CN103498405A - Paver - Google Patents

Paver Download PDF

Info

Publication number
CN103498405A
CN103498405A CN201310487477.2A CN201310487477A CN103498405A CN 103498405 A CN103498405 A CN 103498405A CN 201310487477 A CN201310487477 A CN 201310487477A CN 103498405 A CN103498405 A CN 103498405A
Authority
CN
China
Prior art keywords
paver
mobile jib
lifting
secondary bar
amplitude
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310487477.2A
Other languages
Chinese (zh)
Other versions
CN103498405B (en
Inventor
谢卓君
黄忠敏
徐仁建
罗海斌
刘东海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Longjia Food Co ltd
Original Assignee
Zoomlion Heavy Industry Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zoomlion Heavy Industry Science and Technology Co Ltd filed Critical Zoomlion Heavy Industry Science and Technology Co Ltd
Priority to CN201310487477.2A priority Critical patent/CN103498405B/en
Publication of CN103498405A publication Critical patent/CN103498405A/en
Application granted granted Critical
Publication of CN103498405B publication Critical patent/CN103498405B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Machines (AREA)

Abstract

The invention provides a paver comprising a frame, a hopper, a screed plate and a lifting device. The hopper and the screed plate are arranged on the frame, and the lifting device is arranged on the frame to lift the screed plate. According to the paver, by the lifting device arranged on the frame, the screed plate can be lifted through the lifting device when being mounted and demounted, labor intensity of workers is reduced, other lifting equipment is not required, and accordingly time and cost are saved, and efficiency is improved.

Description

Paver
Technical field
The present invention relates to the road construction machinery field, in particular to a kind of paver.
Background technology
Paver is the equipment for road construction and pavement maintenance, and its effect is to pave equably on smooth good roadbed or basic unit being used for the good compound (comprising bituminous concrete and basic unit's Stabilized Soil) by mixing.Particularly, the paving machine is in paving process, at first accept by hopper the compound shipped from dump truck, by screw material-distributing system, it is laterally evenly paved and is dispersed in roadbed or basic unit again, finally by screed with preliminary compacting, shaping, form a laying that one fixed width, certain thickness and definite shape are arranged.
According to the needs of construction width, paver can be widened screed, and screed is widened the modes such as general employing hydraulically extensible and mechanical splice.Relative hydraulic telescopic type, the screed that the mechanical splice formula is widened is rigidly connected by bolt, large and bear good rigidly under larger load in width widen, can guarantee control accuracy and the paving effect of paver, for large-scale high-grade engineerings such as speedways, machinery is widened screed and is possessed obvious advantage.
Yet, while installing with the lengthening spiral mechanical splice formula screed is assembled, ironing board and spiral are heavier, manually are difficult to lift, need to temporarily transfer third-party hanging device, as crane, loader etc.But, in work progress, hanging device is often in other duties, not necessarily on time used by being required to be the installation paver, delays man-hour.In addition, the weight of screed and helical axis generally is not more than 2 tons, if temporarily transfer other special hoisting equipment, its lifting weight, much smaller than the ability to work of hanging device, is wasted one's talent on a petty job, and wastes man-hour.
Summary of the invention
The present invention aims to provide paver for convenience detach and the installation screed.
The invention provides a kind of paver, comprise frame, be arranged on hopper and screed on frame, paver also comprises lifting gear, and lifting gear is arranged on frame with the lifting screed.
Further, lifting gear comprises mount pad and is arranged on rotationally the lift arm assembly on mount pad.
Further, lift arm assembly comprises: mobile jib, and the vertical direction of take is arranged on mount pad as axis rotationally; Secondary bar, on the hinged mobile jib of first end; The luffing pulling device, between the second end of the upper end of the mobile jib that length connects adjustablely and secondary bar to regulate the amplitude of secondary bar; Suspension hook, be arranged on the second end of secondary bar by lifting pulley group adjustable ground.
Further, the luffing pulling device is the luffing assembly pulley.
Further, the lifting pulley group has the lifting reel of Wound steel rope with the adjusting lift hook height, and lifting reel drives by motor or rocking handle; The luffing assembly pulley has Wound steel rope to regulate the amplitude-changing drum of secondary bar amplitude, and amplitude-changing drum drives by motor or rocking handle.
Further, lifting reel and amplitude-changing drum respectively correspondence be provided with the anti-anxious inversion set that returns.
Further, lift arm assembly also comprises the transfer that drives mobile jib to rotate relative to mount pad.
Further, transfer is the steering wheel be fixedly installed on mobile jib, or the motor gear mechanism that drives mobile jib to rotate.
Further, mount pad be provided with thrust bearing and self-aligning bearing corresponding to the bottom of mobile jib.
Further, secondary bar comprises the body of rod and removably is connected to the connector at body of rod two ends.
According to paver of the present invention, by lifting gear is set on frame, when the installation and removal screed, can lift screed by lifting gear, alleviate labor strength, also need not call other hanging devices, thereby save time, save cost, raise the efficiency.
The accompanying drawing explanation
The accompanying drawing that forms the application's a part is used to provide a further understanding of the present invention, and schematic description and description of the present invention the present invention does not form inappropriate limitation of the present invention for explaining.In the accompanying drawings:
Fig. 1 is the structural representation according to paver of the present invention;
Fig. 2 is the structural representation according to lifting gear of the present invention;
Fig. 3 is the connection diagram according to mobile jib of the present invention and mount pad;
Fig. 4 is the main TV structure schematic diagram according to secondary bar of the present invention; And
Fig. 5 is the side-looking structural representation according to secondary bar of the present invention.
The specific embodiment
Describe below with reference to the accompanying drawings and in conjunction with the embodiments the present invention in detail.
As shown in Figure 1, according to paver of the present invention, comprise frame 10, be arranged on hopper 20 and screed 30 on frame 10, paver also comprises lifting gear 40, and lifting gear 40 is arranged on frame 10 with lifting screed 30.The present invention, by lifting gear 40 is set on frame 10, when installation and removal screed 30, can lift screeds 30 by lifting gear 40, alleviate labor strength, also need not call other hanging devices, thereby save time, save cost, raise the efficiency.
Particularly, shown in Fig. 1 and Fig. 2, lifting gear 40 comprises mount pad 41 and is arranged on rotationally the lift arm assembly on mount pad 41, and lift arm assembly can rotate relative to mount pad 41 in horizontal plane, also can carry out corresponding luffing operation, thereby meet lifting requirements.
Particularly, lifting gear can adopt the form of structure such as masts type, telescopic boom, cable type and truss-like.Preferably, in an embodiment of the present invention, adopt masts type, masts type lifting gear structure is relatively simple, mounts and dismounts more conveniently, manufactures simply, with low cost, takes up room little, and changes little to existing paver.
Particularly, the lift arm assembly of masts type lifting gear comprises mobile jib 42, secondary bar 43, suspension hook 44 and lifting pulley group 45, mobile jib 42 be take vertical direction and is arranged on rotationally on mount pad 41 as axis, preferably, shown in Fig. 3, mobile jib 42 is connected with thrust bearing 41a and self-aligning bearing 41b and axle sleeve with the centre of mount pad 41, thrust bearing 41a bears the axial load of mobile jib 42, self-aligning bearing 41b bear radially bend load by, thereby make mobile jib 42 to rotate around axis in horizontal plane.On the hinged mobile jib 42 of first end of secondary bar 43, the second end of secondary bar 43 and the upper end of mobile jib 42 are connected with the luffing pulling device, thus the amplitude that secondary bar 43 is regulated on the adjustable ground of the length of luffing pulling device.Suspension hook 44 is arranged on the second end of secondary bar 43 by lifting pulley group 45 adjustable grounds, by the height of lifting pulley group 45 adjusting lift hooks 44, thereby screed is sling.
Preferably, the luffing pulling device adopts luffing assembly pulley 46, and luffing assembly pulley 46 is equipped with on mobile jib 42 and secondary bar 43 to regulate the amplitude of secondary bar 43.In secondary bar 43 luffing operating process, drive suspension hook 44 motions, thereby adjust the operating radius of suspension hook.
More specifically, lifting pulley group 45 has the lifting reel 45a of Wound steel rope with adjusting lift hook 44 height, and lifting reel 45a drives by motor or rocking handle, in lifting reel 45a rotation process, and the height of adjusting lift hook 44, thus screed is lifted by crane.Luffing assembly pulley 46 has Wound steel rope to regulate the amplitude-changing drum 46a of secondary bar 43 amplitudes, amplitude-changing drum 46a drives by motor or rocking handle, in amplitude-changing drum 46a rotation process, makes relative mobile jib 42 motions of secondary bar 43, regulate the amplitude of secondary bar 43, thus the operating radius of adjusting lift hook 44.
Preferably, lift arm assembly also comprises the transfer 47 that drives mobile jib 42 to rotate relative to mount pad 41, by transfer 47, rotates mobile jib 41, thus the direction of regulating secondary bar 43 and suspension hook 44.Transfer 47 can, for being fixedly installed on the steering wheel on mobile jib 42, rotate thereby manually rotate steering wheel the orientation that mobile jib 42 carrys out adjusting lift hook.Transfer 47 also can adopt motor or hydraulic motor directly to drive, or through chain or gear speed governing rear drive.
Lifting gear is by arranging the degree of freedom of amplitude-changing drum 46a, lifting reel 45a and transfer 47 adjusting lift hooks 44, be that lifting gear is adjusted the direction of secondary bar 43 and suspension hook 44 by transfer 47, manually control the pulley winding by amplitude-changing drum 46a and lifting reel 45a suspension hook 44 is moved or lifting.Suspension hook 44 has 3 degree of freedom of movement in rotation, one-movement-freedom-degree and the vertical plane in horizontal plane like this, can adapt to lifting and the installation of different operating mode diverse locations.
Because the weight of screed is relatively little, generally be no more than 2 tons, lifting reel 45a, amplitude-changing drum 46a and transfer 47 all can adopt hand-driven mode, and lifting reel 45a, amplitude-changing drum 46a are by the rocking handle manual drive, and transfer 47 is steering wheel.Adopt hand-driven mode, effectively reduced the complexity of lifting gear, make its structure simpler, installation and easy to operate, improve reliability, and can effectively reduce costs.
Preferably, lifting reel 45a and amplitude-changing drum 46a correspondence respectively are provided with anti-anxious time inversion set 48, thereby prevent that weight from dropping suddenly, guarantee safety, preferably, the anti-anxious inversion set that returns is comprised of crevis and ratchet, also can adopt brake type, clutch type etc. to prevent the device of reversion.
As shown in Figure 4 and Figure 5, in preferred embodiment of the present invention, secondary bar 43 comprises body of rod 43a and removably is connected to the connector 43b at body of rod 43a two ends, and connector 43b and the mobile jib of first end are hinged, and the connector 43b of the second end and lifting pulley group 45 and luffing assembly pulley 46 are connected.Secondary bar 43 adopts this dismountable structure design, can change as required the body of rod of different length, thus make lift by crane radius and rangeability is larger.More preferably, body of rod 43a can adopt steel pipe, as required, can be replaced by the steel pipe of different length, in order to improve intensity, also can adopt two steel pipes, connector 43b is plugged on the two ends of two steel pipes simultaneously simultaneously, easy to connect reliable, steel pipe can directly be used the screw pull rod of existing paver, thereby the raising material use, reduce costs, conserve space.
Shown in Fig. 1, during the paver running, construction the tractor driver usually be placed on the lengthening screed disassembled in hopper.Before construction, need to be spliced on the basic screed in rear portion lengthening screed.In order to hang the tailstock from hopper by lengthening ironing board, in order to make lifting gear screed can be lifted into from hopper to the tailstock, lifting gear 40 can be arranged on the middle part of frame, in the situation that the operating radius of lifting gear 40 is enough large, also can be arranged on front portion or the rear portion of frame.During actual installation, the corresponding pedestal with bolt hole can be set on frame, then mount pad be bolted on pedestal, thereby lifting gear 40 removably is fixed on frame.
As can be seen from the above description, the above embodiments of the present invention have realized following technique effect:
According to paver of the present invention, by lifting gear is set on frame, when the installation and removal screed, can lift screed by lifting gear, alleviate labor strength, also need not call other hanging devices, thereby save time, raise the efficiency.And it is low that paver has the chassis center of gravity, the characteristics that the fuselage deadweight is larger, after lifting gear is installed, have good overturn-preventing.
The foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, for a person skilled in the art, the present invention can have various modifications and variations.Within the spirit and principles in the present invention all, any modification of doing, be equal to replacement, improvement etc., within all should being included in protection scope of the present invention.

Claims (10)

1. a paver, comprise frame (10), be arranged on hopper (20) and screed (30) on described frame (10), it is characterized in that, described paver also comprises lifting gear (40), and it is upper to lift described screed (30) that described lifting gear (40) is arranged on described frame (10).
2. paver according to claim 1, is characterized in that,
Described lifting gear (40) comprises mount pad (41) and is arranged on rotationally the lift arm assembly on described mount pad (41).
3. paver according to claim 2, is characterized in that, described lift arm assembly comprises:
Mobile jib (42), the vertical direction of take is arranged on described mount pad (41) rotationally as axis;
Secondary bar (43), on the hinged described mobile jib of first end (42);
The luffing pulling device, between the upper end of the described mobile jib (42) that length connects adjustablely and the second end of described secondary bar (43) to regulate the amplitude of described secondary bar (43);
Suspension hook (44), be arranged on the second end of described secondary bar (43) by lifting pulley group (45) adjustable ground.
4. paver according to claim 3, is characterized in that,
Described luffing pulling device is luffing assembly pulley (46).
5. paver according to claim 4, is characterized in that,
Described lifting pulley group (45) has Wound steel rope to regulate the lifting reel (45a) of described suspension hook (44) height, and described lifting reel (45a) drives by motor or rocking handle;
Described luffing assembly pulley (46) has Wound steel rope to regulate the amplitude-changing drum (46a) of described secondary bar (43) amplitude, and described amplitude-changing drum (46a) drives by motor or rocking handle.
6. paver according to claim 5, is characterized in that,
Described lifting reel (45a) and described amplitude-changing drum (46a) correspondence respectively are provided with the anti-anxious inversion set (48) that returns.
7. according to the described paver of claim 3 or 4, it is characterized in that,
Described lift arm assembly also comprises the transfer (47) that drives described mobile jib (42) to rotate relative to described mount pad (41).
8. paver according to claim 7, is characterized in that,
Described transfer (47) is for to be fixedly installed on the steering wheel on described mobile jib (42), or the motor gear mechanism that drives described mobile jib (42) to rotate.
9. paver according to claim 3, is characterized in that,
Described mount pad (41) be provided with thrust bearing (41a) and self-aligning bearing (41b) corresponding to the bottom of described mobile jib (42).
10. paver according to claim 3, is characterized in that,
Described secondary bar (43) comprises the body of rod (43a) and removably is connected to the connector (43b) at the described body of rod (43a) two ends.
CN201310487477.2A 2013-10-17 2013-10-17 Paver Active CN103498405B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310487477.2A CN103498405B (en) 2013-10-17 2013-10-17 Paver

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310487477.2A CN103498405B (en) 2013-10-17 2013-10-17 Paver

Publications (2)

Publication Number Publication Date
CN103498405A true CN103498405A (en) 2014-01-08
CN103498405B CN103498405B (en) 2015-08-05

Family

ID=49863655

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310487477.2A Active CN103498405B (en) 2013-10-17 2013-10-17 Paver

Country Status (1)

Country Link
CN (1) CN103498405B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590308A (en) * 2013-11-04 2014-02-19 湖南三一路面机械有限公司 Paving machine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5015120A (en) * 1987-08-25 1991-05-14 Barber-Greene Company Methods and apparatus for making an asphalt-aggregate pavement
JP2009287301A (en) * 2008-05-30 2009-12-10 Sumitomo (Shi) Construction Machinery Manufacturing Co Ltd Wheel type road paving machine
CN101649599A (en) * 2009-09-01 2010-02-17 句容市宁武化工有限公司 Paver special for epoxy asphalt
CN102061656A (en) * 2010-11-23 2011-05-18 中国二十二冶集团有限公司 Assembly vehicle for ironing plate of paver
CN102409597A (en) * 2011-11-11 2012-04-11 中联重科股份有限公司 Ironing plate and spreading machine
CN202440745U (en) * 2012-02-23 2012-09-19 三一重工股份有限公司 Wheel type paver lifting device and wheel type paver

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5015120A (en) * 1987-08-25 1991-05-14 Barber-Greene Company Methods and apparatus for making an asphalt-aggregate pavement
JP2009287301A (en) * 2008-05-30 2009-12-10 Sumitomo (Shi) Construction Machinery Manufacturing Co Ltd Wheel type road paving machine
CN101649599A (en) * 2009-09-01 2010-02-17 句容市宁武化工有限公司 Paver special for epoxy asphalt
CN102061656A (en) * 2010-11-23 2011-05-18 中国二十二冶集团有限公司 Assembly vehicle for ironing plate of paver
CN102061656B (en) * 2010-11-23 2013-02-13 中国二十二冶集团有限公司 Assembly vehicle for ironing plate of paver
CN102409597A (en) * 2011-11-11 2012-04-11 中联重科股份有限公司 Ironing plate and spreading machine
CN202440745U (en) * 2012-02-23 2012-09-19 三一重工股份有限公司 Wheel type paver lifting device and wheel type paver

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590308A (en) * 2013-11-04 2014-02-19 湖南三一路面机械有限公司 Paving machine
CN103590308B (en) * 2013-11-04 2016-04-06 湖南三一路面机械有限公司 Paver

Also Published As

Publication number Publication date
CN103498405B (en) 2015-08-05

Similar Documents

Publication Publication Date Title
CN104891396B (en) Telescopic arm crawler type aerial work platform
CN103303817B (en) Hoisting mechanism and dynamic compactor
CN103010966A (en) Multi-functional material conveying, distributing and hoisting equipment
CN202449769U (en) Superlift device for liftable self-propelled crawler and crane
CN106087990B (en) Movable reinforcement cage installs equipment
CN202658902U (en) Hoisting and spreading dual-purpose type concrete spreader
CN103498405B (en) Paver
CN103253602B (en) The elevated super lifting device of crawler vehicle voluntarily and hoisting crane
CN207209809U (en) A kind of extraordinary Dramatic Air Lifts
CN204454333U (en) Wind-power tower manufactures special crawler belt suspension transferring machine
CN109384162A (en) A kind of planer-type component transportation vehicle and component conveying method
CN107344698A (en) A kind of extraordinary Dramatic Air Lifts
CN208037866U (en) A kind of Architectural Equipment hanging apparatus
CN210684379U (en) Material paving device and paving vehicle for roadbed earthwork and road surface material filling
CN204324755U (en) A kind of tower crane for building engineering
CN204487811U (en) Concrete mixer travel steering device and concrete mixer thereof
CN206266124U (en) Rubber tired crane
US20190136465A1 (en) Articulating rolling compactor attachment
CN103590308B (en) Paver
CN211569924U (en) Self-disassembling device for crane boom of tower crane
CN207175317U (en) A kind of terrace project crane
CN202865819U (en) Strong compaction machine and upper segment arm device thereof
CA2919767C (en) Luffing cross member
CN203411257U (en) Hoisting mechanism and dynamic compactor
CN204675234U (en) Adjustable counterweight mechanism

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20161212

Address after: Five groups of North Hunan Province Chengguan town Yueyang city Huarong County 414200

Patentee after: Huang Wanhui

Address before: 410013 Yuelu District, Hunan, silver basin Road, No. 361, No.

Patentee before: ZOOMLION HEAVY INDUSTRY SCIENCE&TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220623

Address after: 414200 Zhang Hua Zhen Shi Fu Cun Zhu tou Shan, Huarong County, Yueyang City, Hunan Province

Patentee after: Hunan Longjia Food Co.,Ltd.

Address before: 414200 group 5, North Street, Chengguan Town, Huarong County, Yueyang City, Hunan Province

Patentee before: Huang Wanhui