changed; due to the description of the configuration of all devices of whole transformer station all at SCD(Substation Configuration Description; substation configuration description) in file; so; once the former ICD file modification of certain power equipment; will inevitably affect the SCD file of whole transformer station, now the appropriate section in the SCD file of this transformer station just must be modified.For this reason, in prior art, conventionally be all that the appropriate section in SCD file is deleted, again import again amended ICD file, and then again to relevant subnet and GOOSE(Generic Object Oriented Substation Event, general in transformer station's object time) empty terminal reconfigures and debugs, to meet real work demand.
Yet, in actual transformation process, conventionally all can repeatedly revise the former ICD file of power equipment, now, prior art just need to repeatedly make amended ICD file replace SCD file appropriate section, and each replacement all needs to debug subnet and/or the empty terminal arrangement of GOOSE (being communication configuration and/or GOOSE configuration) after configuring of this power equipment, difficulty and the workload of field adjustable work have greatly been increased, reduced the efficiency of field adjustable work, especially in the transformation later stage of transformer station, need to modify to ICD file, through so repeatedly working, greatly affected the work efficiency of Transfomer Substation Reconstruction engineering.
Summary of the invention
In view of this, the invention provides information processing method and system in a kind of Transfomer Substation Reconstruction process, once solve in prior art after the ICD file modification of target power equipment, just need to delete the corresponding part information in the former SCD file of transformer station, again import amended ICD file, and also to again debug the original configuration relevant to this amended ICD file of this target power equipment, difficulty and the workload of field adjustable work have greatly been increased, reduced the efficiency of field adjustable work, affected the technical matters of the efficiency of Transfomer Substation Reconstruction engineering.
For achieving the above object, the invention provides following technical scheme:
An information processing method in Transfomer Substation Reconstruction process, described method comprises:
Obtain the former ICD file of target power equipment and amended ICD file;
Described former ICD file and described amended ICD file are compared, determine the first modification information in described amended ICD file;
Described the first modification information is imported in former SCD file and revises information corresponding part with described first, generate new SCD file.
Preferably, described obtain the former ICD file of target power equipment and amended ICD file after, and described former ICD file and described amended ICD file are being compared, and before determining the first modification information in described amended ICD file, described method also comprises:
According to preset requirement, judge whether to retain original configuration of described target power equipment;
If not, described amended ICD file is directly imported to part corresponding with described amended ICD file in former SCD file;
According to the described amended ICD file importing in described former SCD file, original configuration of target power equipment described in described former SCD file is modified and debugged, generate new SCD file;
If so, directly enter and described described former ICD file and described amended ICD file are compared, determine that first in described amended ICD file revise information step and continue to carry out.
Preferably, original configuration of described target power equipment comprises communication configuration and/or GOOSE configuration.
Preferably, after generating new SCD file, described method also comprises:
Described new SCD file and described former SCD file are compared, determine the second modification information in described new SCD file;
Described the second modification information is imported to the part corresponding with described the second modification information in background data base.
Preferably, after generating new SCD file, described method also comprises:
Described new SCD file and described former SCD file are compared, determine the 3rd modification information in described new SCD file;
Described the 3rd modification information is imported to background data base, and replace configuration information corresponding with described the 3rd modification information in described background data base.
An information handling system in Transfomer Substation Reconstruction process, described system comprises:
Acquiring unit: for obtaining the former ICD file of target power equipment and amended ICD file;
Compare determining unit: for described former ICD file and the amended ICD file that described acquiring unit is obtained, compare, determine the first modification information in described amended ICD file;
The first information imports unit: for described relatively the first modification information that determining unit is determined is imported to the part that former SCD file is corresponding with described the first modification information, generate new SCD file.
Preferably, described system also comprises:
The first judging unit: for according to preset requirement, judge whether to retain original configuration of described target power equipment;
The second information is revised unit: when the determination result is NO at described judging unit, described amended ICD file is directly imported to part corresponding with described amended ICD file in former SCD file;
Configuration information is revised unit: for according to the described amended ICD file that imports described former SCD file, the configuration information of original configuration of target electronic device described in described former SCD file is modified, generate new SCD file.
Preferably, original configuration of described target power equipment comprises: communication configuration and/or GOOSE configuration.
Preferably, described system also comprises:
The second judging unit: for described new SCD file and described former SCD file are compared, determine the second modification information in described new SCD file;
The second information imports unit: for the second modification information that described the second judging unit is determined, import the background data base part corresponding with described the second modification information.
Preferably, described system also comprises:
The 3rd judging unit: for described new SCD file and described former SCD file are compared, determine the 3rd modification information in described new SCD file;
The 3rd information imports unit: for the 3rd modification information that the 3rd judging unit is determined, import background data base, and replace configuration information corresponding with described the 3rd modification information in described background data base.
Known via above-mentioned technical scheme, compared with prior art, the present invention openly provides information processing method and system in a kind of Transfomer Substation Reconstruction process, after to the former ICD file modification of target power equipment, by the former ICD file of this target power equipment and amended ICD file to obtaining, compare, determine the first modification information of making change in this amended ICD file, afterwards, by the transfer portion in amended ICD file, be that the first modification information directly imports the corresponding part of former SCD file, transfer portion is not without importing, thereby solved in Transfomer Substation Reconstruction process, when the former ICD file of target power equipment is repeatedly revised, prior art need repeatedly be replaced this amended ICD file the corresponding part of former SCD file, and original configuration of correspondingly debugging this target power equipment according to the ICD file of each modification, and difficulty and the workload of field adjustable work have been increased, reduced the efficiency of field adjustable work, also be, avoided the duplication of labour, improved the work efficiency of Transfomer Substation Reconstruction engineering.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only embodiments of the invention, for those of ordinary skills, do not paying under the prerequisite of creative work, other accompanying drawing can also be provided according to the accompanying drawing providing.
Fig. 1 is the process flow diagram of the embodiment 1 of the information processing method in a kind of Transfomer Substation Reconstruction process of the present invention;
Fig. 2 is the process flow diagram of the embodiment 2 of the information processing method in a kind of Transfomer Substation Reconstruction process of the present invention;
Fig. 3 is the structural representation of the embodiment 1 of the information handling system in a kind of Transfomer Substation Reconstruction process of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, obviously, described embodiment is only the present invention's part embodiment, rather than whole embodiment.Embodiment based in the present invention, those of ordinary skills, not making the every other embodiment obtaining under creative work prerequisite, belong to the scope of protection of the invention.
The embodiment of the invention discloses information processing method and system in a kind of Transfomer Substation Reconstruction process, as the former ICD(IED Capability Description to target power equipment, intelligent power equipment ability description) after file modification, by the former ICD file of this target power equipment and amended ICD file to obtaining, compare, determine the first modification information of making change in this amended ICD file, afterwards, by the transfer portion in amended ICD file, be that the first modification information directly imports former SCD(Substation Configuration Description, substation configuration description) corresponding part of file, transfer portion is not without importing, thereby solved in Transfomer Substation Reconstruction process, when the former ICD file of target power equipment is repeatedly revised, prior art need repeatedly be replaced this amended ICD file the corresponding part of former SCD file, and original configuration of correspondingly debugging this target power equipment according to the ICD file of each modification, and difficulty and the workload of field adjustable work have been increased, reduced the efficiency of field adjustable work, also be, avoided the duplication of labour, improved the work efficiency of Transfomer Substation Reconstruction engineering.
As shown in Figure 1, be the process flow diagram of the embodiment 1 of the information processing method in a kind of Transfomer Substation Reconstruction process of the present invention, the method can comprise:
Step S11: obtain the former ICD file of target power equipment and amended ICD file.
Step S12: former ICD file and amended ICD file are compared, determine the first modification information in this amended ICD file.
Step S13: this first modification information is imported to the part corresponding with it in former SCD file, generate new SCD file.
In the process that is intelligent substation by old-fashioned Transfomer Substation Reconstruction, the situation that often there will be the ICD file of certain power equipment to change, and because transformer station adopts SCL language (Substation Configuration Description Language, substation configuration description language) the IED(Intelligent Electronic Devices in Dui Gai transformer station, intelligent power equipment) configuration information is described, form the ICD file of describing this IED function information, by one of these ICD file generated, to whole substation configuration description file, be SCD file again, so, once the ICD file of target power equipment changes, the SCD file of its place transformer station just must be revised.To this, the information processing method of prior art is that each amended ICD file is all imported in SCD file, substitute the part corresponding with this amended ICD file in this SCD file, and again debug all and the device-dependent configuration of this target power, as communication configuration and/or GOOSE(Generic Object Oriented Substation Event, general in transformer station's object time) configuration, to meet the work requirements of intelligent grid.
Yet, in actual applications, conventionally to the modification of former ICD file, be not that its full content is modified, thereby, amended ICD file can comprise the modification information of transfer portion and not the original information of transfer portion be the information of former ICD file corresponding part, so, prior art will be deleted with whole amended ICD file corresponding part in SCD file, replace in the mode of amended ICD file, in amended SCD file, must have partial content and be identical with the content of appropriate section in former SCD file, thereby, for this part identical content, above-mentioned replacement operation is actually insignificant, belong to idle work operation.So after the ICD file to this target power equipment is repeatedly revised, this idle work operation will repeatedly, affect the work efficiency of Transfomer Substation Reconstruction greatly; And, amended ICD file is imported after SCD file at every turn, also must re-start debugging to configuration relevant to this amended ICD file in tested target power equipment, difficulty and the workload of field adjustable work have greatly been increased, reduce the efficiency of field adjustable work, thereby further affected the work efficiency of Transfomer Substation Reconstruction.
For this reason, the embodiment of the present invention is by comparing the former ICD file of target power equipment and amended ICD file, thereby the content of determining transfer portion in amended ICD file is the first modification information, and only this first modification information is imported to the corresponding part in former SCD file, without the not transfer portion content in amended ICD file, also without the corresponding part of deleting in former SCD file, avoid the generation of idle work operation, improved the work efficiency of Transfomer Substation Reconstruction; And, owing to not deleting information in former SCD file, thereby, it has retained the device-dependent configuration of this target power, without it being repeated to debugging, has reduced field adjustable workload, improve the efficiency of field adjustable work, thereby improved further the work efficiency of Transfomer Substation Reconstruction.
As shown in Figure 2, be the process flow diagram of the embodiment 2 of the information processing method in a kind of Transfomer Substation Reconstruction process of the present invention, the method can comprise:
Step S21: obtain the former ICD file of target power equipment and amended ICD file.
Step S22: according to preset requirement, judge whether to retain original configuration of this target power equipment, if so, perform step S25, if not, directly enter step S23.
Wherein, this preset requirement can be that the actual needs in Transfomer Substation Reconstruction process is determined, original configuration of target power equipment can comprise communication configuration and/or GOOSE configuration.
Step S23: amended ICD file is directly imported to the part corresponding with it in former SCD file.
Step S24: according to the amended ICD file importing in former SCD file, original configuration of target power equipment in this former SCD file modified and debugged, generating new SCD file.
In actual applications, owing to not retaining original configuration of target power equipment, so, when whole amended ICD file all imports after SCD file, just need to be according to amended ICD file, to target power equipment, original configuration is modified and debugs.In this process of the embodiment of the present invention, while importing amended ICD file, without the appropriate section of deleting in former SCD file, as long as directly import this amended ICD file, reduced the operation steps of Transfomer Substation Reconstruction at every turn, improved work efficiency.
Step S25: former ICD file and amended ICD file are compared, determine the first modification information in this amended ICD file.
Step S26: this first modification information is imported to the part corresponding with it in former SCD file, generate new SCD file.
In embodiments of the present invention, relatively and the disposal route of above-mentioned steps S23~S24, the change content of the disposal route that step S25~step S26 provides is fewer, the configuration that need to again debug also relatively still less, more improved the work efficiency of Transfomer Substation Reconstruction, in actual applications, can be according to the actual conditions of Transfomer Substation Reconstruction, and select suitable disposal route.
Wherein, in actual applications, obtain after the new SCD file of transformer station by said method, system configuration utility conventionally can be according to the instantiation configuration file of this SCD file generated IED (Configured IED Description file; be called for short CID file), to control IED normal operation.
Step S27: new SCD file and former SCD file are compared, determine the second modification information in this new SCD file.
Step S28: this second modification information is imported to the part corresponding with it in background data base.
In the practical application of transformer station, its SCD file all will store in background data base conventionally, to call information needed from this background data base from now in the operational process of transformer station, thereby guarantees the safe and reliable operation of this transformer station.
In embodiments of the present invention, equally in order to reduce idle work operation, increase work efficiency, it is only that the second modification information imports background data base by the transfer portion with respect to former SCD file in amended SCD file, without whole amended SCD file is imported to background data base, and the corresponding prime information in background data base is also without deletion, thereby reduce workload, improved the work efficiency of Transfomer Substation Reconstruction.
As another embodiment of the present invention, according to actual needs, at the SCD file to new and former SCD file, compare, determine after the 3rd modification information (i.e. the second modification information) in this new SCD file, the 3rd modification information can also be imported to background data base, and replace configuration information corresponding with it in this background data base.Step S27~step the S28 of itself and the embodiment of the present invention all belongs to protection domain of the present invention, and the mode that the present invention does not import background data base to the second modification information does not limit.
In the embodiment of the present invention, after the ICD file to target power equipment is modified, and when the SCD file of this target power equipment place transformer station is modified, by judging whether to retain original configuration of target power equipment, when judgment result is that while being, directly the transfer portion of amended ICD file (i.e. the first modification information) is imported to SCD file, without the not transfer portion importing in amended ICD file, and without deleting the information corresponding with this transfer portion in SCD file, thereby retained original configuration of target power equipment, field adjustable workload and difficulty have been greatly reduced, improved the work efficiency of field adjustable, thereby improved the work efficiency of Transfomer Substation Reconstruction, and when the determination result is NO, whole amended ICD file is directly imported to SCD file, also without deleting appropriate section in this SCD file, corresponding prior art, has also improved the work efficiency of Transfomer Substation Reconstruction.In addition, after SCD file modification is completed, the method that the present invention imports by increment, only imports background data base by the transfer portion of this SCD file, thereby has further improved the work efficiency of Transfomer Substation Reconstruction.
As shown in Figure 3, be the structural representation of the information handling system in a kind of Transfomer Substation Reconstruction process of the present invention, this system can comprise:
Acquiring unit S31: for obtaining the former ICD file of target power equipment and amended ICD file.
In actual applications, as another embodiment of the present invention, this system can also comprise:
The first judging unit: for according to preset requirement, judge whether to retain original configuration of target power equipment.
Wherein, as further embodiment of this invention, this system can be carried out corresponding operating by a system configuration utility, concrete, in the transformation process of Dui transformer station, can be by the function of this system configuration utility design a kind of " upgrading IED ", on the function interface providing at it, select to need the target power equipment of renewal, obtain corresponding amended ICD file, at this moment the reservation that one of the common ejection of this configuration tool is provided with " retaining communication configuration " and " retaining GOOSE configures " two options configures selection window, now, staff can be according to preset requirement, therefrom select to need original configuration of reservation.
The second information is revised unit: when the determination result is NO at judging unit, amended ICD file is directly imported to the part corresponding with it in former SCD file.
Configuration information is revised unit: for according to the amended ICD file that imports former SCD file, original configuration of target electronic device in former SCD file modified and debugged, generating new SCD file.
Compare determining unit S32: for former ICD file and the amended ICD file that acquiring unit S31 is obtained, compare, determine the first modification information in amended ICD file.
Still, with above-mentioned another embodiment, when judgment result is that of the first judging unit is, retain communication configuration and the GOOSE configuration of target power equipment, just can trigger this comparison determining unit S32.
The first information imports cell S 33: for the first modification information that relatively determining unit S32 determines is imported to the part that former SCD file is corresponding with the first modification information, generate new SCD file.
After completing the modification of the SCD file of transformer station, also need to be imported background data base, for this reason, this system can also comprise:
The second judging unit: for the new SCD file and the former SCD file that generate are compared, determine the second modification information in this new SCD file.
Wherein, this second modification information is the transfer portion in the new SCD file generating.
The second information imports unit: for the second modification information that the second judging unit is determined, import the background data base part corresponding with it.
Or this system can also comprise:
The 3rd judging unit: for the new SCD file and the former SCD file that generate are compared, determine the 3rd modification information in this new SCD file.
Wherein, the 3rd modification information is identical with the second modification information.
The 3rd information imports unit: for the 3rd modification information that the 3rd judging unit is determined, import background data base, and replace configuration information corresponding with it in background data base.
In the embodiment of the present invention, after acquiring unit obtains the former ICD file of target power equipment and amended ICD file, by comparing determining unit, the former ICD file of target power equipment and amended ICD file are compared, the content of determining transfer portion in amended ICD file is the first modification information, and only this first modification information is imported to the corresponding part in former SCD file by first information importing unit, without the not transfer portion content in amended ICD file, also without the corresponding part of deleting in former SCD file, avoided the generation of idle work operation, improved the work efficiency of Transfomer Substation Reconstruction, and, owing to not deleting information in former SCD file, thereby, it has retained the device-dependent configuration of this target power, without it being repeated to debugging, has reduced field adjustable workload, improve the efficiency of field adjustable work, thereby improved further the work efficiency of Transfomer Substation Reconstruction.
It should be noted that, for words such as " first " that occur in the above embodiment of the present invention, " second ", " the 3 ", it does not represent order relation in addition, and it is only to play difference effect.And the above embodiment of the present invention is a kind of exemplary example, should be as restriction, given particular content should in no way limit the application's object.For example, the division of described unit, is only that a kind of logic function is divided, and during actual realization, can have other dividing mode, and for example a plurality of unit combine; In addition, a plurality of unit can or assembly can in conjunction with or can be integrated into another system, or some features can ignore, or do not carry out.And; in this article; term " comprises ", " comprising " or its any other variant are intended to contain comprising of nonexcludability; thereby the process, method, article or the equipment that make to comprise a series of key elements not only comprise those key elements; but also comprise other key elements of clearly not listing; or be also included as the intrinsic key element of this process, method, article or equipment; at this, will repeat no longer one by one; those skilled in the art creative make great efforts to determine so long as not paying, and all belong to protection scope of the present invention.
In this instructions, each embodiment adopts the mode of going forward one by one to describe, and each embodiment stresses is the difference with other embodiment, between each embodiment identical similar part mutually referring to.For the disclosed system of embodiment, because it corresponds to the method disclosed in Example, so description is fairly simple, relevant part partly illustrates referring to method.
Above-mentioned explanation to the disclosed embodiments, makes professional and technical personnel in the field can realize or use the present invention.To the multiple modification of these embodiment, will be apparent for those skilled in the art, General Principle as defined herein can, in the situation that not departing from the spirit or scope of the present invention, realize in other embodiments.Therefore, the present invention will can not be restricted to these embodiment shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.

Claims (10)

1. the information processing method in Transfomer Substation Reconstruction process, is characterized in that, described method comprises:
Obtain the former ICD file of target power equipment and amended ICD file;
Described former ICD file and described amended ICD file are compared, determine the first modification information in described amended ICD file;
Described the first modification information is imported in former SCD file and revises information corresponding part with described first, generate new SCD file.
2. method according to claim 1, it is characterized in that, described obtain the former ICD file of target power equipment and amended ICD file after, and described former ICD file and described amended ICD file are being compared, before determining the first modification information in described amended ICD file, described method also comprises:
According to preset requirement, judge whether to retain original configuration of described target power equipment;
If not, described amended ICD file is directly imported to part corresponding with described amended ICD file in former SCD file;
According to the described amended ICD file importing in described former SCD file, original configuration of target power equipment described in described former SCD file is modified and debugged, generate new SCD file;
If so, directly enter and described described former ICD file and described amended ICD file are compared, determine that first in described amended ICD file revise information step and continue to carry out.
3. method according to claim 2, is characterized in that, original configuration of described target power equipment comprises communication configuration and/or GOOSE configuration.
4. according to the method described in claim 1-3 any one, it is characterized in that, after generating new SCD file, described method also comprises:
Described new SCD file and described former SCD file are compared, determine the second modification information in described new SCD file;
Described the second modification information is imported to the part corresponding with described the second modification information in background data base.
5. according to the method described in claim 1-3 any one, it is characterized in that, after generating new SCD file, described method also comprises:
Described new SCD file and described former SCD file are compared, determine the 3rd modification information in described new SCD file;
Described the 3rd modification information is imported to background data base, and replace configuration information corresponding with described the 3rd modification information in described background data base.
6. the information handling system in Transfomer Substation Reconstruction process, is characterized in that, described system comprises:
Acquiring unit: for obtaining the former ICD file of target power equipment and amended ICD file;
Compare determining unit: for described former ICD file and the amended ICD file that described acquiring unit is obtained, compare, determine the first modification information in described amended ICD file;
The first information imports unit: for described relatively the first modification information that determining unit is determined is imported to the part that former SCD file is corresponding with described the first modification information, generate new SCD file.
7. system according to claim 6, is characterized in that, described system also comprises:
The first judging unit: for according to preset requirement, judge whether to retain original configuration of described target power equipment;
The second information is revised unit: when the determination result is NO at described judging unit, described amended ICD file is directly imported to part corresponding with described amended ICD file in former SCD file;
Configuration information is revised unit: for according to the described amended ICD file that imports described former SCD file, the configuration information of original configuration of target electronic device described in described former SCD file is modified, generate new SCD file.
8. system according to claim 7, is characterized in that, original configuration of described target power equipment comprises: communication configuration and/or GOOSE configuration.
9. according to the system described in claim 6-8 any one, it is characterized in that, described system also comprises:
The second judging unit: for described new SCD file and described former SCD file are compared, determine the second modification information in described new SCD file;
The second information imports unit: for the second modification information that described the second judging unit is determined, import the background data base part corresponding with described the second modification information.
10. according to the system described in claim 6-8 any one, it is characterized in that, described system also comprises:
The 3rd judging unit: for described new SCD file and described former SCD file are compared, determine the 3rd modification information in described new SCD file;
The 3rd information imports unit: for the 3rd modification information that the 3rd judging unit is determined, import background data base, and replace configuration information corresponding with described the 3rd modification information in described background data base.
CN201310670691.1A 2013-12-10 2013-12-10 Information processing method and information processing system in substation transformation process Active CN103605814B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310670691.1A CN103605814B (en) 2013-12-10 2013-12-10 Information processing method and information processing system in substation transformation process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310670691.1A CN103605814B (en) 2013-12-10 2013-12-10 Information processing method and information processing system in substation transformation process

Publications (2)

Publication Number Publication Date
CN103605814A true CN103605814A (en) 2014-02-26
CN103605814B CN103605814B (en) 2017-02-15

Family

ID=50124036

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310670691.1A Active CN103605814B (en) 2013-12-10 2013-12-10 Information processing method and information processing system in substation transformation process

Country Status (1)

Country Link
CN (1) CN103605814B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104065163A (en) * 2014-06-19 2014-09-24 国家电网公司 Intelligent substation warning message delivering method
CN104657176A (en) * 2015-02-09 2015-05-27 南京南瑞继保电气有限公司 File updating method and electronic equipment
CN106294750A (en) * 2016-08-10 2017-01-04 国家电网公司 ICD model file familial defect upgrade-system and method
CN106888113A (en) * 2017-01-21 2017-06-23 国网浙江省电力公司绍兴供电公司 A kind of method and device for intelligent substation business configuration
CN110896363A (en) * 2019-11-25 2020-03-20 东方电子股份有限公司 Access configuration method for realizing plug and play of IEC61850 intelligent device
CN115499520A (en) * 2022-11-21 2022-12-20 北京蓝天航空科技股份有限公司 Interface control file updating method and device, electronic equipment and storage medium

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102867274A (en) * 2012-07-27 2013-01-09 江苏省电力公司电力科学研究院 Management and graphical display system for intelligent substation SCL (substation configuration description language) configuration files
CN103399888A (en) * 2013-07-19 2013-11-20 广东电网公司电力科学研究院 Differential synchronization method and system for power grid model data

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102867274A (en) * 2012-07-27 2013-01-09 江苏省电力公司电力科学研究院 Management and graphical display system for intelligent substation SCL (substation configuration description language) configuration files
CN103399888A (en) * 2013-07-19 2013-11-20 广东电网公司电力科学研究院 Differential synchronization method and system for power grid model data

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104065163A (en) * 2014-06-19 2014-09-24 国家电网公司 Intelligent substation warning message delivering method
CN104065163B (en) * 2014-06-19 2016-08-17 国家电网公司 Delivery method on a kind of intelligent substation warning information
CN104657176A (en) * 2015-02-09 2015-05-27 南京南瑞继保电气有限公司 File updating method and electronic equipment
CN106294750A (en) * 2016-08-10 2017-01-04 国家电网公司 ICD model file familial defect upgrade-system and method
CN106294750B (en) * 2016-08-10 2019-08-06 国家电网公司 ICD model file familial defect upgrade-system and method
CN106888113A (en) * 2017-01-21 2017-06-23 国网浙江省电力公司绍兴供电公司 A kind of method and device for intelligent substation business configuration
CN106888113B (en) * 2017-01-21 2019-10-29 国网浙江省电力公司绍兴供电公司 A kind of method and device for intelligent substation business configuration
CN110896363A (en) * 2019-11-25 2020-03-20 东方电子股份有限公司 Access configuration method for realizing plug and play of IEC61850 intelligent device
CN110896363B (en) * 2019-11-25 2022-07-29 东方电子股份有限公司 Plug-and-play access configuration method for IEC61850 intelligent device
CN115499520A (en) * 2022-11-21 2022-12-20 北京蓝天航空科技股份有限公司 Interface control file updating method and device, electronic equipment and storage medium
CN115499520B (en) * 2022-11-21 2023-03-10 北京蓝天航空科技股份有限公司 Interface control file updating method and device, electronic equipment and storage medium

Also Published As

Publication number Publication date
CN103605814B (en) 2017-02-15

Similar Documents

Publication Publication Date Title
CN103605814A (en) Information processing method and information processing system in substation transformation process
CN105335584B (en) Distribution network systems line chart generates optimization device and method
US20150294037A1 (en) System and method for automated substation design and configuration
CN104679488A (en) Flow path customized development platform and method
CN103093276B (en) Urban power grid risk assessment method
CN103902763A (en) Automatic matching method of virtual terminals of cross-interval device of intelligent substation
CN110569557A (en) Intelligent autonomous design platform for power transmission and transformation project and working method thereof
CN103927256A (en) Method for controlling multiple Android devices
CN103323714A (en) Automatic test method based on report template technology in intelligent substation test system
CN104459385A (en) Relay protection automatic testing method
CN102593954A (en) Power grid model constructing and updating method and device based on distribution network automation system
CN104267365A (en) Portable small current earth-fault line selection closed loop performance tester
CN105487970A (en) Interface display method and apparatus
JP2020527925A (en) Power distribution methods and electronic devices used in multi-machine parallel power electronic transformers
CN107332702A (en) A kind of SCD file visualization parsing automatic generation method based on network topology
CN110867956A (en) Topology automatic identification system and method based on intelligent platform area
CN103632307A (en) Method for checking consistency between SCD and virtual loop table of intelligent substation
CN103985023A (en) Operation and maintenance decision support system for secondary equipment of intelligent substation and data mining method
CN103353857A (en) Communication test method of integrated monitoring unit in substation
CN105988863A (en) Event processing method and device
CN105373008A (en) Full physics model simulation method for electric power system
CN110658804A (en) Test platform for inter-station stability control device wide-area joint debugging and implementation method thereof
CN110021995A (en) A kind of distribution network automated information joint debugging emulation test system
CN106532667B (en) Intelligent distribution network differential protection parameter network topology adaptation method
CN103631854A (en) ICD and SCD consistency calibration method based on model objectification semantics

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant