CN103577898A CN201310576271.7A CN201310576271A CN103577898A CN 103577898 A CN103577898 A CN 103577898A CN 201310576271 A CN201310576271 A CN 201310576271A CN 103577898 A CN103577898 A CN 103577898A
Authority
CN
China
Prior art keywords
load
user
function
controlled
load control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310576271.7A
Other languages
Chinese (zh)
Other versions
CN103577898B (en
Inventor
王风雨
刘隽
谢迎新
刘茵
张宇
柳劲松
方陈
伍亮
刘超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Shanghai Electric Power Co Ltd
Beijing Guodiantong Network Technology Co Ltd
Beijing Zhongdian Feihua Communication Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Shanghai Electric Power Co Ltd
Beijing Guodiantong Network Technology Co Ltd
Beijing Fibrlink Communications Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Shanghai Electric Power Co Ltd, Beijing Guodiantong Network Technology Co Ltd, Beijing Fibrlink Communications Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310576271.7A priority Critical patent/CN103577898B/en
Publication of CN103577898A publication Critical patent/CN103577898A/en
Application granted granted Critical
Publication of CN103577898B publication Critical patent/CN103577898B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a load control distribution method and system of the electric power industry. The load control distribution method of the electric power industry comprises the steps of (1) obtaining the load control priority sequence and the total load control quantity of a supply side, determining that a load control mode with the maximum priority serves as a current load control mode, and determining that the total load control quantity serves as the current total load control quantity; (2) determining users with the load control modes same as the current load control mode to serve as current alternative users according to preset screening conditions; (3) determining a target user from the current alternative users according to preset constraint conditions by using preset optimizing distribution functions which comprise a power grid loss revenue function, a user influenced range function and/or a load control effectiveness function when the sum of the load control quantities of the current alternative users is larger than or equal to the current total load control quantity. The load control distribution method of the electric power industry achieves the purposes that the power grid loss revenue is as low as possible, the number of influenced users is as small as possible, and/or load control effectiveness is as high as possible according to the load control priority sequence under the condition that the total load control quantity and the constraint conditions are met.

Description

A kind of load of power industry is controlled distribution method and system
Technical field
The application relates to power industry, and especially a kind of load of power industry is controlled distribution method and system.
Background technology
China in Recent Years rapid economic development, electricity needs is sustainable growth thereupon also, and electricity supply and demand contradiction is increasingly serious, and especially, in peak of power consumption period, electric power supply breach is increasing.Alleviating one of method with Voltage force is that user participates in the load control project that supply side is formulated.It is that user cuts down power consumption or the electricity consumption period is shifted that user participates in load control, and being equivalent to user provides a kind of electric power resource to electric system, can alleviate power supply shortage.Detailed process is: the load that supply side was created under certain period is controlled total quantity index, and user cuts down power consumption or the transfer electricity consumption period completes described control total quantity index and obtains certain economic compensation.
User participate in mode that load controls have multiple, for example: control that direct load is controlled, interruptible load is controlled and demand is bidded.Supply side can, according to the difference of user's load control mode, generate load and control the selection course that priority is controlled user.In addition, other information that user participates in described load control are also different, as participated in date, participation period, load controlled quentity controlled variable, compensating account form, executive mode etc.Therefore,, when a plurality of users meet load control and participate in condition, if all use is defined as to final participating user per family, not only strengthened the coverage to user's productive life, and lost more electrical network income.So the described load that need to generate according to supply side is controlled priority, generates the optimal distributing scheme that load is controlled total quantity index in a plurality of participating users.
Summary of the invention
In view of this, the application provides a kind of load of power industry to control distribution method and system, in order to the described load generating according to supply side, controls priority, generates the optimal distributing scheme that load is controlled total quantity index in a plurality of participating users.The application's technical scheme is as follows:
Load control a distribution method, comprising:
Obtain load control priority and load control total amount that supply side generates, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload;
According to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Wherein, described current alternative user is a plurality of;
Obtain the described corresponding load controlled quentity controlled variable of each current alternative user;
When described each load controlled quentity controlled variable sum is more than or equal to describedly when preload is controlled total amount, according to default constraint condition, apply default optimization partition function, definite targeted customer in described each current alternative user; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
Preferably, also comprise:
When described each load controlled quentity controlled variable sum is less than, describedly when preload is controlled total amount, described each current alternative user is defined as to targeted customer, according to described load, controls the definite preload control mode of working as of priority;
Judge whether to exist when preload control mode, if, by described value deducting after described each load controlled quentity controlled variable sum when preload control total amount, as the new preload of working as, control total amount, and return and carry out according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described;
If not, all described targeted customer who determines is merged into final targeted customer.
Preferably, described basis is preset screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described, comprising:
Using with described when identical each user of preload control mode is as current elementary alternative user;
Obtain load control time, load control notice time that supply side generates;
Whether described each the current elementary alternative user of judgement meets default screening conditions successively, if so, described current elementary alternative user is defined as to current alternative user; Wherein, described default screening conditions are: load that described load control time comprises described current elementary alternative user is controlled the time period on date, and described load control the notice time early than or equal notice time of described current elementary alternative user.
Preferably, described default constraint condition comprises load power ratio control constraint condition and electric power safety operation constraint condition:
Describedly be more than or equal to describedly when preload is controlled total amount when described each load controlled quentity controlled variable sum, according to default constraint condition, apply default optimization partition function, definite targeted customer in described each current alternative user, comprising:
If each current alternative user meets load power ratio control constraint condition and electric power safety operation constraint condition simultaneously, the algorithm according to default, utilizes default optimization partition function to obtain the set of described each functional value of optimization partition function; Wherein: described load power ratio control constraint condition is: current alternative user's load controlled quentity controlled variable sum is more than or equal to when preload control total amount; Described electric power safety operation constraint condition is: the load controlled quentity controlled variable sum of current alternative user in load control time is less than or equal to the electric power decline upper limit default in the described period, and the in the situation that of changing load, the load controlled quentity controlled variable of current alternative user in the time period after changing load is more than or equal to electric power default in the time period after described change increases the upper limit;
Determine the minimum value in described optimization partition function value set;
Described each the alternative user who makes described optimization partition function obtain minimum value is defined as to targeted customer.
Preferably, when described optimization partition function comprises that grid loss revenue function, the influenced range function of user and load are controlled Validity Function, when described each load controlled quentity controlled variable sum, be more than or equal to described when preload is controlled total amount, according to default constraint condition, apply default optimization partition function, determine targeted customer in described each current alternative user before, also comprise:
Obtain respectively the weight coefficient of described grid loss revenue function, the weight coefficient of the influenced range function of user and load are controlled the weight coefficient of Validity Function; Wherein: described three weight coefficients add up to 1, the receivable electric money that described grid loss revenue function reduces for load control time adds the load control and compensation amount of money, the influenced range function of described user is controlled user's number addition for participating in load, described load is controlled Validity Function and is added for participating in load control user's credit worthiness;
When the alternative user in described alternative user's set meets load power ratio control constraint condition and electric power safety operation constraint condition simultaneously, according to preset algorithm, minimum value and maximal value when the minimum value while calculating respectively described in each minimum value when alternative user applies described grid loss revenue function and maximal value, the influenced range function of the described user of application and maximal value, the described load of application are controlled Validity Function;
According to described grid loss revenue function, the influenced range function of user and load, control Validity Function weight coefficient and maximal value separately and minimum value separately, set up and optimize partition function.
Preferably, after described method, also comprise:
Generate described each targeted customer's who participates in described load control information table; Wherein, in described information table, at least comprise with the next item down or several information: the device name of user ID, user's name, station address, user's contact method, participation, load control mode, load controlled quentity controlled variable, load are controlled notice time, load control time, the amount of compensation;
According to described information table, to described each targeted customer, send the load control information that comprises load control time, load controlled quentity controlled variable;
The actual execution information of loading and controlling according to described each targeted customer of receiving, upgrades participated in number of times and the credit worthiness of each targeted customer described in described load resources bank; Wherein, described actual execution information comprises the actual execution period that described each targeted customer's load is controlled actual execution amount and loaded and control.
Load control a distribution system, comprising:
Determine when precondition unit, the load control priority and the load control total amount that for obtaining supply side, generate, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload;
Determine alternative subscriber unit, for according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Wherein, described current alternative user is a plurality of;
Obtain user's controlled quentity controlled variable unit, for obtaining the described corresponding load controlled quentity controlled variable of each current alternative user;
Determine target subscriber units, described when preload is controlled total amount for being more than or equal to when described each load controlled quentity controlled variable sum, according to default constraint condition, apply default optimization partition function, in described each current alternative user, determine targeted customer; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
Preferably, also comprise:
Redefine when precondition unit, described in being less than for controlled quentity controlled variable sum of loading when described each, when preload is controlled total amount, described each current alternative user is defined as to targeted customer, according to described load, control the definite preload control mode of working as of priority;
Judging unit, for judging whether to exist when preload control mode;
The first judged result unit, for new during when preload control mode when existing, by described value deducting after described each load controlled quentity controlled variable sum when preload control total amount, as the new preload of working as, control total amount, and return and carry out according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described;
The second judged result unit, for new during when preload control mode when not existing, merges into final targeted customer by all described targeted customer who determines.
Preferably, described definite alternative subscriber unit comprises:
First determines subelement, for using with described when identical each user of preload control mode is as current elementary alternative user;
First obtains subelement, the load control time, the load control notice time that for obtaining supply side, generate;
Second determines subelement, for judging that successively whether described each current elementary alternative user meets default screening conditions, is if so, defined as current alternative user by described current elementary alternative user; Wherein, described default screening conditions are: load that described load control time comprises described current elementary alternative user is controlled the time period on date, and described load control the notice time early than or equal notice time of described current elementary alternative user.
Preferably, described default constraint condition comprises load power ratio control constraint condition and electric power safety operation constraint condition, and described definite target subscriber units comprises:
Obtain functional value set subelement, if meet load power ratio control constraint condition and electric power safety operation constraint condition for each current alternative user simultaneously, algorithm according to default, utilizes default optimization partition function to obtain the set of described each functional value of optimization partition function; Wherein: described load power ratio control constraint condition is: current alternative user's load controlled quentity controlled variable sum is more than or equal to when preload control total amount; Described electric power safety operation constraint condition is: the load controlled quentity controlled variable sum of current alternative user in load control time is less than or equal to the electric power decline upper limit default in the described period, and the in the situation that of changing load, the load controlled quentity controlled variable of current alternative user in the time period after changing load is more than or equal to electric power default in the time period after described change increases the upper limit;
Determine minimum value subelement, for determining the minimum value of described optimization partition function value set;
Determine targeted customer's subelement, for described each the alternative user who makes described optimization partition function obtain minimum value is defined as to targeted customer.
Preferably, when described optimization partition function comprises that grid loss revenue function, the influenced range function of user and load are controlled Validity Function, also comprise;
Obtain weight coefficient unit, for obtaining respectively the weight coefficient of described grid loss revenue function, the weight coefficient of the influenced range function of user and load are controlled the weight coefficient of Validity Function; Wherein: described three weight coefficients add up to 1, the receivable electric money that described grid loss revenue function reduces for load control time adds the load control and compensation amount of money, the influenced range function of described user is controlled user's number addition for participating in load, described load is controlled Validity Function and is added for participating in load control user's credit worthiness;
Calculate value cell, while meeting load power ratio control constraint condition and electric power safety operation constraint condition for the alternative user when described alternative user's set simultaneously, according to preset algorithm, minimum value and maximal value when the minimum value while calculating respectively described in each minimum value when alternative user applies described grid loss revenue function and maximal value, the influenced range function of the described user of application and maximal value, the described load of application are controlled Validity Function;
Set up function unit, for controlling Validity Function weight coefficient and maximal value separately and minimum value separately according to described grid loss revenue function, the influenced range function of user and load, set up optimization partition function.
Preferably, also comprise:
Information generated table unit, for generating described each targeted customer's who participates in described load control information table; Wherein, in described information table, at least comprise with the next item down or several information: the device name of user ID, user's name, station address, user's contact method, participation, load control mode, load controlled quentity controlled variable, load are controlled notice time, load control time, the amount of compensation;
Send message unit, for according to described information table, to described each targeted customer, send the load control information that comprises load control time, load controlled quentity controlled variable;
Updating block, for the actual execution information of loading and controlling according to described each targeted customer of receiving, upgrades participated in number of times and the credit worthiness of each targeted customer described in described load resources bank; Wherein, described actual execution information comprise described each targeted customer load control the actual execution period that actual execution amount and load are controlled.
From above technical scheme, the application provides a kind of load of power industry to control distribution method and system, this comprises: obtain load control priority and load control total amount that supply side generates, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload; According to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Obtain the described corresponding load controlled quentity controlled variable of each current alternative user; When described each load controlled quentity controlled variable sum is more than or equal to describedly when preload is controlled total amount, according to default constraint condition, apply default optimization partition function, definite targeted customer in described each current alternative user; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.As can be seen here, this method is by determining alternative user in the user who is limit priority in load control mode, because user's number is when more than enough, the user that load control mode is limit priority is also abundant, the alternative user who determines also enough meets the condition that load is controlled total amount, in described alternative user, utilize to optimize partition function and determine and participate in the targeted customer (one or more) that load is controlled, complete and described load is controlled to index total amount distribute to targeted customer described in each.Wherein, described optimization partition function can be the one or more combination in grid loss revenue function, the influenced range function of user, load control Validity Function, thereby can load to be controlled priority and load is controlled under the prerequisite of total amount meeting, the load of realize simultaneously and try one's best supply side grid loss income little, try one's best the influenced scope of little user, trying one's best high is controlled one or more in three optimization aim of validity.
Accompanying drawing explanation
In order to be illustrated more clearly in the technical scheme in the embodiment of the present application, below the accompanying drawing of required use during embodiment is described is briefly described, apparently, accompanying drawing in the following describes is only some embodiment of the application, for those of ordinary skills, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
A kind of power industry load that Fig. 1 provides for the application is controlled the process flow diagram of distribution method embodiment mono-;
A kind of power industry load that Fig. 2 provides for the application is controlled the process flow diagram of distribution method embodiment bis-;
A kind of power industry load that Fig. 3 provides for the application is controlled the part process flow diagram of distribution method embodiment tri-;
A kind of power industry load that Fig. 4 provides for the application is controlled the part process flow diagram of distribution method embodiment tetra-;
A kind of power industry load that Fig. 5 provides for the application is controlled the part process flow diagram of distribution method embodiment five;
A kind of power industry load that Fig. 6 provides for the application is controlled the part process flow diagram of distribution method embodiment six;
A kind of power industry load that Fig. 7 provides for the application is controlled the structural representation of distribution system embodiment seven;
A kind of power industry load that Fig. 8 provides for the application is controlled the structural representation of distribution method embodiment eight;
A kind of power industry load that Fig. 9 provides for the application is controlled the part-structure schematic diagram of distribution method embodiment nine;
A kind of power industry load that Figure 10 provides for the application is controlled the part-structure schematic diagram of distribution method embodiment ten;
A kind of power industry load that Figure 11 provides for the application is controlled the part-structure schematic diagram of distribution method embodiment 11;
A kind of power industry load that Figure 12 provides for the application is controlled the part-structure schematic diagram of distribution method embodiment 12.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present application, the technical scheme in the embodiment of the present application is clearly and completely described, obviously, described embodiment is only the application's part embodiment, rather than whole embodiment.Embodiment based in the application, those of ordinary skills are not making the every other embodiment obtaining under creative work prerequisite, all belong to the scope of the application's protection.
Refer to Fig. 1, a kind of power industry load that it shows the application provides is controlled the process flow diagram of distribution method embodiment mono-, and the present embodiment can comprise:
Step 101: obtain load control priority and load control total amount that supply side generates, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload.
User participate in loading control item object mode can have multiple, for example: control that direct load is controlled, interruptible load is controlled and demand is bidded.Certainly, described load control mode, including but not limited to above-mentioned one or more modes, is used the load control form of electric power all in the application's protection domain so long as can be used for cutting down user's side load equipment.
Supply side can assumed load control mode according to power shortage situation priority, it is any one in described load control mode permutation and combination result that described load is controlled priority, for preferentially choosing the user with certain load control mode.According to described priority, the highest load control mode of priority is defined as when preload control mode, in order to choose there is described load control mode user as alternative user.For example, direct load control mode is made as to A, interruptible load control mode is made as to B, the demand control mode of bidding is made as to C, described load is controlled priority and be can be CBA, chooses C and is demand and bid control mode for when preload control mode.
When there is the situation of power supply shortage, in order to alleviate with Voltage force, supply side generates the demand of loading and controlling, and wherein, includes load and controls total amount, in order to represent described electric power breach situation in described demand.For example, 1000 watts.Described load is controlled to total amount to be defined as controlling total amount when preload.
Step 102: according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Wherein, described current alternative user is a plurality of.
User participates in described load and controls project, need apply in advance, and submit to the described load of participation to control required information to supply side.Described informational needs is preserved, and the form of preservation can have multiple.Preferably, set up in advance load resources bank, the load control information that includes user in described load resources bank, described load control information includes but not limited to the following: the device name of user ID, user's name, station address, user's contact method, participation, load control mode, load controlled quentity controlled variable, the from date of participation, the date of expiry of participation, notice time, carry out duration, compensation account form, penalty for nonperformance of contract account form, can participate in number of times, credit worthiness, participation period and/or participation method.
From described load resources bank, obtain successively each user's load control mode, choose with described when the identical user of preload control mode is as current alternative user.For example, when preload control mode is the demand control mode of bidding, choosing load control mode and be the bid user of control mode of demand is current alternative user, and described alternative user's number is a plurality of, for example: described alternative user is 100.
Step 103: obtain the described corresponding load controlled quentity controlled variable of each current alternative user.
In described load resources bank, obtain the described corresponding load controlled quentity controlled variable of each current alternative user, for example: 100 current alternative users are user 1,2,3 ... 100, obtain successively described user 1 to 100 load controlled quentity controlled variable separately, if user 1 load controlled quentity controlled variable is 10 watts, user 2 load controlled quentity controlled variable is 20 watts.
Step 104: when described each load controlled quentity controlled variable sum is more than or equal to describedly when preload is controlled total amount, according to default constraint condition, apply default optimization partition function, definite targeted customer in described each current alternative user; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
Each the current alternative user's who obtains in step 103 load controlled quentity controlled variable sum is more than or equal to described when preload is controlled total amount, for example, described current alternative user's 1 to 100 load controlled quentity controlled variable sum is 2000 watts, described when preload, to control total amount be 1000 watts, and in described each current alternative user, select target user is used for participating in described load and controls project.
Described default constraint condition can be the constraint condition generating according to the load controlled quentity controlled variable of supply side generation and safe operation of electric network situation, comprises load power ratio control constraint condition and electric power safety operation constraint condition.Wherein, described load power ratio control constraint condition refers to that customer charge controlled quentity controlled variable sum meets load and controls total amount requirement; The constraint condition of described electric power safety operation, the electric weight that finger user cuts down in load control time will meet the safety requirements of electric power slippage, if in the situation that user carries out translation or transfer by the electricity consumption period, the electric weight that the period user in translation or after shifting increases also will meet translation or shift the safety requirements of rear corresponding electric power recruitment.Described electric power safety operation constraint condition is in order to guarantee grid equipment safety, as line security.
According to optimizing partition function, utilize default algorithm, as enumeration, genetic algorithm etc., described alternative user, concentrate and determine targeted customer.Certainly, described preset algorithm is not limited to the above-mentioned algorithm of enumerating, so long as can be at the algorithm of alternative concentrated select target value all in the protection domain in the application.
It should be noted that, optimizing partition function can be one or more in grid loss revenue function, the influenced range function of user, load control Validity Function.When described majorized function is grid loss revenue function, the alternative user when making grid loss income be minimum value is defined as targeted customer.When described majorized function is the influenced range function of user, the alternative user when making the influenced scope of user be minimum value is defined as targeted customer.When described majorized function is controlled Validity Function for load, by making load control the alternative user of validity preferably time, be defined as targeted customer.Wherein, described load control Validity Function be user credit worthiness and value, described load is controlled the credit worthiness sum maximum that validity preferably refers to user.Certainly, described alternative user comes from the alternative user who determines in described step S102.
When described optimization partition function comprises that grid loss revenue function, the influenced range function of user, load are controlled Validity Function simultaneously, described optimization partition function is multiple objective function, described grid loss revenue function, the influenced range function of user, load are controlled Validity Function and are respectively sub-goal, according to the weight coefficient of described three sub-goals that obtain (described three weight coefficients add up to 1), the targeted customer in the time of can obtaining making grid loss income, the influenced scope of user and load control validity account for any weight separately.
As, the weight coefficient of described grid loss income is 0.8, the weight coefficient of the influenced scope of user is 0.1, the weight coefficient that load is controlled validity is 0.1, the targeted customer who determines according to described weight coefficient, can realize and consider a little, on the basis of the influenced scope of user and load control validity, to guarantee that grid loss income is as far as possible few.
For another, the weight coefficient of described grid loss income is 0.1, the weight coefficient of the influenced scope of user is 0.8, the weight coefficient that load is controlled validity is 0.1, the targeted customer who determines according to described weight coefficient, can realize and consider a little, on the basis of grid loss income and load control validity, to guarantee that user's participation number is as far as possible few.
And for example, the weight coefficient of described grid loss income is 0.1, the weight coefficient of the influenced scope of user is 0.1, the weight coefficient that load is controlled validity is 0.8, the targeted customer who determines according to described weight coefficient, can realize on the basis of participation number of considering a little grid loss income and user, the control validity that guarantees to load is tried one's best.
For another example, the weight coefficient of described grid loss income is 0.3, the weight coefficient of the influenced scope of user is 0.3, the weight coefficient that load is controlled validity is 0.4, the targeted customer who determines according to described weight coefficient can guarantee the grid loss income of trying one's best few, the influenced scope of few user of trying one's best and to the greatest extent measured load control validity simultaneously.
It should be noted that, described each weight coefficient can be default fixed value, can be also the input value of obtaining.When being the input value of obtaining, can realizing according to different demands different optimization and distribute target.
From above technical scheme, the present embodiment provides a kind of load of power industry to control distribution method, the method comprises, obtain load control priority and load control total amount that supply side generates, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload; According to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Obtain the described corresponding load controlled quentity controlled variable of each current alternative user; When described each load controlled quentity controlled variable sum is more than or equal to describedly when preload is controlled total amount, according to default constraint condition, apply default optimization partition function, definite targeted customer in described each current alternative user; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
Because user's number is when more than enough, the user that load control mode is limit priority is also abundant, the alternative user who determines also enough meets the condition that load is controlled total amount, described a plurality of alternative user can jointly participate in described load and control project, if but common participation can cause user in a big way influenced, and cause electrical network income to be subject to larger loss due to participating user is compensated.Wherein, described optimization partition function can be the one or more combination in grid loss revenue function, the influenced range function of user, load control Validity Function, thereby can control under the prerequisite of total amount and load control security meeting load, the load of realize simultaneously and try one's best supply side grid loss income little, try one's best the influenced scope of little user, trying one's best high is controlled three of validity and is optimized one or more in sub-goals.
In addition, when majorized function target comprises a plurality of sub-goal, by obtaining the weight coefficient value of each sub-goal of input, according to different actual demands, set up different optimization partition functions.Utilize described each different optimization partition function to realize different optimization aim, realize load and control the dirigibility that distributes target.
When if power tense situation is severeer, it is larger that the load that supply side generates is controlled total amount, the current alternative user in embodiment mono-is not enough to meet the requirement that described load is controlled total amount, needs to control priority according to described load and determines each targeted customer that the described load of participation is controlled.Refer to Fig. 2, a kind of power industry load that it shows the application provides is controlled the process flow diagram of distribution method embodiment bis-, and the present embodiment can comprise:
Step S201: obtain load control priority and load control total amount that supply side generates, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload.
Step S202: according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Wherein, described current alternative user is a plurality of.
Step S203: obtain the described corresponding load controlled quentity controlled variable of each current alternative user.
Described step S201 to S203 is identical with the step S101 to S103 in embodiment mono-, at this, does not repeat.
Step S204: whether described each load controlled quentity controlled variable sum of judgement is more than or equal to the described preload of working as is controlled total amount.
The corresponding load controlled quentity controlled variable of each current alternative user of determining in obtaining step S203, by described each addition acquisition of load controlled quentity controlled variable and value, whether judgement is described is more than or equal to when preload control total amount with value.Described addition calculation mode can be: load is controlled to being divided into for 24 hours of the same day a plurality of equal time of section, the load controlled quentity controlled variable of described load being controlled to total amount and user represents with discrete-time series respectively, calculates the load controlled quentity controlled variable sum of each user in the discrete time section corresponding with described load control time.
It should be noted that, described load controls total amount and load controlled quentity controlled variable can be understood as each discrete time section internal loading control total amount and load controlled quentity controlled variable.For example, load control time be on November 12nd, 2013 the load controlled quentity controlled variable of 11:00 to 13:00 be 1000 watts, as shown in table 1, will be divided into 48 periods on November 12nd, 1, the described time period is that load in 23 to 26 control total amount is 1000 watts; Three current alternative user C1, the C2 that demand bids that load comprises under control mode and the load controlled quentity controlled variable of C3 are respectively 100 watts, 150 watts and 200 watts, as shown in table 2, current alternative user C1, C2 and C3 are that the load controlled quentity controlled variable of each time period of 23 to 26 is 100 watts, 150 watts and 200 watts respectively at t.Certainly, described three current alternative user C1, C2 and C3 are just for giving an example, and described alternative user can comprise a plurality of.
Figure BDA0000416094140000141
Table 1
Figure BDA0000416094140000142
Table 2
For example: by load control the same day within 24 hours, be divided into 48 equal time section, every 30 minutes is a time period.Accordingly, by control the load that total amount is expressed as in described 48 time periods when preload, control component combination, i.e. ExeLoad={EP (1) ..., EP (t) ... EP (48) }.Wherein: described ExeLoad is for controlling total amount when preload; Described t is certain time period in 1-48 time period; Described EP (t) is that the load of t in the time period controlled component.If t belongs to described load control time section, EP (t) equals to load accordingly controlled quentity controlled variable, otherwise EP (t) equals 0.:
In direct load control mode user, i user's load controlled quentity controlled variable can be characterized by Load DLC i = { P DLC i ( 1 ) , . . . , P DLC i ( t ) . . . P DLC i ( 48 ) } , Wherein: described in
Figure BDA0000416094140000144
load controlled quentity controlled variable for i user; Described t is certain time period in 1-48 time period; Described
Figure BDA0000416094140000145
for the load of t in the time period controlled component.If t belongs to described load control time section,
Figure BDA0000416094140000146
equal corresponding load controlled quentity controlled variable value (represent to cut down or consume by sign, cut down load for just, consume load for negative), otherwise
In interruptible load control mode user, i user's load controlled quentity controlled variable can be characterized by Load IL i = { P IL i ( 1 ) , . . . , P IL i ( t ) . . . P IL i ( 48 ) } , Wherein: described in load controlled quentity controlled variable for i user; Described t is certain time period in 1-48 time period; Described for the load of t in the time period controlled component.If t belongs to described load control time section,
Figure BDA00004160941400001411
equal corresponding load controlled quentity controlled variable value (represent to cut down or consume by sign, cut down load for just, consume load for negative), otherwise
Figure BDA00004160941400001412
Demand i user's the load controlled quentity controlled variable in control mode user of bidding can be characterized by Load DSB i = { P DSB i ( 1 ) , . . . , P DSB i ( t ) . . . P DSB i ( 48 ) } , Wherein: described in
Figure BDA0000416094140000152
load controlled quentity controlled variable for i user; Described t is certain time period in 1-48 time period; Described
Figure BDA0000416094140000153
for the load of t in the time period controlled component.If t belongs to described load control time section,
Figure BDA0000416094140000154
equal corresponding load controlled quentity controlled variable value (represent to cut down or consume by sign, cut down load for just, consume load for negative), otherwise
Figure BDA0000416094140000155
If in described step S201, determine when preload control mode be the demand load control mode of bidding, the corresponding load controlled quentity controlled variable of each current alternative user that the demand of obtaining is bidded and loaded under control mode, whether described each load controlled quentity controlled variable sum of judgement is more than or equal to the described preload of working as is controlled total amount.After each current alternative user that demand is bidded under control mode levies by above-mentioned time series table, judgment rule is:
Σ i = 1 N DSB _ act P i ( t ) ≥ EP ( t ) , t = 1,2 . . . 48 , Wherein: described in
Figure BDA0000416094140000157
for demand load each current alternative user under control mode each load controlled quentity controlled variable sum in the t time period of bidding; Described EP (t) is that the load of t time period is controlled total amount.
Table 1 for example, t is that to control total amount EP (t) be 1000 watts to 23 o'clock loads.Table 2 for example, t is that the load controlled quentity controlled variable of 23 o'clock current alternative user C1, C2 and C3 is respectively 100 watts, 150 watts and 200 watts, each current alternative user is in each load controlled quentity controlled variable sum of t time period
Figure BDA0000416094140000158
for 450 watts of 100+150+200.Therefore, t is 23 o'clock, and described judgment rule is also false, and represents describedly to judge whether each load controlled quentity controlled variable sum is more than or equal to that described the determination result is NO when preload is controlled total amount.If by t in table 1 be 23 o'clock loads to control total amount EP (t) be 300 watts, described judgment rule is set up, and represents describedly to judge whether each load controlled quentity controlled variable sum is more than or equal to and describedly when preload, control judgment result is that of total amount and be.
Step S205: if so,, according to default constraint condition, apply default optimization partition function, determine in described each current alternative user and targeted customer enter step S209; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
It should be noted that, the step S104 in described embodiment mono-is last step of embodiment mono-, and step S205 is identical with the content of step S104, but step S205 following step is step S209.
Step S206: if not, described each current alternative user is defined as to targeted customer, controls priority according to described load and determine when preload control mode.
Load controlled quentity controlled variable sum in each current alternative user in this step is less than or equal to described when preload control total amount,, there is the described alternative user when preload control mode and be not enough to meet the described requirement that preload is controlled total amount of working as, described each current alternative use is defined as per family finally participating in described load control item object targeted customer, and with load controlled quentity controlled variable separately, participates in described load and control project.For example, when preload control mode is that C is the demand control mode of bidding, have demand bid control mode alternative user 1 to 100 each load controlled quentity controlled variable be 5 watts, the controlled quentity controlled variable of loading sum is 500 watts, be less than described when 1000 watts of preload control total amounts, described current alternative user 1 to 100 is all defined as to targeted customer, the load controlled quentity controlled variable of 5 watts is provided separately.
According to the described load obtaining in step S201, control priority load control mode for when preload control mode, for example, it is CBA that described load is controlled priority, when preload control mode is C, new when preload control mode be B; If that work as preload control mode is A, the new preload control mode of working as is empty.
Step S207: judge whether to exist when preload control mode.
Judge whether to exist when preload control mode, judge whether all users all to screen, in the present embodiment, circulate and choose the end condition of current alternative user procedures.
Step S208: if so, control total amount by described value deducting after described each load controlled quentity controlled variable sum when preload control total amount as the new preload of working as, and enter step S202.
If exist, new when preload control mode, in the user with described new load control mode, select new current alternative user, and according to default optimization partition function, determine targeted customer in described new current alternative user.For example, new when preload control mode be B, it is interruptible load control mode, in described step S204 t be 23 o'clock when preload, to control total amount be 1000 watts, t is that each load controlled quentity controlled variable sum of 23 o'clock is 450 watts, with 1000 watts, deducting 450 watts of surpluses is 550 watts, as new, controls total amount when preload using described remaining 550 watts, and reenters step S202.
Step S209: if not, all described targeted customer who determines is merged into final targeted customer.
If do not exist new for preload control mode, for example, new when preload control mode be empty, represent that circulation chooses described targeted customer's process and meet cut-off condition, each targeted customer definite in described step S205 and step S206 is merged as final targeted customer.
From above technical scheme, the present embodiment provides a kind of power industry load to control distribution method.If when the situation of described supply side power tense is more serious, may generate larger load and control total amount, the control mode that causes loading is the demand that load controlled quentity controlled variable that maximum load is controlled the alternative user of priority can not meet described supply side.The described load generating according to described supply side in the method that the present embodiment provides is controlled priority, the current alternative user who does not meet current load control total amount is defined as to targeted customer, upgrade described when preload control mode, and in thering is the alternative user of new current control mode, determine targeted customer, until do not exist new load control mode or described current alternative user's load controlled quentity controlled variable sum to be enough to meet when the requirement of preload control total amount, thereby at supply side, generate larger during when load control total amount, provide a kind of load to control allocative decision, the targeted customer who determines participates in described load and controls project.
Refer to Fig. 3, a kind of power industry load that it shows the application provides is controlled the part process flow diagram of distribution method embodiment tri-, and the step S102 in described embodiment mono-or the step S202 in embodiment bis-can comprise:
Step S301: using with described when identical each user of preload control mode is as current elementary alternative user;
In the load resources bank of setting up, obtain described each user's load control mode, using the user identical with described load control mode as current elementary alternative user in described step S102.For example, load includes user 1 to 1000 in resources bank, described when preload control mode be the demand control of bidding, user 1 to 150 load control mode is the demand control of bidding, using described user 1 to 150 as current elementary alternative user.
Step S302: obtain load control time, load control notice time that supply side generates;
The load demand for control that supply side generates needs user's change power mode within certain period of user's side, and as interrupted electricity consumption or using other power supply modes instead, described certain period is load control time.In described demand, including but not limited to load control time, load, control notice time and three information of load control total amount, wherein, described load control time is certain period in certain day, as 11:00 to 14:00 on November 12nd, 2013; It is prior notice user's time that described load is controlled the notice time, and as shifted to an earlier date 2 hours ' notice users, the described load control notice time is 9:00 on November 12nd, 2013.
Step S303: whether described each the current elementary alternative user of judgement meets default screening conditions successively, if so, described current elementary alternative user is defined as to current alternative user; Wherein, described default screening conditions are: load that described load control time comprises described current elementary alternative user is controlled the time period on date, and described load control the notice time early than or equal notice time of described current elementary alternative user.
According to the described load control time obtaining in step S302, described load is controlled the notice time, at described load, control and in resources bank, obtain current elementary alternative user's load described in each and control time period on date (from date and the load control time section in the date of expiry, on Dec 1,1 day to 2013 October in 2013 for example, every day 10:00 to 15:00) and load control the notice time, respectively with step S302 in the described load control time that obtains and load control the notice time and compare, find out in load control date range and comprise described load control time, and the notice time is later than the user that described load is controlled the notice time, using described current elementary alternative user as current alternative user.Certainly, described current alternative user's participated in number of times meets and is greater than 0 requirement simultaneously.
For example, the described load control time obtaining in step S302 is 11:00 to 14:00 on November 12nd, 2013, it is within 2 hours, to be 9:00 on November 12nd, 2013 that described load is controlled the notice time, in described current elementary alternative user, certain user's the load control time period on date is the 10:00 to 15:00 of 1, every day of 1 day to 2013 on Dec July in 2013, the notice time is within 1 hour, to be 10:00 on November 12nd, 2013, and can participate in number of times is 2, and this user can be confirmed as current alternative user.
Default constraint condition in step S205 in step S104 in embodiment mono-or embodiment bis-comprises load power ratio control constraint condition and electric power safety operation constraint condition, refer to Fig. 4, a kind of power industry load that it shows the application provides is controlled the part process flow diagram of distribution method embodiment tetra-, and the step S205 in the step S104 in embodiment mono-or embodiment bis-can comprise:
Step S401: if each current alternative user meets load power ratio control constraint condition and electric power safety operation constraint condition simultaneously, the algorithm according to default, utilizes default optimization partition function to obtain the set of described each functional value of optimization partition function; Wherein: described load power ratio control constraint condition is: current alternative user's load controlled quentity controlled variable sum is more than or equal to when preload control total amount; Described electric power safety operation constraint condition is: the load controlled quentity controlled variable sum of current alternative user in load control time is less than or equal to the electric power decline upper limit default in the described period, and the in the situation that of changing load, the load controlled quentity controlled variable of current alternative user in the time period after changing load is more than or equal to electric power default in the time period after described change increases the upper limit;
Use the load controlled quentity controlled variable that represents load control total amount, various load control mode users in embodiment bis-step S204 with discrete-time series.Described load power ratio control constraint condition can be expressed as:
Σ i = 1 N act x i p i ( t ) ≥ EP ( t ) , t = 1,2 . . . 48 , Wherein: described in for each current alternative customer charge controlled quentity controlled variable sum, described EP (t) is load control total amount.
Described electric power safety operation constraint condition can be expressed as: the first constraint condition, or, the first constraint condition and the second constraint condition, wherein:
The first constraint condition is: Σ i = 1 N act x i p i ( t ) ≤ p down _ lim ( t ) , t = 1,2 . . . 48 , t=1,2,…,48;
The second constraint condition is: Σ i = 1 N act x i p i ( t ) ≥ - p up _ lim ( t ) , t = 1,2 . . . 48 , t=1,2,…,48。
Wherein: described in
Figure BDA0000416094140000195
for the load controlled quentity controlled variable sum of each alternative user within certain time period; Described p down_lim(t) be the upper limit of supply side electric power slippage in certain period that requirement is set according to power grid security; Described p down_lim(t) be the upper limit of supply side electric power recruitment in certain time period that requirement is set according to power grid security.
It should be noted that, the use prerequisite of described the second constraint condition is: the load in described current alternative user's load control mode is controlled the situation that has changing load, and described current alternative user's interaction mode is load translation or load transfer.Described load translation refers to electric weight that user control to cut down integral load control time internal loading in advance or delays use.As, load control time is 11:00 to 14:00, user cuts down power consumption within this period, and makes power consumption at 15:00 to 18:00.Described load shifts and refers to that user controls the load in certain a period of time in load control time the electric weight cut down in advance or delays use.As, load control time is 11:00 to 14:00, user cuts down power consumption at 11:00 to 14:00 in the period, and makes power consumption at 15:00 to 16:00.Setting described the second constraint condition is in order to prevent that the unexpected increase of electric weight from too much causing the impaired problem of grid equipment, guarantees electric power safety operation.Certainly, if current alternative user's load is controlled interaction mode, be not that described load translation or load shift, do not need to use described the second constraint condition.
Use any one in each optimization partition function in embodiment mono-step S104, utilize preset algorithm, the current alternative user who determines in step S102 in embodiment mono-or embodiment bis-step S202 be take to a plurality of forms as a group and put into the optimization partition function of use, obtain the set of optimizing partition function value.
It should be noted that, described preset algorithm can be enumeration, genetic algorithm etc., and certainly, described preset algorithm is not limited to the above-mentioned algorithm of enumerating, so long as can be at the algorithm of alternative concentrated select target value all in the protection domain in the application.
Step S402: determine the minimum value in described optimization partition function value set;
In the set of the optimization partition function value obtaining, determine minimum value from described step S401.For example, described optimization partition function value set be 100,200,300}, by 100, be defined as minimum value.
Step S403: described each the alternative user who makes described optimization partition function obtain minimum value is defined as to targeted customer.
Record in described step S401 and make described optimization partition function obtain described each current alternative user of minimum value, described each current alternative user is defined as to targeted customer, in order to realize the reduction of power consumption in load control.For example, minimum value definite in step 302 is 100, and making the current alternative user of described optimization partition function acquisition value 100 is C1 and C2, described C1 and C2 is defined as to targeted customer.
When load, controlling what in assigning process, use is multiple-objection optimization partition function, as: as described in optimization partition function while comprising that grid loss revenue function, the influenced range function of user and load are controlled Validity Function, that is:
MutiTotal = α · LosProfit - LosProfit _ min LosProfit _ max - LosProfit _ min + β · Num - Num _ min Num _ max - Num _ min + γ · Relia - Relia _ min Relia _ max - Relia _ min
Wherein: described MutiTotal is for optimizing the value of partition function, described min refers to optimize partition function and gets minimum value, described α, β, γ is weight coefficient, described LosProfit is grid loss financial value, described LosProfit_min is the minimum value of grid loss income, described LosProfit_max is the maximal value of grid loss income, described Num is the influenced value range of user, described Num_min is the minimum value of the influenced scope of user, described Num_max is the maximal value of the influenced scope of user, described Relia is load control validity value, described Relia_min is the minimum value of load control validity, described Relia_max is the maximal value of load control validity.
Refer to Fig. 5, a kind of power industry load that it shows the application provides is controlled the part process flow diagram of distribution method embodiment five, before the step S104 of embodiment mono-, can comprise the process of setting up described multiple-objection optimization partition function, is specially:
Step S501: obtain respectively the weight coefficient of described grid loss revenue function, the weight coefficient of the influenced range function of user and load are controlled the weight coefficient of Validity Function; Wherein: described three weight coefficients add up to 1, the receivable electric money that described grid loss revenue function reduces for load control time adds the load control and compensation amount of money, the influenced range function of described user is controlled user's number addition for participating in load, described load is controlled Validity Function and is added for participating in load control user's credit worthiness;
According to using discrete-time series method for expressing in embodiment bis-step S204, it is as follows respectively that described network loss is lost revenue function, the influenced range function of user and load control Validity Function:
LosProfit = Σ i = 1 n Σ t = 1 N act x i p i ( t ) · Price i ( t ) · 0.5 + Σ i = 1 n x i · ComPrice i
Num = Σ i = 1 n x i
Relia = - Σ i = 1 n x i · Cred i
Wherein: Price i(t) be the electricity price of user i in the t period; x iwhether representative of consumer i participates in load is controlled, x i=1 represents to participate in, x i=0 represents not participate in; N is the number of users in controllable burden resources bank; For user i in load control resources bank is in the load controlled quentity controlled variable of t period, if p i(t), for just representing to cut down load, be the negative consumption load that represents; ComPrice iby user i participates in load, control the obtainable amount of compensation, the load control mode participating according to each user, compensation unit price, control continue the information such as duration, working control amount and calculate; Cred ifor the credit worthiness that user i participates in, first participant is all set to 1, can according to participating user, at load, control the information such as the fitness of implementation and performance and upgrade.It is pointed out that described Cred ican be the numerical value of 0 to 1.
The influenced range function of grid loss revenue function, user that described multiobject optimization partition function comprises and load are controlled Validity Function and are called as each sub-goal.In multi-objective optimization question, between each sub-goal, be likely restriction and conflicting mutually, thereby generally do not have absolute optimal solution, do not exist and make each sub-goal reach optimum solution simultaneously.It is Zero-one integer programming problem that described multiobject optimization distributes, and has default relation, that is: 0≤α, β, γ >=1 and alpha+beta+γ=1 between weight coefficient.
It should be noted that, the mode of obtaining described three weight coefficients in the present embodiment can be to obtain default weight coefficient, thereby can be also that the weight coefficient realization of obtaining input reaches and optimizes the optimization aim that partition function will be realized according to different actual demands.
Step S502: when the alternative user in described alternative user's set meets load power ratio control constraint condition and electric power safety operation constraint condition simultaneously, according to preset algorithm, minimum value and maximal value when the minimum value while calculating respectively described in each minimum value when alternative user applies described grid loss revenue function and maximal value, the influenced range function of the described user of application and maximal value, the described load of application are controlled Validity Function;
Utilize default algorithm as genetic algorithm, enumeration, the minimum value when minimum value while calculating respectively described in each minimum value when current alternative user applies described grid loss revenue function as 500 yuan and 10000 yuan of maximal values, the described influenced range function of user of application is loaded control Validity Function as 10 and maximal value as 50, application are described as 3.7 and maximal value as 8.7.
Step S503: control Validity Function weight coefficient and maximal value separately and minimum value separately according to described grid loss revenue function, the influenced range function of user and load, set up and optimize partition function.
Determined value using described each maximal value calculating in described step S502 and minimum value as each sub-goal function, is about to function:
MutiTotal = α · LosProfit - LosProfit _ min LosProfit _ max - LosProfit _ min + β · Num - Num _ min Num _ max - Num _ min + γ · Relia - Relia _ min Relia _ max - Relia _ min
In LosProfit_min, LosProfit_max, Num_min, Num_max, Relia_min and Relia_max for the corresponding numerical value of concrete each replace, thereby set up, optimize partition function.
It is to be noted; the method of setting up optimization partition function described in the present embodiment is not only applicable to comprise the optimization partition function of described grid loss revenue function, the influenced range function of user and three functions of load control Validity Function; it is applicable equally when described optimization partition function comprises two or more sub-goal function; therefore the protection domain that, all belongs to the present embodiment.
From above technical scheme, when described optimization aim function is multiple objective function, a kind of power industry load that the application provides is controlled distribution method, by obtaining the weight coefficient value of each sub-goal of input, according to different actual demands, set up different optimization partition functions.Utilize described each different optimization partition function to realize different optimization aim, as the grid loss income of trying one's best few, the influenced scope of few user of trying one's best or to the greatest extent measured load control validity, thereby realize load, control the dirigibility of optimizing distribution target.
Refer to Fig. 6, a kind of power industry load that it shows the application provides is controlled the part process flow diagram of distribution method embodiment six, after the method for embodiment mono-any embodiment in five, can also comprise:
Step S601: the information table that generates described each targeted customer who participates in described load control; Wherein, in described information table, at least comprise with the next item down or several information: the device name of user ID, user's name, station address, user's contact method, participation, load control mode, load controlled quentity controlled variable, load are controlled notice time, load control time, the amount of compensation;
In described load resources bank, obtain device name, load control mode, the load controlled quentity controlled variable of the corresponding user ID of each targeted customer, user's name, station address, user's contact method, participation, obtain described load control time, load control notice time that supply side generates, according to the compensation account form in load resources bank, obtain the amount of compensation, described every terms of information is generated to the corresponding information table of each targeted customer.
For example: targeted customer A: user ID is: No. 2034, user's name is: Panpan Food Co., Ltd, station address is: No. 86, sunlight street, Chaoyang District, Beijing City, user's contact method is: 010-8943087, participation device name is called central air conditioner, load control mode is: demand is bidded, and controlled quentity controlled variable is: 800 watts.
Step S602: according to described information table, send the load control information that comprises load control time, load controlled quentity controlled variable to described each targeted customer;
According to the information table generating in step S601, to each targeted customer, send relative load control information, described load control information include but not limited to load control time, load controlled quentity controlled variable.
For example, the load control information sending to targeted customer C1 is: 11:00 to the 13:00 control of load on November 12nd, 2013, the controlled quentity controlled variable of loading is 50 watts.Certainly, the concrete form of described load control information is not limited to this, as long as can comprise that the arbitrary format of described load control information implication all belongs to the application's protection domain.
Step S603: the actual execution information of loading and controlling according to described each targeted customer of receiving, upgrade participated in number of times and the credit worthiness of each targeted customer described in described load resources bank; Wherein, described execution information comprises the actual execution period that described each targeted customer's load is controlled actual execution amount and loaded and control.
After carrying out complete this load control, supply side can pass through monitoring objective user's execution information, and whether as carried out, load is controlled duration, the execution amount etc. carried out.Receive each targeted customer's that described supply side monitors execution information, and according to described execution information, upgrade described load and control the corresponding information of each targeted customer in resources bank, including but not limited to participating in number of times and credit worthiness.As, can participate in number of times and deduct 1, credit worthiness is reduced to 0.9 or increase to 0.9 by 0.8 by 1.
From above technical scheme, a kind of power industry load that the application provides is controlled distribution method, can be by obtaining described each targeted customer's implementation status, according to described each implementation status, upgrade the information of the corresponding user in described load resources bank, realized the feedback of load control procedure and upgraded.
Refer to Fig. 7, its load that shows a kind of power industry that the application provides is controlled the structural representation of distribution system embodiment seven, the present embodiment can comprise: determines when precondition unit 701, determines alternative subscriber unit 702, obtains user's controlled quentity controlled variable unit 703 and definite target subscriber units 704, wherein:
Described definite when precondition unit 701, the load control priority and the load control total amount that for obtaining supply side, generate, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload;
User participate in loading control item object mode can have multiple, for example: control that direct load is controlled, interruptible load is controlled and demand is bidded.Certainly, described load control mode, including but not limited to above-mentioned one or more modes, is used the load control form of electric power all in the application's protection domain so long as can be used for cutting down user's side load equipment.
Supply side can assumed load control mode according to power shortage situation priority, it is any one in described load control mode permutation and combination result that described load is controlled priority, for preferentially choosing the user with certain load control mode.According to described priority, the highest load control mode of priority is defined as when preload control mode, in order to choose there is described load control mode user as alternative user.For example, direct load control mode is made as to A, interruptible load control mode is made as to B, the demand control mode of bidding is made as to C, described load is controlled priority and be can be CBA, chooses C and is demand and bid control mode for when preload control mode.
When there is the situation of power supply shortage, in order to alleviate with Voltage force, supply side generates the demand of loading and controlling, and wherein, includes load and controls total amount, in order to represent described electric power breach situation in described demand.For example, 1000 watts.Described definite when precondition unit 701 is defined as described load control total amount to control total amount when preload.
Describedly determine alternative subscriber unit 702, for according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Wherein, described current alternative user is a plurality of;
User participates in described load and controls project, need apply in advance, and submit to the described load of participation to control required information to supply side.Described informational needs is preserved, and the form of preservation can have multiple.Preferably, set up in advance load resources bank, the load control information that includes user in described load resources bank, described load control information includes but not limited to the following: the device name of user ID, user's name, station address, user's contact method, participation, load control mode, load controlled quentity controlled variable, the from date of participation, the date of expiry of participation, notice time, carry out duration, compensation account form, penalty for nonperformance of contract account form, can participate in number of times, credit worthiness, participation period and/or participation method.
Describedly determine that alternative subscriber unit 702, from described load resources bank, obtains each user's load control mode successively, choose with described when the identical user of preload control mode is as current alternative user.For example, when preload control mode is the demand control mode of bidding, choosing load control mode and be the bid user of control mode of demand is current alternative user, and described alternative user's number is a plurality of, for example: described alternative user is 100.
The described user's controlled quentity controlled variable unit 703 that obtains, for obtaining the described corresponding load controlled quentity controlled variable of each current alternative user;
The described user's of obtaining controlled quentity controlled variable unit 703 obtains the described corresponding load controlled quentity controlled variable of each current alternative user in described load resources bank, for example: 100 current alternative users are user 1,2,3 ... 100, obtain successively described user 1 to 100 load controlled quentity controlled variable separately, if user 1 load controlled quentity controlled variable is 10 watts, user 2 load controlled quentity controlled variable is 20 watts.
Described definite target subscriber units 704, for being more than or equal to described when preload is controlled total amount when described each load controlled quentity controlled variable sum, according to default constraint condition, apply default optimization partition function, in described each current alternative user, determine targeted customer; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
Each the current alternative user's who obtains when the described user's of obtaining controlled quentity controlled variable unit 703 load controlled quentity controlled variable sum is more than or equal to described when preload control total amount, for example, described current alternative user's 1 to 100 load controlled quentity controlled variable sum is 2000 watts, described when preload, to control total amount be 1000 watts, and described definite target subscriber units 704 select target user in described each current alternative user is used for participating in described load and controls project.
According to optimizing partition function, utilize default algorithm, as enumeration, genetic algorithm etc., described alternative user, concentrate and determine targeted customer.Certainly, described preset algorithm is not limited to the above-mentioned algorithm of enumerating, so long as can be at the algorithm of alternative concentrated select target value all in the protection domain in the application.
It should be noted that, optimizing partition function can be one or more in grid loss revenue function, the influenced range function of user, load control Validity Function.When described majorized function is grid loss revenue function, the alternative user when making grid loss income be minimum value is defined as targeted customer.When described majorized function is the influenced range function of user, the alternative user when making the influenced scope of user be minimum value is defined as targeted customer.When described majorized function is controlled Validity Function for load, by making load control the alternative user of validity preferably time, be defined as targeted customer.Wherein, described load control Validity Function be user credit worthiness and value, described load is controlled the credit worthiness sum maximum that validity preferably refers to user.Certainly, described alternative user comes from the described alternative user who determines that alternative subscriber unit 702 is determined.
When described optimization partition function comprises that grid loss revenue function, the influenced range function of user, load are controlled Validity Function simultaneously, described optimization partition function is multiple objective function, described grid loss revenue function, the influenced range function of user, load are controlled Validity Function and are respectively sub-goal, according to the weight coefficient of described three sub-goals that obtain (described three weight coefficients add up to 1), the targeted customer in the time of can obtaining making grid loss income, the influenced scope of user and load control validity account for any weight separately.
As, the weight coefficient of described grid loss income is 0.8, the weight coefficient of the influenced scope of user is 0.1, the weight coefficient that load is controlled validity is 0.1, the targeted customer who determines according to described weight coefficient, can realize and consider a little, on the basis of the influenced scope of user and load control validity, to guarantee that grid loss income is as far as possible few.
For another, the weight coefficient of described grid loss income is 0.1, the weight coefficient of the influenced scope of user is 0.8, the weight coefficient that load is controlled validity is 0.1, the targeted customer who determines according to described weight coefficient, can realize and consider a little, on the basis of grid loss income and load control validity, to guarantee that user's participation number is as far as possible few.
And for example, the weight coefficient of described grid loss income is 0.1, the weight coefficient of the influenced scope of user is 0.1, the weight coefficient that load is controlled validity is 0.8, the targeted customer who determines according to described weight coefficient, can realize on the basis of participation number of considering a little grid loss income and user, the control validity that guarantees to load is tried one's best.
For another example, the weight coefficient of described grid loss income is 0.3, the weight coefficient of the influenced scope of user is 0.3, the weight coefficient that load is controlled validity is 0.4, the targeted customer who determines according to described weight coefficient can guarantee the grid loss income of trying one's best few, the influenced scope of few user of trying one's best and to the greatest extent measured load control validity simultaneously.
It should be noted that, described each weight coefficient can be default fixed value, can be also the input value of obtaining.When being the input value of obtaining, can realizing according to different demands different optimization and distribute target.
From above technical scheme, the present embodiment provides a kind of load of power industry to control distribution system, in this system, settled precondition unit 701 obtains load control priority and the load control total amount that supply side generates really, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload; Determine that alternative subscriber unit 702 is according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Obtain user's controlled quentity controlled variable unit 703 and obtain the described corresponding load controlled quentity controlled variable of each current alternative user; When described each load controlled quentity controlled variable sum is more than or equal to describedly when preload is controlled total amount, determine that target subscriber units 704 according to default constraint condition, applies default optimization partition function, definite targeted customer in described each current alternative user; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
Because user's number is when more than enough, the user that load control mode is limit priority is also abundant, the alternative user who determines also enough meets the condition that load is controlled total amount, described a plurality of alternative user can jointly participate in described load and control project, if but common participation can cause user in a big way influenced, and cause electrical network income to be subject to larger loss due to participating user is compensated.Wherein, described optimization partition function can be the one or more combination in grid loss revenue function, the influenced range function of user, load control Validity Function, thereby can control under the prerequisite of total amount and load control security meeting load, the load of realize simultaneously and try one's best supply side grid loss income little, try one's best the influenced scope of little user, trying one's best high is controlled three of validity and is optimized one or more in sub-goals.
In addition, when majorized function target comprises a plurality of sub-goal, by obtaining the weight coefficient value of each sub-goal of input, according to different actual demands, set up different optimization partition functions.Utilize described each different optimization partition function to realize different optimization aim, realize load and control the dirigibility that distributes target.
Refer to Fig. 8, its load that shows a kind of power industry that the application provides is controlled the structural representation of distribution system embodiment eight, the present embodiment can comprise: determine when precondition unit 801, determine alternative subscriber unit 802, obtain user's controlled quentity controlled variable unit 803, determine target subscriber units 804, redefine when precondition unit 805, judging unit 806, the first judged result unit 807 and the second judged result unit 808, wherein:
Described definite when precondition unit 801, the load control priority and the load control total amount that for obtaining supply side, generate, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload;
Describedly determine alternative subscriber unit 802, for according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Wherein, described current alternative user is a plurality of;
The described user's controlled quentity controlled variable unit 803 that obtains, for obtaining the described corresponding load controlled quentity controlled variable of each current alternative user;
Described definite target subscriber units 804, for being more than or equal to described when preload is controlled total amount when described each load controlled quentity controlled variable sum, according to default constraint condition, apply default optimization partition function, in described each current alternative user, determine targeted customer.
It should be noted that, described definite target subscriber units 804 is connected with described the second judged result unit 808, can realize embodiment bis-and by step S205, be entered the function of step S209.
Described redefining when precondition unit 805, for being less than described when preload is controlled total amount when described each load controlled quentity controlled variable sum, described each current alternative user is defined as to targeted customer, according to described load, controls priority and determine when preload control mode;
Described judging unit 806, for judging whether to exist when preload control mode;
Described the first judged result unit 807, for new during when preload control mode when existing, by described value deducting after described each load controlled quentity controlled variable sum when preload control total amount, as the new preload of working as, control total amount, and return and carry out according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described;
Described the second judged result unit 808, for new during when preload control mode when not existing, merges into final targeted customer by all described targeted customer who determines.
It should be noted that, described the first judged result unit 807 determines that with described alternative subscriber unit 802 is connected, and can realize the function that is entered step S202 in embodiment bis-by step S208.Described the first judged result unit 807 is all connected with described judging unit 806 with described the first judged result unit 807, for receiving the judged result of described judging unit 806.Functional unit in the present embodiment can be realized the flow process in embodiment bis-, and can produce the beneficial effect of embodiment bis-, illustrates and refers to embodiment bis-, at this, does not repeat.
Refer to Fig. 9, its load that shows a kind of power industry that the application provides is controlled the part-structure schematic diagram of distribution system embodiment nine, in 702 or embodiment eight in embodiment seven 802 can comprise: first determines that subelement 901, first obtains subelement 902 and second and determines subelement 903, wherein:
Described first determines subelement 901, for using with described when identical each user of preload control mode is as current elementary alternative user;
Described first obtains subelement 902, the load control time, the load control notice time that for obtaining supply side, generate;
Described second determines subelement 903, for judging that successively whether described each current elementary alternative user meets default screening conditions, is if so, defined as current alternative user by described current elementary alternative user; Wherein, described default screening conditions are: load that described load control time comprises described current elementary alternative user is controlled the time period on date, and described load control the notice time early than or equal notice time of described current elementary alternative user.
It should be noted that, the functional unit in the present embodiment can be realized the flow process in embodiment tri-, and can produce the beneficial effect of embodiment tri-, illustrates and refers to embodiment tri-, at this, does not repeat.
Refer to Figure 10, its load that shows a kind of power industry that the application provides is controlled the part-structure schematic diagram of distribution system embodiment ten, and 704 in embodiment nine can comprise: obtain functional value set subelement 1001, determine minimum value subelement 1002 and definite targeted customer's subelement 1003.
The described functional value set subelement 1001 that obtains, if meet load power ratio control constraint condition and electric power safety operation constraint condition for each current alternative user simultaneously, algorithm according to default, utilizes default optimization partition function to obtain the set of described each functional value of optimization partition function; Wherein: described load power ratio control constraint condition is: current alternative user's load controlled quentity controlled variable sum is more than or equal to when preload control total amount; Described electric power safety operation constraint condition is: the load controlled quentity controlled variable sum of current alternative user in load control time is less than or equal to the electric power decline upper limit default in the described period, and the in the situation that of changing load, the load controlled quentity controlled variable of current alternative user in the time period after changing load is more than or equal to electric power default in the time period after described change increases the upper limit;
Described definite minimum value subelement 1002, for determining the minimum value of described optimization partition function value set;
Described definite targeted customer's subelement 1003, for being defined as targeted customer by described each the alternative user who makes described optimization partition function obtain minimum value.
Functional unit application scenarios in the present embodiment is identical with embodiment tetra-, can realize the flow process in embodiment tetra-and produce the beneficial effect of embodiment tetra-, illustrates and refers to embodiment tetra-, at this, does not repeat.
When described optimization partition function comprises that grid loss revenue function, the influenced range function of user and load are controlled Validity Function, refer to Figure 11, its load that shows a kind of power industry that the application provides is controlled the part-structure schematic diagram of distribution system embodiment 11, on the basis of embodiment ten, the present embodiment can also comprise: obtain weight coefficient unit 1101, calculate value cell 1102 and set up function unit 1103.Wherein:
The described weight coefficient unit 1101 that obtains, for obtaining respectively the weight coefficient of described grid loss revenue function, the weight coefficient of the influenced range function of user and load are controlled the weight coefficient of Validity Function; Wherein: described three weight coefficients add up to 1, the receivable electric money that described grid loss revenue function reduces for load control time adds the load control and compensation amount of money, the influenced range function of described user is controlled user's number addition for participating in load, described load is controlled Validity Function and is added for participating in load control user's credit worthiness;
Calculate value cell 1102, while meeting load power ratio control constraint condition and electric power safety operation constraint condition for the alternative user when described alternative user's set simultaneously, according to preset algorithm, minimum value and maximal value when the minimum value while calculating respectively described in each minimum value when alternative user applies described grid loss revenue function and maximal value, the influenced range function of the described user of application and maximal value, the described load of application are controlled Validity Function;
Set up function unit 1103, for controlling Validity Function weight coefficient and maximal value separately and minimum value separately according to described grid loss revenue function, the influenced range function of user and load, set up optimization partition function.
Functional unit application scenarios in the present embodiment is identical with embodiment five, can realize the flow process in embodiment five and produce the beneficial effect of embodiment five, illustrates and refers to embodiment five, at this, does not repeat.
Refer to Figure 12, its load that shows a kind of power industry that the application provides is controlled the part-structure schematic diagram of distribution system embodiment 12, on the basis of embodiment seven to 11 any embodiment, the present embodiment can also comprise: information generated table unit 1201, transmission message unit 1202 and updating block 1203.Wherein:
Described information generated table unit 1201, for generating described each targeted customer's who participates in described load control information table; Wherein, in described information table, at least comprise with the next item down or several information: the device name of user ID, user's name, station address, user's contact method, participation, load control mode, load controlled quentity controlled variable, load are controlled notice time, load control time, the amount of compensation;
Described transmission message unit 1202, for according to described information table, sends the load control information that comprises load control time, load controlled quentity controlled variable to described each targeted customer;
Described updating block 1203, for the actual execution information of loading and controlling according to described each targeted customer of receiving, upgrades participated in number of times and the credit worthiness of each targeted customer described in described load resources bank; Wherein, described actual execution information comprise described each targeted customer load control the actual execution period that actual execution amount and load are controlled.
Functional unit in the present embodiment can be realized the flow process in embodiment six, and can produce the beneficial effect of embodiment six, illustrates and refers to embodiment six, at this, does not repeat.
It should be noted that, each embodiment in this instructions all adopts the mode of going forward one by one to describe, and each embodiment stresses is the difference with other embodiment, between each embodiment identical similar part mutually referring to.
Above a kind of power industry load control distribution method provided by the present invention and system are described in detail, the above-mentioned explanation to the disclosed embodiments, makes professional and technical personnel in the field can realize or use the present invention.To the multiple modification of these embodiment, will be apparent for those skilled in the art, General Principle as defined herein can, in the situation that not departing from the spirit or scope of the present invention, realize in other embodiments.Therefore, the present invention will can not be restricted to these embodiment shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.

Claims (12)

1. the load of power industry is controlled a distribution method, it is characterized in that, comprising:
Obtain load control priority and load control total amount that supply side generates, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload;
According to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Wherein, described current alternative user is a plurality of;
Obtain the described corresponding load controlled quentity controlled variable of each current alternative user;
When described each load controlled quentity controlled variable sum is more than or equal to describedly when preload is controlled total amount, according to default constraint condition, apply default optimization partition function, definite targeted customer in described each current alternative user; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
2. method according to claim 1, is characterized in that, also comprises:
When described each load controlled quentity controlled variable sum is less than, describedly when preload is controlled total amount, described each current alternative user is defined as to targeted customer, according to described load, controls the definite preload control mode of working as of priority;
Judge whether to exist when preload control mode, if, by described value deducting after described each load controlled quentity controlled variable sum when preload control total amount, as the new preload of working as, control total amount, and return and carry out according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described;
If not, all described targeted customer who determines is merged into final targeted customer.
3. method according to claim 1 and 2, is characterized in that, described basis is preset screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described, comprising:
Using with described when identical each user of preload control mode is as current elementary alternative user;
Obtain load control time, load control notice time that supply side generates;
Whether described each the current elementary alternative user of judgement meets default screening conditions successively, if so, described current elementary alternative user is defined as to current alternative user; Wherein, described default screening conditions are: load that described load control time comprises described current elementary alternative user is controlled the time period on date, and described load control the notice time early than or equal notice time of described current elementary alternative user.
4. method according to claim 3, is characterized in that, described default constraint condition comprises load power ratio control constraint condition and electric power safety operation constraint condition:
Describedly be more than or equal to describedly when preload is controlled total amount when described each load controlled quentity controlled variable sum, according to default constraint condition, apply default optimization partition function, definite targeted customer in described each current alternative user, comprising:
If each current alternative user meets load power ratio control constraint condition and electric power safety operation constraint condition simultaneously, the algorithm according to default, utilizes default optimization partition function to obtain the set of described each functional value of optimization partition function; Wherein: described load power ratio control constraint condition is: current alternative user's load controlled quentity controlled variable sum is more than or equal to when preload control total amount; Described electric power safety operation constraint condition is: the load controlled quentity controlled variable sum of current alternative user in load control time is less than or equal to the electric power decline upper limit default in the described period, and the in the situation that of changing load, the load controlled quentity controlled variable of current alternative user in the time period after changing load is more than or equal to electric power default in the time period after described change increases the upper limit;
Determine the minimum value in described optimization partition function value set;
Described each the alternative user who makes described optimization partition function obtain minimum value is defined as to targeted customer.
5. method according to claim 4, it is characterized in that, when described optimization partition function comprises that grid loss revenue function, the influenced range function of user and load are controlled Validity Function, when described each load controlled quentity controlled variable sum, be more than or equal to described when preload is controlled total amount, according to default constraint condition, apply default optimization partition function, determine targeted customer in described each current alternative user before, also comprise:
Obtain respectively the weight coefficient of described grid loss revenue function, the weight coefficient of the influenced range function of user and load are controlled the weight coefficient of Validity Function; Wherein: described three weight coefficients add up to 1, the receivable electric money that described grid loss revenue function reduces for load control time adds the load control and compensation amount of money, the influenced range function of described user is controlled user's number addition for participating in load, described load is controlled Validity Function and is added for participating in load control user's credit worthiness;
When the alternative user in described alternative user's set meets load power ratio control constraint condition and electric power safety operation constraint condition simultaneously, according to preset algorithm, minimum value and maximal value when the minimum value while calculating respectively described in each minimum value when alternative user applies described grid loss revenue function and maximal value, the influenced range function of the described user of application and maximal value, the described load of application are controlled Validity Function;
According to described grid loss revenue function, the influenced range function of user and load, control Validity Function weight coefficient and maximal value separately and minimum value separately, set up and optimize partition function.
6. method according to claim 5, is characterized in that, after described method, also comprises:
Generate described each targeted customer's who participates in described load control information table; Wherein, in described information table, at least comprise with the next item down or several information: the device name of user ID, user's name, station address, user's contact method, participation, load control mode, load controlled quentity controlled variable, load are controlled notice time, load control time, the amount of compensation;
According to described information table, to described each targeted customer, send the load control information that comprises load control time, load controlled quentity controlled variable;
The actual execution information of loading and controlling according to described each targeted customer of receiving, upgrades participated in number of times and the credit worthiness of each targeted customer described in described load resources bank; Wherein, described actual execution information comprises the actual execution period that described each targeted customer's load is controlled actual execution amount and loaded and control.
7. the load of power industry is controlled a distribution system, it is characterized in that, comprising:
Determine when precondition unit, the load control priority and the load control total amount that for obtaining supply side, generate, and according to described load control priority, the highest load control mode of priority is defined as when preload control mode, described load is controlled to total amount and be defined as controlling total amount when preload;
Determine alternative subscriber unit, for according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described; Wherein, described current alternative user is a plurality of;
Obtain user's controlled quentity controlled variable unit, for obtaining the described corresponding load controlled quentity controlled variable of each current alternative user;
Determine target subscriber units, described when preload is controlled total amount for being more than or equal to when described each load controlled quentity controlled variable sum, according to default constraint condition, apply default optimization partition function, in described each current alternative user, determine targeted customer; Wherein, described optimization partition function comprises grid loss revenue function, the influenced range function of user and/or load control Validity Function.
8. system according to claim 7, is characterized in that, also comprises:
Redefine when precondition unit, described in being less than for controlled quentity controlled variable sum of loading when described each, when preload is controlled total amount, described each current alternative user is defined as to targeted customer, according to described load, control the definite preload control mode of working as of priority;
Judging unit, for judging whether to exist when preload control mode;
The first judged result unit, for new during when preload control mode when existing, by described value deducting after described each load controlled quentity controlled variable sum when preload control total amount, as the new preload of working as, control total amount, and return and carry out according to default screening conditions, will be defined as current alternative user as the corresponding user of preload control mode with described;
The second judged result unit, for new during when preload control mode when not existing, merges into final targeted customer by all described targeted customer who determines.
9. according to the system described in claim 7 or 8 any one, it is characterized in that, described definite alternative subscriber unit comprises:
First determines subelement, for using with described when identical each user of preload control mode is as current elementary alternative user;
First obtains subelement, the load control time, the load control notice time that for obtaining supply side, generate;
Second determines subelement, for judging that successively whether described each current elementary alternative user meets default screening conditions, is if so, defined as current alternative user by described current elementary alternative user; Wherein, described default screening conditions are: load that described load control time comprises described current elementary alternative user is controlled the time period on date, and described load control the notice time early than or equal notice time of described current elementary alternative user.
10. system according to claim 9, is characterized in that, described default constraint condition comprises load power ratio control constraint condition and electric power safety operation constraint condition, and described definite target subscriber units comprises:
Obtain functional value set subelement, if meet load power ratio control constraint condition and electric power safety operation constraint condition for each current alternative user simultaneously, algorithm according to default, utilizes default optimization partition function to obtain the set of described each functional value of optimization partition function; Wherein: described load power ratio control constraint condition is: current alternative user's load controlled quentity controlled variable sum is more than or equal to when preload control total amount; Described electric power safety operation constraint condition is: the load controlled quentity controlled variable sum of current alternative user in load control time is less than or equal to the electric power decline upper limit default in the described period, and the in the situation that of changing load, the load controlled quentity controlled variable of current alternative user in the time period after changing load is more than or equal to electric power default in the time period after described change increases the upper limit;
Determine minimum value subelement, for determining the minimum value of described optimization partition function value set;
Determine targeted customer's subelement, for described each the alternative user who makes described optimization partition function obtain minimum value is defined as to targeted customer.
11. systems according to claim 10, is characterized in that, when described optimization partition function comprises that grid loss revenue function, the influenced range function of user and load are controlled Validity Function, also comprise;
Obtain weight coefficient unit, for obtaining respectively the weight coefficient of described grid loss revenue function, the weight coefficient of the influenced range function of user and load are controlled the weight coefficient of Validity Function; Wherein: described three weight coefficients add up to 1, the receivable electric money that described grid loss revenue function reduces for load control time adds the load control and compensation amount of money, the influenced range function of described user is controlled user's number addition for participating in load, described load is controlled Validity Function and is added for participating in load control user's credit worthiness;
Calculate value cell, while meeting load power ratio control constraint condition and electric power safety operation constraint condition for the alternative user when described alternative user's set simultaneously, according to preset algorithm, minimum value and maximal value when the minimum value while calculating respectively described in each minimum value when alternative user applies described grid loss revenue function and maximal value, the influenced range function of the described user of application and maximal value, the described load of application are controlled Validity Function;
Set up function unit, for controlling Validity Function weight coefficient and maximal value separately and minimum value separately according to described grid loss revenue function, the influenced range function of user and load, set up optimization partition function.
12. systems according to claim 11, is characterized in that, also comprise:
Information generated table unit, for generating described each targeted customer's who participates in described load control information table; Wherein, in described information table, at least comprise with the next item down or several information: the device name of user ID, user's name, station address, user's contact method, participation, load control mode, load controlled quentity controlled variable, load are controlled notice time, load control time, the amount of compensation;
Send message unit, for according to described information table, to described each targeted customer, send the load control information that comprises load control time, load controlled quentity controlled variable;
Updating block, for the actual execution information of loading and controlling according to described each targeted customer of receiving, upgrades participated in number of times and the credit worthiness of each targeted customer described in described load resources bank; Wherein, described actual execution information comprise described each targeted customer load control the actual execution period that actual execution amount and load are controlled.
CN201310576271.7A 2013-11-18 2013-11-18 Load control distribution method and system of electric power industry Active CN103577898B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310576271.7A CN103577898B (en) 2013-11-18 2013-11-18 Load control distribution method and system of electric power industry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310576271.7A CN103577898B (en) 2013-11-18 2013-11-18 Load control distribution method and system of electric power industry

Publications (2)

Publication Number Publication Date
CN103577898A true CN103577898A (en) 2014-02-12
CN103577898B CN103577898B (en) 2017-02-15

Family

ID=50049641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310576271.7A Active CN103577898B (en) 2013-11-18 2013-11-18 Load control distribution method and system of electric power industry

Country Status (1)

Country Link
CN (1) CN103577898B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103942641A (en) * 2014-03-31 2014-07-23 国网上海市电力公司 Method for improving limited electricity calculating efficiency based on linear programming
CN104037771A (en) * 2014-05-20 2014-09-10 国家电网公司 Power grid load decline adjusting method and system
CN105023095A (en) * 2015-07-07 2015-11-04 上海申瑞继保电气有限公司 User side energy management system load limiting control method
CN105096040A (en) * 2015-07-21 2015-11-25 国家电网公司 Method for automatically sorting demand response users
CN105932664A (en) * 2015-12-11 2016-09-07 国家电网公司 Active management scheduling method of comprehensive load of nodes in transformer station supply area
CN106952145A (en) * 2017-03-24 2017-07-14 广州茶途网络科技有限公司 It is a kind of to try out user's choosing method and device based on the commodity that big data is analyzed
CN107093902A (en) * 2017-06-27 2017-08-25 南方电网科学研究院有限责任公司 Power load regulation and control method and system
CN107123986A (en) * 2017-05-04 2017-09-01 珠海优特电力科技股份有限公司 Region power consumption control method and device
CN109407523A (en) * 2017-08-16 2019-03-01 佛山市顺德区美的电热电器制造有限公司 The control method of heating platform component and the control system of heating platform component
CN110413706A (en) * 2019-07-15 2019-11-05 东软集团股份有限公司 Data processing method, device, storage medium and electronic equipment
CN113162031A (en) * 2021-04-01 2021-07-23 南方电网数字电网研究院有限公司 Industrial load monitoring and scheduling method and device, computer equipment and storage medium
CN114254838A (en) * 2022-01-07 2022-03-29 深圳供电局有限公司 Method for determining short-term power load prediction influence factor
CN114971400A (en) * 2022-06-24 2022-08-30 东南大学溧阳研究院 User side energy storage polymerization method based on Dirichlet distribution-multinomial distribution conjugate prior
CN116526496A (en) * 2023-06-16 2023-08-01 国网山西省电力公司晋城供电公司 Novel auxiliary decision-making method for power system load control

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102025150A (en) * 2009-09-11 2011-04-20 通用电气公司 Method and system for demand response in a distribution network
CN102738801A (en) * 2012-05-28 2012-10-17 深圳市科陆电子科技股份有限公司 Power demand responding method and system
US20130184881A1 (en) * 2012-01-17 2013-07-18 Vlaamse Instelling Voor Technologisch Onderzoek (Vito) Demand response adaptor for connecting a device to a demand response system or home automation system, device and such demand response adaptor and use thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102025150A (en) * 2009-09-11 2011-04-20 通用电气公司 Method and system for demand response in a distribution network
US20130184881A1 (en) * 2012-01-17 2013-07-18 Vlaamse Instelling Voor Technologisch Onderzoek (Vito) Demand response adaptor for connecting a device to a demand response system or home automation system, device and such demand response adaptor and use thereof
CN102738801A (en) * 2012-05-28 2012-10-17 深圳市科陆电子科技股份有限公司 Power demand responding method and system

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
WADAED UTURBEY ET AL.: "Interruptible Load Management Assessment via Dynamic Optimal Power Flow", 《2003 IEEE BOLOGNA POWER TECH CONFERENCE》 *
张钦等: "电力市场下需求响应研究综述", 《电力系统自动化》 *
王蓉蓉: "可中断负荷管理的激励机制研究", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 *
魏琳琳: "需求侧管理中的可中断负荷问题研究", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 *

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103942641A (en) * 2014-03-31 2014-07-23 国网上海市电力公司 Method for improving limited electricity calculating efficiency based on linear programming
CN104037771A (en) * 2014-05-20 2014-09-10 国家电网公司 Power grid load decline adjusting method and system
CN105023095A (en) * 2015-07-07 2015-11-04 上海申瑞继保电气有限公司 User side energy management system load limiting control method
CN105023095B (en) * 2015-07-07 2020-10-23 上海申瑞继保电气有限公司 Load limiting control method for energy management system of user side
CN105096040A (en) * 2015-07-21 2015-11-25 国家电网公司 Method for automatically sorting demand response users
CN105932664A (en) * 2015-12-11 2016-09-07 国家电网公司 Active management scheduling method of comprehensive load of nodes in transformer station supply area
CN105932664B (en) * 2015-12-11 2018-08-14 国家电网公司 A kind of active management dispatching method of substation for each node synthetic load in area
CN106952145A (en) * 2017-03-24 2017-07-14 广州茶途网络科技有限公司 It is a kind of to try out user's choosing method and device based on the commodity that big data is analyzed
CN107123986B (en) * 2017-05-04 2021-08-10 珠海优特电力科技股份有限公司 Regional power utilization control method and device
CN107123986A (en) * 2017-05-04 2017-09-01 珠海优特电力科技股份有限公司 Region power consumption control method and device
CN107093902A (en) * 2017-06-27 2017-08-25 南方电网科学研究院有限责任公司 Power load regulation and control method and system
CN109407523A (en) * 2017-08-16 2019-03-01 佛山市顺德区美的电热电器制造有限公司 The control method of heating platform component and the control system of heating platform component
CN110413706A (en) * 2019-07-15 2019-11-05 东软集团股份有限公司 Data processing method, device, storage medium and electronic equipment
CN110413706B (en) * 2019-07-15 2022-03-04 东软集团股份有限公司 Data processing method, data processing device, storage medium and electronic equipment
CN113162031A (en) * 2021-04-01 2021-07-23 南方电网数字电网研究院有限公司 Industrial load monitoring and scheduling method and device, computer equipment and storage medium
CN113162031B (en) * 2021-04-01 2022-07-29 南方电网数字电网研究院有限公司 Industrial load monitoring and scheduling method and device, computer equipment and storage medium
CN114254838A (en) * 2022-01-07 2022-03-29 深圳供电局有限公司 Method for determining short-term power load prediction influence factor
CN114971400A (en) * 2022-06-24 2022-08-30 东南大学溧阳研究院 User side energy storage polymerization method based on Dirichlet distribution-multinomial distribution conjugate prior
CN114971400B (en) * 2022-06-24 2023-01-31 东南大学溧阳研究院 User side energy storage polymerization method based on Dirichlet distribution-multinomial distribution conjugate prior
CN116526496A (en) * 2023-06-16 2023-08-01 国网山西省电力公司晋城供电公司 Novel auxiliary decision-making method for power system load control
CN116526496B (en) * 2023-06-16 2023-09-08 国网山西省电力公司晋城供电公司 Novel auxiliary decision-making method for power system load control

Also Published As

Publication number Publication date
CN103577898B (en) 2017-02-15

Similar Documents

Publication Publication Date Title
CN103577898A (en) Load control distribution method and system of electric power industry
Dehghanpour et al. Real-time multiobjective microgrid power management using distributed optimization in an agent-based bargaining framework
Ibars et al. Distributed demand management in smart grid with a congestion game
Jabr Optimization of AC transmission system planning
Jiang et al. Load shaping strategy based on energy storage and dynamic pricing in smart grid
Mavalizadeh et al. Hybrid expansion planning considering security and emission by augmented epsilon-constraint method
Wang et al. Privacy-preserving energy scheduling in microgrid systems
An et al. A distributed and resilient bargaining game for weather-predictive microgrid energy cooperation
CN103337039A (en) Multi-target multi-constrained medium and long term power purchase decision-making method
CN107767086A (en) New energy station output lower limit rolling amendment method based on generated power forecasting
Rana et al. Heuristic enhanced evolutionary algorithm for community microgrid scheduling
CN104319777B (en) A kind of Demand-side load flexible control method
CN110015090A (en) A kind of electric automobile charging station scheduling system and orderly charge control method
CN101794994A (en) Power generation plan method considering network loss sharing under power market environment containing bilateral transaction
CN109472463A (en) A kind of more peak load regulation network dispatching methods of especially big basin water station group and system
Ferrero et al. Dynamic economic dispatch in deregulated systems
Mussadiq et al. Economic and climatic impacts of different peer-to-peer game theoretic–based energy trading systems
CN116342166A (en) Energy game regulation and control method and equipment based on multi-region sharing
CN110119855A (en) A kind of pneumoelectric coupled system running optimizatin method
Sobhani et al. Two-level distributed demand-side management using the smart energy hub concept
Carreras et al. Assessing blackout risk with high penetration of variable renewable energies
Cheng et al. Optimized configuration of distributed power generation based on multi-stakeholder and energy storage synergy
CN109685397A (en) A kind of meter and direct load control lower electrical couplings system reliability estimation method
CN105914762A (en) Interconnected network frequency deviation coefficient setting method based on cooperative game theory
EP3997639A1 (en) Data structure comprising an energy schedule and method for providing a data structure comprising an energy schedule

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 100033 West Chang'an Avenue, Xicheng District, Xicheng District, Beijing

Co-patentee after: STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER Co.

Patentee after: STATE GRID CORPORATION OF CHINA

Co-patentee after: BEIJING GUODIANTONG NETWORK TECHNOLOGY Co.,Ltd.

Co-patentee after: Beijing Zhongdian Feihua Communications Co.,Ltd.

Address before: 100031 West Chang'an Avenue, Xicheng District, Xicheng District, Beijing

Co-patentee before: STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER Co.

Patentee before: State Grid Corporation of China

Co-patentee before: BEIJING GUODIANTONG NETWORK TECHNOLOGY Co.,Ltd.

Co-patentee before: Beijing Zhongdian Feihua Communications Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190625

Address after: 100033 West Chang'an Avenue, Xicheng District, Xicheng District, Beijing

Co-patentee after: STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER Co.

Patentee after: STATE GRID CORPORATION OF CHINA

Co-patentee after: BEIJING GUODIANTONG NETWORK TECHNOLOGY Co.,Ltd.

Address before: 100033 West Chang'an Avenue, Xicheng District, Xicheng District, Beijing

Co-patentee before: STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER Co.

Patentee before: State Grid Corporation of China

Co-patentee before: BEIJING GUODIANTONG NETWORK TECHNOLOGY Co.,Ltd.

Co-patentee before: Beijing Zhongdian Feihua Communications Co.,Ltd.