CN103590424B - The underground engineering construction method of road - Google Patents

The underground engineering construction method of road Download PDF

Info

Publication number
CN103590424B
CN103590424B CN201310632030.XA CN201310632030A CN103590424B CN 103590424 B CN103590424 B CN 103590424B CN 201310632030 A CN201310632030 A CN 201310632030A CN 103590424 B CN103590424 B CN 103590424B
Authority
CN
China
Prior art keywords
section
construction
earthwork
top board
wallboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310632030.XA
Other languages
Chinese (zh)
Other versions
CN103590424A (en
Inventor
李涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHEN DENGXING
SHEN LESHENG
Original Assignee
CHEN DENGXING
SHEN LESHENG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHEN DENGXING, SHEN LESHENG filed Critical CHEN DENGXING
Priority to CN201310632030.XA priority Critical patent/CN103590424B/en
Publication of CN103590424A publication Critical patent/CN103590424A/en
Application granted granted Critical
Publication of CN103590424B publication Critical patent/CN103590424B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The present invention discloses the underground engineering construction method of a kind of road, comprises the following steps: construction ground is divided into three sections by (1), is respectively A, B section of middle C section and both sides; (2) closing C section, to the construction of C section, the excavation top layer earthwork, does C section top board; (3) backfilling the C section earthwork, to the construction of A section, the excavation top layer earthwork, to base plate basic unit, does A section base plate; (4) A section wallboard is done; (5) A section top board is done; (6) backfilling the A section earthwork, to the construction of B section, the excavation top layer earthwork, to base plate basic unit, does B section and C section base plate; Do B section wallboard; Do B section top board; (7) the B section earthwork is backfilled.

Description

The underground engineering construction method of road
Technical field
The present invention relates to a kind of construction technology, it is specifically related to the underground engineering construction method of a kind of road.
Background technology
Domestic city development just day by day face: soil is in short supply, congested in traffic, environmental pollution, energy shortage, take precautions against natural calamities fragility etc. problem. City spatial colonization mode just turns to " solid " from " on the ground ", and more and more public works and civil engineering are selected to underground development, and the newly-built Large Underground Structure thing of One's name is legion. But the exploitation place of underground structure is often in the central position in city, road is closed the pressure of traffic is quite big in construction period, especially, when not having peripheral path can detour for vehicle, carry out road closed construction, the paralysis of Urban traffic function will be caused.
The common at present method of underground engineering construction mainly contains Open Cut Method or sheltered reverse excavation. Open Cut Method refers to after completing building enclosure, is excavated to substrate absolute altitude, base plate �� wallboard �� basement roof of then successively constructing from bottom to top. The defect of Open Cut Method: have safety supports to exist, excavates restricted; Traffic impact is big; Urban life interference is big; Surrounding environment is destroyed big. Open Cut Method is applicable to shallow excavation project, and the sheltered reverse excavation engineering time is longer, and difficulty of construction is bigger.
Summary of the invention
The object of the present invention is exactly the defect in order to make up prior art, it is provided that the underground engineering construction method of a kind of road, it is possible to solves engineering construction and is subject to excavating the restriction of the degree of depth, problem that a rate of advance is low.
In order to realize above-mentioned purpose, the present invention provides two kinds of constructional methods, its one:
A underground engineering construction method for road, comprises the following steps:
(1) construction ground is divided into three sections, it is respectively A, B section of middle C section and both sides;
(2) closing C section, to the construction of C section, the excavation top layer earthwork, does C section top board;
(3) backfilling the C section earthwork, to the construction of A section, the excavation top layer earthwork, to base plate basic unit, does A section base plate;
(4) A section wallboard is done;
(5) A section top board is done;
(6) backfilling the A section earthwork, to the construction of B section, the excavation top layer earthwork, to base plate basic unit, does B section and C section base plate; Do B section wallboard; Do B section top board;
(7) the B section earthwork is backfilled.
As further improvement, in step (2), after closing C section, before the excavation top layer earthwork, carrying out two row's pile foundation constructions, steel lattice column construction, C section top board and two row's steel lattice columns are connected to form a reinforced concrete bridge;
In step (3), after closing A section, carry out steel sheet pile or drilled pile construction, and do grit and form foundation pit enclosure structure, then pile foundation construction, makees horizontal steel pipe at interval of a segment distance and supports, connect together supporting the top board with C section, after earth excavation to base plate basic unit, the earthwork under C section top board is put slope process or local reinforcing;
Before step (6) backfills the A section earthwork, remove steel pipe support, do WATER REPELLENT; In the lump the C section earthwork is excavated when excavating the B section earthwork.
As further improvement, it is 0.67 that the earthwork under C section top board is put setting sloping coefficient when slope processes.
Its two:
A underground engineering construction method for road, comprises the following steps:
(1) construction ground is divided into three sections, it is respectively A, B section of middle C section and both sides;
(2) closing C section, to the construction of C section, the excavation top layer earthwork, does C section top board;
(3) backfilling the C section earthwork, A section and B section are constructed simultaneously, the excavation top layer earthwork, to base plate basic unit, does A, B, C section base plate;
(4) A, B section wallboard is done;
(5) A, B section top board is done;
(6) A, B section earthwork is backfilled.
As further improvement, in step (2), after closing C section, before the excavation top layer earthwork, carrying out two row's pile foundation constructions, steel lattice column construction, C section top board and two row's steel lattice columns are connected to form a reinforced concrete bridge;
In step (3), when A section and B section are constructed simultaneously, carry out steel sheet pile or drilled pile construction, and do grit and form foundation pit enclosure structure, then pile foundation construction, makees horizontal steel pipe at interval of a segment distance and supports, connect together supporting the top board with C section, after earth excavation to base plate basic unit, the earthwork under C section top board is dug out below A section or B section or respectively excavates 50% from A and B section respectively;
Before step (6) backfills A, B section earthwork, remove steel pipe support, do WATER REPELLENT.
Present invention also offers the treatment process for the construction joint produced in above two kinds of constructional methods:
Top board construction seam between A section and C section, C section and B section is done WATER REPELLENT, extends along top board construction seam to both sides and be provided with coating waterproof layer, sealing coat, pea gravel concreten protective layer from bottom to up successively.
Construction of bottom plates seam is done WATER REPELLENT, extends along construction of bottom plates seam to both sides and be provided with concrete bed course, waterproof layer, pea gravel concreten protective layer from bottom to up successively.
The wallboard construction joint of A section and B section is done WATER REPELLENT, is provided with outside wallboard and goes along with sb. to guard him wall together, outside the wallboard extended along wallboard construction joint to both sides, be provided with waterproof layer, screed-coat successively.
As further improvement: top board construction stitches the coating waterproof layer within the scope of the 30-50cm of both sides and is provided with coating water-proof enhancement Layer between top board; In top board construction seam, upper section is provided with water-swellable water-stop glue, and hypomere is provided with muptiple-use Grouting Pipe; Pea gravel concreten protective layer thickness is 6-8cm.
As further improvement: construction of bottom plates stitches the waterproof layer within the scope of the 30-45cm of both sides and is provided with waterproof reinforced layer between pea gravel concreten protective layer; Construction of bottom plates seam in hypomere be provided with water-swellable water-stop glue, upper section be provided with muptiple-use Grouting Pipe; Pea gravel concreten protective layer thickness is 4-6cm.
As further improvement: waterproof layer within the scope of wallboard construction joint both sides 30-45cm and be provided with waterproof reinforced layer between wallboard; Being provided with water-swellable water-stop glue in wallboard construction joint, muptiple-use Grouting Pipe is arranged in the middle of wallboard construction joint, and water-swellable water-stop glue is between wallboard and muptiple-use Grouting Pipe, and distance wallboard 9-11cm, apart from muptiple-use Grouting Pipe 5-7cm.
The optimum scope of application of the present invention:
1, region, the north, ground water table >=-10 meter;
2, soil property is the good soil layers of earth bearing strength such as sandy soil, loess, clay.
Compared with prior art, the present invention has following feature:
1, road surface is disposed adjacent as A section, C section and B section by the present invention successively, it is achieved that efficient, safe construction; While building underground works, the duration shortens, and ensures that driveway is two-way current; Solve engineering construction to be subject to excavating the restriction of the degree of depth, problem that a rate of advance is low; Comparing sheltered reverse excavation, engineering drops into and more economizes, and difficulty of construction is less simultaneously.
2, adopting the 2nd kind of scheme, basement bottom board can be once-forming, does not stay construction joint, water-repellancy and reliability height; Under C section top board, the earthwork can be dug up together with A with the B section earthwork, need not put slope process, reduce by a procedure, security height; A and B constructs simultaneously and can save for 1/3 duration, and benefit is higher; But requiring that road is wider, wagon flow amount is less. Therefore can adopt the first scheme when, wagon flow amount narrower at road is bigger, the 2nd kind of scheme when road is wider, wagon flow amount is less, can be adopted.
Accompanying drawing explanation
Fig. 1 is top board construction seam waterproof construction schematic diagram;
Fig. 2 is construction of bottom plates seam waterproof construction schematic diagram;
Fig. 3 is wallboard construction joint waterproof construction schematic diagram.
In figure: 1-top board, 2-base plate, 3-wallboard, 4-top board construction seam, 5-construction of bottom plates seam, 6-wallboard construction joint, 7-water-swellable water-stop glue, the muptiple-use Grouting Pipe of 8-, 9-coating waterproof layer, 10-sealing coat, 11-pea gravel concreten protective layer, 12-coating water-proof enhancement Layer, 13-concrete bed course, 14-waterproof layer, 15-waterproof reinforced layer, 16-go along with sb. to guard him wall, 17-screed-coat.
Embodiment
Embodiment will in conjunction with Figure of description below, and the present invention is described further.
Embodiment 1
For place narrower at road, that wagon flow amount is bigger as underground garage is built in railway station, the first scheme is adopted to construct:
(1) construction ground is divided into three sections, it is respectively A, B section of middle C section and both sides
(2) closing C section, surrounding arranges building enclosure and road surface enclosing, traffic diversion, before the excavation top layer earthwork, carries out two row's pile foundation constructions, steel lattice column construction, and to the construction of C section, the excavation top layer earthwork, does C section top board 1; C section top board 1 and two row's steel lattice columns are connected to form a reinforced concrete bridge;
(3) pipeline is recovered, the backfill C section earthwork, recovers traffic, A section is constructed, carry out steel sheet pile or drilled pile construction, and do grit and form foundation pit enclosure structure, then pile foundation construction, make horizontal steel pipe at interval of a segment distance and support, connect together supporting the top board 1 with C section, after earth excavation to base plate basic unit, the 1 time earthwork of C section top board being put slope process or local reinforcing, putting setting sloping coefficient when slope processes is 0.67; The excavation top layer earthwork, to base plate basic unit, does A section base plate 2;
(4) A section wallboard 3 is done;
(5) do A section top board 1 to be connected with C section top board 1;
(6) removing steel pipe to support, do WATER REPELLENT, recover pipeline, the backfill A section earthwork, recovers traffic, and to the construction of B section, the C section earthwork, to base plate basic unit, is excavated by the excavation top layer earthwork in the lump, does B section and C section base plate 2 is one overall; Do B section wallboard 3; Do B section top board 1 and connect C section top board 1;
(7) recovering pipeline, the backfill B section earthwork, recovers traffic.
Embodiment 2
For local construction wider at road, that wagon flow amount is less, adopt the 2nd kind of scheme construction:
(1) construction ground is divided into three sections, it is respectively A, B section of middle C section and both sides
(2) closing C section, surrounding arranges building enclosure and road surface enclosing, traffic diversion, before the excavation top layer earthwork, carries out two row's pile foundation constructions, steel lattice column construction, and to the construction of C section, the excavation top layer earthwork, does C section top board 1;C section top board 1 and two row's steel lattice columns are connected to form a reinforced concrete bridge;
(3) pipeline is recovered, the backfill C section earthwork, recover traffic, A section and B section are constructed simultaneously, carries out steel sheet pile or drilled pile construction, and do grit and form foundation pit enclosure structure, then pile foundation construction, makees horizontal steel pipe at interval of a segment distance and supports, connect together supporting the top board 1 with C section, the excavation top layer earthwork, to base plate basic unit, respectively excavates 50% from A and B section respectively for the 1 time earthwork of C section top board; Doing A, B, C section base plate 2 is an entirety;
(4) A, B section wallboard 3 is done;
(5) doing A, B section top board 1 is an entirety;
(6) removing steel pipe to support, do WATER REPELLENT, recover pipeline, backfill A, B section earthwork, recovers traffic.
For embodiment 1 and 2, the top board construction seam 4 between A section and C section, C section and B section is done WATER REPELLENT, stitch 4 along top board construction and be provided with coating waterproof layer 9, sealing coat 10, pea gravel concreten protective layer 11 from bottom to up successively to both sides extension. Top board construction stitches the coating waterproof layer 9 within the scope of 4 both sides 30cm and is provided with coating water-proof enhancement Layer 12 between top board 1; In top board construction seam 4, upper section is provided with water-swellable water-stop glue 7, and hypomere is provided with muptiple-use Grouting Pipe 8; Pea gravel concreten protective layer 11 thickness is 7cm.
For embodiment 1, the construction of bottom plates seam 5 between A section and B section is done WATER REPELLENT, stitch 5 along construction of bottom plates and be provided with concrete bed course 13, waterproof layer 14, pea gravel concreten protective layer 11 from bottom to up successively to both sides extension; Construction of bottom plates stitches the waterproof layer 14 within the scope of 5 both sides 30cm and is provided with waterproof reinforced layer 15 between pea gravel concreten protective layer 11; Construction of bottom plates seam 5 in hypomere be provided with water-swellable water-stop glue 7, upper section be provided with muptiple-use Grouting Pipe 8; Pea gravel concreten protective layer 11 thickness is 5cm.
For embodiment 1 and 2, the wallboard construction joint 6 of A section and B section is done WATER REPELLENT, is provided with outside wallboard 3 and goes along with sb. to guard him wall 16 together, outside the wallboard 3 extended along wallboard construction joint 6 to both sides, be provided with waterproof layer 9, screed-coat 17 successively. Waterproof layer 9 within the scope of wallboard construction joint 6 both sides 30cm and be provided with waterproof reinforced layer 15 between wallboard 3; Being provided with water-swellable water-stop glue 7 in wallboard construction joint 6, muptiple-use Grouting Pipe 8 is arranged in the middle of wallboard construction joint 6, and water-swellable water-stop glue 7 is between wallboard 3 and muptiple-use Grouting Pipe 8, and distance wallboard 3 has 10cm, has 6cm apart from muptiple-use Grouting Pipe 8.
The thickness of underground wallboard 3 can be determined according to the soil property situation that the distance of the height of surrounding buildings thing, the scale of construction and wallboard, ground preloading and geological prospecting report are indicated, buried depth is two times of underground works buried depth.
Owing to underground works is positioned at below ordinary water level, reliable measure of anti float must be taked, outside the wallboard of underground, within the scope of 1m, it is provided with well-points dewatering, ground water table is controlled 1.5m place below shoveling layer, only complete at underground engineering construction, the backfill earthwork and recovery road can be removed after completing.

Claims (9)

1. the underground engineering construction method of a road, it is characterised in that comprise the following steps:
(1) construction ground is divided into three sections, it is respectively A, B section of middle C section and both sides;
(2) close C section, to the construction of C section, before the excavation top layer earthwork, carry out two row's pile foundation constructions, steel lattice column construction; The excavation top layer earthwork, does C section top board, and C section top board and two row's steel lattice columns are connected to form a reinforced concrete bridge;
(3) backfill the C section earthwork, after closing A section, to the construction of A section, carry out steel sheet pile or drilled pile construction, and do grit and form foundation pit enclosure structure, then pile foundation construction, make horizontal steel pipe at interval of a segment distance and support, connect together supporting the top board with C section;The earthwork under C section top board, to base plate basic unit, is put slope process or local reinforcing, is done A section base plate by the excavation top layer earthwork;
(4) A section wallboard is done;
(5) A section top board is done;
(6) remove steel pipe before backfilling the A section earthwork to support, do WATER REPELLENT; The backfill A section earthwork, to the construction of B section, the C section earthwork, to base plate basic unit, is excavated when excavating the B section earthwork, is done B section and C section base plate by the excavation top layer earthwork in the lump; Do B section wallboard; Do B section top board;
(7) the B section earthwork is backfilled.
2. the underground engineering construction method of a road, it is characterised in that comprise the following steps:
(1) construction ground is divided into three sections, it is respectively A, B section of middle C section and both sides;
(2) close C section, to the construction of C section, before the excavation top layer earthwork, carry out two row's pile foundation constructions, steel lattice column construction; The excavation top layer earthwork, does C section top board, and C section top board and two row's steel lattice columns are connected to form a reinforced concrete bridge;
(3) the C section earthwork is backfilled, A section and B section are constructed simultaneously, carry out steel sheet pile or drilled pile construction, and do grit and form foundation pit enclosure structure, then pile foundation construction, make horizontal steel pipe at interval of a segment distance and support, connect together supporting the top board with C section, the excavation top layer earthwork, to base plate basic unit, is dug out below A section or B section for the earthwork under C section top board or is respectively excavated 50% from A and B section respectively, do A, B, C section base plate;
(4) A, B section wallboard is done;
(5) A, B section top board is done;
(6) remove steel pipe before backfilling A, B section earthwork to support, do WATER REPELLENT; Backfill A, B section earthwork.
3. the underground engineering construction method of road according to claim 1 and 2; it is characterized in that: the top board construction seam between A section and C section, C section and B section is done WATER REPELLENT, extend along top board construction seam to both sides and be provided with coating waterproof layer, sealing coat, pea gravel concreten protective layer from bottom to up successively.
4. the underground engineering construction method of road according to claim 1 and 2; it is characterized in that: construction of bottom plates seam is done WATER REPELLENT, extend along construction of bottom plates seam to both sides and be provided with concrete bed course, waterproof layer, pea gravel concreten protective layer from bottom to up successively.
5. the underground engineering construction method of road according to claim 1 and 2, it is characterized in that: the wallboard construction joint of A section and B section is done WATER REPELLENT, it is provided with outside wallboard and goes along with sb. to guard him wall together, outside the wallboard extended along wallboard construction joint to both sides, be provided with waterproof layer, screed-coat successively.
6. the underground engineering construction method of road according to claim 1, it is characterised in that: it is 0.67 that the earthwork under C section top board is put setting sloping coefficient when slope processes.
7. the underground engineering construction method of road according to claim 3, it is characterised in that: top board construction stitches the coating waterproof layer within the scope of the 30-50cm of both sides and is provided with coating water-proof enhancement Layer between top board; In top board construction seam, upper section is provided with water-swellable water-stop glue, and hypomere is provided with muptiple-use Grouting Pipe; Pea gravel concreten protective layer thickness is 6-8cm.
8. the underground engineering construction method of road according to claim 4, it is characterised in that: construction of bottom plates stitches the waterproof layer within the scope of the 30-45cm of both sides and is provided with waterproof reinforced layer between pea gravel concreten protective layer; Construction of bottom plates seam in hypomere be provided with water-swellable water-stop glue, upper section be provided with muptiple-use Grouting Pipe; Pea gravel concreten protective layer thickness is 4-6cm.
9. the underground engineering construction method of road according to claim 5, it is characterised in that: waterproof layer within the scope of wallboard construction joint both sides 30-45cm and be provided with waterproof reinforced layer between wallboard;Being provided with water-swellable water-stop glue in wallboard construction joint, muptiple-use Grouting Pipe is arranged in the middle of wallboard construction joint, and water-swellable water-stop glue is between wallboard and muptiple-use Grouting Pipe, and distance wallboard 9-11cm, apart from muptiple-use Grouting Pipe 5-7cm.
CN201310632030.XA 2013-11-29 2013-11-29 The underground engineering construction method of road Active CN103590424B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310632030.XA CN103590424B (en) 2013-11-29 2013-11-29 The underground engineering construction method of road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310632030.XA CN103590424B (en) 2013-11-29 2013-11-29 The underground engineering construction method of road

Publications (2)

Publication Number Publication Date
CN103590424A CN103590424A (en) 2014-02-19
CN103590424B true CN103590424B (en) 2016-06-08

Family

ID=50080726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310632030.XA Active CN103590424B (en) 2013-11-29 2013-11-29 The underground engineering construction method of road

Country Status (1)

Country Link
CN (1) CN103590424B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104153397B (en) * 2014-08-06 2016-05-18 中国三冶集团有限公司 A kind of concrete wall Case Study on Construction Joint Water-proofing
CN106759367A (en) * 2017-02-24 2017-05-31 中铁大桥勘测设计院集团有限公司 The temporary road laying method of open-cut foundation ditch
CN108678000B (en) * 2018-07-20 2020-06-12 中铁三局集团有限公司 U-shaped retaining structure for roadbed underpass highway and construction method thereof
CN109667229A (en) * 2018-10-17 2019-04-23 中铁二十四局集团安徽工程有限公司 A kind of contrary sequence method foundation pit top temporary trestle bridge plate method for dismounting

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1904232A (en) * 2006-08-07 2007-01-31 上海市隧道工程轨道交通设计研究院 Open trench tunnel suitable for large value stratum ununiform settling or diastrophism
CN200946276Y (en) * 2006-08-07 2007-09-12 上海市隧道工程轨道交通设计研究院 Opencut tunnel for adapting to large uneven precipitation or stagger of stratum
CN101250883A (en) * 2008-04-03 2008-08-27 上海市第一建筑有限公司 Side-discharging construction method for subway station shared underground wall
CN101298782A (en) * 2008-06-13 2008-11-05 朱邃科 Method and system for basement engineering water proof and water drain
CN102296502A (en) * 2011-06-03 2011-12-28 天津住宅集团建设工程总承包有限公司 Post construction method of automobile ramp near building
CN102535520A (en) * 2010-12-13 2012-07-04 五冶集团上海有限公司 Waterproof construction method of large-area civil air defense basement
CN103334452A (en) * 2013-07-11 2013-10-02 李涛 Underground engineering mixed construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1904232A (en) * 2006-08-07 2007-01-31 上海市隧道工程轨道交通设计研究院 Open trench tunnel suitable for large value stratum ununiform settling or diastrophism
CN200946276Y (en) * 2006-08-07 2007-09-12 上海市隧道工程轨道交通设计研究院 Opencut tunnel for adapting to large uneven precipitation or stagger of stratum
CN101250883A (en) * 2008-04-03 2008-08-27 上海市第一建筑有限公司 Side-discharging construction method for subway station shared underground wall
CN101298782A (en) * 2008-06-13 2008-11-05 朱邃科 Method and system for basement engineering water proof and water drain
CN102535520A (en) * 2010-12-13 2012-07-04 五冶集团上海有限公司 Waterproof construction method of large-area civil air defense basement
CN102296502A (en) * 2011-06-03 2011-12-28 天津住宅集团建设工程总承包有限公司 Post construction method of automobile ramp near building
CN103334452A (en) * 2013-07-11 2013-10-02 李涛 Underground engineering mixed construction method

Also Published As

Publication number Publication date
CN103590424A (en) 2014-02-19

Similar Documents

Publication Publication Date Title
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
Zhang et al. Construction of a large-section long pedestrian underpass using pipe jacking in muddy silty clay: A case study
CN102943479A (en) System and method for controlling deformation of deep and large foundation pit through partition unloading
CN103334452B (en) A kind of underground construction mixed construction method
CN108612117A (en) A kind of seabed water-retaining structure across municipal tunnel greatly and construction method
CN103590424B (en) The underground engineering construction method of road
Wang et al. A study on the environmental geology of the Middle Route Project of the South–North water transfer
Wang et al. Investigation of the geological and hydrogeological environment with relation to metro system construction in Jinan, China
Singh et al. Ground movements over longwall workings in the Kamptee coalfield, India
Xie et al. Environmentally sustainable groundwater control during dewatering with barriers: A case study in Shanghai
Edmonds Five decades of settlement and subsidence
Goel Status of tunnelling and underground construction activities and technologies in India
CN202954367U (en) System for controlling deformation of deep and big foundation pit by utilizing divisional unloading
Corsini et al. Investigation and monitoring in support of the structural mitigation of large slow moving landslides: an example from Ca'Lita (Northern Apennines, Reggio Emilia, Italy)
Wang et al. Seepage prevention of mining-disturbed riverbed
El-Nahhas Tunnelling and supported deep excavations in the Greater Cairo
Kim et al. Disturbance of groundwater table by subway construction in the Seoul area, Korea
Scarborough Risk and reward: Pipes and sinkholes in East Tennessee
El-Nahhas Geotechnical aspects of controlling groundwater levels in urban areas
Iegupov et al. Geological hazards during construction and operation of shallow subway stations and tunnels by the example of the Kharkiv Metro (1968–2018)
CN103696438A (en) Double-amplitude type hybrid construction method for underground engineering
Tian et al. Influence of underground engineering on surrounding water environment in sedimentary rock distribution area and its treatment principle
Huang et al. Identification and Treatment of Collapse and Mud Inrush Caused by Deep Karst Trough in Tunnels
Aye et al. Diaphragm wall support deep-excavations for underground space in Bangkok subsoil
Zhang et al. Study on deep and large foundation pit of a national first-class key tomb protection project

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant