CN103595725A - Screen cabinet resource control system and method - Google Patents

Screen cabinet resource control system and method Download PDF

Info

Publication number
CN103595725A
CN103595725A CN201310596308.2A CN201310596308A CN103595725A CN 103595725 A CN103595725 A CN 103595725A CN 201310596308 A CN201310596308 A CN 201310596308A CN 103595725 A CN103595725 A CN 103595725A
Authority
CN
China
Prior art keywords
data update
instruction
terminal
data
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310596308.2A
Other languages
Chinese (zh)
Other versions
CN103595725B (en
Inventor
朱振洪
陆强
沈中尉
陈柏军
潘劲松
陈国军
任文文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Powershine Information & Technology Co ltd
State Grid Zhejiang Yuyao Power Supply Co ltd
Yongyao Science And Technology Branch Of Ningbo Transmission And Transfer Construction Co ltd
State Grid Corp of China SGCC
Ningbo Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
NINGBO YONGYAO INFORMATION TECHNOLOGY Co Ltd
STATE GRID ZHEJIANG YUYAO POWER SUPPLY Co
State Grid Corp of China SGCC
Ningbo Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGBO YONGYAO INFORMATION TECHNOLOGY Co Ltd, STATE GRID ZHEJIANG YUYAO POWER SUPPLY Co, State Grid Corp of China SGCC, Ningbo Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical NINGBO YONGYAO INFORMATION TECHNOLOGY Co Ltd
Priority to CN201310596308.2A priority Critical patent/CN103595725B/en
Publication of CN103595725A publication Critical patent/CN103595725A/en
Application granted granted Critical
Publication of CN103595725B publication Critical patent/CN103595725B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Information Transfer Between Computers (AREA)

Abstract

The invention discloses a screen cabinet resource control system and method. A central server sends a data updating instruction, a transformer substation terminal server identifies the data updating instruction, and sends a data updating permission instruction to a screen cabinet terminal after the identification is passed, and the screen terminal controls a display terminal to update data according to the data updating permission instruction. According to the scheme, due to the fact that the central server sends data updating instructions regularly, data updating situations of the transformer substation screen cabinet terminal can be mastered at any time, the problems that the distance between a transformer substation screen cabinet terminal and an operation station is larger and update is not conducted timely when a plurality of transformer substation screen cabinet terminals needs updating in the prior art are solved, and the central server of the operation station can master the data updating situations of the transformer substation screen cabinet terminal in real time.

Description

A kind of screen cabinet resource control system and method
Technical field
The present invention relates to shield cabinet resource control field, relate in particular to a kind of screen cabinet resource control system and method.
Background technology
In the machine room of each transformer station, settling a lot of screen cabinets, in each screen cabinet, relay protection devices, automation equipment, information equipment, communication equipment, power-supply device etc. are being installed, be i.e. the related data resource of in store its place transformer station in each screen cabinet.
And realize after intensive management, each active station is managed several transformer stations simultaneously.
When need to screen, the data resource in cabinet upgrade, need to first arrive the transformer station at screen cabinet place, screen cabinet resource is carried out to Data Update, and then arrive active station, to the renewal of modifying of the information of the Gai Pinggui place transformer station preserving in active station.
When distant between transformer station's display terminal and active station, or a plurality of transformer stations display terminal is while all needing to upgrade, and can occur to upgrade the problem showing not in time, thus the problem that causes work not launch in time.
Summary of the invention
In view of this, the invention provides a kind of screen cabinet resource control system and method, to solve in prior art data resource between transformer station's display terminal and active station, upgrade problem not in time, its concrete scheme is as follows:
A cabinet resource control system, comprising:
Central server, the transformer station's terminal server being connected with described central server, the screen cabinet terminal being connected with described transformer station terminal server, the display terminal being connected with described screen cabinet terminal,
The central server interval set time sends Data Update instruction to described transformer station terminal server;
Transformer station's terminal server receives described Data Update instruction, and described Data Update instruction is authenticated, and after authentication is passed through, sends Data Update grant instruction to described screen cabinet terminal;
Screen cabinet terminal receives Data Update grant instruction, controls display terminal and carries out Data Update.
Further, described transformer station terminal server comprises: the first receiver module, and the authentication module being connected with described the first receiver module, the sending module being connected with described authentication module,
Described the first receiver module receives the Data Update instruction that described central server sends, and described Data Update instruction is sent to described authentication module;
Described authentication module receives described Data Update instruction, and described Data Update instruction is authenticated, and after authentication is passed through, generated data upgrades grant instruction, and is sent to sending module;
Described sending module receives described Data Update grant instruction, and is sent to described screen cabinet terminal.
Further, described display terminal comprises: the second receiver module, and the key entry module being connected with described the second receiver module, the update module being connected with described key entry module, the display module being connected with described update module,
Described the second receiver module receives the Data Update grant instruction that described screen cabinet terminal sends, and described Data Update grant instruction is sent to described key entry module;
Described key entry module is according to described Data Update grant instruction, and the data message that needs are upgraded is keyed in;
The data that described update module is keyed in described key entry module are upgraded;
The data that described display module upgrades described update module show.
Further, described central server is connected and is specially with transformer station terminal server:
Described central server is connected with described transformer station terminal server by Ethernet.
Further, described transformer station terminal server is connected and is specially with screen cabinet terminal:
Described transformer station terminal server is connected with described screen cabinet terminal by 485 buses.
Further, described screen cabinet terminal is connected and is specially with display terminal:
Described screen cabinet terminal is connected with described display terminal by 485 buses.
A cabinet resource control method, comprising:
The interval set time issues Data Update instruction;
To Data Update, instruction authenticates, and after authentication is passed through, sends Data Update grant instruction;
According to Data Update grant instruction, the data of display terminal are upgraded to demonstration.
Further, according to Data Update grant instruction, the data of display terminal are upgraded to demonstration and specifically comprise:
Receive Data Update grant instruction;
According to described Data Update grant instruction, the data message that needs are upgraded is keyed in;
The data message of key entry is upgraded;
Data after described renewal are shown.
Further, issue Data Update instruction, be specially:
By Ethernet, issue Data Update instruction.
Further, send Data Update grant instruction, be specially:
By 485 buses, send Data Update grant instruction.
From technique scheme, can find out, screen cabinet resource control system disclosed by the invention and method, by central server, send Data Update instruction, to Data Update, instruction authenticates transformer station's terminal server, after authentication is passed through, send Data Update grant instruction to shielding cabinet terminal, screen cabinet terminal is controlled display terminal according to Data Update grant instruction and is carried out Data Update.Scheme disclosed by the invention, issue Data Update instruction by the central server interval set time, grasp at any time the data change situation of substation cabinet terminal, solved substation cabinet terminal and active station spacing is far away, or a plurality of substation cabinet terminals are while all needing to upgrade, upgrade problem not in time, realized the central server of active station and grasped in real time substation cabinet terminal data update status.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skills, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is the disclosed a kind of structural representation that shields cabinet resource control system of the embodiment of the present invention;
Fig. 2 is the structural representation of the disclosed a kind of transformer station of embodiment of the present invention terminal server;
Fig. 3 is the structural representation of the disclosed a kind of display terminal of the embodiment of the present invention;
Fig. 4 is the disclosed a kind of flow chart that shields cabinet resource control method of the embodiment of the present invention;
Fig. 5 is that the disclosed a kind of data to display terminal of the embodiment of the present invention are upgraded the flow chart showing.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, obviously, described embodiment is only the present invention's part embodiment, rather than whole embodiment.Embodiment based in the present invention, those of ordinary skills, not making the every other embodiment obtaining under creative work prerequisite, belong to the scope of protection of the invention.
The present embodiment discloses a kind of screen cabinet resource control system, and its structural representation as shown in Figure 1, comprising:
Central server 11, the connected screen cabinet terminal 13 of terminal server 12,Yu transformer station of transformer station terminal server 12 being connected with central server 11, the display terminal 14 being connected with screen cabinet terminal 13.
The 11 interval set times of central server send Data Update instruction to transformer station's terminal server 12.
In order to realize the real-time update of data, central server 11 can send Data Update instruction the interval set time, when not having data to upgrade, when Data Update instruction is sent to display terminal 14, display terminal 14 can only show legacy data again, do not upgrade, do not change.
Transformer station's terminal server 12 receives Data Update instruction, and instruction authenticates to Data Update, after authentication is passed through, sends Data Update grant instruction to shielding cabinet terminal 13.
12 pairs of Data Update instructions of transformer station's terminal server authenticate, to determine the accuracy of instruction, thereby avoid the mistake of substation data to upgrade.When the authentication of Data Update instruction is not passed through, the continuation of command for stopping sends, and now, also can return to false command to central server 11, and send alarm signal.
Screen cabinet terminal 13 receives Data Update grant instruction, controls display terminal 14 and carries out Data Update.
The disclosed screen cabinet of the present embodiment resource control system, by central server, send Data Update instruction, to Data Update, instruction authenticates transformer station's terminal server, after authentication is passed through, send Data Update grant instruction to shielding cabinet terminal, screen cabinet terminal is controlled display terminal according to Data Update grant instruction and is carried out Data Update.Scheme disclosed by the invention, issue Data Update instruction by the central server interval set time, grasp at any time the data change situation of substation cabinet terminal, solved substation cabinet terminal and active station spacing is far away, or a plurality of substation cabinet terminals are while all needing to upgrade, upgrade problem not in time, realized the central server of active station and grasped in real time substation cabinet terminal data update status.
Preferably, in the disclosed screen cabinet of the present embodiment resource control system, central server 11Yu transformer station terminal server 12 connects by Ethernet;
Transformer station's terminal server 12 is connected by 485 buses with screen cabinet terminal 13;
Screen cabinet terminal 13 is connected by 485 buses with display terminal 14.
The present embodiment discloses a kind of transformer station terminal server, and its structural representation as shown in Figure 2, comprising:
The first receiver module 21, the authentication module 22 being connected with the first receiver module 21, the sending module 23 being connected with authentication module 22.
The Data Update instruction that the first receiver module 21 receiving center servers send, and Data Update instruction is sent to authentication module 22.
Authentication module 22 receives Data Update instruction, and to Data Update, instruction authenticates, and after authentication is passed through, generated data upgrades grant instruction, and is sent to sending module 23.
Whether the Data Update instruction that 22 pairs of authentication modules receive authenticates, and judges its accuracy, be false command, or the corresponding central server transmission of Fou Weigai transformer station terminal server.When authentication by time, continue subsequent operation, when authentication is not when passing through, the transmission of command for stopping, returns to false command to central server simultaneously, and sends alarm signal; Maybe when authenticate for not by time, alarm signal is sent in the transmission of command for stopping simultaneously.
Sending module 23 receives Data Update grant instruction, and is sent to screen cabinet terminal.
The disclosed transformer station of the present embodiment terminal server, has realized the authentication to Data Update instruction by authentication module, has improved the accuracy of Data Update, has effectively avoided the bug patch data ,Wei staff of transformer station work to bring facility.
The present embodiment discloses a kind of display terminal, and its structural representation as shown in Figure 3, comprising:
The second receiver module 31, the key entry module 32 being connected with the second receiver module 31, with the update module 33 that key entry module 32 is connected, the display module 34 being connected with update module 33.
The Data Update grant instruction that the second receiver module 31 receiving screen cabinet terminals send, and Data Update grant instruction is sent to and keys in module 32.
Key in module 32 according to Data Update grant instruction, the data message that needs are upgraded is keyed in.
In Data Update grant instruction, comprise the data that need to upgrade, with and corresponding former data message.Key in module 32 and receive after Data Update grant instruction, the Data Update information providing according to Data Update grant instruction, searches the data that need renewal, and the data message that needs are upgraded is keyed in.
Update module 33 is upgraded the data of keying in module 32 key entries.
Update module 33 replaces keying in the former data of position by the data of keying in module 32 key entries, realizes the renewal of data.
The data that display module 34 upgrades update module 33 show.
The disclosed display terminal of the present embodiment, by the cooperation of the second receiver module, key entry module, update module, display module, realized the automatic renewal to data according to Data Update grant instruction, reduced manually-operated step, save human and material resources and time, realized long-range object of display terminal being carried out to data real-time update.
The present embodiment discloses a kind of screen cabinet resource control method, and its flow chart as shown in Figure 4, comprising:
Step S41, interval set time issue Data Update instruction;
In order to realize the real-time update of data, can the interval set time send Data Update instruction, when not having data to upgrade, when Data Update instruction is sent to display terminal, display terminal can only show legacy data again, does not upgrade, and does not change.
Step S42, to Data Update, instruction authenticates, and after approval is passed through, sends Data Update grant instruction;
Whether the Data Update instruction receiving is authenticated, judge its accuracy, be false command, or the corresponding central server transmission of Fou Weigai transformer station terminal server.When authentication by time, continue subsequent operation, when authentication is not when passing through, the transmission of command for stopping, returns to false command to central server simultaneously, and sends alarm signal; Maybe when authenticate for not by time, alarm signal is sent in the transmission of command for stopping simultaneously.
Step S43, according to Data Update grant instruction, the data of display terminal are upgraded to demonstration.
The disclosed screen cabinet of the present embodiment resource control method, issues Data Update instruction by the interval set time, and to Data Update, instruction authenticates, after authentication is passed through, send Data Update grant instruction, according to Data Update grant instruction, the data of display terminal are upgraded to demonstration.Scheme disclosed by the invention, issue Data Update instruction by the interval set time, grasp at any time the data change situation of substation cabinet terminal, solved substation cabinet terminal and active station spacing is far away, or a plurality of substation cabinet terminals are while all needing to upgrade, upgrade problem not in time, realized the central server of active station and grasped in real time substation cabinet terminal data update status.
Preferably, in the disclosed screen cabinet of the present embodiment resource control method, issue Data Update instruction, be specially: by Ethernet, issue Data Update instruction;
Send Data Update grant instruction, be specially: by 485 buses, send Data Update grant instruction.
The present embodiment discloses a kind of data to display terminal and has upgraded the idiographic flow showing, its flow chart as shown in Figure 5, comprising:
Step S51, reception Data Update grant instruction;
Step S52, according to Data Update grant instruction, the data message that needs are upgraded is keyed in;
In Data Update grant instruction, comprise the data that need to upgrade, with and corresponding former data message.Receive after Data Update grant instruction, the Data Update information providing according to Data Update grant instruction, searches the data that need renewal, and the data message that needs are upgraded is keyed in.
Step S53, the data message of key entry is upgraded;
The former data that the data message that the needs of keying in are upgraded replaces keying in position, realize the renewal of data
Step S54, the data after upgrading are shown.
The present embodiment is realized the process that the information of needs renewal is keyed in by Data Update grant instruction, realized the automatic renewal to data according to Data Update grant instruction, reduced manually-operated step, save human and material resources and time, realized long-range object of display terminal being carried out to data real-time update.
In this specification, each embodiment adopts the mode of going forward one by one to describe, and each embodiment stresses is the difference with other embodiment, between each embodiment identical similar part mutually referring to.For the disclosed device of embodiment, because it corresponds to the method disclosed in Example, so description is fairly simple, relevant part partly illustrates referring to method.
Professional can also further recognize, unit and the algorithm steps of each example of describing in conjunction with embodiment disclosed herein, can realize with electronic hardware, computer software or the combination of the two, for the interchangeability of hardware and software is clearly described, composition and the step of each example described according to function in the above description in general manner.These functions are carried out with hardware or software mode actually, depend on application-specific and the design constraint of technical scheme.Professional and technical personnel can specifically should be used for realizing described function with distinct methods to each, but this realization should not thought and exceeds scope of the present invention.
The software module that the method for describing in conjunction with embodiment disclosed herein or the step of algorithm can directly use hardware, processor to carry out, or the combination of the two is implemented.Software module can be placed in the storage medium of any other form known in random asccess memory (RAM), internal memory, read-only memory (ROM), electrically programmable ROM, electrically erasable ROM, register, hard disk, moveable magnetic disc, CD-ROM or technical field.
Above-mentioned explanation to the disclosed embodiments, makes professional and technical personnel in the field can realize or use the present invention.To the multiple modification of these embodiment, will be apparent for those skilled in the art, General Principle as defined herein can, in the situation that not departing from the spirit or scope of the present invention, realize in other embodiments.Therefore, the present invention will can not be restricted to these embodiment shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.

Claims (10)

1. a screen cabinet resource control system, is characterized in that, comprising:
Central server, the transformer station's terminal server being connected with described central server, the screen cabinet terminal being connected with described transformer station terminal server, the display terminal being connected with described screen cabinet terminal,
The central server interval set time sends Data Update instruction to described transformer station terminal server;
Transformer station's terminal server receives described Data Update instruction, and described Data Update instruction is authenticated, and after authentication is passed through, sends Data Update grant instruction to described screen cabinet terminal;
Screen cabinet terminal receives Data Update grant instruction, controls display terminal and carries out Data Update.
2. system according to claim 1, is characterized in that, described transformer station terminal server comprises: the first receiver module, and the authentication module being connected with described the first receiver module, the sending module being connected with described authentication module,
Described the first receiver module receives the Data Update instruction that described central server sends, and described Data Update instruction is sent to described authentication module;
Described authentication module receives described Data Update instruction, and described Data Update instruction is authenticated, and after authentication is passed through, generated data upgrades grant instruction, and is sent to sending module;
Described sending module receives described Data Update grant instruction, and is sent to described screen cabinet terminal.
3. system according to claim 1, is characterized in that, described display terminal comprises: the second receiver module, and the key entry module being connected with described the second receiver module, the update module being connected with described key entry module, the display module being connected with described update module,
Described the second receiver module receives the Data Update grant instruction that described screen cabinet terminal sends, and described Data Update grant instruction is sent to described key entry module;
Described key entry module is according to described Data Update grant instruction, and the data message that needs are upgraded is keyed in;
The data that described update module is keyed in described key entry module are upgraded;
The data that described display module upgrades described update module show.
4. system according to claim 1, is characterized in that, described central server is connected and is specially with transformer station terminal server:
Described central server is connected with described transformer station terminal server by Ethernet.
5. system according to claim 1, is characterized in that, described transformer station terminal server is connected and is specially with screen cabinet terminal:
Described transformer station terminal server is connected with described screen cabinet terminal by 485 buses.
6. system according to claim 1, is characterized in that, described screen cabinet terminal is connected and is specially with display terminal:
Described screen cabinet terminal is connected with described display terminal by 485 buses.
7. a screen cabinet resource control method, is characterized in that, comprising:
The interval set time issues Data Update instruction;
To Data Update, instruction authenticates, and after authentication is passed through, sends Data Update grant instruction;
According to Data Update grant instruction, the data of display terminal are upgraded to demonstration.
8. method according to claim 7, is characterized in that, according to Data Update grant instruction, the data of display terminal is upgraded to demonstration and specifically comprise:
Receive Data Update grant instruction;
According to described Data Update grant instruction, the data message that needs are upgraded is keyed in;
The data message of key entry is upgraded;
Data after described renewal are shown.
9. method according to claim 7, is characterized in that, issues Data Update instruction, is specially:
By Ethernet, issue Data Update instruction.
10. method according to claim 7, is characterized in that, sends Data Update grant instruction, is specially:
By 485 buses, send Data Update grant instruction.
CN201310596308.2A 2013-11-21 2013-11-21 A kind of screen cabinet resource control system and method Active CN103595725B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310596308.2A CN103595725B (en) 2013-11-21 2013-11-21 A kind of screen cabinet resource control system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310596308.2A CN103595725B (en) 2013-11-21 2013-11-21 A kind of screen cabinet resource control system and method

Publications (2)

Publication Number Publication Date
CN103595725A true CN103595725A (en) 2014-02-19
CN103595725B CN103595725B (en) 2018-05-18

Family

ID=50085707

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310596308.2A Active CN103595725B (en) 2013-11-21 2013-11-21 A kind of screen cabinet resource control system and method

Country Status (1)

Country Link
CN (1) CN103595725B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106487595A (en) * 2016-10-26 2017-03-08 宁波永耀信息科技有限公司 Power transformation O&M big data network control platform

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1790208A (en) * 2004-11-19 2006-06-21 费舍-柔斯芒特系统股份有限公司 Secure data write apparatus and methods for use in safety instrumented process control systems
CN101105780A (en) * 2006-07-10 2008-01-16 株式会社日立制作所 Storage control system, control method for storage control system, port selector, and controller
CN101576742A (en) * 2009-06-19 2009-11-11 西安交通大学 Remote monitoring and fault diagnosing system for numerical control slitter and method for realizing same
CN102156795A (en) * 2010-02-12 2011-08-17 华东电网有限公司 Simulation information system of digital transformer station based on transformer station configuration description file
CN102323885A (en) * 2011-05-23 2012-01-18 中国科学院软件研究所 Dynamic configuration method of sensing network node operation system
CN102385375A (en) * 2011-11-18 2012-03-21 安徽省电力公司滁州供电公司 Control room panel monitoring system based on Internet of Things technology
CN102541123A (en) * 2011-12-30 2012-07-04 诸城市供电公司 Novel temperature/humidity controller
CN102632309A (en) * 2012-03-23 2012-08-15 江苏省艾格森数控设备制造有限公司 Control method of movement control module of electrosparking machine
CN102665196A (en) * 2012-04-28 2012-09-12 清华大学 On-line progressive program updating method for wireless sensor network
CN102736922A (en) * 2011-03-31 2012-10-17 海洋王照明科技股份有限公司 Method for updating application programs of embedded system and terminal of embedded system
CN102853941A (en) * 2012-09-06 2013-01-02 上海欣影电力科技发展有限公司 Wireless temperature on-line monitoring system for base station type switch cabinet
CN102882854A (en) * 2012-09-05 2013-01-16 南方电网科学研究院有限责任公司 Power grid data access method
CN103116346A (en) * 2013-02-22 2013-05-22 西安众恒科技有限公司 Power quality online monitoring system of network topology wireless communication
CN103368264A (en) * 2013-07-22 2013-10-23 国家电网公司 Safety operation detecting platform of substation relay protection room
CN203261351U (en) * 2013-05-16 2013-10-30 国家电网公司 Intelligent power distribution terminal with digital signature authentication

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1790208A (en) * 2004-11-19 2006-06-21 费舍-柔斯芒特系统股份有限公司 Secure data write apparatus and methods for use in safety instrumented process control systems
CN101105780A (en) * 2006-07-10 2008-01-16 株式会社日立制作所 Storage control system, control method for storage control system, port selector, and controller
CN101576742A (en) * 2009-06-19 2009-11-11 西安交通大学 Remote monitoring and fault diagnosing system for numerical control slitter and method for realizing same
CN102156795A (en) * 2010-02-12 2011-08-17 华东电网有限公司 Simulation information system of digital transformer station based on transformer station configuration description file
CN102736922A (en) * 2011-03-31 2012-10-17 海洋王照明科技股份有限公司 Method for updating application programs of embedded system and terminal of embedded system
CN102323885A (en) * 2011-05-23 2012-01-18 中国科学院软件研究所 Dynamic configuration method of sensing network node operation system
CN102385375A (en) * 2011-11-18 2012-03-21 安徽省电力公司滁州供电公司 Control room panel monitoring system based on Internet of Things technology
CN102541123A (en) * 2011-12-30 2012-07-04 诸城市供电公司 Novel temperature/humidity controller
CN102632309A (en) * 2012-03-23 2012-08-15 江苏省艾格森数控设备制造有限公司 Control method of movement control module of electrosparking machine
CN102665196A (en) * 2012-04-28 2012-09-12 清华大学 On-line progressive program updating method for wireless sensor network
CN102882854A (en) * 2012-09-05 2013-01-16 南方电网科学研究院有限责任公司 Power grid data access method
CN102853941A (en) * 2012-09-06 2013-01-02 上海欣影电力科技发展有限公司 Wireless temperature on-line monitoring system for base station type switch cabinet
CN103116346A (en) * 2013-02-22 2013-05-22 西安众恒科技有限公司 Power quality online monitoring system of network topology wireless communication
CN203261351U (en) * 2013-05-16 2013-10-30 国家电网公司 Intelligent power distribution terminal with digital signature authentication
CN103368264A (en) * 2013-07-22 2013-10-23 国家电网公司 Safety operation detecting platform of substation relay protection room

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106487595A (en) * 2016-10-26 2017-03-08 宁波永耀信息科技有限公司 Power transformation O&M big data network control platform

Also Published As

Publication number Publication date
CN103595725B (en) 2018-05-18

Similar Documents

Publication Publication Date Title
US9690565B2 (en) Application assisted software update for connected devices without a display
CN103677946B (en) Method and system for updating elevator device control programs
WO2008013897A3 (en) System and method for server configuration control and management
CN103701640A (en) Method and system of using intelligent management terminal to update ODN (optical distribution network) equipment
CN105204880B (en) computer system and setting method of basic input and output system
CN103917955A (en) Data-loading system, transportable data-loading device, and a method for loading software configurations into aircraft
CN102710436A (en) Network equipment management method, device, relative equipment and system
CN109782724B (en) Control method for preventing misoperation-locking and terminal equipment
CN102970699B (en) A kind of fault handling method and distributed base station
CN103257694A (en) Monitoring power source redundancy via power distribution unit
CN103297266A (en) System access management method based on enterprise integration bus
CN103595725A (en) Screen cabinet resource control system and method
US9870234B2 (en) Automatic identification of returned merchandise in a data center
CN104503724A (en) Method and system for ring joint configuration of jointing wall
CN104168145A (en) System and method for conducting wireless updating on wireless communication units
CN102708181A (en) Distributed data instancing method of charging station monitoring system
CN105094899A (en) Distributed-type intelligent apparatus sub-module program automatic configuration method
CN103729891A (en) Road side unit equipment, method for processing transaction with the same and ETC system
CN103473344A (en) Information inquiry and issuing system
CN104853145B (en) The adaptive upgrade-system of apparatus assembly
CN203552257U (en) Information query and release system
US10462683B1 (en) Connectivity apparatus for remote cell tower integration
CN104698948A (en) Industrial second-screen system and master control system of an automatic device
CN102542394A (en) Authority management method for semiconductor equipment
CN109189436A (en) The firmware update of Complex Programmable Logic Devices

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100031 West Chang'an Avenue, Xicheng District, Xicheng District, Beijing

Co-patentee after: STATE GRID ZHEJIANG YUYAO POWER SUPPLY Co.,Ltd.

Patentee after: State Grid Corporation of China

Co-patentee after: STATE GRID ZHEJIANG ELECTRIC POWER CO., LTD. NINGBO POWER SUPPLY Co.

Co-patentee after: NINGBO POWERSHINE INFORMATION & TECHNOLOGY CO.,LTD.

Address before: 100031 West Chang'an Avenue, Xicheng District, Xicheng District, Beijing

Co-patentee before: STATE GRID ZHEJIANG YUYAO POWER SUPPLY Co.

Patentee before: State Grid Corporation of China

Co-patentee before: STATE GRID NING BO CURRENT SUPPLY COMPANY OF ZHEJIANG ELECTRIC POWER Co.

Co-patentee before: NINGBO POWERSHINE INFORMATION & TECHNOLOGY CO.,LTD.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190110

Address after: 100031 West Chang'an Avenue, Xicheng District, Xicheng District, Beijing

Co-patentee after: STATE GRID ZHEJIANG YUYAO POWER SUPPLY Co.,Ltd.

Patentee after: State Grid Corporation of China

Co-patentee after: STATE GRID ZHEJIANG ELECTRIC POWER CO., LTD. NINGBO POWER SUPPLY Co.

Co-patentee after: Yongyao Science and Technology Branch of Ningbo Transmission and Transfer Construction Co.,Ltd.

Address before: 100031 West Chang'an Avenue, Xicheng District, Xicheng District, Beijing

Co-patentee before: STATE GRID ZHEJIANG YUYAO POWER SUPPLY Co.,Ltd.

Patentee before: State Grid Corporation of China

Co-patentee before: STATE GRID ZHEJIANG ELECTRIC POWER CO., LTD. NINGBO POWER SUPPLY Co.

Co-patentee before: NINGBO POWERSHINE INFORMATION & TECHNOLOGY CO.,LTD.