CN103398218A - Construction and protection method for long-distance parallel subsea pipeline - Google Patents

Construction and protection method for long-distance parallel subsea pipeline Download PDF

Info

Publication number
CN103398218A
CN103398218A CN2013102082213A CN201310208221A CN103398218A CN 103398218 A CN103398218 A CN 103398218A CN 2013102082213 A CN2013102082213 A CN 2013102082213A CN 201310208221 A CN201310208221 A CN 201310208221A CN 103398218 A CN103398218 A CN 103398218A
Authority
CN
China
Prior art keywords
anchor
pipeline
construction
theta
hawser
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102082213A
Other languages
Chinese (zh)
Other versions
CN103398218B (en
Inventor
张志鹏
高兆鑫
郑理
关幼耕
高晓明
赵海
陈海涛
付春丽
田乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CNPC Offshore Engineering Co Ltd
Original Assignee
CNPC Offshore Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Offshore Engineering Co Ltd filed Critical CNPC Offshore Engineering Co Ltd
Priority to CN201310208221.3A priority Critical patent/CN103398218B/en
Publication of CN103398218A publication Critical patent/CN103398218A/en
Application granted granted Critical
Publication of CN103398218B publication Critical patent/CN103398218B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention relates to a construction and protection method for a long-distance parallel subsea pipeline. The method comprises the steps of comparative analysis on original pipeline design material and a research report, analysis on pipeline parallel laying risk points, analysis on a pipe-laying ship mooring system, analysis on an anchor cable catenary and rendering and filed conduction of a construction anchor settling drawing. By means of research on the anchor cable catenary, with combination of a calculation result, the construction anchor settling drawing is rendered according to the engineering ship anchor settling theory, and the stress situation of each anchor in the anchor settling state of a ship under the extreme working condition is counted through relative software. The method has the advantages of economical, efficient, free of pollution, strong in operability and the like. In addition, the construction requirement is met.

Description

The parallel submerged pipeline construction of a kind of long distance guard method
Technical field
The present invention relates to the technical field of undersea pipe-laying, be specifically related to the parallel submerged pipeline construction of a kind of long distance guard method.
Background technique
Along with the offshore oil and gas field exploitation is constantly expanded to deep layer and frontier, offshore platform process treating flow process is more and more simplified, increasing submerged pipeline is used, inevitably there will be pipeline installation and the existing pipeline phenomenon that walks abreast in the pipe installation process, the present invention's problem for this reason provides simple and practical operating method.
At present, standard does not have corresponding standard to long apart from parallel pipeline pipe laying construction resist technology both at home and abroad, and domestic not long apart from parallel pipeline construction precedent, only engineering ship rear anchor hawser crossover line in place arranges floating drum and do not move the anchor job execution.
For above situation; we are consulting on the basis of data at home and abroad; by large component analysis; develop the method that a cover meets the parallel submerged pipeline construction of long distance protection; the method is based on catenary equation; work out the parallel submerged pipeline cloth anchor method of long distance, realized the control to pipe laying construction cloth anchor, solved the difficult problem of the parallel submerged pipeline protection of long distance.The method has proposed the solution of the parallel submerged pipeline construction of long distance first, has ensured the safety of pipeline during original pipeline operation.Break through first traditional buoy anchoring system mode, will grow the parallel submerged pipeline resist technology successful Application of distance in the branch line submarine pipeline state key project financing of the second west to east gas pipeline project Hong Kong.
The method has the characteristics such as economy, efficient, pollution-free, strong operability, meets construction requirement.
Summary of the invention
For above-mentioned deficiency of the prior art, the object of the invention is based on catenary equation, has worked out the parallel submerged pipeline cloth anchor method of long distance, has realized the control to pipe laying construction cloth anchor, has solved the difficult problem of the parallel submerged pipeline protection of long distance.The method has proposed the solution of the parallel submerged pipeline construction of long distance first, has ensured the safety of pipeline during original pipeline operation.Consider controlled investment, reduction of erection time, facilitate the aspect factor such as site operation, form the technological scheme that is applicable to the parallel submerged pipeline construction of long distance protection.
In order to realize the foregoing invention purpose, the application provides following technological scheme:
(1) original pipeline design data and survey report comparative analysis
, by the pipeline route survey report to original pipeline design data and employing GeoPulse sub-bottom profiler/pipeline instrument, analyze the present routing condition of pipeline, pipe top buried depth and cover the soil property type.
(2) the parallel laying of pipeline risk point analysis
In construction operation, maximum risk sources is in the impact on pipeline of the anchor of operation boats and ships and anchor hawser.Because long distance is parallel, the pipe laying barge construction is a dynamic process, often complete a sea pipe job execution, need to carry out folding and unfolding anchor hawser reach pipe laying barge, and there is an operation of casting anchor of rising of cycle, anchor hawser is crossed over original pipeline, has scraping and sawing risk to original pipeline, works the operation of casting anchor and has equally this risk.
(3) the pipe laying barge mooring system is analyzed
By construction operation pipe laying barge self mooring system is studied, each parameter of clear and definite mooring system.Comprise anchor weight, anchor hawser model, anchor hawser length and windlass maximum pull etc.
Adopt the anchoring analytical technology, check cloth anchor scheme and whether meet the mechanical equilibrium requirement; The mechanics projecting point of clear and definite each cloth anchor scheme, the cloth anchor work of accurate instruction practice of construction, thereby the destruction that the mechanical structure of avoiding wrong cloth anchor scheme to form causes to extra large pipe.
(4) mooring line catenary analysis
Boats and ships are when casting anchor mooring, and anchor cable is the stretched wire state.The anchor hawser wire rope has good flexibility and uniform quality, and therefore single anchor chain or the anchor cable of wire rope can be regarded the simple cautionary suspension line as, are below the catenary formula.
y = a [ sec α ( ch x a ) - 1 ] + tgα · sh x a = R w [ 1 cos α ( e x · w R + e - x · w R 2 - 1 ) + tg · e x · w R + e - x · w R 2 ] - - - ( 1 )
The y depth of water in formula, m;
R effect external force aboard ship, t;
The x anchoring point is to the horizontal equivalent of chaining point, m;
The a angle of weighing anchor, °;
Every meter chain weight of w, t/m
Suppose that the anchor cable that hitches boats and ships is that an intensity is very large, and do not have ponderable anchor cable.The pulling force H that acts on boats and ships is substantially horizontal, and this power acts on anchor by anchor cable.When anchor cable is strained and is not dragged of anchor, the horizontal pull H0 of anchor and environmental forces H balance, i.e. H0=H.Equilibrium of forces as shown in Figure 1.If the angle theta of the horizontal force H0 at anchor point O place, vertical force V0, tension force T0 and tension force and horizontal force 0, the vertical force V of hawse pipe outlet port A, tension force T, and the angle theta of tension force and horizontal force.According to equilibrium of forces, following equation is arranged:
V 0=H 0tanθ 0=Htanθ 0 (2)
T 0 = H 0 2 + V 0 2 = H sec θ 0 - - - ( 3 )
If anchor cable is ponderable, the linear mass load of anchor cable in seawater is w, and the length of anchor cable (catenary) is s, and the horizontal equivalent of A to O is x, and vertical distance (depth of water) is z.
w H s = tan θ - tan θ 0 - - - ( 4 )
w H z = sec θ - sec θ 0 - - - ( 5 )
w H x = ln ( sec θ + tan θ sec θ 0 + tan θ 0 ) - - - ( 6 )
Have the characteristics such as friendly interface, computational speed be fast based on the simulated program of VB programming, and be easy to grasp.The program that adopts is that VB writes.
The program solution step:
Determine initial catenary parameter a (each anchor cable is the same).
Set up the newton iteration formula of each anchor cable about a value.
Carry out iteration.
Determine whether requirement, meet, finish to calculate; Otherwise, increase iterations, until full
Till the foot condition.
(5) construction cloth anchor figure draws and field conduct
According to cloth anchor principle, draw cloth anchor figure, crossover line one side, anchor point and pipeline safety, apart from considering to slip the anchor distance, guarantee greater than more than 100 meters.Original pipeline top is every 200 meters indication buoys of arranging 30 meters of three color different interval.Need the tension force of pre-imputation during site operation cloth anchor, guarantee while casting anchor operation that anchor is placed on safely on the anchor boat deck and fixing, avoid from landing on anchor boat.Work the shape cast anchor between operational period by special messenger's charge of overseeing anchor hawser stressing conditions and anchor hawser.
Beneficial effect:
1, be first domestic.Parallel submerged pipeline construction, the pipeline standard is without clear and recommend way, and the parallel submerged pipeline construction of long distance, at home and abroad all beyond example;
2, economic, efficient, strong operability can solve effectively that engineering place marine area function zoning complexity, boats and ships frequent activity, project investment are controlled sternly, the tight requirement of implementing plan duration.
3, the parallel submerged pipeline construction of long distance protection, construction forms danger to the primary tube line, moves the anchor Job Operations in construction improper, very easily original pipeline is worked the mischief, and produces immeasurable consequence.This scheme can meet this project project investment and control tight, tight characteristics of implementing plan duration, meets the field engineering requirement.
4, the parallel submerged pipeline construction of long distance guard method, can obtain good effect in engineering, can solve long actual conditions apart from parallel pipeline construction and duration anxiety.Compare conventional scheme, reduce investment outlay, produce obvious economic benefit.
5, the parallel submerged pipeline construction of long distance guard method, at home and abroad all beyond example, apply first in the branch line submarine pipeline engineering of the second west to east gas pipeline project Hong Kong, successfully solved the difficult problem with parallel 6.11 kilometers of precipice municipal administration line.Therefore, the breakthrough of this technology, have great importance to the technical barrier that fills the domestic gaps, solve China parallel pipeline construction protection etc.For the construction of submarine pipeline of the same trade provides strong reference reference value.
Description of drawings
Fig. 1 basis cloth anchor figure
The phase diagram of Fig. 2 anchor hawser stretched wire
Fig. 3 anchor hawser stretched wire state free-body diagram
Fig. 4 program is calculated interface
Fig. 5 indication buoy schematic diagram
The parallel section of Fig. 6 straight line cloth anchor figure
The parallel section of Fig. 7 camber line cloth anchor figure
Progressive section cloth anchor figure of Fig. 8
Embodiment
The parallel submerged pipeline arrangement and method for construction of long distance:
By presetting pretensioning, calculate the different water depth anchor hawser according to the catenary program and touch the mud point horizontal length that dangles, guarantee that anchor hawser touches the mud point in original pipeline outside, to guarantee that anchor hawser does not contact with pipeline.
Catenary equation programming calculated data
Figure BDA00003271246600061
Three kinds of operating modes for the parallel existence of pipeline:
The parallel section of pipeline straight line;
The parallel section of pipeline curve;
Progressive section of pipeline.
(1) the parallel section construction of pipeline straight line
Calculate the distance of crossing over the tactile original pipeline of mud point of anchor hawser according to program.By controlling the pipe laying barge pretensioning, while guaranteeing that pipe laying barge moves, anchor hawser touches mud point in the precipice municipal administration line outside, guarantees that anchor hawser above pipeline, does not contact with pipeline., at anchor point reasonable Arrangement anchor point monitoring ship, monitor the position, anchor hawser length, each anchor of the anchor point angle with respect to pipe laying barge constantly.
(2) the parallel section construction of pipeline curve.
Calculate and cross over anchor hawser and touch mud point distance by the catenary program, rationally the cloth anchor, control pipe laying barge anchor hawser tension variation and realize that anchor hawser touches the mud point outside original pipeline, avoids contacting of anchor hawser and pipeline., at anchor point reasonable Arrangement anchor point monitoring ship, monitor the position, anchor hawser length, each anchor of the anchor point angle with respect to pipe laying barge constantly.
(3) progressive section construction of pipeline.
Calculate and cross over anchor hawser and touch mud point distance by the catenary program, rationally the cloth anchor, control pipe laying barge anchor hawser tension variation and realize that anchor hawser touches the mud point outside original pipeline, avoids contacting of anchor hawser and pipeline., at anchor point reasonable Arrangement anchor point monitoring ship, monitor the position, anchor hawser length, each anchor of the anchor point angle with respect to pipe laying barge constantly.
It should be noted that finally: obviously, above-described embodiment is only for example of the present invention clearly is described, and is not the restriction to mode of execution.For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description.Here need not also can't give all mode of executions exhaustive.And the apparent variation of being amplified out thus or change still are among protection scope of the present invention.

Claims (5)

1. the parallel submerged pipeline construction of a long distance guard method, is characterized in that, comprises the steps
The original pipeline design data of step 1 and survey report comparative analysis
, by the pipeline route survey report to original pipeline design data and employing GeoPulse sub-bottom profiler or pipeline instrument, analyze the present routing condition of pipeline, pipe top buried depth and cover the soil property type;
The analysis of the parallel laying of step 2 pipeline risk point
In construction operation, maximum risk sources is in the impact on pipeline of the anchor of operation boats and ships and anchor hawser;
Step 3 pipe laying barge mooring system is analyzed
By construction operation pipe laying barge self mooring system is studied, each parameter of clear and definite mooring system, comprise anchor weight, anchor hawser model, anchor hawser length and windlass maximum pull;
The step 4 mooring line catenary is analyzed
Boats and ships are after casting anchor, and anchor cable is the stretched wire state, and anchor chain or wire rope have good flexibility and uniform quality, and single anchor chain or the anchor cable of wire rope are regarded the simple cautionary suspension line as;
Step 5 construction cloth anchor figure draws and field conduct
, by to mooring line catenary research,, in conjunction with result of calculation,, according to engineering ship cloth anchor point theory, draw construction cloth anchor figure, and by the related software module, adjust this cloth anchor state of boats and ships each anchor hawser stressing conditions under extreme operating condition.
2. method according to claim 1, it is characterized in that: the pipe laying barge mooring system in described step 3 is analyzed, pipe laying barge anchor, anchoring cable and displacement winch are studied, and clear and definite pipe laying barge anchor weight, anchor hawser model and winch performance parameter, determine the anchoring ability of pipe laying barge.
3. method according to claim 1 is characterized in that: the mooring line catenary analysis in described step 4, and boats and ships are after the cloth anchor, anchor hawser is the stretched wire state, single anchor hawser is considered as simple catenary,, according to the catenary formula, passes through method of iteration, according to construction depth of water situation, default different tension forces, calculate engineering ship in the same depth of water situation, goes out the chain hole and touch the horizontal equivalent of mud point to anchor hawser, distance between selection level distance is parallel greater than pipeline, determine the pretensioning size.
4. method according to claim 1, it is characterized in that: in step 4, the catenary formula is
y = a [ sec α ( ch x a ) - 1 ] + tgα · sh x a = R w [ 1 cos α ( e x · w R + e - x · w R 2 - 1 ) + tg · e x · w R + e - x · w R 2 ]
In formula
The y depth of water, m;
R effect external force aboard ship, t;
The x anchoring point is to the horizontal equivalent of chaining point, m;
The a angle of weighing anchor, °;
Every meter chain weight of w, t/m
When the anchor cable that hitches boats and ships is that an intensity is very large, and while not having ponderable anchor cable, the pulling force H that acts on boats and ships is substantially horizontal, and this power acts on anchor by anchor cable, when the anchor cable tension and while not dragging of anchor, and the horizontal pull H of anchor 0With environmental forces H balance, i.e. H 0=H, the horizontal force H at anchor point O place 0, vertical force V 0, tension force T 0And the angle theta of tension force and horizontal force 0, the vertical force V of hawse pipe outlet port A, tension force T, and the angle theta of tension force and horizontal force have following equation according to equilibrium of forces:
V 0=H 0tanθ 0=Htanθ 0
T 0 = H 0 2 + V 0 2 = H sec θ 0
When anchor cable is ponderable, the linear mass load of anchor cable in seawater is w, and the length of anchor cable is s, and the horizontal equivalent of A to O is x, and vertical distance (depth of water) is z,
w H s = tan θ - tan θ 0
w H z = sec θ - sec θ 0
w H x = ln ( sec θ + tan θ sec θ 0 + tan θ 0 ) ·
5. method according to claim 1, it is characterized in that: construct in described step 5 cloth anchor figure and field conduct, according to cloth anchor principle, draw cloth anchor figure, crossover line one side, anchor point and pipeline safety are apart from considering to slip the anchor distance, assurance is greater than more than 100 meters, adjust this cloth anchor state of boats and ships each anchor hawser stressing conditions under extreme operating condition by the related software module, original pipeline top is every 200 meters indication buoys of arranging 30 meters of three color different interval, need preset according to the tension force that calculates in step 4 during site operation cloth anchor, guarantee while casting anchor operation that anchor is placed on safely on the anchor boat deck and fixes, avoid from landing on anchor boat, work the shape cast anchor between operational period by special messenger's charge of overseeing anchor hawser stressing conditions and anchor hawser.
CN201310208221.3A 2013-05-30 2013-05-30 Construction and protection method for long-distance parallel subsea pipeline Active CN103398218B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310208221.3A CN103398218B (en) 2013-05-30 2013-05-30 Construction and protection method for long-distance parallel subsea pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310208221.3A CN103398218B (en) 2013-05-30 2013-05-30 Construction and protection method for long-distance parallel subsea pipeline

Publications (2)

Publication Number Publication Date
CN103398218A true CN103398218A (en) 2013-11-20
CN103398218B CN103398218B (en) 2015-06-17

Family

ID=49561902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310208221.3A Active CN103398218B (en) 2013-05-30 2013-05-30 Construction and protection method for long-distance parallel subsea pipeline

Country Status (1)

Country Link
CN (1) CN103398218B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105864509A (en) * 2016-06-06 2016-08-17 青岛理工大学 Method for rapidly repairing submarine pipeline through replacement pipe section
CN106051303A (en) * 2016-05-27 2016-10-26 安徽科恩新能源有限公司 Hydraulic limiting protection device
CN106122591A (en) * 2016-07-14 2016-11-16 青岛理工大学 Guiding type inflator balance submarine pipeline access device and method
CN106609885A (en) * 2017-01-09 2017-05-03 浙江海洋大学 A design method based on the protection of shallow sea reclamation area subsea pipelines

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1581847A (en) * 1976-08-09 1980-12-31 Standard Oil Co Gas flare system for use in a body of water
US5275510A (en) * 1992-01-16 1994-01-04 Jacob De Baan Offshore tanker loading system
US20050196242A1 (en) * 2004-03-02 2005-09-08 Petroleo Brasileiro S.A. - Petrobras Compensating suspension element configuration
CN101280862A (en) * 2007-04-03 2008-10-08 上海市基础工程公司 Seabed PE pipe rim spreading and imbedding construction method
CN102269328A (en) * 2011-08-18 2011-12-07 浙江大学 Offshore oil and gas transportation flexible vertical pipeline
WO2012143671A2 (en) * 2011-04-18 2012-10-26 Magma Global Limited Subsea conduit system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1581847A (en) * 1976-08-09 1980-12-31 Standard Oil Co Gas flare system for use in a body of water
US5275510A (en) * 1992-01-16 1994-01-04 Jacob De Baan Offshore tanker loading system
US20050196242A1 (en) * 2004-03-02 2005-09-08 Petroleo Brasileiro S.A. - Petrobras Compensating suspension element configuration
CN101280862A (en) * 2007-04-03 2008-10-08 上海市基础工程公司 Seabed PE pipe rim spreading and imbedding construction method
WO2012143671A2 (en) * 2011-04-18 2012-10-26 Magma Global Limited Subsea conduit system
CN102269328A (en) * 2011-08-18 2011-12-07 浙江大学 Offshore oil and gas transportation flexible vertical pipeline

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106051303A (en) * 2016-05-27 2016-10-26 安徽科恩新能源有限公司 Hydraulic limiting protection device
CN105864509A (en) * 2016-06-06 2016-08-17 青岛理工大学 Method for rapidly repairing submarine pipeline through replacement pipe section
CN105864509B (en) * 2016-06-06 2017-11-21 青岛理工大学 One kind changes pipeline section and quickly repairs submarine pipeline method
CN106122591A (en) * 2016-07-14 2016-11-16 青岛理工大学 Guiding type inflator balance submarine pipeline access device and method
CN106609885A (en) * 2017-01-09 2017-05-03 浙江海洋大学 A design method based on the protection of shallow sea reclamation area subsea pipelines
CN106609885B (en) * 2017-01-09 2019-03-15 浙江海洋大学 A kind of design method of the protection based on submarine pipeline in shallow sea reclamation area

Also Published As

Publication number Publication date
CN103398218B (en) 2015-06-17

Similar Documents

Publication Publication Date Title
CN104696588B (en) Deepwater subsea pipeline starting laying method
CN103527851B (en) Pre-laying process of submarine pipeline start laying system
CN103398218B (en) Construction and protection method for long-distance parallel subsea pipeline
CN109506044A (en) A kind of pipeline under the ocean construction technology
CN104480865B (en) A kind of Large Steel open caisson accurate positioning method
CN103790189B (en) The on-the-spot method for early warning of stake is slipped during ocean engineering piling
CN104692247B (en) Twisting-resisting installation method of deepwater underwater structure
CN103482026A (en) Hybrid mooring system for ultra-deepwater floating structures and mooring method
CN103600818B (en) A kind of regulatable semisubmersible platform in buoyancy aid direction and regulate and control method
CN106979382A (en) The starting laying process of deepwater S-shaped submarine pipeline
CN101746484B (en) Operation method of anchoring type operating vessel when crossing over submarine facility during anchoring
CN103411028B (en) A kind of not iceound pipe laying construction method in benthal oil-gas pipeline navigation channel
CN107084784B (en) A kind of four body ship type underwater measurement platform of movable lifting
Zhou et al. Development and application of a new ballast water system for immersed tunnel installation: A case study of the Yuliangzhou tunnel in Xiangyang, China
CN106096288A (en) The security evaluation of suction type injection plate anchor and method for early warning
CN103899842B (en) Method for installing deepwater online tee joint
CN102661444B (en) Installation method of deepwater double piping system of offshore platform
CN203876952U (en) Pontoon system for immersed pipes to pass through rivers
CN102305703A (en) Cable subsurface buoy real-time internal wave monitoring device installed on ocean platform
CN202092644U (en) Cable subsurface buoy real-time internal wave monitoring device installed on ocean platform
CN106300147B (en) Water bridge under extra large cable with laying tension force monitoring function
CN105952969A (en) Deep sea water taking pipe protecting mode and laying construction process
KR20090118466A (en) Installation method of the pipelines using laying barge with sub-sea anchor block
Chakrabarti et al. Design, construction, and installation of a floating caisson used as a bridge pier
CN102001419B (en) Deep water float-over mooring device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant