Summary of the invention
For solving the problems of the technologies described above, the embodiment of the present application provides a kind of method and device of determining middle electric design admittance distributed electrical source capability, to reflect exactly low and medium voltage distribution network, admits the ability of distributed power source.
Definite low and medium voltage distribution network that the application provides admits the method for distributed electrical source capability to comprise:
Determine the installed capacity of each distributed power source according to current allowance permeability, described allowance permeability is to allow under the prerequisite that ensures electric power netting safe running and reliable power supply to the maximum distribution formula power supply installed capacity of low and medium voltage distribution network access and the ratio of low and medium voltage distribution network power supply peak load;
Node voltage and/or short circuit current according to each Nodes of the low and medium voltage distribution network of the installed capacity of distributed power source access Computation distribution formula power supply;
Node voltage and/or short circuit current to each node are checked: when the node voltage of each node and/or short circuit current during greater than predeterminated voltage threshold values and/or predetermined current threshold values, judge that the difference of current allowance permeability and previous allowance permeability is whether in preset range, if not, to low direction, upgrade described current allowance permeability, if so, with current allowance permeability as final allowance permeability; When the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, to high direction, upgrade described current allowance permeability; Allowance permeability after upgrading, as new current allowance permeability, is returned to the step of determining the installed capacity of each distributed power source according to current allowance permeability;
Determine the ability of low and medium voltage distribution network admittance distributed power source according to final allowance permeability.
Preferably, describedly upgrade described current allowance permeability to high direction and comprise:
Ask for the mean value of current allowance permeability and previous larger allowance permeability, with this mean value, upgrade current allowance permeability;
Describedly upgrade described current allowance permeability to low direction and comprise:
Ask for the mean value of current allowance permeability and previous less allowance permeability, with this mean value, upgrade current allowance permeability.
Further preferably, the described difference that judges current allowance permeability and previous allowance permeability whether be specially in preset range judge current allowance permeability and previous allowance permeability difference whether in 1 scope.
Preferably, specifically comprise according to node voltage and/or the short circuit current of each Nodes of the installed capacity Computation distribution formula power supply of distributed power source access low and medium voltage distribution network:
Build the computation model of distributed power source access power distribution network according to the power distribution network parameter of the low and medium voltage distribution network that accesses distributed power source, carry out trend by described computation model according to the installed capacity of distributed power source and calculate and/or calculation of short-circuit current, access node voltage and/or the short circuit current of each Nodes of low and medium voltage distribution network to obtain distributed power source.
Further preferably, the power distribution network parameter of described low and medium voltage distribution network comprises: power distribution network network topological structure parameter, transformer rated capacity, short-circuit impedance, no-load loss, line length, distributed power source access point, power producing characteristics curve and/or payload.
Preferably, the final allowance permeability of described basis determines that the ability of low and medium voltage distribution network admittance distributed power source specifically comprises the installed capacity of admitting distributed power source according to final allowance computing permeability low and medium voltage distribution network, determines the ability of low and medium voltage distribution network admittance distributed power source by this installed capacity.
The application also provides a kind of definite low and medium voltage distribution network to admit the device of distributed electrical source capability.This device comprises: installed capacity determining unit, electric current and voltage calculate unit, electric current and voltage is checked unit, permeability judging unit, and permeability updating block and distributed power source are admitted ability determining unit, wherein:
Described installed capacity determining unit, be used for determining according to current allowance permeability the installed capacity of each distributed power source, described allowance permeability is to allow under the prerequisite that ensures electric power netting safe running and reliable power supply to the maximum distribution formula power supply installed capacity of low and medium voltage distribution network access and the ratio of low and medium voltage distribution network power supply peak load;
Electric current and voltage calculates unit, is used for calculating according to the installed capacity of distributed power source node voltage and/or the short circuit current of each Nodes of the low and medium voltage distribution network that accesses distributed power source;
Electric current and voltage is checked unit, is used for node voltage and/or the short circuit current of each node are checked: when the node voltage of each node and/or short circuit current, during greater than predeterminated voltage threshold values and/or predetermined current threshold values, trigger the permeability judging unit; When the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, trigger the permeability updating block;
Described permeability judging unit, whether the difference that is used for judging current allowance permeability and previous allowance permeability in preset range, if not, triggers the permeability updating block, if so, triggers distributed power source admittance ability determining unit;
Described permeability updating block, be used at the node voltage of each node and/or short circuit current during greater than predeterminated voltage threshold values and/or predetermined current threshold values and the difference of current permeability and previous allowance permeability when preset range is not in preset range, to the low described current allowance permeability of direction renewal; When the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, to high direction, upgrade described current allowance permeability; Allowance permeability after upgrading, as new current allowance permeability, is returned to the step of determining the installed capacity of each distributed power source according to current allowance permeability;
Distributed power source is admitted ability determining unit, is used for determining according to final allowance permeability the ability of low and medium voltage distribution network admittance distributed power source.
Preferably, when described permeability updating block is used for upgrading described current allowance permeability to high direction, specifically comprise: be used for asking for the first mean value subelement of current allowance permeability and the mean value of previous larger allowance permeability, and with the first permeability renewal subelement of the current allowance permeability of this mean value renewal;
When described permeability updating block is used for upgrading described current allowance permeability to low direction, specifically comprise: be used for asking for the second mean value subelement of current allowance permeability and the mean value of previous less allowance permeability, and with the second permeability renewal subelement of the current allowance permeability of this mean value renewal.
Preferably, described electric current and voltage calculates unit and comprises that computation model builds subelement, electric current and voltage computation subunit, described computation model builds subelement, is used for building according to the power distribution network parameter of the low and medium voltage distribution network that accesses distributed power source the computation model of distributed power source access power distribution network; Described electric current and voltage computation subunit, be used for carrying out trend by described computation model according to the installed capacity of distributed power source and calculate and/or calculation of short-circuit current, access node voltage and/or the short circuit current of each Nodes of low and medium voltage distribution network to obtain distributed power source.
Preferably, distributed power source admits ability determining unit specifically to comprise the installed capacity computation subunit, be used for admitting according to final allowance computing permeability low and medium voltage distribution network the installed capacity of distributed power source, determine the ability of low and medium voltage distribution network admittance distributed power source by this installed capacity.
The embodiment of the present application is after the allowance permeability according to preliminary obtains installed capacity, according to this installed capacity computing node voltage and/or short circuit current, then it is checked, according to the result of checking, preliminary allowance permeability is upgraded, until the allowance permeability after upgrading is while meeting default condition, the allowance permeability that obtains, as final allowance permeability, is determined the admittance ability of distributed power source access low and medium voltage distribution network according to final allowance permeability.Compared with prior art, the boundary condition of such key that whether the embodiment of the present application raises by the check node voltage and/or whether short circuit current exceeds standard, automatic exploration and definite distributed power source access the allowance permeability of power distribution network repeatedly, thereby realize permitting automatic, the accurate analysis of permeability, and obtain on this basis determining the admittance ability of low and medium voltage distribution network to distributed power source more accurately.
Embodiment
In order to make those skilled in the art person understand better technical scheme in the application, below in conjunction with the accompanying drawing in the embodiment of the present application, technical scheme in the embodiment of the present application is clearly and completely described, obviously, described embodiment is only the application's part embodiment, rather than whole embodiment.Based on the embodiment in the application, those of ordinary skills are not making under the creative work prerequisite the every other embodiment that obtains, and all should belong to the scope of the application's protection.
Referring to Fig. 1, the definite low and medium voltage distribution network that the figure shows the application is admitted the flow process of the embodiment of the method for distributed electrical source capability.This flow process comprises:
Step S101: determine the installed capacity of each distributed power source according to current allowance permeability, described allowance permeability is to allow under the prerequisite that ensures electric power netting safe running and reliable power supply to the maximum distribution formula power supply installed capacity of low and medium voltage distribution network access and the ratio of low and medium voltage distribution network power supply peak-peak load;
Permit permeability and given expression to relation between the accessible maximum distribution formula power supply installed capacity of low and medium voltage distribution network is loaded with this power distribution network power supply peak-peak, in the situation that two key elements wherein can be determined another key element according to the concept of permitting permeability.Generally, low and medium voltage distribution network power supply peak-peak load is comparatively fixing over a period to come, can determine by the mean value of asking for this regular period the peak-peak load of power distribution network power supply, the low and medium voltage distribution network here is generally the following power distribution network of 10kV, the scale less of this power distribution network, be different from the big-and-middle-sized power distribution networks such as provincial.Also need to prove: the current allowance permeability here comprises two kinds of situations: the one, while initially carrying out the embodiment of the present application, current allowance permeability need to preset, predefined permission permeability can be random, because according to the step of the present embodiment back as can be known, final allowance permeability and the allowance permeability of initial setting are had little or nothing to do with, no matter initial allowance permeability arranges too much or too small, after several adjustment of taking turns of subsequent step, all will converge on final allowance permeability.Certainly, in order to reduce the number of times of cycle calculations, the initial allowance permeability of near final, permitting permeability can be set as much as possible rule of thumb.
Step S102: the node voltage and/or the short circuit current that calculate each Nodes of the low and medium voltage distribution network that accesses distributed power source according to the installed capacity of distributed power source;
here the boundary condition of selecting to calculate is node voltage or short circuit current, perhaps both computing node voltage, calculate again short circuit current, concrete which kind of calculating purpose of selecting, the situation that depends on actual power distribution network, such as, for urban distribution network, owing to affected by circuit breaker interrupting capacity and usually adopting low-impedance cable, substantially the problem that does not have voltage to raise, therefore, the emphasis of paying close attention to can be short circuit current, and then the scheme of short circuit current is only calculated in employing, certainly, in this case, for the purpose of accurately, also can consider the variation of node voltage, being about to two boundary conditions all considers in the ability process of determining power distribution network admittance distributed power source.Here why selecting these two boundary conditions is because they admit the ability of distributed power source to have material impact to low and medium voltage distribution network, belongs to core and checks criterion.Concrete computing node voltage, the mode that can adopt trend to calculate; The concrete short circuit current that calculates, can adopt the addition method to calculate.
Step S103: node voltage and/or short circuit current to each node are checked: when the node voltage of each node and/or short circuit current, during greater than predeterminated voltage threshold values and/or predetermined current threshold values, enter step S104; When the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, execution step S103(a): to high direction, upgrade described current allowance permeability, allowance permeability after upgrading, as new current allowance permeability, is returned to step S101;
As previously mentioned, may there be two kinds of situations in mode of operation to permeability after the node voltage to each node and short circuit current are checked: when being while checking for the first time, when if the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, the initial permeability of explanation setting may be less, need to tune up, namely to high direction, carry out the renewal of initial permeability, and then return to step S101 and carry out correlation computations; , if the node voltage of each node and/or short circuit current during greater than predeterminated voltage threshold values and/or predetermined current threshold values, can't directly illustrate the situation of the initial permeability of setting, also need further with permeability last time, to compare; When being for the second time and during follow-up the check, when if the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, illustrate that current permeability may be less, need to heighten, namely to high direction, carry out the renewal of initial permeability.
Step S104: judge that the difference of current allowance permeability and previous allowance permeability is whether in preset range, if not, perform step S104(a): upgrade described current allowance permeability to low direction, allowance permeability after upgrading, as new current allowance permeability, is returned to step S101; If so, enter step S105;
through being compared, current allowance permeability and previous allowance permeability (annotate: when carrying out the comparison of twice permeability for the first time, last time permeability can adopt zero), if this difference is in preset range, such as in 1 scope (namely the difference degree of two permeabilities is no more than 1), illustrate that this current allowance permeability can meet the demands, the low and medium voltage distribution network of determining by this permeability can not have a negative impact to stable operation and the reliable power supply of electrical network to the admittance ability of distributed power source, at this moment this allowance permeability can be defined as final permeability, if this difference not in preset range, illustrates that current permeability is also unstable, and higher, need to adjust current allowance permeability to low direction, namely reduce current allowance permeability.Can see by aforementioned two steps, the embodiment of the present application can automatically be regulated the allowance permeability, and after taking turns above circulation by one, the allowance permeability of initial setting up will converge on the final allowance permeability of really admitting ability near low and medium voltage distribution network.
Step S105: the ability of determining low and medium voltage distribution network admittance distributed power source according to final allowance permeability.
This method embodiment is after the allowance permeability according to preliminary obtains installed capacity, according to this installed capacity computing node voltage and/or short circuit current, then it is checked, according to the result of checking, preliminary allowance permeability is upgraded, until the allowance permeability after upgrading is while meeting default condition, the allowance permeability that obtains, as final allowance permeability, is determined the admittance ability of distributed power source access low and medium voltage distribution network according to final allowance permeability.Compared with prior art, the boundary condition of such key that whether this method embodiment raises by the check node voltage and/or whether short circuit current exceeds standard, automatic exploration and definite distributed power source access the allowance permeability of power distribution network repeatedly, thereby realize permitting automatic, the accurate analysis of permeability, and obtain on this basis determining the admittance ability of low and medium voltage distribution network to distributed power source more accurately.
, in order to further illustrate the application's technical scheme, below on the basis of previous embodiment, provide a concrete example., referring to Fig. 2, the figure shows the flow process of this example.This flow process comprises:
Step S201: the power distribution network parameter of determining to contain distributed power source, these parameters can comprise chooses typical power distribution network, determine the network connection mode, transformer rated capacity, short-circuit impedance, no-load loss, circuit model, length, impedance, distributed power source access point and power producing characteristics curve, payload, access point and characteristic curve.
Step S202: according to current allowance permeability, determine each distributed power source installed capacity, in this step, if determine for the first time installed capacity, adopt the default initial allowance permeability that limits to determine the installed capacity of each distributed power source, for the second time and after this, if, adopt current allowance permeability to determine the installed capacity of each distributed power source;
Step S203: utilize aforementioned data to build the computation model of distributed power source access power distribution network; This example can be by creation analysis model in CeaDER software.CeaDER(Comprehensive economic analysis of Distributed Energy Resource, distributed power source access complex art Economic Analysis Software) be the software of Based on Distributed power supply access power distribution network synthesis technical economic analysis, have accurate three-phase imbalance trend and calculate and the calculation of short-circuit current function.
Step S204: by computation model, undertaken that trend is calculated and short circuit calculation is obtained voltage and the short circuit current of each node that accesses distributed power source;
Calculate for trend, as an example of the structure of the power distribution network in Fig. 3 example, describe: usually require any two adjacent nodes in power distribution network to meet following calculating formula and require:
In following formula, r and x are respectively resistance and the reactance values of circuit, and U, P and Q are voltage, active power and the reactive powers of this section circuit left end; UL, PL and QL are voltage, active power and the reactive powers of this section circuit right-hand member; The algorithm that concrete trend is calculated comprises multiple: front pushing manipulation, modified Newton method, circuit impedance method and the implicit expression Zbus Gaussian processes of pushing back.
For calculation of short-circuit current, can adopt the addition method to calculate, the state before namely at first utilizing result that Three-phase Power Flow calculates as fault, obtain the voltage before the short dot fault; Then short circuit is regarded as at negative voltage source of short dot stack, short trouble is decomposed into normal operating mode and the fault component with a voltage source; Then utilize trend result and failure boundary condition to calculate the Fault Compensation electric current at place, fault point; Finally with the Fault Compensation electric current as the injection rate malfunctioning node that is added to, just can calculate each branch trouble electric current and each node voltage through pushing through journey before once pushing back.
Step S205: according to result of calculation, node voltage and the short circuit current of each node in network are checked, judge whether to require and power distribution network switchgear ability greater than the supply power voltage of national Specification; If greater than, enter step S206; If be not more than, illustrate that the permeability of this time souning out is less, do not reach the allowance permeability, enter step S208;
Step S206: judge and whether sound out current permeability and last time the permeability difference greater than 1, if so, the permeability of this time exploration of explanation is larger, surpasses and permits permeability, enters step S207; If not, the permeability of this time exploration of explanation, for permitting permeability, enters step S209;
Step S207: this exploration permeability and before once less exploration permeability are averaged, and round, return to step S202;
Step S208: with this sound out permeability and before once larger exploration permeability average, and round, return to step S202;
Step S209: according to the final allowance permeability and the payload that calculate, determine the admittance ability.
The method of previous embodiment and embodiment is applied to the typical power distribution network of China, can obtain following conclusion: if the electrical network of choosing is urban distribution network, because mainly being subjected to circuit breaker interrupting capacity, it affects, distributed natural gas generating and wind-powered electricity generation are retrained by short circuit current, and it is permitted permeability and is about 15%.And the short circuit current of photovoltaic generation and rated current are more or less the same, its contribution to short circuit current is little, permitting permeability is subjected to power constraint less, when if the circuit breaker rated capacity is chosen 20kA, it is 20.58% that the wind-powered electricity generation that allows in whole change radio area is permitted permeability, and it is 15.54% that permeability is permitted in natural gas power.
Above-described embodiment has described definite low and medium voltage distribution network of the application in detail and has admitted the embodiment of the method for distributed electrical source capability, and correspondingly, the application also provides a kind of definite low and medium voltage distribution network to admit the device embodiment of distributed electrical source capability., referring to Fig. 4, the figure shows the structured flowchart of the device embodiment that determines low and medium voltage distribution network admittance distributed electrical source capability.This device comprises: installed capacity determining unit 401, electric current and voltage calculate unit 402, electric current and voltage is checked unit 403, permeability judging unit 404, and permeability updating block 405 and distributed power source are admitted ability determining unit 406, wherein:
Installed capacity determining unit 401, be used for determining according to current allowance permeability the installed capacity of each distributed power source, described allowance permeability is to allow under the prerequisite that ensures electric power netting safe running and reliable power supply to the maximum distribution formula power supply installed capacity of low and medium voltage distribution network access and the ratio of low and medium voltage distribution network power supply peak load;
Electric current and voltage calculates unit 402, is used for calculating according to the installed capacity of distributed power source node voltage and/or the short circuit current of each Nodes of the low and medium voltage distribution network that accesses distributed power source;
Electric current and voltage is checked unit 403, is used for node voltage and/or the short circuit current of each node are checked: when the node voltage of each node and/or short circuit current, during greater than predeterminated voltage threshold values and/or predetermined current threshold values, trigger the permeability judging unit; When the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, trigger the permeability updating block;
Permeability judging unit 404, whether the difference that is used for judging current allowance permeability and previous allowance permeability in preset range, if not, triggers the permeability updating block, if so, triggers distributed power source admittance ability determining unit;
Permeability updating block 405, be used at the node voltage of each node and/or short circuit current during greater than predeterminated voltage threshold values and/or predetermined current threshold values and the difference of current permeability and previous allowance permeability when preset range is not in preset range, to the low described current allowance permeability of direction renewal; When the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, to high direction, upgrade described current allowance permeability; Allowance permeability after upgrading, as new current allowance permeability, is returned to the step of determining the installed capacity of each distributed power source according to current allowance permeability;
Distributed power source is admitted ability determining unit 406, is used for determining according to final allowance permeability the ability of low and medium voltage distribution network admittance distributed power source.
The course of work of this device embodiment is: installed capacity determining unit 401 is determined the installed capacity of each distributed power source according to current allowance permeability, and electric current and voltage calculates node voltage and/or the short circuit current of unit 402 according to each Nodes of the installed capacity Computation distribution formula power supply access low and medium voltage distribution network of distributed power source; Node voltage and/or the short circuit current of then by electric current and voltage, checking 403 pairs of each nodes in unit are checked: when the node voltage of each node and/or short circuit current during greater than predeterminated voltage threshold values and/or predetermined current threshold values, trigger permeability judging unit 404 and judge that the difference of current allowance permeability and previous allowance permeability is whether in preset range, if not, trigger permeability updating block 405 and upgrade described current allowance permeability to high direction, if so, trigger distributed power source and admit ability determining unit 406; When the node voltage of each node and/or short circuit current are not more than predeterminated voltage threshold values and/or predetermined current threshold values, trigger permeability updating block 405 and upgrade described current allowance permeability to low direction, the installation volume determining unit 401 of then setting out; Finally, by distributed power source, admit ability determining unit 406, determine the ability of low and medium voltage distribution network admittance distributed power source according to final allowance permeability.
This device embodiment is after the allowance permeability according to preliminary obtains installed capacity, according to this installed capacity computing node voltage and/or short circuit current, then it is checked, according to the result of checking, preliminary allowance permeability is upgraded, until the allowance permeability after upgrading is while meeting default condition, the allowance permeability that obtains, as final allowance permeability, is determined the admittance ability of distributed power source access low and medium voltage distribution network according to final allowance permeability.Compared with prior art, the boundary condition of such key that whether this device embodiment raises by the check node voltage and/or whether short circuit current exceeds standard, automatic exploration and definite distributed power source access the allowance permeability of power distribution network repeatedly, thereby realize permitting automatic, the accurate analysis of permeability, and obtain on this basis determining the admittance ability of low and medium voltage distribution network to distributed power source more accurately.
Said apparatus embodiment is based on the different implementations to each functional unit, and its internal structure may be different.Such as, for the permeability updating block, when being used for upgrading described current allowance permeability to high direction, can specifically comprise: be used for asking for the first mean value subelement of current allowance permeability and the mean value of previous larger allowance permeability, and with the first permeability renewal subelement of the current allowance permeability of this mean value renewal; When being used for upgrading described current allowance permeability to low direction, can specifically comprise: be used for asking for the second mean value subelement of current allowance permeability and the mean value of previous less allowance permeability, and with the second permeability renewal subelement of the current allowance permeability of this mean value renewal.Also such as, calculate unit 402 for electric current and voltage and can comprise that computation model builds subelement 4021, electric current and voltage computation subunit 4022, computation model builds subelement 4021, is used for building according to the power distribution network parameter of the low and medium voltage distribution network that accesses distributed power source the computation model of distributed power source access power distribution network; Electric current and voltage computation subunit 4022, be used for carrying out trend by described computation model according to the installed capacity of distributed power source and calculate and/or calculation of short-circuit current, access node voltage and/or the short circuit current of each Nodes of low and medium voltage distribution network to obtain distributed power source.For another example, if when above-mentioned distributed power source admits ability determining unit 406 to adopt the mode of calculating installed capacity to determine that power distribution network is admitted the ability of distributed power source, can specifically comprise installed capacity computation subunit 4061.One skilled in the art will appreciate that based on various purpose, can also carry out various distortion to above-described embodiment under the driving of actual needs, better to be installed.
Need to prove: easy for what narrate, what the various distortion implementations of above-described embodiment of this specification and embodiment stressed is all and the difference of other embodiment or mode of texturing that between each situation, identical similar part is mutually referring to getting final product.Especially, for several improved procedures of device embodiment, substantially similar in appearance to embodiment of the method, so describe fairly simplely, relevant part gets final product referring to the part explanation of embodiment of the method due to it.Each unit of device embodiment described above can or can not be also physically to separate, and both can be positioned at a place, perhaps also can be distributed to a plurality of net environments.In actual application, can select according to the actual needs wherein some or all of unit to realize the purpose of the present embodiment scheme, those of ordinary skills in the situation that do not pay creative work, namely can understand and implement.
The above is only the application's embodiment; should be pointed out that for those skilled in the art, under the prerequisite that does not break away from the application's principle; can also make some improvements and modifications, these improvements and modifications also should be considered as the application's protection range.