CN103388372B - Suspended ceiling stone dry-hanging structure and construction method thereof - Google Patents

Suspended ceiling stone dry-hanging structure and construction method thereof Download PDF

Info

Publication number
CN103388372B
CN103388372B CN201310336223.0A CN201310336223A CN103388372B CN 103388372 B CN103388372 B CN 103388372B CN 201310336223 A CN201310336223 A CN 201310336223A CN 103388372 B CN103388372 B CN 103388372B
Authority
CN
China
Prior art keywords
stone material
furred ceiling
ceiling stone
suspension member
suspended ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310336223.0A
Other languages
Chinese (zh)
Other versions
CN103388372A (en
Inventor
崔畅
颉建明
岳晓申
张磊
孙炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING CONSTRUCTION ENGINEERING DECORATION Co Ltd
Original Assignee
BEIJING CONSTRUCTION ENGINEERING DECORATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING CONSTRUCTION ENGINEERING DECORATION Co Ltd filed Critical BEIJING CONSTRUCTION ENGINEERING DECORATION Co Ltd
Priority to CN201310336223.0A priority Critical patent/CN103388372B/en
Publication of CN103388372A publication Critical patent/CN103388372A/en
Application granted granted Critical
Publication of CN103388372B publication Critical patent/CN103388372B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a suspended ceiling stone dry-hanging structure and a construction method thereof. The structure comprises a suspended ceiling stone and hanging pieces; two opposite side edges of the suspended ceiling stone are provided with grooves, and slot port reinforcing plates are pasted along two side edges of the opening slots at the upper face of the suspended ceiling stone; each hanging piece is U-shaped; two openings of the U-shaped hanging pieces oppositely clamp the two opposite side edges of the suspended ceiling stone, the length of each U-shaped piece is adaptive to the edge length of the suspended ceiling stone, a long round hole parallel with the length direction of the hanging piece is formed in each of two ends of the upper edge of each U-shaped hanging piece, and the lower edge of each U-shaped hanging piece is narrower than the upper edge; each lower edge is horizontally inserted into the grooves of the suspended ceiling stone. The U-shaped hanging piece disclosed by the invention can embrace the suspended ceiling stone like a person with two hands, can doubly improve the safety of the suspended ceiling stone, improve construction efficiency, and enable the fixing modes to be more diversified and convenient, solves the problem that the suspended ceiling stone can not be separately replaced, and is suitable for the construction of any suspended ceiling stone.

Description

Furred ceiling stone material dry suspending structure and construction method thereof
Technical field
The present invention relates to a kind of cladding structure of stone material, particularly a kind of furred ceiling stone material dry suspending structure and construction method thereof.
Background technology
The safety of furred ceiling stone material is shown great attention in decorative engineering always, and designing a furred ceiling dry-hanging piece for stone more reliably becomes the key improving furred ceiling stone material security performance, and suspension member also will be made more convenient fixing simultaneously.U-shaped dry hanging article design starting point of the present invention is just this.
Current and the present invention's immediate furred ceiling stone material dry suspending technical scheme is: utilize T-shaped dry hanging article, and arrange 2 ~ 3 suspension members at furred ceiling stone material edge joint position, each suspension member bears the weight of adjacent two blocks of stone materials.
Existing T-shaped dry-hanging piece for stone fixed ceilings stone material shortcoming is:
1, hanging piece for stone becomes point-like to arrange, stone material stress point and T-shaped dry hanging article contact area are only " suspension member width (50mm) x15mm ";
2, a T-shaped suspension member shared by adjacent two blocks of stone materials, the not easily leveling of furred ceiling stone material, and cutting stone material notch can make Stone Strength greatly reduce repeatedly, and stone protectant can destroy;
3, T-shaped suspension member must be fixed on steelframe, cannot correct the deviation that steelframe and stone material are split in operation.
4, because a T-shaped suspension member shared by adjacent furred ceiling stone material, the rear possibility changing stone material without secondary of having constructed.
Summary of the invention
The invention provides a kind of furred ceiling stone material dry suspending structure and construction method thereof, solve existing furred ceiling stone material dry suspending structure suspension member load large, the technical problem of poor stability, and the not easily leveling of furred ceiling stone material, cannot adjust deviation, is difficult to the technical problem changed after construction.
The technical solution adopted for the present invention to solve the technical problems is:
This furred ceiling stone material dry suspending structure, comprise furred ceiling stone material and suspension member, the relative dual-side of described furred ceiling stone material has groove, and furred ceiling stone material upper surface is bonded with notch stiffener along the dual-side of fluting;
Described suspension member is U-shaped suspension member, U-shaped suspension member between two opening blocks the relative dual-side of furred ceiling stone material relatively, length and the furred ceiling stone material length of side of U-shaped suspension member adapt, respectively there is a slotted hole parallel with suspension member length direction at the two ends, top of U-shaped suspension member, U-shaped suspension member be narrower than top below, following level is inserted in the groove of furred ceiling stone material.
Described furred ceiling stone material has groove relative to long limit, both sides.
The upper trough rim of described groove is shorter than lower trough rim, is mutually spliced, and form the gap through U-shaped suspension member between adjacent two blocks of furred ceiling stone materials by the lower trough rim of groove between the upper trough rim of groove.
The AB glue fixed with U-shaped suspension member and cloud stone glue is filled with in the groove of described furred ceiling stone material.
Described U-shaped suspension member is by corrosion resistant plate bending forming, or customization aluminium alloys profiled member.
The construction method of this furred ceiling stone material dry suspending structure, the construction sequence that described furred ceiling stone material dry suspending is configured in beam bottom is as follows:
Step one, in beam bottom according to the size typesetting unwrapping wire of furred ceiling stone material, and the beam sides fixed corner code in the frame bar left and right sides, corner brace accomplishes fluently bolt hole in advance, and hole location is corresponding with the slotted hole on U-shaped suspension member;
Step 2, is fixed the first single u-shaped suspension member by bolt and corner brace, then furred ceiling stone material one side and the first single u-shaped suspension member grafting is fixed;
Step 3, fixes another single u-shaped suspension member and another side grafting of furred ceiling stone material, then is fixed by bolt and corner brace by this U-shaped suspension member;
Step 4, repeatedly verifies the position of the furred ceiling stone material of installation, adjusts deviation in time;
Step 5, repeats above-mentioned steps two to four, and the furred ceiling stone material completing beam bottom is installed.
The construction method of this furred ceiling stone material dry suspending structure, the construction sequence that described furred ceiling stone material dry suspending is configured in top board place is as follows:
Step one, according to the size typesetting unwrapping wire of furred ceiling stone material on top board;
Step 2, the position to be fixed of cross bar is determined in corresponding suspension member slotted hole position, calculates montant size and way;
Step 3, arranges montant according to roof conditions, is fixed in montant top and top board, fixedly secured by cross bar on montant;
Step 4, by temporary fixed in the groove of U-shaped suspension member insertion furred ceiling stone material, is fixed the U-shaped suspension member at least one block of furred ceiling stone material through slotted hole and cross bar by bolt;
Step 5, repeatedly verifies the position of the furred ceiling stone material of installation, adjusts deviation in time;
Step 6, repeats above-mentioned steps four to five, and the furred ceiling stone material completing top board place is installed.
Beneficial effect of the present invention is as follows:
U-shaped suspension member of the present invention is by stainless steel bending and molding or adopt customization aluminium alloys profiled member, and avoid the pad of T-shaped suspension member, intensity is larger.U-shaped suspension member upper surface is bonded with notch stiffener, and that improves suspension member notch is subject to force intensity, improves furred ceiling stone material security performance.The bolt box of suspension member upper side edge is Long Circle, can regulate stone material position after installation in certain scope.
The line (face) that T-shaped suspension member and the point cantact of stone material are become U-shaped dry hanging article by the present invention contacts, namely contact area is become " the stone material length of side (times over 50mm) x20mm " from " suspension member width (50mm) x15mm ", the contact area of suspension member and stone material sidewall doubles, make stone material sidewall stressed at double reduce and stressed more even.
Every block stone material configures separately at least two U-shaped suspension members, and adjacent stone material mounts separately, does not interfere with each other, and is convenient to leveling.The notch of stone material side can in the direct machine-shaping of stone material producer, and stone protectant remains intact.
The fixed form of U-shaped dry hanging article meets ceiling construction custom more, can utilize to hang muscle or corner brace etc. and to be fixed at the bottom of structure floor, beam, by the restriction that stone material steelframe is arranged.
Every block furred ceiling stone material mounts separately, needs can independently remove when changing stone material to hang muscle or corner brace, stone material monoblock is taken off, for convenience detach.
Furred ceiling stone material " both hands " can be embraced by U-shaped suspension member of the present invention, coordinate stone material fluting and stiffener, the safety of furred ceiling stone material can be significantly improved, improve efficiency of construction, also make fixed form more various, convenient simultaneously, solve the problem that furred ceiling stone material cannot be changed separately, be applicable to the construction of any furred ceiling stone material.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the present invention is further described.
Fig. 1 is the perspective view of U-shaped suspension member.
Fig. 2 is the perspective view of furred ceiling stone material dry suspending structure.
Fig. 3 is the installation drawing that furred ceiling stone material dry suspending is configured in beam bottom.
Fig. 4 is the installation drawing that furred ceiling stone material dry suspending is configured in furred ceiling place.
Fig. 5 is the lateral view of Fig. 4.
Reference numeral: at the bottom of 1-furred ceiling stone material, 1.1-groove, 2-U shape suspension member, 2.1-slotted hole, 3-notch stiffener, 4-beam, 5-corner brace, 6-bolt, 7-top board, 8-cross bar, 9-montant.
Detailed description of the invention
Embodiment is see shown in Fig. 1, Fig. 2, and this furred ceiling stone material dry suspending structure, comprise furred ceiling stone material 1 and suspension member, the long limit, relative both sides of described furred ceiling stone material 1 has groove 1.1, is filled with the AB glue and cloud stone glue fixed with U-shaped suspension member 2 in groove 1.1.Furred ceiling stone material 1 upper surface has notch stiffener 3 along the dual-side AB slotted is gluing.
The thickness of described furred ceiling stone material 1 can be 25mm, groove 1.1 apart from bottom surface 12mm ~ 17mm, the wide 5mm of groove 1.1, degree of depth 25mm.Notch stiffener 3 can be the thick stone material of 17mm.The furred ceiling stone material of corresponding different-thickness can provide the U-shaped suspension member of plurality of specifications.
Described suspension member is U-shaped suspension member 2, and U-shaped suspension member 2 by 2mm thick 304 corrosion resistant plate bending forming, also can adopt customization aluminium alloys profiled member.U-shaped suspension member between two opening blocks the relative dual-side of furred ceiling stone material 1 relatively, the length of U-shaped suspension member 2 or short 1 ~ 10cm equal with the length of side of furred ceiling stone material 1, respectively there is a slotted hole 2.1 parallel with suspension member length direction at the two ends, top of U-shaped suspension member 2, U-shaped suspension member 2 be narrower than top below, following level is inserted in the groove 1.1 of furred ceiling stone material 1.
Shown in Figure 3, the upper trough rim of described groove 1.1 is shorter than lower trough rim, is mutually spliced, and form the gap through U-shaped suspension member 2 between adjacent two blocks of furred ceiling stone materials 1 by the lower trough rim of groove 1.1 between the upper trough rim of groove 1.1.
Shown in Figure 3, the construction method of this furred ceiling stone material dry suspending structure, the construction sequence that described furred ceiling stone material dry suspending is configured in 4 places at the bottom of beam is as follows:
Step one, at the bottom of beam, 4 places are according to the size typesetting unwrapping wire of furred ceiling stone material 1, and the beam sides fixed corner code 5 in the frame bar left and right sides, corner brace accomplishes fluently bolt hole in advance, and hole location is corresponding with the slotted hole 2.1 on U-shaped suspension member;
Step 2, is fixed the first single u-shaped suspension member 2 by bolt 6 and corner brace 5, then furred ceiling stone material 1 one side and the first single u-shaped suspension member 2 grafting is fixed;
Step 3, fixes another single u-shaped suspension member 2 with another side grafting of furred ceiling stone material 1, then is fixed by bolt 6 and corner brace 5 by this U-shaped suspension member 2;
Step 4, repeatedly verifies the position of the furred ceiling stone material 1 of installation, adjusts deviation in time;
Step 5, repeats above-mentioned steps two to four, and the furred ceiling stone material completing beam bottom is installed.
Shown in Fig. 4,5, the construction method of this furred ceiling stone material dry suspending structure, the construction sequence that described furred ceiling stone material dry suspending is configured in top board 7 place is as follows:
Step one, according to the size typesetting unwrapping wire of furred ceiling stone material 1 on top board 7;
Step 2, the position to be fixed of cross bar 8 is determined in corresponding suspension member slotted hole position 2.1, calculates montant 9 size and way;
Step 3, arranges montant 9 according to roof conditions, is fixed in montant top and top board 7, fixedly secured by cross bar 8 on montant 9;
Step 4, temporary fixed in the groove U-shaped suspension member 2 being inserted furred ceiling stone material 1, the U-shaped suspension member 2 at least one block of furred ceiling stone material 1 is fixed through slotted hole 2.1 and cross bar 8 by bolt 6;
Step 5, repeatedly verifies the position of the furred ceiling stone material 1 of installation, adjusts deviation in time;
Step 6, repeats above-mentioned steps four to five, and the furred ceiling stone material completing top board place is installed.

Claims (6)

1. a furred ceiling stone material dry suspending structure, comprises furred ceiling stone material (1) and suspension member, it is characterized in that:
The relative dual-side of described furred ceiling stone material (1) has groove (1.1), and furred ceiling stone material (1) upper surface is bonded with notch stiffener (3) along the dual-side of fluting;
Described suspension member is U shape suspension member (2), U shape suspension member between two opening blocks the relative dual-side of furred ceiling stone material (1) relatively, length and furred ceiling stone material (1) length of side of U shape suspension member (2) adapt, respectively there is a slotted hole (2.1) parallel with suspension member length direction at the two ends, top of U shape suspension member (2), U shape suspension member (2) be narrower than top below, following level is inserted in the groove (1.1) of furred ceiling stone material (1);
The upper trough rim of described groove (1.1) is shorter than lower trough rim, is mutually spliced, and form the gap through U shape suspension member (2) between adjacent two pieces of furred ceiling stone materials (1) by the lower trough rim of groove (1.1) between the upper trough rim of groove (1.1).
2. furred ceiling stone material dry suspending structure according to claim 1, is characterized in that: described furred ceiling stone material (1) has groove (1.1) in long limit, both sides relatively.
3. furred ceiling stone material dry suspending structure according to claim 1, is characterized in that: be filled with the AB glue fixing with U shape suspension member (2) and cloud stone glue in the groove (1.1) of described furred ceiling stone material (1).
4. furred ceiling stone material dry suspending structure according to claim 1, is characterized in that: described U shape suspension member (2) is by corrosion resistant plate bending forming, or customization aluminium alloys profiled member.
5. a construction method for the furred ceiling stone material dry suspending structure as described in Claims 1 to 4 any one, is characterized in that: the construction sequence that described furred ceiling stone material dry suspending is configured in (4) place at the bottom of beam is as follows:
Step one, at the bottom of beam, (4) place is according to the size typesetting unwrapping wire of furred ceiling stone material (1), and the beam sides fixed corner code (5) in the frame bar left and right sides, corner brace accomplishes fluently bolt hole in advance, and hole location is corresponding with the slotted hole (2.1) on U shape suspension member;
Step 2, is fixed first U type suspension member (2) by bolt (6) and corner brace (5), then furred ceiling stone material (1) side and the grafting of first U type suspension member (2) is fixed;
Step 3, fixes another root U type suspension member (2) with another side grafting of furred ceiling stone material (1), then is fixed by bolt (6) and corner brace (5) by this U type suspension member (2);
Step 4, repeatedly verifies the position of the furred ceiling stone material (1) of installation, adjusts deviation in time;
Step 5, repeats above-mentioned steps two to four, and the furred ceiling stone material completing beam bottom is installed.
6. a construction method for the furred ceiling stone material dry suspending structure as described in Claims 1 to 4 any one, is characterized in that:
The construction sequence that described furred ceiling stone material dry suspending is configured in top board (7) place is as follows:
Step one, at the upper size typesetting unwrapping wire according to furred ceiling stone material (1) of top board (7);
Step 2, corresponding suspension member slotted hole position (2.1) determines the position to be fixed of cross bar (8), calculates montant (9) size and way;
Step 3, arranges montant (9) according to roof conditions, is fixed in montant top and top board (7), is fixedly secured by cross bar (8) on montant (9);
Step 4, by temporary fixed in the groove of U type suspension member (2) insertion furred ceiling stone material (1), is fixed the U type suspension member (2) at least one piece of furred ceiling stone material (1) through slotted hole (2.1) and cross bar (8) by bolt (6);
Step 5, repeatedly verifies the position of the furred ceiling stone material (1) of installation, adjusts deviation in time;
Step 6, repeats above-mentioned steps four to five, and the furred ceiling stone material completing top board place is installed.
CN201310336223.0A 2013-08-05 2013-08-05 Suspended ceiling stone dry-hanging structure and construction method thereof Expired - Fee Related CN103388372B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310336223.0A CN103388372B (en) 2013-08-05 2013-08-05 Suspended ceiling stone dry-hanging structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310336223.0A CN103388372B (en) 2013-08-05 2013-08-05 Suspended ceiling stone dry-hanging structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN103388372A CN103388372A (en) 2013-11-13
CN103388372B true CN103388372B (en) 2015-05-06

Family

ID=49532785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310336223.0A Expired - Fee Related CN103388372B (en) 2013-08-05 2013-08-05 Suspended ceiling stone dry-hanging structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN103388372B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105649253A (en) * 2015-12-07 2016-06-08 浙江宝兰电气有限公司 Integrated ceiling structure
CN105952051B (en) * 2016-06-13 2018-09-04 浙江宝兰电气有限公司 A kind of indoor suspended ceiling structure
CN109129952B (en) * 2018-09-07 2020-06-30 江苏晶天建设工程有限公司 Building exterior wall decorative material dry-hanging stone machining workbench
CN108890903B (en) * 2018-09-07 2020-05-15 浙江绿城建筑工程管理有限公司 Building decoration is with hanging stone material processing machine people futilely

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2702795B2 (en) * 1989-11-15 1998-01-26 松下電工株式会社 Ceiling material mounting structure
CN2504339Y (en) * 2001-09-25 2002-08-07 中山市沙溪镇乐美装饰材料厂 Hanging splicing ceiling and hanging skeleton and groove shape skeleton
WO2008125164A1 (en) * 2007-04-13 2008-10-23 A. Raymond Et Cie Clip for fastening to a threaded rod for supporting a ceiling covering
CN201785921U (en) * 2010-08-06 2011-04-06 上海克拉美空调有限公司 Strip-shaped metallic ceiling with longitude and latitude fixing structure
CN202899393U (en) * 2012-11-21 2013-04-24 苏州苏明装饰股份有限公司 Unit assembly type suspended ceiling connection structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2702795B2 (en) * 1989-11-15 1998-01-26 松下電工株式会社 Ceiling material mounting structure
CN2504339Y (en) * 2001-09-25 2002-08-07 中山市沙溪镇乐美装饰材料厂 Hanging splicing ceiling and hanging skeleton and groove shape skeleton
WO2008125164A1 (en) * 2007-04-13 2008-10-23 A. Raymond Et Cie Clip for fastening to a threaded rod for supporting a ceiling covering
CN201785921U (en) * 2010-08-06 2011-04-06 上海克拉美空调有限公司 Strip-shaped metallic ceiling with longitude and latitude fixing structure
CN202899393U (en) * 2012-11-21 2013-04-24 苏州苏明装饰股份有限公司 Unit assembly type suspended ceiling connection structure

Also Published As

Publication number Publication date
CN103388372A (en) 2013-11-13

Similar Documents

Publication Publication Date Title
CN103388372B (en) Suspended ceiling stone dry-hanging structure and construction method thereof
CA2661360A1 (en) Suspended ceiling cloud with flexible panel
KR100930886B1 (en) Mounting structure of decoration panel for revetment-block
CN203839863U (en) Groove type large-span straight-through cable tray
KR101201610B1 (en) Mounting structure of Decoration panel Block By T-tape connecter
CN202945726U (en) Adjustable edge strip accommodation installation structure for indoor ceiling wall surface
CN102900193A (en) Cellular board ceiling system
CN213868695U (en) Wallboard fastener
CN201877744U (en) Practical and novel multifunctional right triangular wire slot
CN211114329U (en) Concatenation formula furred ceiling
CN203569769U (en) Novel suspended ceiling unit
CN203939206U (en) Heat insulation and decoration integrated board
CN203475691U (en) Convex type cladding light steel keel
CN205136833U (en) Cable fixing clip of quick installation
CN202227557U (en) Keel and cellular board suspended ceiling system constructed by same
CN205476001U (en) Prefabricated insulation block that easily installs
CN204728604U (en) Integral bathroom wallboard
CN204238406U (en) A kind of novel building furred ceiling
CN204356944U (en) Metallic partition agent structure
CN204691157U (en) A kind of stone material dry suspending connector
CN102287025B (en) Integrated ceiling structure
CN210713591U (en) Environment-friendly brick capable of dissipating heat
CN202244412U (en) Novel fastener on packaging box
CN209492480U (en) A kind of trim panel for car floor
CN211172656U (en) One-step formed light steel keel for lamp groove

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: 100101, Beijing, Chaoyang District Hui Yi Bei Yi Park, No. 28 Yat Yuen business building

Applicant after: BEIJING CONSTRUCTION ENGINEERING DECORATION CO., LTD.

Address before: 100101, Beijing, Chaoyang District Hui Yi Bei Yi Park, No. 28 Yat Yuen business building

Applicant before: Beijing Building Engineering Decoration Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: BEIJING BUILDING ENGINEERING DECORATION CO., LTD. TO: BEIJING CONSTRUCTION ENGINEERING DECORATION GROUP CO. LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150506

Termination date: 20190805

CF01 Termination of patent right due to non-payment of annual fee