CN103558770B - 用于机网协调分析的发电厂数字-物理混合仿真模型 - Google Patents
用于机网协调分析的发电厂数字-物理混合仿真模型 Download PDFInfo
- Publication number
- CN103558770B CN103558770B CN201310441315.5A CN201310441315A CN103558770B CN 103558770 B CN103558770 B CN 103558770B CN 201310441315 A CN201310441315 A CN 201310441315A CN 103558770 B CN103558770 B CN 103558770B
- Authority
- CN
- China
- Prior art keywords
- control system
- generating plant
- simulation model
- software
- power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Testing And Monitoring For Control Systems (AREA)
- Feedback Control In General (AREA)
- Control Of Turbines (AREA)
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310441315.5A CN103558770B (zh) | 2013-09-25 | 2013-09-25 | 用于机网协调分析的发电厂数字-物理混合仿真模型 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310441315.5A CN103558770B (zh) | 2013-09-25 | 2013-09-25 | 用于机网协调分析的发电厂数字-物理混合仿真模型 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103558770A CN103558770A (zh) | 2014-02-05 |
CN103558770B true CN103558770B (zh) | 2016-01-20 |
Family
ID=50013053
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310441315.5A Active CN103558770B (zh) | 2013-09-25 | 2013-09-25 | 用于机网协调分析的发电厂数字-物理混合仿真模型 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103558770B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104049539B (zh) * | 2014-05-29 | 2016-08-17 | 华中科技大学 | 一种汽轮机回热系统的全工况仿真系统 |
CN104765282B (zh) * | 2015-04-10 | 2018-03-27 | 三峡大学 | 一种电站全数字综合仿真平台 |
TWI655554B (zh) * | 2018-02-09 | 2019-04-01 | 中國鋼鐵股份有限公司 | 動力系統模型的調節方法 |
CN112631144B (zh) * | 2020-11-20 | 2023-09-05 | 国网山东省电力公司电力科学研究院 | 一种综合能源实时数字物理混合仿真系统 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001255903A (ja) * | 2000-03-14 | 2001-09-21 | Toshiba Corp | プロセス制御システム |
CN101364109A (zh) * | 2008-09-28 | 2009-02-11 | 华北电力大学 | 基于实测的机网动态安全评估系统及方法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8028526B2 (en) * | 2007-12-06 | 2011-10-04 | Giberson Melbourne F | Geared boiler feed pump drive |
-
2013
- 2013-09-25 CN CN201310441315.5A patent/CN103558770B/zh active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001255903A (ja) * | 2000-03-14 | 2001-09-21 | Toshiba Corp | プロセス制御システム |
CN101364109A (zh) * | 2008-09-28 | 2009-02-11 | 华北电力大学 | 基于实测的机网动态安全评估系统及方法 |
Non-Patent Citations (4)
Title |
---|
孤网高频问题的分析与控制策略研究;马世俊等;《现代电力》;20120630;第29卷(第3期);摘要,第1.2-2.1节,图1-5 * |
机网协调在现代电力系统中的作用(待续);陈迅;《广东电力》;20130531;第26卷(第5期);第57-62页 * |
机网协调在现代电力系统中的作用(续1);陈迅;《广东电力》;20130630;第26卷(第6期);第52-59页 * |
机网协调在现代电力系统中的作用(续完);陈迅;《广东电力》;20130831;第26卷(第8期);第56-63页 * |
Also Published As
Publication number | Publication date |
---|---|
CN103558770A (zh) | 2014-02-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105512388B (zh) | 一种基于labview的亚临界火电机组增强激励仿真建模方法 | |
Flynn et al. | A drum boiler model for long term power system dynamic simulation | |
Smrekar et al. | Prediction of power output of a coal-fired power plant by artificial neural network | |
CN103558770B (zh) | 用于机网协调分析的发电厂数字-物理混合仿真模型 | |
CN102621945B (zh) | 基于火力发电机组最优工况的效率动态寻优运行闭环优化控制方法 | |
Plis et al. | A mathematical model of an existing gas-steam combined heat and power plant for thermal diagnostic systems | |
Liu et al. | An overview of modelling and simulation of thermal power plant | |
Lu et al. | An object-oriented power plant adaptive control system design tool | |
Tawfeic | Boiler drum-level modeling | |
Silva et al. | Evaluation of the efficiency of a heat recovery steam generator via computational simulations of off-design operation | |
CN109709911A (zh) | 一种火电机组循环工质外漏在线测量方法及测量系统 | |
CN104154531A (zh) | 一种循环流化床机组能效优化方法及系统 | |
Mohamed et al. | Predictive control strategy for a supercritical power plant and study of influences of coal mills control on its dynamic responses | |
Budnik et al. | Exergetic cost of steam power plant operation | |
Neuman | Power plant and boiler models for operator training simulators | |
CN106444419B (zh) | 一种基于性能数据的自抗扰控制硬件在线闭环仿真控制方法 | |
CN101546179B (zh) | 一种火电机组过热器的非线性仿真装置 | |
Wang et al. | Heat transfer characteristics and energy-consumption benchmark state with varying operation boundaries for coal-fired power units: An exergy analytics approach | |
Li et al. | Parametric optimization of steam turbine networks by using commercial simulation software | |
Gao et al. | Modeling large modern fossil-fueled steam-electric power plant and its coordinated control system for power system dynamic analysis | |
Neuman et al. | Principles of Smart Grids on the generation electrical and thermal energy and control of heat consumption within the District Heating Networks | |
Wijaksono et al. | Design of virtual SCADA simulation system for pressurized water reactor | |
CUI et al. | Thermal dynamic calculation method and characteristic analysis of marine secondary circuit system under all operating conditions | |
Świerzewski et al. | Modelling of Commercial Biomass-fired ORC System Using EBSILON Professional Software | |
Jiang et al. | Modeling and Simulation of Secondary Loop Systems of a Pressurized Water Reactor Based on the 3KEYMASTER Platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8 Applicant after: ELECTRIC POWER RESEARCH INSTITUTE, GUANGDONG POWER GRID CO., LTD. Applicant after: Beijing gale Tianli Technology Co., Ltd. Address before: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8 Applicant before: Electrical Power Research Institute of Guangdong Power Grid Corporation Applicant before: BEIJING HENGHE DAFENG SOFTWARE TECHNOLOGY CO., LTD. |
|
COR | Change of bibliographic data | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20170823 Address after: 510630, No. fifth, No. 146-150, Whampoa Avenue, Tianhe District, Guangdong, Guangzhou Co-patentee after: Beijing gale Tianli Technology Co., Ltd. Patentee after: Guangdong Electric Power Research Institute of energy technology limited liability company Address before: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8 Co-patentee before: Beijing gale Tianli Technology Co., Ltd. Patentee before: ELECTRIC POWER RESEARCH INSTITUTE, GUANGDONG POWER GRID CO., LTD. |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200706 Address after: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8 Co-patentee after: Beijing Dafeng Tianli Technology Co.,Ltd. Patentee after: Electric Power Research Institute of Guangdong Power Grid Co.,Ltd. Address before: 510630, No. 146-150, No. fifth, Whampoa Avenue, Tianhe District, Guangdong, Guangzhou Co-patentee before: Beijing Dafeng Tianli Technology Co.,Ltd. Patentee before: GUANGDONG ELECTRIC POWER SCIENCE RESEARCH INSTITUTE ENERGY TECHNOLOGY Co.,Ltd. |
|
TR01 | Transfer of patent right |