CN103464468B - Method for controlling weight deviation through after-rolling length of hot-rolled steel bar - Google Patents

Method for controlling weight deviation through after-rolling length of hot-rolled steel bar Download PDF

Info

Publication number
CN103464468B
CN103464468B CN201310355486.6A CN201310355486A CN103464468B CN 103464468 B CN103464468 B CN 103464468B CN 201310355486 A CN201310355486 A CN 201310355486A CN 103464468 B CN103464468 B CN 103464468B
Authority
CN
China
Prior art keywords
weight
deviation
hot
strand
rolled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310355486.6A
Other languages
Chinese (zh)
Other versions
CN103464468A (en
Inventor
鲁维东
周旭东
赵肖飞
王洪锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Jiu Steel Group Hongxing Iron and Steel Co Ltd
Original Assignee
Gansu Jiu Steel Group Hongxing Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Jiu Steel Group Hongxing Iron and Steel Co Ltd filed Critical Gansu Jiu Steel Group Hongxing Iron and Steel Co Ltd
Priority to CN201310355486.6A priority Critical patent/CN103464468B/en
Publication of CN103464468A publication Critical patent/CN103464468A/en
Application granted granted Critical
Publication of CN103464468B publication Critical patent/CN103464468B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Metal Rolling (AREA)

Abstract

The invention discloses a method for controlling weight deviation through after-rolling length of a hot-rolled steel bar. A numerical relationship model between the weight deviation of a steel bar and the weight of a single ingot blank, the oxidation burning loss of the single ingot blank, the rolling process cutting loss of the single ingot blank and the total after-rolling length of the hot-rolled steel bar is established, the control on the weight deviation is realized through adjusting the total after-rolling length of the hot-rolled steel bar, and the numerical relationship model of the parameters is shown in the formula. The method has the advantages that the operability is strong and the method is easy to master, the weight deviation of a hot-rolled ribbed steel bar can be measured by means of monitoring and stabilizing the piece weight of an ingot blank, tracing the weight deviations corresponding to the after-rolling total lengths of different specifications of hot-rolled ribbed steel bars and utilizing the after-rolling total length which is displayed in online and real-time manners, of the hot-rolled ribbed steel bar, so that the effects of visualization and real-time monitoring are realized, the frequency and number of sampling are greatly reduced, and the labor intensity of workers is reduced.

Description

The method of rear cut to lengthen deviation of weight is rolled by hot-rolled reinforced bar
Technical field
The invention belongs to reinforcing bar rolling technical field, particularly relate to a kind of hot-rolled ribbed and plain bar rolls rear cut to lengthen deviation of weight method by hot-rolled reinforced bar.
Background technology
In standard GB/T 1499.2-2007 " concrete reinforcement steel part 2 hot rolled ribbed bars " and GB1499.1-2008 " concrete reinforcement steel part 1 hot calendering round bar ", the deviation of weight of different size hot-rolled reinforced bar is made and has explicitly called for.According to the rules, often criticize reinforcing bar and roll rear needs sampling and carry out weighing and detect rear calculating, just can know deviation of weight.In production reality, often find the problem of following two aspects: one is because reinforcing bar detection of weighing belongs to sampling observation, after rolling condition in the sampling observation time interval changes, the change of reinforcing bar deviation of weight can not Timeliness coverage, only has could find and corresponding adjustment to have hysteresis quality after sampling observation next time; Two is because reinforcing bar poker size has fluctuation, and the measurement result of the different reinforcing bar deviation of weight of sampling point is also different, can not reflect the deviation of weight actual state of whole reinforcing bar all-sidedly and accurately.For above problem, the art of this patent has invented effective computational methods, not only solves problem, and greatly reduces the sampling frequency, reduces the labour intensity of workman, achieves good effect.
Summary of the invention
The object of the invention is to for the deficiencies in the prior art, provide a kind of hot-rolled ribbed and plain bar to be rolled the method for rear cut to lengthen deviation of weight by hot-rolled reinforced bar.
For achieving the above object, the technical scheme that the present invention takes is:
A kind of method of being rolled rear cut to lengthen deviation of weight by hot-rolled reinforced bar, set up the deviation of weight of reinforcing bar and single strand weight, single strand oxidization burning loss, single strand operation of rolling cut damage, hot-rolled reinforced bar rolls numerical relation model between rear total length, the adjustment of rolling rear total length by hot-rolled reinforced bar realizes the control of deviation of weight, and the numerical relation model of described each parameter is:
In formula: the deviation of weight of F-reinforcing bar, W 0-mono-strand weight, W 1-mono-strand oxidization burning loss, W 2-mono-the strand operation of rolling cuts damage, and L-hot-rolled reinforced bar rolls rear total length, the theory every meter weight of M-reinforcing bar, -correction factor.
Described list props up strand oxidization burning loss W 1for single strand weight W 00.8 ~ 1.2%.
Described list props up the strand operation of rolling and cuts damage W 2for single strand weight W 00.8 ~ 1.6%.
The described method of being rolled rear cut to lengthen deviation of weight by hot-rolled reinforced bar, is comprised the following steps:
Step 1: single strand weight W 0calculating, according to the target control size of single strand and the solid density of strand, calculate single strand theoretical weight;
Step 2: single strand oxidization burning loss W 1for single strand weight W 00.8 ~ 1.2%;
Step 3: single the strand operation of rolling is cut and damaged W 2, be single strand weight W 00.8 ~ 1.6%;
Step 4: the deviation of weight F calculating reinforcing bar 1, found the theory every meter weight M of different size reinforcing bar by national standard, obtain hot-rolled reinforced bar by online display in real time and roll rear total length L, then by W 0, W 1, W 2substitute into relational expression, obtain: F 1=[(W 0-W 1-W 2)/(L × M)-1] × 100%;
Step 5: practice examining deviation of weight F 2, the reinforcing bar different parts after single strand rolling is taken to few 5 samples, detects the deviation of weight F of reinforcing bar by weight method 2;
Step 6: the deviation of weight F calculating reinforcing bar 1with practice examining deviation of weight F 2difference A, by the deviation of weight F of primary Calculation reinforcing bar 1with the deviation of weight F detecting reinforcing bar 2compare, the difference A of Reinforcing Steel Bar Calculation deviation of weight and actual sense weight deviation can be drawn, i.e. A=F 1-F 2;
Step 7: correction factor determination, through repeatedly repeated examinations test, namely repeat step 4 ~ 6, multiple A value can be obtained, get the mean value of multiple A value as correction factor;
Step 8: finally obtaining the relational expression that reinforcing bar deviation of weight and hot-rolled reinforced bar roll rear total length is:
F=[(W 0-W 1-W 2)/(L×M)-1]×100%+
Step 9: the deviation of weight desired value of the hot-rolled reinforced bar preset is substituted into the relational expression in step 8, can obtain corresponding hot-rolled reinforced bar and roll rear total length desired value;
Step 10: hot-rolled reinforced bar is rolled rear total length and be adjusted to desired value, rolls rear deviation of weight requirement with what meet hot-rolled reinforced bar.
Theoretically, the strand of certain substance, is rolled into the reinforcing bar of certain specification, and the total length rolling rear reinforcing bar should be definitely.In actual production process, because the substance of strand can produce fluctuation, strand heated oxide scaling loss have deviation, the sectional dimension of rolling concrete steel bar also has fluctuation, and namely deviation of weight produces fluctuation, therefore rolls that the total length of rear reinforcing bar is also corresponding to change.Generally, by the adjustment of conticaster, the substance change of strand is relatively very little, can be controlled within 3 ‰, therefore can be similar to and think that the substance of strand is stablized constant.In addition, under stable as-rolled condition, the heated condition of strand is substantially constant, and namely oxidization burning loss is also substantially identical.So, just there is directly related relation with steel area size and deviation of weight in the total length rolling rear reinforcing bar.
National regulations, the deviation of weight computing formula of reinforcing bar is formula (1), and regulation sample should intercept from different root reinforcing bar simultaneously, and quantity is no less than 5, often props up specimen length and is not less than 500mm.Length by a measurement, need should be accurate to 1mm.When measuring sample gross weight, should be accurate to and be not more than 1% of gross weight.
--formula (1).
When sampling amount is enough large, the whole reinforcing bar being about to shut out all detects as sample, above formula (1) can be converted to formula (2), thus, can set up reinforcing bar deviation of weight and the dependency relation formula of rolling rear reinforcing bar total length:
--formula (2).
Reinforcing bar actual gross weight deducts oxidization burning loss and process by strand substance and cuts damage and obtain in formula (2), and theoretical weight is the datum that standard specifies, reinforcing bar total length detects by electrical equipment and shows in real time.Therefore, the relation of reinforcing bar deviation of weight and total length can be set up and mutually solve, roll rear length by the reinforcing bar observing display in real time and just can calculate corresponding reinforcing bar deviation of weight, roll rear length with regard to adjustable reinforcing bar deviation of weight by adjustment reinforcing bar, reach and monitor in real time and adjust the object of reinforcing bar deviation of weight.
Method of being rolled rear cut to lengthen deviation of weight by hot-rolled reinforced bar provided by the invention, workable, be simple and easy to grasp, by monitoring and stablizing the substance of strand, tracking different size hot rolled ribbed bars rolls the deviation of weight corresponding to rear total length, utilize the hot rolled ribbed bars of online display in real time to roll rear total length, the deviation of weight of hot rolled ribbed bars can be calculated, thus reach directly perceived and the effect of monitoring in real time.Traditional sampling is weighed and is detected only as the means that a kind of selective examination and comparison confirm, thus greatly reduces the sampling frequency and quantity, reduces the labour intensity of workman.
Detailed description of the invention
Below in conjunction with specific embodiment, the present invention is described in further detail, but embodiments of the present invention are not limited thereto.
Embodiment 1:
The HRB400E hot rolled ribbed bars of rolling nominal diameter 16mm, it rolls by hot-rolled reinforced bar the method that rear total length controls deviation of weight, comprises the following steps:
1. single strand weight W 0calculating: according to the target control size of single strand and the solid density of strand, calculate single strand theoretical weight; To a large amount of strand weigh weighing results statistics after, draw single strand actual weight W 0, when single strand actual weight and theoretical weight differ by more than 3 ‰, can adjust strand length, until strand actual weight differs with theoretical weight be no more than 3 ‰.
Raw material list props up strand and is of a size of 150 × 149 × 12000mm, and the density of strand is 7.8kg/m 3, theoretical single strand weight W 0=1.5 × 1.5 × 120 × 7.8=2092kg.To weigh weighing results according to repeatedly strand again, show that the actual substance of strand is 2090kg, differ with theory calculate weight and be: (2090-2092)/2092=0.96 ‰, meet actual weight and theoretical weight is more or less the same in the condition of 3 ‰.
According to the corresponding relation between the size of heating furnace and the theoretical size of single strand, so substance W under determining the condition that strand length dimension sets by 12m 0=2092kg.
Because the cross dimensions of strand and length dimension are all on fluctuation ground, and the density of strand is also along with the change that do not coexist of pulling rate, therefore carry out selective examination of weighing at any time in process of production, when find strand substance exceed ± 3 ‰ scope time, the length adjustment of subsequent production strand will be carried out in time.After strand is produced, eave tile can be utilized to weigh, or the electronic scale of strand weight is monitored in configuration specially before heating furnace at once.Supposing weighs to former the strands produced exceeds standard, and notifies continuous casting adjustment immediately, can ensure that the strand of subsequent production is in claimed range.In order to ensure single strand weight W 0stable, maintenance to be made regular check on to continuous casting square billet Length-fixing cutting dolly and relevant device, ensure that cut lengths errors is within ± 20mm, and the adjustment of weighed by strand weight selective examination and Length-fixing cutting length, control the weight of continuous casting square billet to be stabilized in ± 3 ‰ scopes in, for steel rolling provides single strand weight W 0stable square billet.
2. single strand oxidization burning loss W 1: according to HRB400E heating cycle, in conjunction with the heating cycle of heating furnace actual operating state and square billet, single strand oxidization burning loss W 1for single strand weight W 01.0%, W 1=W 0× 1%=2092 × 1%=20.9kg.
3. single the strand operation of rolling is cut and is damaged W 2: the situation that comes into operation of cutting according to crop end in each specification reinforcing bar operation of rolling and sheared length, determine that the process of different size reinforcing bar rolling cuts damage amount W 2.According to rolling specs and slab quality, general W 2for single strand weight W 00.6 ~ 1.8%.
Rolling the crop amount that card section cuts during setting is thick is 20mm, and the crop amount that finish rolling card section is cut is 500mm, back-end crop amount is 500mm.Collect cutting head cutting tail amount during 20 strand rollings, weighing results is 440kg, therefore show that the operation of rolling is cut and damages W 2=440/20=22kg.Therefore can calculating single strand, to cut loss rate be 22/2092=1.05%, and namely single the strand operation of rolling is cut and damaged W 2=W 0× 1.05%=2092 × 1.05%=22kg.
4. calculate the deviation of weight F of reinforcing bar 1: the theory every meter weight M being found different size reinforcing bar by national standard, is obtained hot-rolled reinforced bar by online display in real time and rolls rear total length L, then by W 0, W 1, W 2substitute into relational expression, obtain: F 1=[(W 0-W 1-W 2)/(L × M)-1] × 100%.
According to table 2 in GB1499.2-2007, the theory every meter weight M that can find each size hot-rolled ribbed rebar is as follows:
Finding the theoretical every meter of weight M of 16mm hot rolled ribbed bars according to GB1499.2-2007 is 1.58kg/m, and after the rolling of the online strand of display in real time, reinforcing bar rolls rear total length L is 1340m, calculates the deviation of weight of reinforcing bar:
F 1=[(W 0-W 1-W 2)/(L×M)-1]×100%=[(W 0-W 0×1%-W 0×1.05%)/(L×M)-1]×100%
=[0.9795W 0/(L×M)-1]×100%=[(0.9795×2092)/(1340×1.58)-1]×100%=-3.31%。
5. practice examining deviation of weight F 2: the reinforcing bar different parts after single strand rolling is taken to few 5 samples (sampling number is more, and it is more accurate to detect), detects the deviation of weight F of reinforcing bar by weight method 2.
After this strand rolls, the different parts of reinforcing bar gets 10, the sample of 1m length respectively, and weighing up sample gross weight is 15.2kg, therefore can draw inspection deviation of weight: F 2=[15.2/(10 × 1.58)-1] × 100%=-3.80%.
6. calculate the deviation of weight F of reinforcing bar 1with practice examining deviation of weight F 2difference A: will the deviation of weight F of reinforcing bar be calculated 1with practice examining deviation of weight F 2compare, the difference A of Reinforcing Steel Bar Calculation deviation of weight and actual sense weight deviation can be drawn, i.e. A=F 1-F 2=F 1-F 2=-3.31-(-3.80)=0.49%.
7. correction factor determination: through repeatedly repeated examinations test, namely repeat step 4 ~ 6, multiple A value can be obtained, get the mean value of multiple A value as correction factor.
Repeat step 4 ~ 6 five ten time, 50 A values can be obtained, calculate the mean value of 50 A values: =0.26%.
8. finally obtaining 16mm specification HRB400E hot rolled ribbed bars deviation of weight with the relational expression of rolling rear length is:
F=[(W 0-W 1-W 2)/(L×M)-1]×100%+ =[(2047.1/1.58L)-1]×100%+(-0.26%)
Introduce correction factor object be exactly eliminate to calculate the deviation of weight F of reinforcing bar 1with practice examining deviation of weight F 2deviation, according to comparing result, F 1compare F 2large 0.26%, therefore to subtract 0.26%.
Hot-rolled reinforced bar rolls the actual total length of rear total length and single the later reinforcing bar on-line real-time measuremen of strand hot rolling.
9. the deviation of weight desired value of the hot-rolled reinforced bar preset is substituted into the relational expression in step 8, corresponding hot-rolled reinforced bar can be obtained and roll rear total length desired value.
According to the inner quality standard of enterprise, the deviation of weight of reinforcing bar is set with desired value, and enterprise can be as far as possible close to lower limit according to self control ability.Set desired value as-4.5%, F=-4.5% is substituted into above relational expression, obtain hot-rolled reinforced bar and roll rear total length desired value: L=2047.1/ [1.58 × (-0.045+0.0026+1)]=1353m.
10. hot-rolled reinforced bar is rolled rear total length and be adjusted to desired value, roll rear deviation of weight requirement with what meet hot-rolled reinforced bar.When hot-rolled reinforced bar roll rear total length exceed the control range of desired value length time, carry out corresponding rewinding or blowing adjustment, namely increase or reduce hot-rolled reinforced bar roll rear length, until hot-rolled reinforced bar rolls rear total length regressive object scope.
In general, for the hot-rolled reinforced bar of all specifications, according to practical condition, different desired value length variations scopes can be determined, as exceed during rolling 12mm specification reinforcing bar 0.2% of target length just need adjustment, and exceed during rolling 32mm specification reinforcing bar 1.5% of target length need adjustment.
Rolling operation work adjustment material molded dimension, progressively rolls rear total length desired value and adjusts to about 1353m by hot-rolled reinforced bar.Notice that the every root reinforcing bar observing online display in real time rolls rear length simultaneously, when length is at desired value ± 0.3%, i.e., within the scope of 1353 × 0.3%=± 4.1m during fluctuation, can adjust.When fluctuation range exceed ± 4.1m time carry out corresponding rewinding or blowing adjustment, just can ensure reinforcing bar deviation of weight fluctuate within ± 0.3%.
embodiment 2
The HPB300 hot calendering round bar of rolling nominal diameter 20mm, it rolls by hot-rolled reinforced bar the method that rear total length controls deviation of weight, comprises the following steps:
1. single strand weight W 0calculating: according to the target control size of single strand and the solid density of strand, calculate single strand theoretical weight; To a large amount of strand weigh weighing results statistics after, draw single strand actual weight W 0, when single strand actual weight and theoretical weight differ by more than 3 ‰, can adjust the length of subsequent production strand, until strand actual weight differs with theoretical weight be no more than 3 ‰.
Raw material strand is of a size of 150 × 149 × 12000mm, and the density of strand is 7.8kg/m 3, theoretical single strand weight W 0=1.5 × 1.49 × 120 × 7.8=2092kg.
To weigh weighing results according to repeatedly strand again, show that the actual substance of strand is 2085kg, differ with theory calculate weight and be: (2085-2092)/2092=-3.35 ‰, be discontented with sufficient actual weight and theoretical weight is more or less the same in the condition of 3 ‰.The length adjustment of subsequent production strand should be carried out in time, so suitably increase subsequent production strand length.Under final Cutting Length presses the condition of 12.08m setting, weigh statistics of weighing of strand substance is 2091kg, reaches condition.
Because the cross dimensions of strand and length dimension are all on fluctuation ground, and the density of strand is also along with the change that do not coexist of pulling rate, therefore carries out selective examination of weighing at any time in process of production, when discovery strand substance exceed ± 3 ‰ scope time, adjust in time.After strand is produced, eave tile can be utilized to weigh, or the electronic scale of strand weight is monitored in configuration specially before heating furnace at once.Supposing weighs to former the strands produced exceeds standard, and notifies continuous casting adjustment immediately, can ensure that the strand of subsequent production is in claimed range.In order to ensure single strand weight W 0stable, maintenance to be made regular check on to continuous casting square billet Length-fixing cutting dolly and relevant device, ensure that cut lengths errors is within ± 20mm, and the adjustment of weighed by strand weight selective examination and Length-fixing cutting length, control the weight of continuous casting square billet to be stabilized in ± 3 ‰ scopes in, for steel rolling provides single strand weight W 0stable square billet.
2. single strand oxidization burning loss W 1: according to HPB300 heating cycle, in conjunction with the heating cycle of heating furnace actual operating state and square billet, single strand oxidization burning loss W 1for single strand weight W 00.9%, W 1=W 0× 0.9%=2092 × 0.9%=18.8kg.
3. single the strand operation of rolling is cut and is damaged W 2: the situation that comes into operation of cutting according to crop end in each specification reinforcing bar operation of rolling and sheared length, determine that the process of different size reinforcing bar rolling cuts damage amount W 2.According to rolling specs and slab quality, general W 2for single strand weight W 00.6 ~ 1.8%.
Rolling the crop amount that card section cuts during setting is thick is 20mm, and the crop amount that finish rolling card section is cut is 400mm, back-end crop amount is 400mm.Collect cutting head cutting tail amount during 20 strand rollings, weighing results is 416kg, therefore show that the operation of rolling is cut and damages W 2=416/20=20.8kg.
Therefore can calculating single strand, to cut loss rate be 20.8/2092=0.99%, and namely single the strand operation of rolling is cut and damaged W 2=W 0× 0.99%=2092 × 0.99%=20.8kg.
4. the deviation of weight F of primary Calculation reinforcing bar 1: the theory every meter weight M being found different size reinforcing bar by national standard, is obtained hot-rolled reinforced bar by online display in real time and rolls rear total length L, then by W 0, W 1, W 2substitute into relational expression, obtain: F 1=[(W 0-W 1-W 2)/(L × M)-1] × 100%.
According to table 2 in GB1499.1-2008, the theory every meter weight M that can find each size hot-rolled ribbed rebar is as follows:
Finding the theoretical every meter of weight M of 20mm hot rolled ribbed bars according to GB1499.1-2008 is 2.47kg/m, and after the rolling of the online strand of display in real time, reinforcing bar rolls rear total length L is 870m, calculates the deviation of weight of reinforcing bar:
F 1=[(W 0-W 1-W 2)/(L×M)-1]×100%=[(W 0-W 0×0.9%-W 0×0.99%)/(L×M)-1]×100%
=[0.9811W 0/(L×M)-1]×100%=[(0.9811×2092)/(870×2.47)-1]×100%=-4.49%。
5. practice examining deviation of weight F 2: the reinforcing bar different parts after single strand rolling is taken to few 5 samples (sampling number is more, and it is more accurate to detect), detects the deviation of weight F of reinforcing bar by weight method 2.
After this strand rolls, the different parts of reinforcing bar gets 10, the sample of 1m length respectively, and weighing up sample gross weight is 23.7kg, therefore can draw inspection deviation of weight: F 2=[23.7/(10 × 2.47)-1] × 100%=-4.05%.
6. calculate the deviation of weight F of reinforcing bar 1with practice examining deviation of weight F 2difference A: will the deviation of weight F of reinforcing bar be calculated 1with practice examining deviation of weight F 2compare, the difference A of Reinforcing Steel Bar Calculation deviation of weight and actual sense weight deviation can be drawn, i.e. A=F 1-F 2=F 1-F 2=-4.49-(-4.05)=0.44%.
7. correction factor determination: through repeatedly repeated examinations test, namely repeat step 4 ~ 6, multiple A value can be obtained, get the mean value of multiple A value as correction factor.
Repeat step 4 ~ 6 five ten time, 50 A values can be obtained, calculate the mean value of 50 A values: be 0.31%.
8. finally obtaining 20mm specification HPB300 hot calendering round bar deviation of weight with the relational expression of rolling rear length is:
F=[(W 0-W 1-W 2)/(L×M)-1]×100%+ =[(2052.5/2.47L)-1]×100%+(-0.31%)。
Introduce correction factor object be exactly eliminate to calculate the deviation of weight F of reinforcing bar 1with practice examining deviation of weight F 2deviation, according to comparing result, F 1compare F 2large 0.31%, therefore to subtract 0.31%.
Hot-rolled reinforced bar rolls the actual total length of rear total length and single the later reinforcing bar on-line real-time measuremen of strand hot rolling.
9. the deviation of weight desired value of the hot-rolled reinforced bar preset is substituted into the relational expression in step 8, corresponding hot-rolled reinforced bar can be obtained and roll rear total length desired value.
According to the inner quality standard of enterprise, the deviation of weight of reinforcing bar is set with desired value, and enterprise can be as far as possible close to lower limit according to self control ability.Set desired value as-4.5%, F=-4.5% is substituted into above relational expression, obtain hot-rolled reinforced bar and roll rear total length desired value: L=2052.5/ [2.47 × (-0.045+0.0031+1)]=867.3m.
10. hot-rolled reinforced bar is rolled rear total length and be adjusted to desired value, roll rear deviation of weight requirement with what meet hot-rolled reinforced bar; When hot-rolled reinforced bar roll rear total length exceed the control range of desired value length time, carry out corresponding rewinding or blowing adjustment, namely increase or reduce hot-rolled reinforced bar roll rear length, until hot-rolled reinforced bar rolls rear total length regressive object scope.
Rolling operation work adjustment material molded dimension, progressively rolls rear length desired value and adjusts to about 867.3m by hot-rolled reinforced bar.Notice that the every root reinforcing bar observing online display in real time rolls rear length simultaneously, when length is at desired value ± 0.5%, i.e., within the scope of 867.3 × 0.5%=± 4.3m during fluctuation, can adjust.When fluctuation range exceed ± 4.3m time carry out corresponding rewinding or blowing adjustment, just can ensure reinforcing bar deviation of weight fluctuate within ± 0.3%.

Claims (4)

1. one kind is rolled the method for rear cut to lengthen deviation of weight by hot-rolled reinforced bar, it is characterized in that, set up the deviation of weight of reinforcing bar and single strand theoretical weight, single strand oxidization burning loss, single strand operation of rolling cut damage, hot-rolled reinforced bar rolls numerical relation model between rear total length, the adjustment of rolling rear total length by hot-rolled reinforced bar realizes the control of deviation of weight, and the numerical relation model of described each parameter is:
F=[(W 0-W 1-W 2)/(L × M)-1] × 100%+ in formula: the deviation of weight of F-reinforcing bar, W 0-mono-strand theoretical weight, W 1-mono-strand oxidization burning loss, W 2-mono-the strand operation of rolling cuts damage, and L-hot-rolled reinforced bar rolls rear total length, the theory every meter weight of M-reinforcing bar, -correction factor.
2. method of being rolled rear cut to lengthen deviation of weight by hot-rolled reinforced bar according to claim 1, be is characterized in that, described list props up strand oxidization burning loss W 1for single strand theoretical weight W 00.8 ~ 1.2%.
3. method of being rolled rear cut to lengthen deviation of weight by hot-rolled reinforced bar according to claim 1, be is characterized in that, described list props up the strand operation of rolling and cuts damage W 2for single strand theoretical weight W 00.8 ~ 1.6%.
4. method of being rolled rear cut to lengthen deviation of weight by hot-rolled reinforced bar according to claim 1, be is characterized in that, comprise the following steps:
Step 1: single strand theoretical weight W 0calculating, according to the target control size of single strand and the solid density of strand, calculate single strand theoretical weight;
Step 2: single strand oxidization burning loss W 1for single strand theoretical weight W 00.8 ~ 1.2%;
Step 3: single the strand operation of rolling is cut and damaged W 2, be single strand theoretical weight W 00.8 ~ 1.6%;
Step 4: the deviation of weight F calculating reinforcing bar 1, found the theory every meter weight M of different size reinforcing bar by national standard, obtain hot-rolled reinforced bar by online display in real time and roll rear total length L, then by W 0, W 1, W 2substitute into relational expression, obtain: F 1=[(W 0-W 1-W 2)/(L × M)-1] × 100%;
Step 5: practice examining deviation of weight F 2, the reinforcing bar different parts after single strand rolling is taken to few 5 samples, detects the deviation of weight F of reinforcing bar by weight method 2;
Step 6: the deviation of weight F calculating reinforcing bar 1with practice examining deviation of weight F 2difference A, by the deviation of weight F of primary Calculation reinforcing bar 1with the deviation of weight F detecting reinforcing bar 2compare, the difference A of Reinforcing Steel Bar Calculation deviation of weight and actual sense weight deviation can be drawn, i.e. A=F 1-F 2;
Step 7: correction factor determination, through repeatedly repeated examinations test, namely repeat step 4 ~ 6, multiple A value can be obtained, get the mean value of multiple A value as correction factor;
Step 8: finally obtaining the relational expression that reinforcing bar deviation of weight and hot-rolled reinforced bar roll rear total length is:
F=[(W 0-W 1-W 2)/(L×M)-1]×100%+
Step 9: the deviation of weight desired value of the hot-rolled reinforced bar preset is substituted into the relational expression in step 8, can obtain corresponding hot-rolled reinforced bar and roll rear total length desired value;
Step 10: hot-rolled reinforced bar is rolled rear total length and be adjusted to desired value, rolls rear deviation of weight requirement with what meet hot-rolled reinforced bar.
CN201310355486.6A 2013-08-15 2013-08-15 Method for controlling weight deviation through after-rolling length of hot-rolled steel bar Active CN103464468B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310355486.6A CN103464468B (en) 2013-08-15 2013-08-15 Method for controlling weight deviation through after-rolling length of hot-rolled steel bar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310355486.6A CN103464468B (en) 2013-08-15 2013-08-15 Method for controlling weight deviation through after-rolling length of hot-rolled steel bar

Publications (2)

Publication Number Publication Date
CN103464468A CN103464468A (en) 2013-12-25
CN103464468B true CN103464468B (en) 2015-04-15

Family

ID=49789635

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310355486.6A Active CN103464468B (en) 2013-08-15 2013-08-15 Method for controlling weight deviation through after-rolling length of hot-rolled steel bar

Country Status (1)

Country Link
CN (1) CN103464468B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108126988B (en) * 2017-12-13 2019-08-23 中冶京诚工程技术有限公司 Bar negative deviation on-line measuring method and system
CN112139240B (en) * 2020-08-11 2023-04-07 柳州钢铁股份有限公司 Production method for reducing performance line difference of reinforcing steel bar
CN112207129A (en) * 2020-09-30 2021-01-12 盐城市联鑫钢铁有限公司 Detection control method for out-of-roundness of base circle of hot-rolled ribbed steel bar
CN114042764B (en) * 2021-11-16 2024-05-07 重庆钢铁股份有限公司 Hot rolling production line yield prediction method and system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5125250A (en) * 1991-04-26 1992-06-30 China Steel Corporation Flying shear system with adaptive cut-length control and the operational method thereof
CN101053876A (en) * 2007-05-21 2007-10-17 武汉理工大学 Ring weight online weighing and rolling deviation dispensing method
CN101168171A (en) * 2007-12-11 2008-04-30 江苏沙钢集团有限公司 Method for controlling negative deviation of steel bar with rib
CN102294362A (en) * 2010-06-25 2011-12-28 鞍钢股份有限公司 Thickness precision control method for medium plate

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10305304A (en) * 1997-05-07 1998-11-17 Sanyo Special Steel Co Ltd Cutting billets

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5125250A (en) * 1991-04-26 1992-06-30 China Steel Corporation Flying shear system with adaptive cut-length control and the operational method thereof
CN101053876A (en) * 2007-05-21 2007-10-17 武汉理工大学 Ring weight online weighing and rolling deviation dispensing method
CN101168171A (en) * 2007-12-11 2008-04-30 江苏沙钢集团有限公司 Method for controlling negative deviation of steel bar with rib
CN102294362A (en) * 2010-06-25 2011-12-28 鞍钢股份有限公司 Thickness precision control method for medium plate

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"提高热轧带肋钢筋负偏差均衡率的生产实践";彭南超等;《河南冶金》;20070831;第15卷(第4期);全文 *

Also Published As

Publication number Publication date
CN103464468A (en) 2013-12-25

Similar Documents

Publication Publication Date Title
CN103464468B (en) Method for controlling weight deviation through after-rolling length of hot-rolled steel bar
CN106799406B (en) The full scale intelligence control system of rod type steel and scale control method
CN104128581B (en) A kind of online calibration method of fan-shaped sections of slab continuous
CN103170508B (en) Method for controlling width of hot rolling strip steel
CN108126988B (en) Bar negative deviation on-line measuring method and system
CN113083912B (en) Hot-rolled H-shaped steel temperature uniformity control system and control method thereof
CN106475543A (en) A kind of continuous casting billet cutting process scale compensation method
CN107442757A (en) A kind of continuous casting billets of fixed weight sizing and cut method
CN111666653B (en) Online judging method for setting precision of strip steel finish rolling model
CN110508627B (en) Comprehensive test platform and test method for regulating and controlling capability of electromagnetic regulating and controlling roller
CN104785534B (en) A kind of hot rolling width rapid correction method based on finish rolling measured data
CN105251778B (en) Feedback control method for edge thinning of single-taper working roll shifting rolling mill
CN107983778A (en) One kind is weighed milling method
CN103386472B (en) A kind of acquisition methods of continuous cast mold outlet base shell safe thickness and device
CN102277468B (en) Real-time forecasting method of LF refining furnace molten steel temperature
CN101614529A (en) A kind of method of on-line continuous monitoring appearance of continuous casting sheet billet
CN102371278B (en) Method for automatically controlling plate shape of continuous annealing leveling mill based on stability index
CN108655203A (en) The quick identification of hot-continuous-rolling strip steel camber defect and monitoring method
CN105855491A (en) Steel plate blank sizing measurement method based on encoder
CN112285212A (en) System and method for detecting concrete strength based on ultrasonic rebound method
CN104707869A (en) Hot rolling width model fast dynamic self-adapting method
CN103406369A (en) Method for improving strip steel head roll force precision by utilizing temperature function
CN113426840A (en) Negative tolerance rolling and short rule control method for bar production line
CN107941807B (en) Quantitative analysis method for center defects of continuous casting slab
CN105618490A (en) Automatic edge dropping control method for cold rolling electrical steel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant