CN103401258B - 风电场故障状态下紧急功率控制策略 - Google Patents
风电场故障状态下紧急功率控制策略 Download PDFInfo
- Publication number
- CN103401258B CN103401258B CN201310366284.1A CN201310366284A CN103401258B CN 103401258 B CN103401258 B CN 103401258B CN 201310366284 A CN201310366284 A CN 201310366284A CN 103401258 B CN103401258 B CN 103401258B
- Authority
- CN
- China
- Prior art keywords
- power
- energy turbine
- turbine set
- wind energy
- blower fan
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Wind Motors (AREA)
- Control Of Eletrric Generators (AREA)
Abstract
一种风电场故障状态下紧急功率控制策略,包括以下步骤:①实时收集各风机的短期预测的功率、接收调度功率指令,获得风电场功率上限值;②风电场故障时记录以下数据:风电场可控风机、风电场不可控风机、切除风机;③计算风电场可以分配的功率、风电场需要发出的有功功率;④比较风电场可以分配的功率和风电场需要发出的有功功率
Description
技术领域:
本发明涉及风力发电技术领域,特别涉及一种风电场故障状态下紧急功率控制策略。
背景技术:
电力系统是复杂的动态系统,其安全稳定运行本质上要求发电与负荷需求之间必须时刻保持平衡。电力系统如果不能进行有效控制而出现供需失衡,将影响负荷的可靠用电甚至可能引起系统大范围的事故。
风电场是电力系统重要的电源,在电力系统中占有重要地位。随着风电机组技术的不断发展,双馈异步风电机组逐渐成为风电场的主流机型,当与风电场相连输电线路故障时,双馈异步风电机组会投入crowbar(橇杠)保护,这时风机功率不可控,容易造成风电场输出功率的剧烈波动。近年来我国发生的几次大规模风电场脱网事故中功率损失严重,对国民经济造成的直接和间接损失十分巨大。
发明内容:
鉴于此,有必要设计一种风电场故障状态下紧急功率控制策略。
一种风电场故障状态下紧急功率控制策略,对于有着n台风机的风电场,包括以下步骤:
①实时收集各风机的短期预测的功率pi、接收调度功率指令,获得风电场功率上限值其中功率pi的短期预测现有的多种算法可以实现,故不再累述;
②风电场故障时记录以下数据:风电场可控风机(即未投入crowbar保护的风机)、风电场不可控风机(即投入crowbar保护的风机)、切除风机(即未并网发电风机);
③计算风电场可以分配的功率P分配、风电场需要发出的有功功率Pset;
式(1)中,m为切除风机的总数,pj为各切除风机的容量,式(2)中,P损为网损;
④比较风电场可以分配的功率P分配和风电场需要发出的有功功率Pset并进行功率分配,
若P分配≤Pset,进行自由发电,即风电场发出的电,电网全部接收;
若P分配>Pset,则将Pset以备用风机>风电场可控风机>风电场不可控风机的优先级顺序分配直至完毕;
⑤系统故障切除,风电场故障状态下紧急功率控制策略退出,风电场按照正常的功率控制方式运行。
优选的,装备了储能装置的风电场,步骤④中优先级顺序为:备用风机>风电场可控风机>储能装置>风电场不可控风机。
优选的,备用风机以短期预测的功率pi大小排序,pi大的,优先分配;风电场可控风机按照功率裕度p裕降序排序;
p裕=pi-p实 (3)
式(3)中,p实为实发功率,p裕越大,分配功率越多。
优选的,储能装置平滑风电场的功率输出,实现风电场输出功率平抑。
本发明针对目前双馈异步风电机组转子crowbar保护对风机功率失去控制造成的影响,提出了一种新的控制方法,该方法使风电场在紧急时刻实现发电功率转移,减少对已投入crowbar风机的功率依赖,增加正常风机的输出功率,从而提高风电场输出功率的稳定性。
具体实施方式:
一种风电场故障状态下紧急功率控制策略,对于有着n台风机的风电场,包括以下步骤:
①实时收集各风机的短期预测的功率pi、接收调度功率指令,获得风电场功率上限值其中功率pi的短期预测现有的多种算法可以实现,故不再累述;
②风电场故障时记录以下数据:风电场可控风机(即未投入crowbar保护的风机)、风电场不可控风机(即投入crowbar保护的风机)、切除风机(即未并网发电风机);
③计算风电场可以分配的功率P分配、风电场需要发出的有功功率Pset;
式(1)中,m为切除风机的总数,pj为各切除风机的容量,式(2)中,P损为网损;
④比较风电场可以分配的功率P分配和风电场需要发出的有功功率Pset并进行功率分配,
若P分配≤Pset,进行自由发电,即风电场发出的电,电网全部接收;
若P分配>Pset,则将Pset以备用风机>风电场可控风机>风电场不可控风机的优先级顺序分配直至完毕;
⑤系统故障切除,风电场故障状态下紧急功率控制策略退出,风电场按照正常的功率控制方式运行。
在本实施方式中,装备了储能装置的风电场,步骤④中优先级顺序为:备用风机>风电场可控风机>储能装置>风电场不可控风机。
在本实施方式中,备用风机以短期预测的功率pi大小排序,pi大的,优先分配;风电场可控风机按照功率裕度p裕降序排序;
p裕=pi-p实 (3)
式(3)中,p实为实发功率,p裕越大,分配功率越多。
在本实施方式中,储能装置平滑风电场的功率输出,实现风电场输出功率平抑。
Claims (4)
1.一种风电场故障状态下紧急功率控制策略,对于有着n台风机的风电场,其特征在于,包括以下步骤:
①实时收集各风机的短期预测的功率pi、接收调度功率指令,获得风电场功率上限值
②风电场故障时记录以下数据:风电场可控风机、风电场不可控风机、切除风机;
③计算风电场可以分配的功率P分配、风电场需要发出的有功功率Pset;
式(1)中,m为切除风机的总数,pj为各切除风机的容量,式(2)中,P损为网损;
④比较风电场可以分配的功率P分配和风电场需要发出的有功功率Pset并进行功率分配,
若P分配≤Pset,进行自由发电;
若P分配>Pset,则将Pset以备用风机>风电场可控风机>风电场不可控风机的优先级顺序分配直至完毕;
⑤系统故障切除,风电场故障状态下紧急功率控制策略退出,风电场按照正常的功率控制方式运行。
2.如权利要求1所述的风电场故障状态下紧急功率控制策略,其特征在于,装备了储能装置的风电场,步骤④中优先级顺序为:备用风机>风电场可控风机>储能装置>风电场不可控风机。
3.如权利要求1所述的风电场故障状态下紧急功率控制策略,其特征在于,备用风机以短期预测的功率pi大小排序,pi大的,优先分配;风电场可控风机按照功率裕度p裕降序排序;
p裕=pi-p实 (3)
式(3)中,p实为实发功率,p裕越大,分配功率越多。
4.如权利要求2所述的风电场故障状态下紧急功率控制策略,其特征在于,储能装置平滑风电场的功率输出。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310366284.1A CN103401258B (zh) | 2013-08-21 | 2013-08-21 | 风电场故障状态下紧急功率控制策略 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310366284.1A CN103401258B (zh) | 2013-08-21 | 2013-08-21 | 风电场故障状态下紧急功率控制策略 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103401258A CN103401258A (zh) | 2013-11-20 |
CN103401258B true CN103401258B (zh) | 2015-09-16 |
Family
ID=49564831
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310366284.1A Active CN103401258B (zh) | 2013-08-21 | 2013-08-21 | 风电场故障状态下紧急功率控制策略 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103401258B (zh) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6252753B1 (en) * | 1998-12-18 | 2001-06-26 | Southern California Edison Co. | Energy service stabilizer |
CN102013699A (zh) * | 2010-10-25 | 2011-04-13 | 电子科技大学 | 一种风力发电场有功功率分配方法 |
CN102856925A (zh) * | 2012-09-03 | 2013-01-02 | 北京科诺伟业科技有限公司 | 一种风电场功率综合分配方法 |
-
2013
- 2013-08-21 CN CN201310366284.1A patent/CN103401258B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6252753B1 (en) * | 1998-12-18 | 2001-06-26 | Southern California Edison Co. | Energy service stabilizer |
CN102013699A (zh) * | 2010-10-25 | 2011-04-13 | 电子科技大学 | 一种风力发电场有功功率分配方法 |
CN102856925A (zh) * | 2012-09-03 | 2013-01-02 | 北京科诺伟业科技有限公司 | 一种风电场功率综合分配方法 |
Also Published As
Publication number | Publication date |
---|---|
CN103401258A (zh) | 2013-11-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104052159B (zh) | 一种用于风光储微网系统的能量管理控制器 | |
Wang et al. | An ordered curtailment strategy for offshore wind power under extreme weather conditions considering the resilience of the grid | |
ES2722408T5 (es) | Una central de energía eólica, y un método para aumentar la capacidad de potencia reactiva de una central de energía eólica | |
CN105186559B (zh) | 一种双馈风力发电机组低电压穿越电路及其控制方法 | |
CN104184171A (zh) | 一种风电场层有功功率控制系统和方法 | |
KR101687900B1 (ko) | 풍력발전단지에서의 배터리 에너지 저장 시스템에 기반한 풍력 발전 변동의 평활화 방법 | |
CN103527407A (zh) | 用于对诸如组合需求响应、惯性响应以及旋压储备的快速欠频之类的电网事件作出响应的方法和装置 | |
Karbouj et al. | A novel wind farm control strategy to mitigate voltage dip induced frequency excursion | |
CN106786756B (zh) | 一种光伏发电站虚拟同步控制方法及其控制系统 | |
Li et al. | Influence of renewable integration on frequency dynamics | |
Lyu et al. | Concurrent optimal re/active power control for wind farms under low-voltage-ride-through operation | |
CN102748238B (zh) | 带冗余储能的风电能量转换系统及其应用模式与控制方法 | |
Liu et al. | Impacts of large scale wind power integration on power system | |
Liu et al. | The effects of wind turbine and energy storage participating in frequency regulation on system frequency response | |
Rose et al. | Challenges of integrating large amounts of wind power | |
CN104362643A (zh) | 风电场无功补偿配置容量计算方法 | |
CN103401258B (zh) | 风电场故障状态下紧急功率控制策略 | |
CN102646993B (zh) | 一种风电机组低电压穿越系统及其方法 | |
CN102255334B (zh) | 风力发电机组智能单元矩阵并网方法及其专用设备 | |
Michalke et al. | Grid support capabilities of wind turbines | |
CN203103985U (zh) | 智能永磁直驱风力发电机组控制装置 | |
CN202690329U (zh) | 带冗余储能的风电能量转换系统 | |
CN103490424A (zh) | 双馈异步发电机系统故障下提高无功输出能力的方法 | |
CN103956771A (zh) | 低电压穿越系统 | |
Sato et al. | Suppression of frequency fluctuation of power system by output control of PMSG wind generator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: No. 3120, Dalian Road, Jinfeng District, Yinchuan, the Ningxia Hui Autonomous Region Patentee after: The Ningxia Hui Autonomous Region Electric Power Design Institute Co., Ltd. Address before: 750001 East Road, the Great Wall, Yinchuan, Yinchuan, the Ningxia Hui Autonomous Region Patentee before: Ningxia Hui Autonomous Region Electric Power Design Institute |