CN103447579A - Combined system integrating scribing, drilling and threaded rod fastening and construction method - Google Patents

Combined system integrating scribing, drilling and threaded rod fastening and construction method Download PDF

Info

Publication number
CN103447579A
CN103447579A CN201310372071XA CN201310372071A CN103447579A CN 103447579 A CN103447579 A CN 103447579A CN 201310372071X A CN201310372071X A CN 201310372071XA CN 201310372071 A CN201310372071 A CN 201310372071A CN 103447579 A CN103447579 A CN 103447579A
Authority
CN
China
Prior art keywords
rod
vertical rod
cross bar
combined system
boring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310372071XA
Other languages
Chinese (zh)
Other versions
CN103447579B (en
Inventor
李义清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201310372071.XA priority Critical patent/CN103447579B/en
Publication of CN103447579A publication Critical patent/CN103447579A/en
Application granted granted Critical
Publication of CN103447579B publication Critical patent/CN103447579B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention discloses a combined system integrating scribing, drilling and threaded rod fastening and a construction method. The combined system comprises a scribing device, a drilling device and a fastening device. The scribing device comprises a support rod and a cross rod arranged at the top end of the support rod, wherein the support rod is a telescopic rod; a groove is formed in the cross rod; at least one vertical rod capable of moving along the groove is arranged in the groove, and is kept perpendicular to the cross rod all the time; a clamping groove for fixing an inking pen is formed in the top end of the vertical rod. The drilling device comprises a telescopic support and an electric drill arranged on the telescopic support, wherein a power switch of the electric drill is arranged on the telescopic support. The fastening device comprises a telescopic rod, wherein a chuck is fixedly arranged at the top end of the telescopic rod; a step hole is formed in the chuck; a rotating rod is arranged at the lower end of the telescopic rod. According to the combined system with the structure and the construction method, the construction efficiency can be effectively improved, the personal safety of an operator can be ensured, and the cost can be lowered.

Description

A kind of combined system and construction method that integrates setting-out, boring, fastening screw
Technical field
The present invention relates to the realm of building construction, specifically a kind of combined system and construction method that integrates setting-out, boring, fastening screw.
Background technology
In construction, in order to realize that on ceiling corresponding passage, electrical equipment, ornament etc. are installed, need to successively carry out setting-out, boring, the operation such as installation screw rod in the hole of having bored.Setting-out is that the place that needs are punched marks, and is convenient to the electric drill punching; Boring is that electricity consumption is drilled in the place of having done the punching mark, gets out a hole, for screw rod is installed; Screw rod is fixed on ceiling by other instrument, can play to miscellaneous equipment the effect of supplemental support.
Because ceiling is generally not low apart from the height of bottom surface, especially for office building, while carrying out setting-out, boring, installation screw rod on ceiling, all need to or directly take installing rack by mobile ladder, while using mobile ladder to carry out operation, need to move ladder to another place after completing the operation in a place, and then carry out operation, this mode efficiency is lower, operating personnel also may fall from ladder because of error or accident simultaneously, bring the hidden danger of personal safety to operating personnel.In addition, if adopt installing rack to carry out operation, need to build a large amount of installing racks, the installing rack of dismantling again after fulfiling assignment, adopt this mode to carry out operation, and not only cost is higher, and build and to remove and install frame more time-consuming.
Summary of the invention
The invention provides a kind of combined system and construction method that integrates setting-out, boring, fastening screw, solved current setting-out, boring, fastening screw or existed efficiency of construction lower, may bring personal safety hidden danger, or the higher problem of cost.
The present invention is that the technical solution problem is achieved through the following technical solutions: a kind of combined system that integrates setting-out, boring, fastening bolt comprises line-plotting device for doing mark for dowel hold, for the perforating device of boring, for screw rod being arranged on to the fastener on ceiling;
Further, the cross bar that described line-plotting device comprises support bar and is arranged on supporting bar top, described support bar is telescopic rod, described cross bar is provided with groove, at least be provided with the vertical rod that can move along this groove in this groove, it is vertical with cross bar that vertical rod remains, described rod end is provided with for the fixing draw-in groove of writing brush;
Further, described perforating device comprises telescope support and is arranged on the electric drill on telescope support, and the power switch of described electric drill is arranged on telescope support;
Further, described fastener comprises expansion link, and the top of described expansion link is fixed with chuck, and described chuck is provided with stepped hole, and the lower end of described expansion link is provided with bull stick.
The characteristics of line-plotting device, perforating device, fastener are, without by aerial device, operating personnel only need stand and can realize corresponding operation on the ground, as setting-out, punching, fastening screw.Line-plotting device is realized the adjusting of upper and lower distance by support bar, by being fixed on the writing brush in draw-in groove, the place that needs punching on ceiling is marked, so that accurately punching; Perforating device adopts bracing frame to accomplish highly adjusting, the contact that realizes electric drill and ceiling with separate; Fastener is used for screw rod is fixed in the installing hole bored, and by expansion link, regulates different height, the complete operation on the ground so that operating personnel can stand.
Further, also comprise pull bar, described vertical rod is provided with T-shaped groove, and an end of pull bar is fixed on cross bar, and the other end is buckled in the T-shaped groove in vertical rod, and is bolted.Pull bar can strengthen the stability of vertical rod, and an end of pull bar can move up and down in the T-shaped groove of vertical rod, to adapt to the position adjustments of vertical rod.
Further, also comprise reinforced pole, an end of described reinforced pole is fixed on support bar, and the other end is fixed on cross bar, and support bar, cross bar, reinforced pole surround an isosceles right triangle.Reinforced pole, for strengthening the connectivity robustness between support bar and cross bar, make total more firm, and triangle has higher stability.
Further, the groove on described cross bar is T-shaped groove, and the shape of vertical rod lower end and this T-shaped groove are complementary.T-shaped groove has certain effect of contraction to vertical rod, and vertical rod can only be moved along T-shaped groove, avoids vertical rod to topple over, and guarantees that vertical rod keeps vertical state.
Further, described telescope support comprises the first vertical rod, the first cross bar, the second vertical rod and the second cross bar, the first vertical rod and the first cross bar are flexibly connected, the first cross bar and the second vertical rod are flexibly connected, the second vertical rod and the second cross bar are flexibly connected, the second cross bar and the first vertical rod are flexibly connected, and electric drill is arranged on the upper end of the second vertical rod.The first vertical rod, as the core support bar, is propped up whole telescope support and electric drill, and the second cross bar is as adjusting rod, by lift or press down, regulate the vertical position of electric drill, to obtain required drillhole height.
Further, described the first vertical rod, the first cross bar, the second vertical rod, the second cross bar surround a rhombus, and the middle part of the middle part of the first vertical rod and the first cross bar is flexibly connected.Utilize the characteristic of rhombus itself, be convenient to regulate well the position of electric drill, and supporting role is preferably not only played in the first vertical rod, also make the first cross bar more laborsaving in the process of regulating the electric drill height simultaneously.
Further, the power switch of described electric drill is arranged in the first vertical rod, and an end of the second cross bar is connected with the movable upper end of the first vertical rod, and the middle part of the other end of the second cross bar and the second vertical rod is flexibly connected.Substantially keep motionless due to the first vertical rod when the drilling operation, power switch is arranged in the first vertical rod, one can increase the service life of power switch, also convenient in addition power switch is operated.
Further, described expansion link comprises the top body of rod, the middle part body of rod and the bottom body of rod connected successively, and the diameter of the described middle part body of rod is greater than the diameter of the top body of rod, and the diameter of the middle part body of rod is less than the diameter of the bottom body of rod.The structure of expansion link is relatively existing, a common technology to one skilled in the art, and its principle is the same with the expansion link of umbrella, and main purpose is be convenient to elongation and shrink, and conveniently works and carries.
Further, the top of described expansion link is provided with external screw thread, and the bottom of chuck is provided with tapped fixing hole, and chuck is fixed on expansion link by this fixing hole.After adopting between chuck and expansion link and being threaded, can facilitate the replacing of chuck.
A kind ofly adopt the above-mentioned construction method that integrates the combined system of setting-out, boring, fastening screw, comprise the following steps:
(a) distance to operate ground according to ceiling, the length of regulating the telescopic rod of line-plotting device, according to the needs of setting-out, determine quantity and the position of vertical rod on cross bar of vertical rod;
(b), by the writing brush in draw-in groove, on ceiling, the place in requisition for punching is marked;
(c) perforating device is placed in the punching mark under, open electric drill, press down the movable end of the first cross bar, the second vertical rod is moved upward, the electric drill of the second vertical rod upper end moves upward, holed in the place of doing the punching mark, and the backed off after random electric drill of having holed;
(d) regulate the length of the expansion link of fastener, screw rod to be installed is inserted in the chuck of fastener, by the bull stick on rotary fixture, in the corresponding installing hole screwed on ceiling of screw rod, complete screw rod and fix, take off fastener.
The present invention compared with prior art has the following advantages and beneficial effect:
(1) the present invention is by design line-plotting device, perforating device, threaded rod fastening device, in the process that completes setting-out, punching, installation screw rod, operating personnel can stand in the enterprising line operate in ground all the time, and operating efficiency is compared by mobile ladder higher, also can not bring the hidden danger of personal safety aspect simultaneously, build installing rack and compare, the present invention not only cost is lower, and efficiency of construction is also higher.
(2) the present invention adopts line-plotting device, perforating device, threaded rod fastening device to realize setting-out, punching, the operation of installation screw rod one continuous line, and each device closely cooperates, and each device is easy to operate, easy to learn, is conducive to popularize.
The accompanying drawing explanation
The structural representation of the line-plotting device that Fig. 1 is embodiments of the invention 1;
The structural representation of the line-plotting device that Fig. 2 is embodiments of the invention 2;
The structural representation of the line-plotting device that Fig. 3 is embodiments of the invention 3;
The structural representation of the perforating device that Fig. 4 is embodiments of the invention 1:
The structural representation of the fastener that Fig. 5 is embodiments of the invention 1.
The specific embodiment
Below in conjunction with embodiment, the present invention is described in further detail, but embodiments of the present invention are not limited to this.
Embodiment 1:
The present embodiment comprises line-plotting device for doing mark for dowel hold, for the perforating device of boring, for screw rod being arranged on to the fastener on ceiling;
As shown in Figure 1, the cross bar 12 that the line-plotting device of the present embodiment comprises support bar 11 and is arranged on support bar 11 tops, support bar 11 is telescopic rod, cross bar 12 is provided with groove, at least be provided with the vertical rod 13 that can move along this groove in this groove, as preferably, the present embodiment arranges two vertical rods 13, it is vertical with cross bar 12 that vertical rod 13 remains, vertical rod 13 tops are provided with for the fixing draw-in groove 14 of writing brush.
As shown in Figure 4, the perforating device of the present embodiment comprises telescope support and is arranged on the electric drill 21 on telescope support, and the power switch 26 of electric drill 21 is arranged on telescope support.
As shown in Figure 5, the fastener of the present embodiment comprises expansion link 31, and the top of expansion link 31 is fixed with chuck 32, and chuck 32 is provided with stepped hole 34, and the lower end of expansion link 31 is provided with bull stick 33.
Pass through the present embodiment, the sequence of operations such as setting-out on ceiling, punching, fastening screw all can be stood and be realized on the ground, thoroughly abandon the aerial devices such as ladder, stool, installing rack, not only make operating personnel's working environment safer, and owing to having removed the steps such as mobile ladder from, also need not build installing rack, so operating efficiency significantly improves.In addition, because each apparatus structure is reasonable in design, simple to operate, therefore be easy to realize skilled operation, increase substantially operating efficiency.
Embodiment 2:
As shown in Figure 2, the present embodiment also comprises pull bar 15 on the basis of embodiment 1, and vertical rod 13 is provided with T-shaped groove, and an end of pull bar 15 is fixed on cross bar 12, and the other end is buckled in the T-shaped groove in vertical rod 13, and fixing by bolt 16.
Embodiment 3:
As shown in Figure 3, the present embodiment also comprises reinforced pole 17 on the basis of embodiment 2, and an end of reinforced pole 17 is fixed on support bar 11, and the other end is fixed on cross bar 12, and support bar 11, cross bar 12, reinforced pole 17 surround an isosceles right triangle.
Embodiment 4:
The present embodiment is substantially the same manner as Example 3, and different places are, the groove on the cross bar 12 of the present embodiment is T-shaped groove, and the shape of vertical rod 13 lower ends and this T-shaped groove are complementary.
Embodiment 5:
The present embodiment is substantially the same manner as Example 1, different places are, the telescope support of the present embodiment comprises the first vertical rod 22, the first cross bar 23, the second vertical rod 24 and the second cross bar 25, the first vertical rod 22 and the first cross bar 23 are flexibly connected, the first cross bar 23 and the second vertical rod 24 are flexibly connected, the second vertical rod 24 and the second cross bar 25 are flexibly connected, and the second cross bar 25 and the first vertical rod 22 are flexibly connected, and electric drill 21 is arranged on the upper end of the second vertical rod 24.
As preferably, first vertical rod 22 of the present embodiment, the first cross bar 23, the second vertical rod 24, the second cross bar 25 surround a rhombus, and the middle part of the middle part of the first vertical rod 22 and the first cross bar 23 is flexibly connected.
Embodiment 6:
The present embodiment is substantially the same manner as Example 5, different places are, the power switch of the electric drill 21 of the present embodiment is arranged in the first vertical rod 22, and an end of the second cross bar 25 is connected with the movable upper end of the first vertical rod 22, and the middle part of the other end of the second cross bar 25 and the second vertical rod 24 is flexibly connected.
Embodiment 7:
The present embodiment is substantially the same manner as Example 1, different places are, the expansion link 31 of the present embodiment comprises the top body of rod, the middle part body of rod and the bottom body of rod connected successively, and the diameter of the described middle part body of rod is greater than the diameter of the top body of rod, and the diameter of the middle part body of rod is less than the diameter of the bottom body of rod.
As preferably, the top of the expansion link 31 of the present embodiment is provided with external screw thread, and the bottom of chuck 32 is provided with tapped fixing hole, and chuck 32 is fixed on expansion link 31 by this fixing hole.
A kind ofly adopt the above-mentioned construction method that integrates the combined system of setting-out, boring, fastening screw, comprise the following steps:
(a) distance to operate ground according to ceiling, the length of regulating the telescopic rod of line-plotting device, according to the needs of setting-out, determine quantity and the position of vertical rod 13 on cross bar 12 of vertical rod 13;
(b), by the writing brush in draw-in groove 14, on ceiling, the place in requisition for punching is marked;
(c) perforating device is placed in the punching mark under, open electric drill 21, press down the movable end of the first cross bar 23, the second vertical rod 24 is moved upward, the electric drill 21 of the second vertical rod 24 upper ends moves upward, holed in the place of doing the punching mark, and the backed off after random electric drill 21 of having holed;
(d) regulate the length of the expansion link 31 of fastener, screw rod to be installed is inserted in the chuck 32 of fastener, by the bull stick 33 on rotary fixture, in the corresponding installing hole screwed on ceiling of screw rod, complete screw rod and fix, take off fastener.
Above-mentioned construction method closely combines setting-out, punching, fastening screw step dexterously, operating personnel can realize all operations in station on the ground, thereby can abandon former aid fully, as ladder, installing rack etc., reduce to a certain extent cost; In addition, operating personnel are without ascending a height, and have eliminated the tradition personal safety hidden danger that operation may bring of ascending a height, thereby make whole construction safety, carry out effectively and quickly.
The present invention is illustrated by above-described embodiment, but should be understood that, above-described embodiment is the purpose for giving an example and illustrating just, but not is intended to the present invention is limited in described scope of embodiments.In addition, it will be appreciated by persons skilled in the art that the present invention is not limited to above-described embodiment, according to instruction of the present invention, can also make more kinds of variants and modifications, these variants and modifications all drop in the present invention's scope required for protection.

Claims (10)

1. a combined system that integrates setting-out, boring, fastening bolt is characterized in that: comprise line-plotting device for doing mark for dowel hold, for the perforating device of boring, for screw rod being arranged on to the fastener on ceiling;
The cross bar (12) that described line-plotting device comprises support bar (11) and is arranged on support bar (11) top, described support bar (11) is telescopic rod, described cross bar (12) is provided with groove, at least be provided with the vertical rod (13) that can move along this groove in this groove, it is vertical with cross bar (12) that vertical rod (13) remains, described vertical rod (13) top is provided with for the fixing draw-in groove of writing brush (14);
Described perforating device comprises telescope support and is arranged on the electric drill (21) on telescope support, and the power switch (26) of described electric drill (21) is arranged on telescope support;
Described fastener comprises expansion link (31), and the top of described expansion link (31) is fixed with chuck (32), and described chuck (32) is provided with stepped hole (34), and the lower end of described expansion link (31) is provided with bull stick (33).
2. a kind of combined system that integrates setting-out, boring, fastening screw according to claim 1, it is characterized in that: also comprise pull bar (15), described vertical rod (13) is provided with T-shaped groove, one end of pull bar (15) is fixed on cross bar (12), the other end is buckled in the T-shaped groove in vertical rod (13), and fixing by bolt (16).
3. a kind of combined system that integrates setting-out, boring, fastening screw according to claim 1, it is characterized in that: also comprise reinforced pole (17), one end of described reinforced pole (17) is fixed on support bar (11), it is upper that the other end is fixed on cross bar (12), and support bar (11), cross bar (12), reinforced pole (17) surround an isosceles right triangle.
4. a kind of combined system that integrates setting-out, boring, fastening screw according to claim 1, it is characterized in that: the groove on described cross bar (12) is T-shaped groove, shape and this T-shaped groove of vertical rod (13) lower end are complementary.
5. a kind of collection setting-out according to claim 1, boring, fastening screw is in the combined system of one, it is characterized in that: described telescope support comprises the first vertical rod (22), the first cross bar (23), the second vertical rod (24) and the second cross bar (25), the first vertical rod (22) is flexibly connected with the first cross bar (23), the first cross bar (23) is flexibly connected with the second vertical rod (24), the second vertical rod (24) is flexibly connected with the second cross bar (25), the second cross bar (25) is flexibly connected with the first vertical rod (22), electric drill (21) is arranged on the upper end of the second vertical rod (24).
6. a kind of combined system that integrates setting-out, boring, fastening screw according to claim 5, it is characterized in that: described the first vertical rod (22), the first cross bar (23), the second vertical rod (24), the second cross bar (25) surround a rhombus, and the middle part of the middle part of the first vertical rod (22) and the first cross bar (23) is flexibly connected.
7. a kind of combined system that integrates setting-out, boring, fastening screw according to claim 1, it is characterized in that: the power switch of described electric drill (21) is arranged in the first vertical rod (22), one end of the second cross bar (25) is connected with the movable upper end of the first vertical rod (22), and the middle part of the other end of the second cross bar (25) and the second vertical rod (24) is flexibly connected.
8. a kind of combined system that integrates setting-out, boring, fastening screw according to claim 1, it is characterized in that: described expansion link (31) comprises the top body of rod, the middle part body of rod and the bottom body of rod connected successively, the diameter of the described middle part body of rod is greater than the diameter of the top body of rod, and the diameter of the middle part body of rod is less than the diameter of the bottom body of rod.
9. a kind of combined system that integrates setting-out, boring, fastening screw according to claim 1, it is characterized in that: the top of described expansion link (31) is provided with external screw thread, the bottom of chuck (32) is provided with tapped fixing hole, and chuck (32) is fixed on expansion link (31) by this fixing hole.
10. one kind adopts the above-mentioned construction method that integrates the combined system of setting-out, boring, fastening screw, it is characterized in that: comprise the following steps:
(a) distance to operate ground according to ceiling, the length of regulating the telescopic rod of line-plotting device, according to the needs of setting-out, determine quantity and the position of vertical rod (13) on cross bar (12) of vertical rod (13);
(b), by the writing brush in draw-in groove (14), on ceiling, the place in requisition for punching is marked;
(c) perforating device is placed in the punching mark under, open electric drill (21), press down the movable end of the first cross bar (23), the second vertical rod (24) is moved upward, the electric drill (21) of the second vertical rod (24) upper end moves upward, holed in the place of doing the punching mark, the backed off after random electric drill (21) of having holed;
(d) regulate the length of the expansion link (31) of fastener, screw rod to be installed is inserted in the chuck (32) of fastener, by the bull stick on rotary fixture (33), in the corresponding installing hole screwed on ceiling of screw rod, complete screw rod and fix, take off fastener.
CN201310372071.XA 2013-08-23 2013-08-23 A kind of combined system and construction method that integrates setting-out, boring, fastening screw Active CN103447579B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310372071.XA CN103447579B (en) 2013-08-23 2013-08-23 A kind of combined system and construction method that integrates setting-out, boring, fastening screw

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310372071.XA CN103447579B (en) 2013-08-23 2013-08-23 A kind of combined system and construction method that integrates setting-out, boring, fastening screw

Publications (2)

Publication Number Publication Date
CN103447579A true CN103447579A (en) 2013-12-18
CN103447579B CN103447579B (en) 2016-05-11

Family

ID=49730637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310372071.XA Active CN103447579B (en) 2013-08-23 2013-08-23 A kind of combined system and construction method that integrates setting-out, boring, fastening screw

Country Status (1)

Country Link
CN (1) CN103447579B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385991A (en) * 2018-01-19 2018-08-10 滨州学院 A kind of infilled wall tie bar bar planting positioning construction method and dedicated positioning device
CN108980569A (en) * 2018-09-26 2018-12-11 卢俊 A kind of foldable telescopic bracket
CN110006521A (en) * 2019-04-03 2019-07-12 上海船舶电子设备研究所(中国船舶重工集团公司第七二六研究所) Hydrophone mounting device
CN112518644A (en) * 2020-11-30 2021-03-19 国网青海省电力公司黄化供电公司 Single-rod electrified bolt fastening tool
CN112847290A (en) * 2021-01-22 2021-05-28 成都建工装饰装修有限公司 Indoor decoration pay-off device and pay-off method thereof
CN114378334A (en) * 2022-01-28 2022-04-22 中建八局第二建设有限公司 Single operable multi-angle perforating device

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29904074U1 (en) * 1999-04-27 1999-08-05 Sorce, Giacomo, 50859 Köln Marking device for use on roofs and high walls, especially in unreachable places
JP2001073558A (en) * 1999-09-07 2001-03-21 Dai-Dan Co Ltd Marking device
CN102145398A (en) * 2010-02-05 2011-08-10 襄樊学院 Mobile support frame for electric drill
CN102248200A (en) * 2011-07-05 2011-11-23 中国新兴保信建设总公司 Smart tool for planting reinforcing bars and punching holes on roof
CN102407520A (en) * 2011-12-13 2012-04-11 常州鑫鹏工具制造有限公司 Scribing device
CN202199803U (en) * 2011-09-05 2012-04-25 山西四建集团有限公司 Drilling device for bonded rebar
CN202318225U (en) * 2011-11-15 2012-07-11 深圳海外装饰工程有限公司 Fastening device
CN202388496U (en) * 2011-12-13 2012-08-22 常州鑫鹏工具制造有限公司 Scribing device
CN202517082U (en) * 2012-01-12 2012-11-07 中国十七冶集团有限公司 Ceiling drilling machine and tool with adjustable height
CN202528152U (en) * 2012-03-30 2012-11-14 北京港源建筑装饰工程有限公司 Vertical operation rack
CN102962494A (en) * 2012-12-07 2013-03-13 安徽建工集团有限公司 Face-up impacting and drilling device for ceiling
CN202954571U (en) * 2012-12-07 2013-05-29 中铁十九局集团电务工程有限公司 Special device for marking and positioning at height of buildings

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29904074U1 (en) * 1999-04-27 1999-08-05 Sorce, Giacomo, 50859 Köln Marking device for use on roofs and high walls, especially in unreachable places
JP2001073558A (en) * 1999-09-07 2001-03-21 Dai-Dan Co Ltd Marking device
CN102145398A (en) * 2010-02-05 2011-08-10 襄樊学院 Mobile support frame for electric drill
CN102248200A (en) * 2011-07-05 2011-11-23 中国新兴保信建设总公司 Smart tool for planting reinforcing bars and punching holes on roof
CN202199803U (en) * 2011-09-05 2012-04-25 山西四建集团有限公司 Drilling device for bonded rebar
CN202318225U (en) * 2011-11-15 2012-07-11 深圳海外装饰工程有限公司 Fastening device
CN102407520A (en) * 2011-12-13 2012-04-11 常州鑫鹏工具制造有限公司 Scribing device
CN202388496U (en) * 2011-12-13 2012-08-22 常州鑫鹏工具制造有限公司 Scribing device
CN202517082U (en) * 2012-01-12 2012-11-07 中国十七冶集团有限公司 Ceiling drilling machine and tool with adjustable height
CN202528152U (en) * 2012-03-30 2012-11-14 北京港源建筑装饰工程有限公司 Vertical operation rack
CN102962494A (en) * 2012-12-07 2013-03-13 安徽建工集团有限公司 Face-up impacting and drilling device for ceiling
CN202954571U (en) * 2012-12-07 2013-05-29 中铁十九局集团电务工程有限公司 Special device for marking and positioning at height of buildings

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385991A (en) * 2018-01-19 2018-08-10 滨州学院 A kind of infilled wall tie bar bar planting positioning construction method and dedicated positioning device
CN108385991B (en) * 2018-01-19 2023-06-20 滨州学院 Positioning construction method for tie bar planting of filling wall and special positioning device
CN108980569A (en) * 2018-09-26 2018-12-11 卢俊 A kind of foldable telescopic bracket
CN110006521A (en) * 2019-04-03 2019-07-12 上海船舶电子设备研究所(中国船舶重工集团公司第七二六研究所) Hydrophone mounting device
CN112518644A (en) * 2020-11-30 2021-03-19 国网青海省电力公司黄化供电公司 Single-rod electrified bolt fastening tool
CN112847290A (en) * 2021-01-22 2021-05-28 成都建工装饰装修有限公司 Indoor decoration pay-off device and pay-off method thereof
CN112847290B (en) * 2021-01-22 2022-03-25 成都建工装饰装修有限公司 Indoor decoration pay-off device and pay-off method thereof
CN114378334A (en) * 2022-01-28 2022-04-22 中建八局第二建设有限公司 Single operable multi-angle perforating device
CN114378334B (en) * 2022-01-28 2023-08-18 中建八局第二建设有限公司 Single operable multi-angle perforating device

Also Published As

Publication number Publication date
CN103447579B (en) 2016-05-11

Similar Documents

Publication Publication Date Title
CN103447579B (en) A kind of combined system and construction method that integrates setting-out, boring, fastening screw
CN203865989U (en) Special JP cabinet cross arm lifting support frame for transformer rack
CN105442932A (en) Power grid pole burying device and construction method
CN203401097U (en) Multi-hole drilling machine with adjustable distance
CN205276990U (en) Electronic information engineering is with communication tower
CN203585544U (en) Cable bridge support
CN106217478A (en) Circuit boring device
CN206757980U (en) A kind of lifting type workbench for electronic experiment
CN212014400U (en) Jackfruit fruit opener
CN203977994U (en) Safety warning shielding
CN209844373U (en) 66KV transformer substation grounding wire high-altitude hanging device
CN210877698U (en) Fixing platform for installing top plate drilling support
CN104514919A (en) Bracket of cable bridge
CN207736212U (en) A kind of special fixture for dismantling cutter
CN210141035U (en) 10kV circuit pole card tray
CN203156100U (en) Drilling instrument for suspended ceiling construction
CN208178475U (en) A kind of mechanical device for punchinging
CN202937046U (en) Temporary support cross arm for hot-line work
CN204867531U (en) Folding flexible drilling equipment of assembled
CN203394058U (en) Climbing-free line drawing structure
CN204330279U (en) The integrated gathering-device of wind erosion depositing dust
CN220927603U (en) Guideboard guiding device
CN214616314U (en) Tower crane is with cat ladder convenient to installation
CN203720210U (en) Insulating rod experiment table
CN203597743U (en) Outdoor umbrella supporting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant