CN103557898B - Turbulent fluid flow-measuring method in tunnel based on crucial ring - Google Patents

Turbulent fluid flow-measuring method in tunnel based on crucial ring Download PDF

Info

Publication number
CN103557898B
CN103557898B CN201310546143.8A CN201310546143A CN103557898B CN 103557898 B CN103557898 B CN 103557898B CN 201310546143 A CN201310546143 A CN 201310546143A CN 103557898 B CN103557898 B CN 103557898B
Authority
CN
China
Prior art keywords
tunnel
section
cross
ring
crucial
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310546143.8A
Other languages
Chinese (zh)
Other versions
CN103557898A (en
Inventor
何学秋
聂百胜
丁翠
李祥春
孟筠青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology Beijing CUMTB
Original Assignee
China University of Mining and Technology Beijing CUMTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology Beijing CUMTB filed Critical China University of Mining and Technology Beijing CUMTB
Priority to CN201310546143.8A priority Critical patent/CN103557898B/en
Publication of CN103557898A publication Critical patent/CN103557898A/en
Application granted granted Critical
Publication of CN103557898B publication Critical patent/CN103557898B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses turbulent fluid flow-measuring method in a kind of tunnel based on crucial ring, it is first determined the cross sectional shape in tunnel, determine its mean wind speed key ring according to the cross sectional shape in tunnel;Then by measuring the wind speed of arbitrfary point on crucial ring, the average wind i.e. obtained on this cross section hastens, and can calculate the flow of fluid in tunnel according to mean wind speed.It it is a kind of new technique simple, accurately measurement tunnel fluid flow.

Description

Turbulent fluid flow-measuring method in tunnel based on crucial ring
Technical field
The present invention relates to turbulent fluid flow measurement technology in a kind of coal mine roadway, particularly relate to a kind of lane based on crucial ring Turbulent fluid flow-measuring method in road.
Background technology
The coal resources energy sources that Dou Shi China is important all the time, coal is institute's accounting in primary energy production and consumption Heavily it is always held at more than 60%, therefore the dynamics of its exploitation is maximum.Owing to the strip mining transformation colliery of China is less, wherein The coal production of 92% is underground mining, and through exploitation for many years, superficial part mineral resources are the most exhausted, mineral resources Exploitation increasingly develop in depth, probably downwardly extend with the speed of 20 meters every year at present.Simultaneously state-owned heavy at China 724 In some colliery, at coal and gas outburst mine 154, account for 21.3%;At highly gassy mine 152, account for 21.0%.Along with ore deposit The increasing of mountain mining rate and the increase of mining depth, Gas and the journey of gathering in the development end in each stage casing, down-hole Degree is also increasing, and blast and burning occur under certain condition.Coal dust is also the product of underground coal recovery process, Underground work personnel suck the dust of excess for a long time can cause pneumoconiosis, and coal dust reaches certain concentration in atmosphere Time, meet burning things which may cause a fire disaster and be susceptible to dust explosion.In addition, each electric appliances, plant equipment operational situation is bad, electrical network Being short-circuited and naked light etc., also may ignite travelling belt, cable and timbering, causes exogenous mine fire.Cause The increase of this mining intensity and the degree of depth will necessarily cause even more serious gas explosion, fire, dust accident etc. its Its related accidents, the safety in production of down-hole, the life and health of staff and Accident prevention in serious threat.
Coal mining accident take place frequently to mine ventilation system, it was also proposed that the highest requirement.Ventilating system be mine very Important aid system, it is prevention and administers various disaster, it is achieved the basic means of Safety of Coal Mine Production.Mine ventilation Purpose be to be provided enough fresh distinguished and admirable by the staff of down-hole and various wind field, dilute or water down along with ore deposit Mountain exploitation and various poisonous, harmful, the damp that occurs and dust, it is ensured that the good weather bar in underground work space Part, sets up the work situation of safety and comfort for underground work personnel.Fact proved, the quality of mine ventilation system With the success or failure close relation that the security critical such as gas accident, fire, treating flour dust produces key factor, many collieries Major accident all with ventilating system mismanagement or design and unreasonable have important relationship.Particularly gas (coal dust) is quick-fried Fried, fire incident, this two classes accident is always the casualty accident that coal master wants, and all has with ventilating management close Relation, ventilating management is not good at being the main remote cause occurred that causes the accident.The most once occurred repeatedly gas quick-fried with dust Fried accident, all caused by improper ventilation.Such as on August 29th, 2012, colliery, Panzhihua City Xiao Jia gulf, Sichuan Province was sent out The most great raw gas explosion accident, causes that 45 people are dead, 1 people is missing, 54 people are injured.This accident is precisely due to ventilation duct Reason confusion, the reliability that ventilating system does not has is poor, and the tunnel of air return system is the most in bad repair, so that effective wind rate is not enough Caused.On April 16th, 2007, there is the most great gas explosion accident, underground aerial tramway in Wang Zhuan colliery, Pingdingshan City, Henan Province Die 31 people, hinder 9 people, ambulance corps rescue during occur subsequent explosion, cause 15 rescue team members injured.This accident is also It is owing to ventilating management is chaotic, booster blowing-out 1 month, make the methane accumulation of spilling and reach explosion ratio and run into Naked light causes gas explosion, and coal dust has also assisted in blast simultaneously.Within 2000, occur dead 164 people's in wood coombe ore deposit, Guizhou Province Especially big gas explosion accident is exactly also in that field management is not good at occurring in that caused by circulated air.Therefore mine ventilation is in safety Production plays vital effect.
But China still has most mine ventilation system to build imperfection at present, lacks the monitoring for ventilating system, it is impossible to Effectively ensure to be correlated with the air quantity of tunnel and getting working face in down-hole.Therefore, research mine laneway air quantity accurately measures skill Art and method, all have very important significance with having an accident in normal production period period.
In the measuring method of tunnel fluid flow in the prior art, generally use that homalographic is around-France asks for mean flow Speed or calculate cross section mean flow by the mathematical relationship of Peak Flow Rate and mean flow rate again by recording cross section Peak Flow Rate Speed, the former measurement and calculating are the most relatively complicated, and the measurement that the latter typically uses semiempirical formula and Peak Flow Rate also has Certain error.
Summary of the invention
It is an object of the invention to provide a kind of simply, turbulent fluid flow measurement side in tunnel based on crucial ring accurately Method.
It is an object of the invention to be achieved through the following technical solutions:
Turbulent fluid flow-measuring method in the tunnel based on crucial ring of the present invention, including step:
First, determine the cross sectional shape in tunnel, then determine its crucial ring, described crucial ring according to the cross sectional shape in tunnel The wind speed at place is equal to the mean wind speed on cross section, described tunnel;
Then, by measuring the wind speed of arbitrfary point on crucial ring, the average wind i.e. obtained on this cross section hastens, according to averagely Wind speed can calculate the flow of fluid in tunnel.
As seen from the above technical solution provided by the invention, in the tunnel based on crucial ring that the embodiment of the present invention provides Turbulent fluid flow-measuring method, owing to according to the velocity distribution on pipeline section of the turbulent fluid in tunnel, determining Going out the distribution curve of mean flow velocity value on cross section, i.e. VELOCITY DISTRIBUTION " crucial ring ", upper arbitrarily by measuring " crucial ring " The velocity amplitude of point, just can obtain the mean flow velocity value on this cross section, can be calculated the fluid flow in tunnel, is a kind of Simply, the new technique of tunnel fluid flow is accurately measured.
Accompanying drawing explanation
Fig. 1 a is the position view of the crucial ring of trapezoid cross section in the embodiment of the present invention;
Fig. 1 b is the area distribution schematic diagram of the crucial ring of trapezoid cross section in the embodiment of the present invention;
Fig. 2 a is the position view of the crucial ring in basket handle arch cross section in the embodiment of the present invention;
Fig. 2 b is the area distribution schematic diagram of the crucial ring in basket handle arch cross section in the embodiment of the present invention.
Detailed description of the invention
The embodiment of the present invention will be described in further detail below.
Turbulent fluid flow-measuring method in the tunnel based on crucial ring of the present invention, its preferably detailed description of the invention is:
Including step:
First, determine the cross sectional shape in tunnel, then determine its crucial ring, described crucial ring according to the cross sectional shape in tunnel The wind speed at place is equal to the mean wind speed on cross section, described tunnel;
Then, by measuring the wind speed of arbitrfary point on crucial ring, the average wind i.e. obtained on this cross section hastens, according to averagely Wind speed can calculate the flow of fluid in tunnel.
For trapezoid cross section, determine bottom side length on it, the length of side of going to the bottom and height, calculate the position of its crucial ring according to following table:
For basket handle arch cross section, the length of side that determines that three-core arch wall is high and basket handle arch is gone to the bottom, the position of its crucial ring is calculated according to following table Put:
Turbulent fluid flow-measuring method in the tunnel based on crucial ring of the present invention, according to turbulent fluid in tunnel at pipeline Velocity distribution on cross section, determines that the distribution curve of mean flow velocity value on cross section, i.e. VELOCITY DISTRIBUTION are " crucial Ring ", by measuring the velocity amplitude of " crucial ring " upper arbitrfary point, the mean flow velocity value on this cross section just can be obtained, It is calculated the fluid flow in tunnel, is a kind of new technique simple, accurately measurement tunnel fluid flow.
Specific embodiment:
First, determine the shape in tunnel, then according to the shape in tunnel, determine that it is " crucial by relationship Ring ".
As shown in Fig. 1 a, 1b, for trapezoid cross section, determine bottom side length on it, the length of side of going to the bottom and height, calculate it according to table 1 The position of crucial ring:
Table 1 trapezoid cross section " crucial ring " characteristic equation
In above formula: the trapezoidal upper bottom side length of b, m;The trapezoidal length of side of going to the bottom of c, m;The trapezoidal height of H, m;x Crucial abscissa corresponding to ring, m;Vertical coordinate corresponding to y key ring, m;The crucial ring of f (x) is special Levy equation, y value.
Above-mentioned relation formula is utilized to calculate the position of its crucial ring.
As shown in Fig. 2 a, 2b, for basket handle arch cross section, the length of side that determines that three-core arch wall is high and basket handle arch is gone to the bottom, count according to table 2 Calculate the position of its crucial ring:
Table 2 basket handle arch cross section " crucial ring " characteristic equation
In above formula: h three-core arch wall is high, m;Go to the bottom the length of side in d basket handle arch cross section, m;r1Basket handle arch cuts Face top arc radius, m;Abscissa corresponding to x key ring, m;Vertical seat corresponding to y key ring Mark, m;The crucial ring characteristic equation of f (x), y value.
Above-mentioned relation formula is utilized to calculate the position of its crucial ring.
Then, correlation meter is arranged on crucial ring position, the mean wind speed in this cross section can be measured.By " closing Key ring " theory can more accurately record the mean wind speed in tunnel, simultaneously can according in each tunnel normal ventilate period its The predetermined value of wind speed and air quantity arranges alarming value to air velocity transducer, if blower fan is stopped transport, blower fan air supply ability is not enough, wind Speed is the lowest, and down-hole air velocity transducer just can send sound and light alarm, by the ventilation monitoring software at ground monitoring center, and can be real Time monitoring each tunnel, down-hole in wind speed and the change of air quantity, can realize the effectively management to whole mine ventilation system with And the prevention of accident." crucial ring " technology is that the ventilation monitoring system in the Internet of Things construction of whole mine provides reason simultaneously Opinion basis and technological guidance.
The above, the only present invention preferably detailed description of the invention, but protection scope of the present invention is not limited thereto, Any those familiar with the art in the technical scope of present disclosure, the change that can readily occur in or replace Change, all should contain within protection scope of the present invention.Therefore, protection scope of the present invention should be with claims Protection domain is as the criterion.

Claims (1)

1. turbulent fluid flow-measuring method in a tunnel based on crucial ring, it is characterised in that include step:
First, determining the cross sectional shape in tunnel, then determine its crucial ring according to the cross sectional shape in tunnel, the wind speed at described crucial ring is equal to the mean wind speed on cross section, described tunnel;
Then, by measuring the wind speed of arbitrfary point on crucial ring, i.e. obtain the mean wind speed on this cross section, the flow of fluid in tunnel can be calculated according to mean wind speed;
The cross sectional shape in described tunnel is trapezoid cross section or basket handle arch cross section;
For trapezoid cross section, determine bottom side length on it, the length of side of going to the bottom and height, calculate the position of its crucial ring according to following table:
In above formula: the trapezoidal upper bottom side length of b, m;The trapezoidal length of side of going to the bottom of c, m;The trapezoidal height of H, m;Abscissa corresponding to x key ring, m;Vertical coordinate corresponding to y key ring, m;The crucial ring characteristic equation of f (x), y value;
For basket handle arch cross section, the length of side that determines that three-core arch wall is high and basket handle arch is gone to the bottom, the position of its crucial ring is calculated according to following table:
In above formula: h three-core arch wall is high, m;Go to the bottom the length of side in d basket handle arch cross section, m;r1Basket handle arch section-top arc radius, m;Abscissa corresponding to x key ring, m;Vertical coordinate corresponding to y key ring, m;The crucial ring characteristic equation of f (x), y value.
CN201310546143.8A 2013-11-06 2013-11-06 Turbulent fluid flow-measuring method in tunnel based on crucial ring Active CN103557898B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310546143.8A CN103557898B (en) 2013-11-06 2013-11-06 Turbulent fluid flow-measuring method in tunnel based on crucial ring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310546143.8A CN103557898B (en) 2013-11-06 2013-11-06 Turbulent fluid flow-measuring method in tunnel based on crucial ring

Publications (2)

Publication Number Publication Date
CN103557898A CN103557898A (en) 2014-02-05
CN103557898B true CN103557898B (en) 2016-08-17

Family

ID=50012208

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310546143.8A Active CN103557898B (en) 2013-11-06 2013-11-06 Turbulent fluid flow-measuring method in tunnel based on crucial ring

Country Status (1)

Country Link
CN (1) CN103557898B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109085379B (en) * 2018-06-27 2020-10-23 中煤科工集团重庆研究院有限公司 Roadway average wind speed measuring method
CN110398612A (en) * 2019-07-22 2019-11-01 北京奥世欣创科技有限公司 The measuring and monitoring method of ventilation quantity in a kind of tunnel
CN115683243A (en) * 2022-10-19 2023-02-03 西安京兆电力科技有限公司 Air quantity measuring system of non-uniform wind field air duct

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102706532A (en) * 2012-06-01 2012-10-03 华南理工大学 Method for measuring uniformity of wind field in wind tunnel
CN102852555A (en) * 2012-05-31 2013-01-02 山东科技大学 Advanced prediction method of single-alley tunneling gas outburst

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5153665A (en) * 1991-06-14 1992-10-06 The United States Of America As Represented By The Administrator Of The National Aeronautics And Space Administration Vaporizing particle velocimeter
CN103148007A (en) * 2012-11-27 2013-06-12 洛阳源创电气有限公司 Mine ventilating fan control system capable of automatically adjusting air quantity

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852555A (en) * 2012-05-31 2013-01-02 山东科技大学 Advanced prediction method of single-alley tunneling gas outburst
CN102706532A (en) * 2012-06-01 2012-10-03 华南理工大学 Method for measuring uniformity of wind field in wind tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
矿井巷道中外源气体运移-弥散过程仿真研究;李宗翔,王天明,贾进章;《中国矿业大学学报》;20130930;第42卷(第5期);全文 *

Also Published As

Publication number Publication date
CN103557898A (en) 2014-02-05

Similar Documents

Publication Publication Date Title
Ren et al. CFD modelling of ventilation and dust flow behaviour above an underground bin and the design of an innovative dust mitigation system
CN105118367B (en) A kind of rail-road shares shield tunnel Fire Ventilation smoke evacuation analogue experiment installation
CN103603691B (en) A kind of mine ventilation dynamic resolving and analysis early warning method and system
CN103557898B (en) Turbulent fluid flow-measuring method in tunnel based on crucial ring
Arya et al. Design and experimental evaluation of a flooded-bed dust scrubber integrated into a longwall shearer
CN204591331U (en) The mine development end dash system of adjoint high-concentration hydrogen sulfide and gas
CN102944664B (en) The method of test coal gas desorption properties
Liu et al. The influence of ventilation parameters on dust pollution in a tunnel's environment using the CFD method
CN205028570U (en) Public iron sharing shield tunnel conflagration simulation experiment device of discharging fume that ventilates
Ren et al. Computational fluid dynamics modelling of respirable dust and gas behaviour on a longwall face
CN108087012A (en) A kind of mine skip shaft outgoing airflow shuts off partition apparatus
Khave TBM tunnelling in hydrogen sulfide gas bearing ground and its solutions
CN203587585U (en) Novel methane sensor
CN104500142A (en) Underground coal mine dust measuring device
Wang et al. Numerical investigations of airflow patterns on a longwall face
CN207408175U (en) A kind of coal mine gob pernicious gas multipoint acquisition detection device
CN110985129B (en) Coal and gas outburst catastrophe identification method for coal mining working face
Brune Mine ventilation networks optimized for safety and productivity
CN204941603U (en) A kind of mine safety system
CN212154837U (en) Tunnel dust removal curtain device
Rider et al. Benchmarking longwall dust control technology and practices
CN202611702U (en) Water mist and foam dust settling device
Juganda CFD modeling of a tailgate ventilation condition in a longwall bleeder system
Meyer Advancing the technology of methane monitoring on a continuous miner
CN205445651U (en) Modified mine ventilation device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant