Terminal and manufacturing method thereof Download PDFInfo
- Publication number
- CN103594829A CN103594829A CN201210291437.6A CN201210291437A CN103594829A CN 103594829 A CN103594829 A CN 103594829A CN 201210291437 A CN201210291437 A CN 201210291437A CN 103594829 A CN103594829 A CN 103594829A
- Authority
- CN
- China
- Prior art keywords
- shell fragment
- supporting part
- bent
- pars intermedia
- binding post
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Surgical Instruments (AREA)
Abstract
The invention discloses a terminal and a manufacturing method thereof. The terminal comprises a body and a spring sheet. A body upper portion, a body middle portion and a body lower portion are bended on the body. The body upper portion is provided with an opening. The body middle portion is provided with an upper opening and a lower opening. The upper opening is bended and forms an upper abutting portion and the lower opening is bended and forms a lower abutting portion. The spring sheet is bended and forms a spring sheet upper portion, a spring sheet middle portion and a spring sheet lower portion. The spring sheet upper portion is bended and forms a flange. The spring sheet middle portion is in an arc shape. The spring sheet upper portion passes through the upper opening and the flange and then is embedded into the opening. The upper abutting portion abuts against the spring sheet upper portion. The spring sheet lower portion passes through the lower opening and abuts against the lower abutting portion. Therefore, a damage problem can be avoided and a purpose of reaching a wiring function is achieved.
Description
Technical field
The present invention relates to a kind of binding post and manufacture method thereof, espespecially a kind ofly avoid the problem being damaged and can really reach binding post and the manufacture method thereof of connection function.
Background technology
In general electronics, motor component or structure in electrical contact, usually need between different assemblies, carry out the wiring action of transmission line, to allow, between different assemblies, can be electrically connected and carry out signal transmission.
And in order to reach the object of above-mentioned wiring, generally can use so-called binding post as the use of transmission line wiring.
Traditional binding post comprises a body and a shell fragment, and is bonded to each other between body and shell fragment, for example, utilize riveted joint combination, and transmission line can insert binding post, and utilizes the elastic force of shell fragment and be held between shell fragment and body.
Yet, as mentioned above, between its body of traditional binding post and shell fragment, pass through riveted joint combination, but binding post is after constantly reusing, the problem that adhesion that the riveted joint of body between shell fragment is combined is easily damaged, relatively can cause between body and shell fragment and easily to produce damages that come off, and then cause binding post to lose its original connection function, therefore the space being still improved existence.
Summary of the invention
The defect and the deficiency that for prior art, exist, main purpose of the present invention is to provide a kind of binding post and manufacture method thereof.
For achieving the above object, the present invention by the following technical solutions:
Binding post of the present invention comprises a body, body is bent to form a body top connected to each other, a body pars intermedia and a body bottom, body top offers a perforate, body pars intermedia offers a upper shed and a under shed, and body pars intermedia has been bent to form supporting part on, by under shed, has been bent to form supporting part by upper shed respectively; Shell fragment is bent to form a shell fragment top connected to each other, a shell fragment pars intermedia and a shell fragment bottom, and shell fragment top has been bent to form a flange, and shell fragment pars intermedia is arcuation; Shell fragment top passes upper shed, and flange is also embedded in perforate, and upper supporting part is also resisted against shell fragment top, and shell fragment bottom passes under shed and is resisted against lower supporting part.
Therefore,, by above-mentioned structural design, can reach the object of avoiding the problem being damaged and can really reaching connection function.
Above-mentioned shell fragment top offers at least one shrinkage pool, and body convexes with at least one protuberance, and protuberance is embedded in shrinkage pool.By this, when body and shell fragment interosculate, protuberance can block shrinkage pool, the steadiness in the time of so can increasing body and shell fragment and interosculate.
Above-mentioned body bottom protrudes out You Yi foot.
A manufacture method for binding post, comprises the following steps:
One plate is provided;
Bending plate forms a U font;
Punching press plate form a upper shed, a under shed, by upper shed, bent one on supporting part and the supporting part once that bent by under shed;
Put into a shell fragment in upper shed and under shed, and shell fragment is bent to form a shell fragment top connected to each other, a shell fragment pars intermedia and a shell fragment bottom, shell fragment pars intermedia is arcuation, and shell fragment bottom is resisted against lower supporting part;
In bending, supporting part makes it be resisted against shell fragment top.
By the method for above-mentioned formation binding post, can reach the object of the utilizability of saving material.
A manufacture method for binding post, comprises the following steps:
One plate is provided;
The supporting part that punching press plate forms an opening and bent by opening;
Put into a shell fragment in opening; And
Bending supporting part makes it be resisted against shell fragment.
Same, by the above-mentioned another kind of method that forms binding post, also can reach the object of the utilizability of saving material.
Accompanying drawing explanation
Fig. 1 is the exploded view of the present invention's the first preferred embodiment.
Fig. 2 is one of the body of the present invention's the first preferred embodiment and the combination schematic diagram of shell fragment.
Fig. 3 is two of the body of the present invention's the first preferred embodiment and the combination schematic diagram of shell fragment.
Fig. 4 is the cutaway view of the present invention's the first preferred embodiment.
Fig. 5 is the body of the present invention's the second preferred embodiment and the combination schematic diagram of shell fragment.
Fig. 6 is the flow chart that the present invention forms binding post.
Fig. 7 (a~e) forms the schematic diagram of binding post for the present invention.
Fig. 8 is the another kind of flow chart that forms binding post of the present invention.
Fig. 9 (a~d) is the another kind of schematic diagram that forms binding post of the present invention.
[primary clustering symbol description]
1 binding post 2 body 21 body top 211 perforate 22 body pars intermedias
224 times supporting parts of supporting part, 23 body bottoms on 221 upper shed 222 under sheds 223
231 foot's 24 protuberance 3 shell fragment 31 shell fragment top 311 flanges
312 shrinkage pool 32 shell fragment pars intermedia 33 shell fragment bottom 4 body 5 shell fragments
614 times supporting parts of supporting part on 61 plate 611 upper shed 612 under sheds 613
62 shell fragment 621 shell fragment top 622 shell fragment pars intermedia 623 shell fragment bottom 71 plates
711 opening 712 supporting part 72 shell fragment S1~S5 step SS1~SS4 steps
Embodiment
Refer to Fig. 1, it is for the exploded view of the present invention's the first preferred embodiment.
In Fig. 1, show a binding post 1, and this binding post 1 comprises a body 2 and a shell fragment 3.
In the embodiment of Fig. 1, body 2 is bent to form a body top 21, a body pars intermedia 22 and a body bottom 23 connected to each other, wherein, body top 21 offers a perforate 211, body pars intermedia 22 offers a upper shed 221 and a under shed 222, and body pars intermedia 22 has been bent to form supporting part 223 on, by under shed 222, has been bent to form supporting part 224 by upper shed 221 respectively.
In addition, in the embodiment of Fig. 1, shell fragment 3 is bent to form a shell fragment top 31, a shell fragment pars intermedia 32 and a shell fragment bottom 33 connected to each other, and wherein, shell fragment top 31 has been bent to form a flange 311, and shell fragment pars intermedia 32 is arcuation.
Please refer to Fig. 2 to Fig. 4, Fig. 2 is wherein one of the body of the present invention's the first preferred embodiment and combination schematic diagram of shell fragment, Fig. 3 is two of the body of the present invention's the first preferred embodiment and the combination schematic diagram of shell fragment, Fig. 4 is the cutaway view of the present invention's the first preferred embodiment, and please be simultaneously in the lump with reference to Fig. 1.
In graphic middle demonstration, the shell fragment top 31 of shell fragment 3 passes the upper shed 221 of the body pars intermedia 22 of body 2, the flange 311 on shell fragment top 31 is also embedded in the perforate 211 on the body top 21 of body 2, the upper supporting part 223 of the body pars intermedia 22 of body 2 is also resisted against the shell fragment top 31 of shell fragment 3, the shell fragment bottom 33 of shell fragment 3 pass body 2 body pars intermedia 22 under shed 222 and be resisted against the lower supporting part 224 of body pars intermedia 22.
In said process, as shown in Figure 2, after first body 2 and shell fragment 3 being interosculated, more as shown in Figure 3, then bend body 2 body pars intermedia 22 upper supporting part 223 and make it be resisted against the shell fragment top 31 of shell fragment 3.
As mentioned above, when body 2 and shell fragment 3 interosculate, the flange 311 on the shell fragment top 31 of shell fragment 3 is embedded in the perforate 211 on the body top 21 of body 2, the upper supporting part 223 of the body pars intermedia 22 of body 2 is resisted against the shell fragment top 31 of shell fragment 3, the shell fragment bottom 33 of shell fragment 3 is resisted against the lower supporting part 224 of body pars intermedia 22, therefore can form firm combination between body 2 and shell fragment 3, for example the upper supporting part 223 (bending) of the body pars intermedia 22 of body 2 is resisted against the shell fragment top 31 of shell fragment 3, therefore its contact strength can make shell fragment 3 firmly be incorporated into body 2, and can not produce the problem of dropping.
In other words, by above-mentioned structural design, can reach the problem (for example body 2 comes off mutually with shell fragment 3) of avoiding being damaged and can really make binding post 1 reach the object of connection function.
In the present embodiment, the shell fragment top 31 of shell fragment 3 offers at least one shrinkage pool 312, and body 2 convexes with at least one protuberance 24, and protuberance 24 is embedded in shrinkage pool 312.
As shown in the figure, in the present embodiment, the quantity of at least one shrinkage pool 312 that the shell fragment top 31 of shell fragment 3 is offered is two, and be opened in respectively the both sides on the shell fragment top 31 of shell fragment 3, same, the quantity of at least one protuberance 24 that body 2 is convexly equipped with is also two, and is convexly set in respectively the body top 21 of body 2 and the both sides at body pars intermedia 22 adjacent places, and each protuberance 24 is embedded in respectively each shrinkage pool 312.
By this, when body 2 and shell fragment 3 interosculate, except said structure design, utilize protuberance 24 to be embedded in the design of shrinkage pool 312, the steadiness in the time of can more increasing body 2 and interosculate with shell fragment 3.For example, the six directions such as up, down, left, right, before and after all can have locking effect, therefore the problem that more can not occur to come off mutually between body 2 and shell fragment 3.
In said structure, the body bottom 23 of body 2 still protrudes out You Yi foot 231, and it can be as the use of electric connection.
Refer to Fig. 5, it is the body of the present invention's the second preferred embodiment and the combination schematic diagram of shell fragment.
In the present embodiment, its primary structure is all identical with above-mentioned the first preferred embodiment, only difference is that body 4 is open shape in side, shell fragment 5 be by side insert body 4 and with body 4 combinations, and so structural design can be reached the various effects described in above-mentioned the first preferred embodiment equally.
Please refer to Fig. 6 and Fig. 7, wherein Fig. 6 is the flow chart that the present invention manufactures binding post, and Fig. 7 (a~e) manufactures the schematic diagram of binding post for the present invention.
As shown in the figure, first provide a plate 61 (step S1, Fig. 7 (a)); Bending plate 61 forms a U font (step S2, Fig. 7 (b)); Punching press plate 61 form upper sheds 611, a under shed 612, by upper shed 611, bent one on supporting part 613 and the supporting part once 614 (step S3, Fig. 7 (c)) that bent by under shed 612; Put into a shell fragment 62 in upper shed 611 and under shed 612, and shell fragment 62 is bent to form a shell fragment top 621, a shell fragment pars intermedia 622 and a shell fragment bottom 623 connected to each other, shell fragment pars intermedia 622 is arcuation, shell fragment bottom 623 is resisted against lower supporting part 614 (step S4, Fig. 7 (d)); And the upper supporting part 613 of bending makes it be resisted against shell fragment top 621 (step S5, Fig. 7 (e)).
Therefore, by said method, binding post can be formed, and by said method, the object of the utilizability of saving material can be reached.
Please refer to Fig. 8 and Fig. 9, Fig. 8 is wherein the another kind of flow chart of manufacturing binding post of the present invention, and Fig. 9 (a~d) is the another kind of schematic diagram of manufacturing binding post of the present invention.
As shown in the figure, first provide a plate 71 (step SS1, Fig. 9 (a)); The supporting part 712 (step SS2, Fig. 9 (b)) that punching press plate 71 forms an opening 711 and bent by opening 711; Put into a shell fragment 72 in opening 711 (step SS3, Fig. 9 (c)); And bending supporting part 712 makes it be resisted against shell fragment 72 (step SS4, Fig. 9 (d)).
As mentioned above, it is the another kind of method that can manufacture binding post, and the method can reach the object of the utilizability of above-mentioned saving material equally.
The above; be only the specific embodiment of the present invention, but protection scope of the present invention is not limited to this, is anyly familiar with those skilled in the art in the technical scope that the present invention discloses; can expect easily changing or replacing, within all should being encompassed in protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with the protection range of described claim.
Claims (5)
1. a binding post, is characterized in that, comprising:
One body, be bent to form a body top connected to each other, a body pars intermedia and a body bottom, body top offers a perforate, body pars intermedia offers a upper shed and a under shed, and body pars intermedia has been bent to form supporting part on, by under shed, has been bent to form supporting part by upper shed respectively; And
One shell fragment, is bent to form a shell fragment top connected to each other, a shell fragment pars intermedia and a shell fragment bottom, and shell fragment top has been bent to form a flange, and shell fragment pars intermedia is arcuation;
Wherein, shell fragment top passes upper shed, and flange is also embedded in perforate, and upper supporting part is resisted against shell fragment top, and shell fragment bottom passes under shed and is resisted against lower supporting part.
2. binding post according to claim 1, is characterized in that, shell fragment top offers at least one shrinkage pool, and body convexes with at least one protuberance, and protuberance is embedded in shrinkage pool.
3. binding post according to claim 1, is characterized in that, body bottom protrudes out You Yi foot.
4. a manufacture method for binding post, is characterized in that, comprises the following steps:
One plate is provided;
Bending plate forms a U font;
Punching press plate form a upper shed, a under shed, by upper shed, bent one on supporting part and the supporting part once that bent by under shed;
Put into a shell fragment in upper shed and under shed, and shell fragment is bent to form a shell fragment top connected to each other, a shell fragment pars intermedia and a shell fragment bottom, shell fragment pars intermedia is arcuation, and shell fragment bottom is resisted against lower supporting part;
In bending, supporting part makes it be resisted against shell fragment top.
5. a manufacture method for binding post, is characterized in that, comprises the following steps:
One plate is provided;
The supporting part that punching press plate forms an opening and bent by opening;
Put into a shell fragment in opening;
Bending supporting part makes it be resisted against shell fragment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210291437.6A CN103594829A (en) | 2012-08-15 | 2012-08-15 | Terminal and manufacturing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210291437.6A CN103594829A (en) | 2012-08-15 | 2012-08-15 | Terminal and manufacturing method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103594829A true CN103594829A (en) | 2014-02-19 |
Family
ID=50084871
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210291437.6A Pending CN103594829A (en) | 2012-08-15 | 2012-08-15 | Terminal and manufacturing method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103594829A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107799914A (en) * | 2017-10-12 | 2018-03-13 | 东莞市美金兴能源有限公司 | A kind of wire clamp |
DE202017006317U1 (en) * | 2017-12-08 | 2019-03-27 | Wago Verwaltungsgesellschaft Mbh | Spring terminal connection for an electrical conductor |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0472040A1 (en) * | 1990-08-23 | 1992-02-26 | Popp & Co. GmbH | Connecting clamp without screws and method for its manufacture |
CN1150317A (en) * | 1995-07-27 | 1997-05-21 | 欧姆龙公司 | Switch device |
CN101573838A (en) * | 2006-10-06 | 2009-11-04 | Abb股份有限公司 | Installation switching device |
CN101714706A (en) * | 2008-09-26 | 2010-05-26 | Wago管理有限责任公司 | Elastic connection terminal and terminal component |
-
2012
- 2012-08-15 CN CN201210291437.6A patent/CN103594829A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0472040A1 (en) * | 1990-08-23 | 1992-02-26 | Popp & Co. GmbH | Connecting clamp without screws and method for its manufacture |
CN1150317A (en) * | 1995-07-27 | 1997-05-21 | 欧姆龙公司 | Switch device |
CN101573838A (en) * | 2006-10-06 | 2009-11-04 | Abb股份有限公司 | Installation switching device |
CN101714706A (en) * | 2008-09-26 | 2010-05-26 | Wago管理有限责任公司 | Elastic connection terminal and terminal component |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107799914A (en) * | 2017-10-12 | 2018-03-13 | 东莞市美金兴能源有限公司 | A kind of wire clamp |
CN107799914B (en) * | 2017-10-12 | 2023-11-07 | 东莞市美金兴能源有限公司 | Wire clamp |
DE202017006317U1 (en) * | 2017-12-08 | 2019-03-27 | Wago Verwaltungsgesellschaft Mbh | Spring terminal connection for an electrical conductor |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203799778U (en) | Pulse transformer | |
CN206250260U (en) | Secondary cell | |
CN2916996Y (en) | Electric connector | |
CN204088676U (en) | High-speed transfer terminative connector | |
CN103594829A (en) | Terminal and manufacturing method thereof | |
CN205846294U (en) | Auxiliary connection instrument and testing agency | |
CN106159332A (en) | Trapezoidal battery, battery core and manufacture method thereof | |
CN201498607U (en) | Wiring terminal with elastic piece protecting function | |
CN102903862A (en) | Rechargeable battery | |
CN209588864U (en) | A kind of electric detonator capacitance bracket of capacitor | |
CN201262912Y (en) | Welded structure and keyboard with the same | |
CN207165787U (en) | A kind of board to board connector applied to small spacing | |
CN216671782U (en) | Cover plate assembly and battery with same | |
CN203911045U (en) | Battery connector terminal, battery connector and mobile phone | |
CN201298689Y (en) | Economic type universal drawer for functional unit | |
CN107994374A (en) | Monoblock type riveting rectangle jack and its processing method | |
CN104935690A (en) | Mobile terminal and method of manufacturing mobile terminal | |
CN207490153U (en) | Monoblock type riveting rectangle jack | |
CN103296362A (en) | Cavity body structure of cover plate integrated type microwave isolator | |
CN201708341U (en) | Plug bush for socket and socket thereof | |
CN204118339U (en) | multi-piece type FPC connector | |
CN205944166U (en) | Multisection formula battery assembly | |
CN207217814U (en) | Binding post and the wiring board with the binding post | |
CN202855931U (en) | Relay coupling amphenol connector improved structure | |
CN101640130B (en) | Electrolytic capacitor with external connected pin |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20140219 |