CN103435298A - Method of utilizing well-drilling solid waste soil to prepare concrete or concrete blocks - Google Patents

Method of utilizing well-drilling solid waste soil to prepare concrete or concrete blocks Download PDF

Info

Publication number
CN103435298A
CN103435298A CN2013103432159A CN201310343215A CN103435298A CN 103435298 A CN103435298 A CN 103435298A CN 2013103432159 A CN2013103432159 A CN 2013103432159A CN 201310343215 A CN201310343215 A CN 201310343215A CN 103435298 A CN103435298 A CN 103435298A
Authority
CN
China
Prior art keywords
solid waste
concrete
waste soil
well
drilling well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013103432159A
Other languages
Chinese (zh)
Other versions
CN103435298B (en
Inventor
罗平凯
吕玉胜
王勋
彭兵
粟建辉
杜利
罗荣川
宋佳
刘俊
凌兵
邱林青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Sinopec Southwest Petroleum Bureau
Original Assignee
China Petroleum and Chemical Corp
Sinopec Southwest Petroleum Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Chemical Corp, Sinopec Southwest Petroleum Bureau filed Critical China Petroleum and Chemical Corp
Priority to CN201310343215.9A priority Critical patent/CN103435298B/en
Publication of CN103435298A publication Critical patent/CN103435298A/en
Application granted granted Critical
Publication of CN103435298B publication Critical patent/CN103435298B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Processing Of Solid Wastes (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention relates to a method of utilizing well-drilling solid waste soil to prepare concrete or concrete blocks. According to the method, the well-drilling solid waste soil is used as the main raw material, dinas is used as the aggregate, and a glueing material is added, wherein the proportion of the well-drilling solid waste soil to the dinas to the glueing material is 60:30:10. The well-drilling solid waste soil, the dinas and the glueing material are mixed uniformly, the building material with the required strength can be obtained through moulding, and construction of a well-drilling well site revetment and a road is completed through the specific onsite technology. With adoption of the method, the onsite and timely utilization and harmless treatment of the well-drilling solid waste soil are realized, and better economic and social benefits are achieved.

Description

The method for preparing concrete or concrete segment with drilling well solid waste soil
Technical field
The invention belongs to oil-gas field gas development environment protection field, relate to a kind of method for preparing concrete or concrete segment with drilling well solid waste soil, make drilling well solid waste soil be able to recycling.
Background technology
When boring Oil/gas Well, will be constantly to water filling in pit shaft, can produce a large amount of magma waste liquids, metal ion and organism in waste liquid pollute the environment, therefore adopting curing technology is processed, this technology is carried out Zhuanization ﹑ Feng Bi ﹑ by solidifying agent by the objectionable constituent in waste liquid of drilling and is fixed, again through solid-liquid separation, Harmful ingredient content in waste water after making to separate reaches the emission standard of environmental regulations, isolated solid matter is called solid waste soil, need to process again, due to solid waste soil complicated component, water ratio is between 50%-70%, and moisture is comparatively stable, volatilization slowly, be difficult for fragmentation, bring very large difficulty to further recycling treatment.Existing disposal method has following two kinds: the one, and the landfill of digging pit, the 2nd, be used for making ground.Landfill is disposed need to take a large amount of soils; Dispose the inherent nature due to solid waste soil with making, make ground after the short period of time be not suitable for plant-growth, needing could raise crop after the several years slaking.
In sum, find better outlet also at present solid waste soil, along with the rapid expansion of oil-gas field development scale, the handling problems of solid waste soil becomes increasingly conspicuous, and becomes the oil sector problem demanding prompt solution.
On the other hand, in the construction investment of well site, the proportion maximum that construction investment accounts for, civil engineering comprises well site terrace, road and bank protection, due to well site in the wild, need to build road and highway connects, build the road and will expend a large amount of cement, building the well site bank protection will, with a large amount of barnacle pieces and cement, be also secondly terrace, also will use many cement, these three engineerings become the major portion of well site construction investment.If can gather materials on the spot, the solid waste land reform is caused to material of construction, replace cement, for well site, build, will the construction investment of decrease well site.The inorganics that contains 20% left and right due to solid waste soil, mainly silicon, iron, aluminium and calcium etc., therefore available solid waste soil is as the various building materials of raw material production, for example concrete and building block thereof, for well site bank protection, road, terrace, build, thereby realize the innoxious and recycling of drilling well solid waste soil, thoroughly solve solid waste soil handling problems.Not yet find at present with drilling well solid waste soil the report as the raw material production building materials.
Summary of the invention
The object of the present invention is to provide a kind of by the native method of concrete and building block thereof for preparing of drilling well solid waste, concrete prepared by the method and building block thereof are for well site bank protection, terrace, constructing road, thereby realize harmless treatment and the recycling of drilling well solid waste soil, thoroughly solve solid waste soil handling problems.
The objective of the invention is to be achieved through the following technical solutions:
A kind of by the concrete method of drilling well solid waste soil preparation, the method is to use drilling well solid waste soil as main raw material, uses sandstone as aggregate, then adds glueing material, mixes, and obtains concrete, and concrete steps are as follows:
1), preparation step
-solid waste soil filter cake is made to the small-particle of particle diameter≤2cm with shearing breaking method, and its water ratio is adjusted in the 55%-65% scope;
-sandstone is eluriated clean and dried;
-prepare glueing material, the component of following weight part is mixed, make glueing material;
Inorganic coagulation material (cement) 20-24 part
Inorganic coagulation material (modification rice husk) 15-18 part
Macromolecule stabilizer (Natvosol) 0.1-0.2 part
0.2 part of additive (polypropylene phosphide class is synthesized the building stones binding agent)
Additive (hydroscopic high-molecular resin) 0.3-0.6 part
Mineral filler (unslaked lime) 57-64 part
2), mixing step
Raw material in step 1) is mixed by following weight ratio, make concrete, can be used for site operation.
60 parts, the solid waste soil of water ratio 55%-65%
30 parts of glueing materials
10 parts, sandstone
In such scheme, the water ratio of solid waste soil particle preferably adjusts to 60%, and inflation method is: if the water ratio of solid waste soil particle, higher than 60%, is placed in the air airing, if the water ratio of solid waste soil particle is soaked lower than 60%.
Further, by step 2) concrete that makes sends in brick press, and extruding cuts into the building block base, is placed in the air covering curing, depending on temperature and atmospheric moisture maintenance 7-28 days, makes concrete segment.
In such scheme, the concrete steps of described site operation are:
1), by the working-yard ground flatten, compacting, water is rinsed well and is dried;
2), concrete is coated in to on-the-spot earth's surface, floating, troweling surface after initial set, the overlay film maintenance, until final set;
3), use concrete cutting machine, cut out the thermal expansion expansion joint on the concrete after final set;
4), to filled bitumen in expansion joint.
When described working-yard is road, described step 2) concrete is coated in to on-the-spot earth's surface, floating, troweling surface after initial set, and mark anti-slip veins on surface, then overlay film maintenance, until final set.
The invention has the beneficial effects as follows:
1, the present invention compares with the soil of drilling well solid waste in the past method of disposal, and solid waste soil method of disposal is greatly optimized.Curing brickmaking can realize turning waste into wealth, adopt solid waste soil to can be used for building of well site bank protection, country lanes as raw material, not only greatly saved the expense that solid waste soil roping landfill is disposed, solved to a great extent the handling problems of solid waste soil, and saved a large amount of soils.
2, the present invention can realize that the scene of drilling well solid waste soil processes in time, glueing material by development and preferred solid waste soil dispose experimental formula and process the ground surface material that can be met requirement of strength, can realize that through site operation the scene of drilling well solid waste soil utilizes in time.
3, the drilling well solid waste soil resource that the present invention realizes utilizes technology, the advantage such as have that site construction technology is easy, the road surface setting time is fast etc., treatment capacity is large, comprehensive cost is low, on-the-spot effect are good, can meet the pavement grade standard, there is economic benefit and social benefit preferably.
Embodiment
Below in conjunction with embodiment, the present invention is further described;
Present method is to use drilling well solid waste soil as main raw material, uses sandstone as aggregate, then adds glueing material, mixes, and obtains concrete, and concrete steps are as follows:
1), preparation step
-solid waste soil filter cake is made to the small-particle of particle diameter≤2cm with shearing breaking method, and its water ratio is adjusted in the 55%-65% scope;
-sandstone is eluriated clean and dried;
-prepare glueing material, the component of following weight part is mixed, make glueing material;
20 parts of inorganic coagulation materials (cement)
15 parts of inorganic coagulation materials (modification rice husk)
0.1 part of macromolecule stabilizer (Natvosol)
0.2 part of additive (polypropylene phosphide class is synthesized the building stones binding agent)
0.4 part of additive (hydroscopic high-molecular resin)
64 parts of mineral fillers (unslaked lime)
2), mixing step
Raw material in step 1) is mixed by following weight ratio, make concrete, can be used for site operation.
60 parts, the solid waste soil of water ratio 55%-65%
30 parts of glueing materials
10 parts, sandstone
In such scheme, the water ratio of solid waste soil particle preferably adjusts to 60%, and inflation method is: if the water ratio of solid waste soil particle, higher than 60%, is placed in the air airing, if the water ratio of solid waste soil particle is soaked lower than 60%.
Further, by step 2) concrete that makes sends in brick press, and extruding cuts into the building block base, is placed in the air covering curing, depending on temperature and atmospheric moisture maintenance 7-28 days, makes concrete segment.
In such scheme, the concrete steps of described site operation are:
1), by the working-yard ground flatten, compacting, water is rinsed well and is dried;
2), concrete is coated in to on-the-spot earth's surface, floating, troweling surface after initial set, the overlay film maintenance, until final set;
3), use concrete cutting machine, cut out the thermal expansion expansion joint on the concrete after final set;
4), to filled bitumen in expansion joint.
When described working-yard is road, described step 2) concrete is coated in to on-the-spot earth's surface, floating, troweling surface after initial set, and mark anti-slip veins on surface, then overlay film maintenance, until final set.
Application example:
Unit's dam six well solid waste soil are applied to the well site bank protection and build.Develop the glueing material that is applicable to first dam solid waste soil, filter out 5 kinds of representational formulas on the basis of great many of experiments, the increase-volume of corresponding solid waste soil than and to make the raw materials cost of side's solidified earth road-making material as shown in table 1:
table 1area, Langzhong, Sichuan well drilling waste mud is containing scale
Figure 992559DEST_PATH_IMAGE001
Above 5 kinds of corresponding intensity indexs for the treatment of formulations and Environmental indicators are as shown in table 2.
tablebuilding block sample detected result table under 2 different ingredients conditions
Figure 259593DEST_PATH_IMAGE002
At present in inside, Liu Jing well site, first dam according to according to formula 5#, having built the approximately bank protection of 300 square meters, roadbed and road surface one-piece construction meet relevant examination regulations in GBJ97-87 " code for construction and acceptance of cement concrete pavement ".According to first dam six well site operation quality evalution, its ultimate compression strength is 26MPa, suitable with C20 level concrete crushing strength, with reference to the corresponding relation between concrete crushing strength and category of roads, can infer, the corresponding flexural tensile strength of this bank protection pavement grade satisfied by the 4.0MPa normal concrete, meet the correlated quality requirement fully.

Claims (5)

1. one kind prepares concrete method with drilling well solid waste soil, and the method is to use drilling well solid waste soil as main raw material, uses sandstone as aggregate, then adds glueing material, mixes, and obtains concrete, and concrete steps are as follows:
1), preparation step
-solid waste soil filter cake is made to the small-particle of particle diameter≤2cm with shearing breaking method, and its water ratio is adjusted in the 55%-65% scope;
-sandstone is eluriated clean and dried;
-prepare glueing material, the component of following weight part is mixed, make glueing material;
Inorganic coagulation material: cement 20-24 part
Inorganic coagulation material: modification rice husk 15-18 part
Macromolecule stabilizer: Natvosol 0.1-0.2 part
Additive: polypropylene phosphide class is synthesized building stones binding agent 0.2-0.3 part
Additive: hydroscopic high-molecular resin 0.3-0.6 part
Mineral filler: unslaked lime 57-64 part
2), mixing step
Raw material in step 1) is mixed by following weight ratio, make concrete, can be used for site operation;
60 parts, the solid waste soil of water ratio 55%-65%
30 parts of glueing materials
10 parts, sandstone.
2. as claimed in claim 1 by the concrete method of drilling well solid waste soil preparation, it is characterized in that, the water ratio of described solid waste soil particle adjusts to 60%, inflation method is: if the water ratio of solid waste soil particle is higher than 60%, be placed in the air airing, if the water ratio of solid waste soil particle, lower than 60%, is soaked.
3. the concrete method of drilling well solid waste soil preparation of using as claimed in claim 1, is characterized in that, the concrete steps of described site operation are:
1), by the working-yard ground flatten, compacting, water is rinsed well and is dried;
2), concrete is coated in to on-the-spot earth's surface, floating, troweling surface after initial set, the overlay film maintenance, until final set;
3), use concrete cutting machine, cut out the thermal expansion expansion joint on the concrete after final set;
4), to filled bitumen in expansion joint.
4. the concrete method of drilling well solid waste soil preparation of using as claimed in claim 3, is characterized in that, described working-yard is road, described step 2) concrete is coated in to on-the-spot earth's surface, floating, troweling surface after initial set, and marking anti-slip veins on surface, then overlay film maintenance, until final set.
5. a method for preparing concrete segment with drilling well solid waste soil, is characterized in that, the concrete that claim 1 or 2 is made is sent in brick press, extruding cuts into the building block base, be placed in the air covering curing, depending on temperature and atmospheric moisture maintenance 7-28 days, make concrete segment.
CN201310343215.9A 2013-08-08 2013-08-08 Method of utilizing well-drilling solid waste soil to prepare concrete or concrete blocks Active CN103435298B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310343215.9A CN103435298B (en) 2013-08-08 2013-08-08 Method of utilizing well-drilling solid waste soil to prepare concrete or concrete blocks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310343215.9A CN103435298B (en) 2013-08-08 2013-08-08 Method of utilizing well-drilling solid waste soil to prepare concrete or concrete blocks

Publications (2)

Publication Number Publication Date
CN103435298A true CN103435298A (en) 2013-12-11
CN103435298B CN103435298B (en) 2015-04-22

Family

ID=49689048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310343215.9A Active CN103435298B (en) 2013-08-08 2013-08-08 Method of utilizing well-drilling solid waste soil to prepare concrete or concrete blocks

Country Status (1)

Country Link
CN (1) CN103435298B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104710140A (en) * 2015-01-13 2015-06-17 河海大学 Ore powder and sandy waste soil-doped compactness concrete and preparation method thereof
CN106587786A (en) * 2016-12-30 2017-04-26 北京泾渭智能环保有限公司 Well drilling waste brick making method
CN110931186A (en) * 2019-12-11 2020-03-27 江西高鑫电瓷电器有限公司 Cementing process of high-voltage electric porcelain

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1792898A (en) * 2005-11-22 2006-06-28 刘茂平 Solidified agent for drilling well waste mud
CN101234838A (en) * 2007-02-02 2008-08-06 山东寿龙环保工程科技有限公司 Petroleum well drilling waste slurry harmless environmental protection curing agent and producing method thereof
CN101602567A (en) * 2009-07-16 2009-12-16 王军 Waste mud solidification processing method based on polypropylene acetamide
CN101607811A (en) * 2009-07-16 2009-12-23 王军 A kind of slurry curing formula

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1792898A (en) * 2005-11-22 2006-06-28 刘茂平 Solidified agent for drilling well waste mud
CN101234838A (en) * 2007-02-02 2008-08-06 山东寿龙环保工程科技有限公司 Petroleum well drilling waste slurry harmless environmental protection curing agent and producing method thereof
CN101602567A (en) * 2009-07-16 2009-12-16 王军 Waste mud solidification processing method based on polypropylene acetamide
CN101607811A (en) * 2009-07-16 2009-12-23 王军 A kind of slurry curing formula

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104710140A (en) * 2015-01-13 2015-06-17 河海大学 Ore powder and sandy waste soil-doped compactness concrete and preparation method thereof
CN106587786A (en) * 2016-12-30 2017-04-26 北京泾渭智能环保有限公司 Well drilling waste brick making method
CN106587786B (en) * 2016-12-30 2019-04-12 北京泾渭智能环保有限公司 A kind of drilling wastes brick-making method
CN110931186A (en) * 2019-12-11 2020-03-27 江西高鑫电瓷电器有限公司 Cementing process of high-voltage electric porcelain
CN110931186B (en) * 2019-12-11 2021-06-18 江西高鑫电瓷电器有限公司 Cementing process of high-voltage electric porcelain

Also Published As

Publication number Publication date
CN103435298B (en) 2015-04-22

Similar Documents

Publication Publication Date Title
CN104402339B (en) The constructional method of pervious concrete
CN103866667B (en) Half flexible Supporting Load Pavement paving structure
CN103013526B (en) Soil solidifier and soil solidification method
CN102174267B (en) Asphalt cold recycling agent and preparation method thereof
CN100577595C (en) Environmental protection inorganic powder material and polymer composite modified emulsification asphalt grouting material
CN104003661B (en) A kind of permeable reclaimed asphalt mixture pavior brick and preparation method thereof
CN107382358A (en) It is a kind of suitable for permeable alkali-slag concrete of Supporting Load Pavement and preparation method thereof
JP2011038104A (en) Chemical agent for improving engineering properties of soil
CN105152519A (en) Inorganic silt curing agent and preparation method thereof as well as road material
CN101857403B (en) Permeable concrete and preparation method thereof
CN106149500A (en) A kind of construction method of cement emulsified asphalt mortar penetration type half-flexible pavement
CN112047701A (en) High-strength porous pervious concrete pavement and preparation method thereof
CN103435298B (en) Method of utilizing well-drilling solid waste soil to prepare concrete or concrete blocks
CN109160787B (en) Porous water-permeable environment-friendly diluted asphalt cold-patch material and preparation method thereof
CN107129195A (en) A kind of multi-functional water-permeating pitch mixed material and preparation method thereof
CN106587846A (en) Fabric scrap-reinforced environment-friendly crack-resistant cement-based water-permeable brick
CN109608133A (en) A kind of high-performance permeable concrete and preparation method thereof
KR100938936B1 (en) Cement composition for soil concrete, soil concrete including the same and pavement method of soil concrete using the same
CN106673487A (en) Pervious mortar stabilizer for sponge city and preparation method of pervious mortar stabilizer
CN112456918B (en) Silt curing material and silt curing method
CN107540272A (en) It is a kind of to utilize asphalt of concrete debris and preparation method thereof and construction method
CN108570899A (en) A kind of pavement of road base layer structure
CN108083667B (en) Roadbed filling
CN107915858B (en) Asphalt microporous membrane forming agent and high-shear-resistance interpenetrating semi-flexible pavement material
KR101844709B1 (en) Producing method for mastic asphalt lump composition for permanent repair

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant