CN103373639B - Method for preparing cross-wound bobbin and station for implementing method - Google Patents

Method for preparing cross-wound bobbin and station for implementing method Download PDF

Info

Publication number
CN103373639B
CN103373639B CN201310126383.2A CN201310126383A CN103373639B CN 103373639 B CN103373639 B CN 103373639B CN 201310126383 A CN201310126383 A CN 201310126383A CN 103373639 B CN103373639 B CN 103373639B
Authority
CN
China
Prior art keywords
bobbin
winding
yarn
cross
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310126383.2A
Other languages
Chinese (zh)
Other versions
CN103373639A (en
Inventor
克劳斯·坎普豪森
德特勒夫·吕克尔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Saurer Spinning Solutions GmbH and Co KG
Original Assignee
Saurer Germany GmbH and Co KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Saurer Germany GmbH and Co KG filed Critical Saurer Germany GmbH and Co KG
Publication of CN103373639A publication Critical patent/CN103373639A/en
Application granted granted Critical
Publication of CN103373639B publication Critical patent/CN103373639B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H54/00Winding, coiling, or depositing filamentary material
    • B65H54/02Winding and traversing material on to reels, bobbins, tubes, or like package cores or formers
    • B65H54/06Winding and traversing material on to reels, bobbins, tubes, or like package cores or formers for making cross-wound packages
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H55/00Wound packages of filamentary material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H61/00Applications of devices for metering predetermined lengths of running material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H63/00Warning or safety devices, e.g. automatic fault detectors, stop-motions ; Quality control of the package
    • B65H63/08Warning or safety devices, e.g. automatic fault detectors, stop-motions ; Quality control of the package responsive to delivery of a measured length of material, completion of winding of a package, or filling of a receptacle
    • B65H63/082Warning or safety devices, e.g. automatic fault detectors, stop-motions ; Quality control of the package responsive to delivery of a measured length of material, completion of winding of a package, or filling of a receptacle responsive to a predetermined size or diameter of the package
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H67/00Replacing or removing cores, receptacles, or completed packages at paying-out, winding, or depositing stations
    • B65H67/08Automatic end-finding and material-interconnecting arrangements
    • B65H67/081Automatic end-finding and material-interconnecting arrangements acting after interruption of the winding process, e.g. yarn breakage, yarn cut or package replacement
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65HHANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
    • B65H2701/00Handled material; Storage means
    • B65H2701/30Handled filamentary material
    • B65H2701/31Textiles threads or artificial strands of filaments

Landscapes

  • Engineering & Computer Science (AREA)
  • Textile Engineering (AREA)
  • Quality & Reliability (AREA)
  • Filamentary Materials, Packages, And Safety Devices Therefor (AREA)

Abstract

The invention relates to a method for preparing a cross-wound bobbin. According to the invention, before winding of the cross-wound bobbin with a plurality of winding layers begins, data of winding layers of the cross-wound bobbin to be prepared is provided for the central control unit or station computer, a round bobbinmagazine is equipped with different yarn material supply bobbins for preparing winding layers, the winding of the first winding layer is started by a station computer, the yarn length on the first winding layer is monitored, when the preset yarn length is achieved, winding is stopped, a first supply bobbin is switched to a second supply bobbin with the second winding layer, and the process is repeated until the cross-wound bobbin is completed by a plurality of winding layers with accurate preset yarn lengths.

Description

The method and the station for performing the method for manufacture cross winding bobbin
Technical field
The present invention relates to manufacture the method and the station for performing the method for cross winding bobbin.
Background technology
In textile industry, especially in outer collar domain, each colored loom is every year through multiple type selecting stages (Kollektionsphase), must the very short Jing of warping especially for the perparation of specimen fabric on loom in the stage Yarn.In connection with this, generally must warping there was only several meters of long warp thread.Subsequently, weave on looms and make so-called short warp thread, with Thus the dress material fragment of sample fabric or some shapings is made.
Such short warp thread is manufactured so far for only two kinds possible modes of colored loom.The first possibility side Formula is the short piece goods of warping on sectional warper.For this purpose, it is necessary to first wind the little bobbin of hundreds of different colours, they Subsequently must be inserted into hard on a warping creel.The yarn of little bobbin is subsequently drawn into warping machine and is short by warping Warp thread.Subsequently, all bobbins must be removed from bobbin cradle again, can subsequently repeats time-consuming bobbin and insert process again, to make Make new piece goods.That is, the short piece goods warping on sectional warper is very time-consuming, and it is small that this has begun to manufacture Bobbin.Second possible mode for manufacturing short piece goods is the special short warp thread weaving loom of investment.Such short warp thread weaving loom Although only needing to relatively little of feeding bobbin, its not only costly, and colour to be weaved cotton cloth also require that in engineer's workshop and occupies big Amount place.Other of such short warp thread weaving loom have the disadvantage it can number of colors used at the same time and its relatively small warp thread Speed aspect is significantly restrained.
Also it is aware of in textile industry, such as in loom preparation, when observing exactly as far as possible cross winding is wound into During the predetermined length of yarn of the feeding bobbin of bobbin, can always realize that main cost is reduced.This more particularly to when intersect volume It is inserted into jointly on a bobbin cradle, is extracted around bobbin and during by warping or lease making.The yarn of these cross winding bobbins is long Degree deviation is bigger, and the remaining yarn amount stayed on cross winding bobbin is also bigger, and this especially causes by showing in high price thread material Intolerable loss or cause necessary bothersome time-consumingly rewinding around remaining yarn that work rejection number is brought.
In order to be able to observe the length of yarn that be wound into cross winding bobbin exactly as far as possible, it has been proposed that various differences Method or apparatus.
In the A1 of DE 101 18 659, for example, a kind of station of the textile machine of manufacture cross winding bobbin is described, It is equipped with the mechanism that the length of yarn for moving through Yarn senser is determined for high accuracy and for the continuous yarn that adds up The analytical equipment of the continuous length of yarn of length.
Additionally, the station has the mechanism for determining the length of yarn being removed in the range of yarn engaging process, with And with analytical equipment, it is set up for from the length of yarn that the removing is deducted in the yarn total length of Yarn senser. For determining that the mechanism of moving yarn length possesses contactless formula measurement head in high precision, it is equipped with two in moving yarn The direction of motion on before and after arrangement measurement point and the transition time correlator for processing tested measured value.
The content of the invention
In view of the station of the above-mentioned type, task of the present invention is to improve station, and it allows the intersection volume for making such composition Around bobbin, i.e. relatively short piece goods subsequently can be cost-effectively manufactured on loom by means of these cross winding bobbins.
The task will be completed by the method according to the invention or station.
In the methods of the invention, before the winding process in the cross winding bobbin with multiple winding layers starts, to certainly The central control unit of dynamic cross-winding bobbin winder or station computer provide the winding layer of cross winding bobbin to be manufactured Data, and to circular bobbin magazine be equipped with different yarns material feeding bobbin to make winding layer, the inventive method especially has Have the advantage that, can be by plain mode cross winding bobbin of the manufacture with multiple winding layers, the yarn material of these winding layers Material has exactly respectively predetermined length.That is, it is possible to successfully manufacture cross winding bobbin, its have can be predetermined it is certain Winding layer combination, and waste product is minimum because now occurring, and it is highly suitable for manufacture short warp thread.In the inventive method In, winding and monitoring that the first winding layer is preferably started by station computer fall the length of yarn of the first winding layer. When the predetermined length of yarn of the first winding layer is reached, stop the winding process and cut by startup of coming in before circular bobbin magazine Change to the feeding bobbin with the second winding layer thread material.Above-mentioned process is repeated, until completing desired intersection Winding bobbin, that is, until producing a cross winding bobbin, it has the multiple different winding layers of predetermined quantity, it Respectively have can be precisely predetermined length of yarn.
The station has station computer, coiler device, yarn length measurement mechanism in order to perform the inventive method With the circular bobbin magazine equipped with the feeding bobbin with different yarns material.
These components are functionally associated with each other, so as to change by the accurate feeding bobbin for starting on the station To manufacture the cross winding bobbin with least two different winding layers, wherein it is possible to accurately adjust each winding layer respectively The length of thread material.Multiple cross winding bobbins can be smoothly manufactured on such station, they are in its thread material Length situation aspect is optimised respectively.That is, the length dimension of the thread material of each winding layer can be according to subsequently knitting When certain piece goods is weaved on machine it is required as be precisely adjusted.Therefore, by using such cross winding bobbin, not only Can as far as possible prevent remaining yarn amount occur when piece goods is weaved, and can be realized so on " routine " loom by plain mode Piece goods low cost manufacture.
Specify in advantageous embodiment, the thread material of each winding layer of a cross winding bobbin is at least at it Color aspect is different.Manufacture cross winding bobbin textile machine many stations on manufacture cross winding bobbin this When as needed always have similar winding layer, that is, with same color and its thread material always accurately have phase With the winding layer of length.
The yarn length measurement mechanism possesses contactless formula measurement head and with for processing the measured value for measuring Transition time correlator, the contactless formula measurement head include two in the direction of motion of moving yarn before and after arrange Measurement point.
Using such yarn length measurement mechanism, the very high accuracy when yarn speed is measured not only can be realized, and And especially can be achieved on the length of yarn of moving yarn and accurately determine very.
Additionally, the station computer is configured such in hardware and/or software aspects, i.e. reliable to prevent at the wrong moment The startup of the driving means of circular bobbin magazine.
That is, if in example in the winding process of a winding layer of a color sequence bobbin at a station Such as it is attributed to yarn breakage or yarn yarn under working loss occurs when clearing up the winding termination of cut-out, then station computer reliably prevention In order to the circular bobbin magazine that feeding bobbin is changed advances.Ensure that feeding bobbin is changed always only in cross winding in this way The thread material of each winding layer of bobbin just occurs when accurately having reached its predetermined length.
If there is yarn under working loss in the winding process of a winding layer on a station, but the winding layer of correlation Also there is no its predetermined length, then the station is switched to red light at once.That is, the manual intervention of operator is demonstrated the need for, The operator that this means the automatic cross-winding bobbin winder must search for, be received in and be located in as before unwinding position Yarn under working on correct feeding bobbin is simultaneously ready for subsequent yarn engagement.
In addition, it further provides that in advantageous embodiment, the thread material of each winding layer of the cross winding bobbin is long Degree may depend on subsequently will be come with the desired structure of the woven each piece goods (Einzelmetrage) of the winding layer of cross winding bobbin It is precisely predetermined.
The accurate length of yarn of the independent winding layer of cross winding bobbin is now advantageously or can respectively by can borrow It is precisely predetermined that it realizes that the initialized operating mechanism of station area of computer aided comes, or can respectively by manufacturing intersected coiled bobbin The central control unit of the textile machine of son is adjusting.In both cases, the length of yarn of each winding layer can be smooth Be matched with the present situation and also dependent on needing relatively simply changing.
Using the station of the textile machine of the manufacture cross winding bobbin of the present invention, totally can make in a relatively simple manner Cross winding bobbin is made, it is for example constituted in so-called color sequence bobbin form, it declines in the yarn of variant winding layer Material has respectively length of yarn that can be precisely predetermined.
Description of the drawings
Other details of the present invention can be obtained from below with reference to embodiment shown in the drawings, wherein:
Fig. 1 show in a schematic allows manufacture cross winding bobbin of the present invention, manufacture cross winding bobbin weaving The first embodiment of the station of machinery,
Fig. 2 shows can realize cross winding bobbin manufacture of the present invention, manufacture cross winding bobbin textile machine Station second embodiment, and
Fig. 3 is the perspective view of the cross winding bobbin of the present invention with multiple winding layers.
Specific embodiment
The textile machine of manufacture cross winding bobbin and the especially various different embodiment party of automatic cross-winding bobbin winder Formula is known.Such textile machine has multiple identicals, side-by-side order generally between its end support (not shown) The station 2 of arrangement, so-called winder station.
On these stations 2, as it is known and thus do not describe in detail, for example feeding bobbin 3 and be usually in ring spinner Made by upper, the less quill of thread material by rewinding into large package cross winding bobbin.Cross winding bobbin 6 has been manufactured at it Into after for example by the way that the intersected coiled bobbin along machine length can be transferred to along the cross winding bobbin replacing unit of the movement of station 2 Sub- conveyer device is simultaneously transported to therefrom bobbin depot etc. located at machine side.
As described in combining first embodiment in FIG, the station 2 of this automatic cross-winding bobbin winder can There is respectively the circular bobbin magazine 1 of operation height can controlling by regulation, located at operator.According to predetermined in circular bobbin magazine 1 The a large amount of different feeding bobbins 3 of arrangement mode placement, are in the embodiment in accordance with fig. 1 quills, and they are at least in its yarn material The color aspect of material is different from each other.
In winding process, these feeding bobbins 3 can by the corresponding control device of respective circular bobbin magazine 1 be forwarded into Unwinding position 4, yarn is extracted from quill and is wound in the case where being monitored to moving yarn 5 on the unwinding position To cross winding bobbin.That is, the feeding bobbin 3 of such as different colours is wound to a cross winding bobbin 6, its feature It is that it has multiple winding layers (19a, 19b, 19c, 19d...), the thread material of these winding layers is general at least in color side Face is different from each other and has precisely predetermined length of yarn respectively.
In order to be able to perform operation required during rewinding by regulation, it is known that station 2 there are respectively various yarns Or bobbin is manipulated and controlling organization.
As shown in figure 1, the yarn extracted out from the feeding bobbin 3 being positioned in winding process on the unwinding position 4 of station 2 Line 5 first pass around in it is moved to the distance of cross winding bobbin 6 of the rotatable support on bobbin cradle 7 yarn guide 8, can be by Yarn tensioner 9, yarn clearer 10, yarn shut-off mechanism 11 and the Yarn senser equipped with measurement head 12 that regulation is adjusted.Yarn Line 5 is subsequently wound in coiler device 13 (it especially has the bobbin cradle 7 and such as thread guide drum 15 of rotatable support) To the cylinder that the U along clockwise direction of the cross winding bobbin 6 in so-called color sequence bobbin form under finished product state is rotated On pipe 14.The friction-driven cross winding bobbin 6 of thread guide drum 15 and while also make to fall the yarn 5 on cross winding bobbin 6 Traversing.
Replace thread guide drum, naturally it is also possible to which, using simple friction roller, but here, the yarn put that falls subsequently must lead to Cross that single mechanism is for example referred to by guide or the yarn transversing mechanism that is similar to is by traversing.
As described above, cross winding bobbin 6 may be rotatably mounted in bobbin cradle 7, the bobbin cradle can by its rotary shaft 16 Be bearing in finite motion on the housing 17 of station 2 and with bobbin diameter increase and rotation upwards.In addition, such work Position 2 possesses respectively station computer 18, and it is especially connected to above-mentioned manipulating yarn and control machine by corresponding control circuit Structure such as yarn tensioner 9, yarn clearer 10, yarn shut-off mechanism 11 and the Yarn senser equipped with measurement head 12, and pass through Bus 29 is connected to the central control unit 30 of automatic cross-winding bobbin winder.
Station computer 18 can also have the interface for operating mechanism 31, so that operator can be to corresponding station 2 Station computer 18 performs auxiliary initialization (Zusatzinitialisierung).The auxiliary initialization is now related to will be Cross winding bobbin 6 made by relative stations 2 is precisely formed, especially the order and winding layer yarn material of different winding layers The accurate length of yarn of material.
Station computer 18 also possesses as known the analytical equipment of the measured value for measurement head 12, and it sets up use In accumulative through the length of yarn of measurement head 12.Such length of yarn with measurement head 12 and transition time correlator is surveyed Measuring mechanism is for example by disclosed in DE4225842A1 and there has a relatively unambiguous description.
In addition, station computer 18 so sets in hardware and/or software aspects, i.e. it is long that it can store predetermined yarn Degree and continuously predetermined length of yarn is compared with the length of yarn on cross winding bobbin 6 is heretofore fallen.
In addition also as shown in figure 1, each station 2 has respectively suction nozzle 21 and clamp yarn cop 27, wherein, the suction nozzle can be applied With negative pressure and supporting is rotated, and for operating so-called upper yarn;The clamp yarn cop be also rotatable support and And negative pressure can be subjected to, and for operating so-called yarn under working.By suction nozzle 21 or clamp yarn cop 27, can break because of yarn Split or controlled yarn tension cleaning is cut off and has no progeny in the winding of appearance and transfer to yarn jointing machine by the loose thread of upper yarn and yarn under working Structure 26, the yarn engaging mechanism for the normal yarn distance of yarn 5 slightly arrange by recession.
Fig. 2 illustrates the second embodiment of the station 2 of the textile machine of manufacture cross winding bobbin.In this station 2, replace It is on operation height and with the circular bobbin magazine 1 of the accommodating case for quill, arrange relatively large installed in bottom section Circular bobbin magazine 1.Relatively large circular bobbin magazine 1 can with or with for completely rolling up the accommodating case of whole cross winding bobbin, or Accommodating case with the cross winding bobbin for half volume.That is, in the accommodating case of the big circular bobbin magazine 1, for example can be with Or storage six is all the cross winding bobbin of full volume, or 12 accommodating cases are for example provided with for half cross winding rolled up Bobbin.Feeding bobbin 3 in cross winding bobbin or the cross winding bobbin form of winds portions is now such as from the enforcement of Fig. 1 For example have any different in terms of the color of its thread material as disclosed in example.
Fig. 3 illustrate in perspective view the present invention cross winding bobbin 6, its have substantial amounts of different winding layer 19a, 19b, 19c、19d....That is, winding layer 19a, 19b, 19c, 19d... different from each other are overlapped and are wound up on a bobbin 14, Wherein, some winding layer 19a, 19b, 19c, 19d... are different for example, at least in terms of the color of its thread material.In addition, Some winding layer 19a, 19b, 19c, 19d... have respectively accurately predetermined length of yarn.
In this embodiment, winding layer 19a is for example made up of red yarn material, and its length of yarn is 2000 meters.Winding Layer 19b has green thread material, and its length of yarn is, for example, 1500 meters.Winding layer 19c is by the Huang that length of yarn is 3000 meters Dyed yarn wire material is constituted, and winding layer 19d has black yarn material, and its length of yarn is such as 1800 meters.
This cross winding bobbin 6 of color sequence bobbin (Farbsequenzspule) is commonly referred to as in sector coil most Can have winding layer 19a, 19b, 19c, 19d... of up to eight different colours well.
The manufacture method of cross winding bobbin of the invention:
Before the winding process of the cross winding bobbin 6 with multiple winding layer 19a, 19b, 19c, 19d..., to certainly The station computer 18 of the central control unit 30 of dynamic cross-winding bobbin winder or relative stations 2 provide winding layer 19a, 19b, The data of 19c, 19d....In addition, the circular bobbin magazine 1 of station 2 must be equipped with suitable feeding bobbin 3.That is, for example borrow The input mechanism helped in the central control unit 30 of automatic cross-winding bobbin winder, first will be by the desired intersection of regulation manufacture Data required for winding bobbin 6 send the station computer 18 of station 2 to and respectively according to intersected coiled bobbin to be manufactured Son 6 winding layer 19a~19d structure and arrange to the circular bobbin magazine 1 of station 2 be equipped with different feeding bobbins 3,3 ', 3”...。
In the present embodiment, circular bobbin magazine 1 for example accordingly equipped with black yarn material two first is fed for cylinder Son 3, equipped with yellow thread material two the second feeding bobbins 3 ', equipped with green thread material two the Three feeding bobbins 3 " and equipped with red yarn material two the 4th feeding bobbins 3 " '.
That is, when cross winding bobbin 6 of the present invention is wound, first by be furnished with black yarn material two first Feeding bobbin 3 carrys out wound web layer 19d, and the length of yarn put when falling has reached the setting for being respectively directed to related winding layer When (being in the case 1800 meters), station computer 18 is used to terminate the winding process of related winding layer 19d.
It is respectively necessary for how many feeding bobbins to wind certain winding layer depending on different factors, such as depending on each winding The length of yarn that should have of layer and the amount of thread each needed depending on the such winding layer of winding.That is, intersect volume Feeding bobbin 3,3 ', 3 required for each winding layer around bobbin 6 ", 3 " ' ... quantity depend on each winding layer structure, And can significantly fluctuate.
After the winding process of winding layer 19d terminates, feeding bobbin switching is started by station computer 18, that is, The first feeding bobbin 3 with black yarn material for being positioned at unwinding position 4 is discharged and the so advance of circular bobbin magazine 1, So that the second feeding bobbin 3 with yellow thread material is transferred to unwinding position 4.Subsequently, by clamp yarn cop 27 will only by Yellow thread material constitute yarn under working be delivered to yarn engaging mechanism 26 and there by air-flow with by suction nozzle 21 from The upper yarn fetched in cross winding bobbin is engaged, and yarn is the black yarn material composition of thus front processing on this.
That is, make the oral area 20 that can rotate the suction nozzle 21 installed around rotary shaft 22 turn to the week of cross winding bobbin 6 In the region of face.In addition, the valve in negative pressure line is controlled in the sense that opening by station computer 18, here is clear Chu Qijian is without illustrating the valve.Because suction nozzle 21 passes through negative pressure and is connected along machine length suction channel as common Lead to and be connected with the central negative pressure source of automatic cross-winding bobbin winder by the suction channel, so suction nozzle 21 is opened in valve In the case of be connected with the negative pressure source all the time in terms of air pressure.That is, suction nozzle 21 is born negative pressure and is existed in its oral area 20 Suction airstream.
While pendulum on suction nozzle 21, cross winding bobbin 6 is set slowly to rotate on unwinding yarn direction.During here is rotated Cross winding bobbin 6 is set to turn to such angle position, in the angle position, the upper yarn loose thread on package body side face The zone of action of the oral area 20 of suction nozzle 21 is reached, is inhaled in suction nozzle 21 and is subsequently sent to yarn engaging mechanism 26 from suction nozzle. When the loose thread of upper yarn reaches the Yarn senser 23 in suction nozzle 21 when suction nozzle 21 is inhaled into, also simply from intersection volume The length of yarn of regulation is extracted out around bobbin 6 and sucked suction nozzle 21.Measurement length of yarn, wherein, and from cross winding bobbin 6 The detection of the length of yarn of extraction is carried out in known manner according to the mechanism in the region of thread guide drum 15, that is, The rotation of thread guide drum 15 is measured by magnet pulley 24 and angular transducer 25.
Because distance of the Yarn senser 23 away from the oral area 20 of suction nozzle 21 and in the rotational motion of suction nozzle 21 by the institute of oral area 20 In other words corresponding length of yarn is known and is stored in station computer 18 stroke passed by, so from cross winding The length of the loose thread that bobbin 6 is extracted and is inhaled into by suction nozzle 21 can be precisely determined and from through yarn length measurement machine It is subtracted in the accumulative length of yarn of the measurement head 12 of structure 32.
As described above, almost simultaneously also controlling clamp yarn cop 27 with suction nozzle 21, the clamp yarn cop is manipulated and the second feeding bobbin 3 ' connected loose threads are so-called yarn under working.That is, clamp yarn cop 27 receives lower yarn with its suction inlet portion 28 for being also subjected to negative pressure Line is simultaneously transported to the loose thread engaging mechanism in the form of vapour-pressure type yarn engaging mechanism 26 by rotational motion.Clamp yarn cop 27 can The swivel 33 for rotating around it now also is constituted with being connected to the joint form of pneumatic circuit, the pneumatic circuit pass to again from The suction channel along machine length of dynamic cross-winding bobbin winder.
After yarn connection is successfully completed, proceed the winding process of cross winding bobbin 6, that is, start winding Second winding layer 19c.Now, the yarn for being also again started up the yarn 5 of measurement head 12 through yarn length measurement mechanism 32 is long The determination of degree.If the length of yarn of thread material reaches the predetermined value of the related winding layer 19c for cross winding bobbin 6, Then terminate the winding process of the related winding layer 19c.
That is, in the case, when the length of yarn put when falling accurately has reached predetermined value (here is 3000 meters), Terminate the winding process of yellow the second winding layer 19c of cross winding bobbin 6 by station computer 18.In yellow volume Two After the completion of winding layer 19c, the feeding bobbin with process as above is started again and is changed.That is, discharge first in unwinding Second feeding bobbin 3 ' of position 4 and with the 3rd feeding bobbin 3 " replace.
Repeat said process, until cross winding bobbin 6 have its all of different winding layer 19a, 19b, 19c, 19d..., wherein, these winding layers always accurately have the predetermined length of yarn of thread material.
Made by cross winding bobbin 6 subsequently for example by moving more along the station 2 of automatic cross-winding bobbin winder The bobbin that group of changing planes transfers to the cross winding bobbin conveying mechanism along machine length and is sent to located at machine side is loaded and unloaded Stand.After cross winding bobbin made by discharge 6, new winding process is started in relative stations, wherein, typically must first to circle Shape bobbin magazine 1 is refilled by required feeding bobbin 3,3 ', 3 " ....
When appearance volume in the winding process in one of winding layer 19a, 19b, 19c, 19d... of cross winding bobbin 6 Around interrupting (such as because there is yarn breakage or because yarn clearer 10 detects the yarn flaws that are impermissible for and subsequent start-up Yarn cuts off) and subsequently occur during such winding interrupts when yarn under working loses, at once by station computer Related station 2 is switched to red light by 18.That is, clearly indicate that to operator and need manual intervention in related station 2.
By such way, the mistake in relative stations can be reliably prevented to perform feeding bobbin more with relatively easy Change, now accidentally shift to the feeding bobbin of mistake.That is, although for example reliably the winding layer now to be wound will be prevented also It is to need black yarn material but change a feeding bobbin equipped with yellow thread material hastily.
The present invention should not be limited to combine the embodiment described in accompanying drawing.Conversely, driving with regard to the device part of station, Control and the relatedness of in place and manipulating yarn and controlling organization are supported and installed, as long as here is not illustrated, just completely may be used With using other embodiment by disclosed in prior art, such as it is described from cited published document and wherein known to show There is the embodiment disclosed in the wherein described known disclosed in technology.

Claims (10)

1. it is a kind of that method of the cross winding bobbin to produce short warp thread is manufactured on the station of automatic cross-winding bobbin winder, its In, the station equipped with circular bobbin magazine, station computer, coiler device and yarn length measurement mechanism, survey by the length of yarn Measuring mechanism makes it possible to wind such cross winding bobbin, and the thread material of the cross winding bobbin correspondingly has by rule Fixed predetermined length of yarn,
It is characterized in that,
Before the winding process of the cross winding bobbin (6) of multiple winding layers (19a, 19b, 19c, 19d...) starts, to this Automatically the central control unit (30) or station computer (18) of cross-winding bobbin winder provide treat made by intersected coiled bobbin The data of the winding layer (19a, 19b, 19c, 19d...) of sub (6), and the circular bobbin magazine (1) is equipped with different yarns material Feeding bobbin (3,3 ', 3 " ...) for making the winding layer (19a, 19b, 19c, 19d...),
Start the winding of the first winding layer (19d) by the station computer (18) and the first winding layer is fallen in monitoring (19d) length of yarn,
When the predetermined length of yarn of first winding layer (19d) is reached, stop winding process and pass through before circular bobbin magazine (1) Come in start the second feeding bobbin that the first feeding bobbin (3) is switched to the thread material with the second winding layer (19c) (3 '), and
The above-mentioned process of repetition, until completing the cross winding bobbin (6), that is, form such cross winding bobbin (6), the cross winding bobbin has multiple winding layers (19a, 19b, 19c, 19d...) different from each other, these winding layers point Length of yarn that Ju You be not precisely predetermined.
2. it is a kind of for perform according to claim 1 method manufacture cross winding bobbin textile machine station,
It is characterized in that,
Station computer (18), coiler device (13), yarn length measurement mechanism (32) and equipped with different yarns material The circular bobbin magazine (1) of the feeding bobbin (3) of material is functionally so to be mutually related, i.e. can be borrowed on the station (2) The feeding bobbin for helping accurate startup switches to manufacture such cross winding bobbin (6), and the cross winding bobbin (6) is with extremely Few two winding layers (19a, 19b, 19c, 19d...) different from each other, wherein, each winding layer (19a, 19b, 19c, The length of thread material 19d...) can distinguish accurate adjustment.
3. station according to claim 2, is characterized in that, each winding layer of cross winding bobbin (6) (19a, 19b, 19c, 19d...) thread material be different from each other at least in terms of its color.
4. station according to claim 2, is characterized in that, the yarn length measurement mechanism (32) is with contactless formula Measurement head (12) and transition time correlator, wherein, the measurement head is included in the direction of motion (F) of moving yarn (5) and goes forward Two measurement points for arranging afterwards, and the transition time correlator is used for the measured value that process is measured.
5. station according to claim 2, is characterized in that, the station computer (18) is in hardware and/or software aspects quilt Such setting, i.e. if in the winding of one of winding layer (19a, 19b, 19c, 19d...) of color sequence bobbin (6) There is yarn under working loss when the station (2) is in interruption spinning in journey, then prevent circular bobbin magazine (1) to switch feeding bobbin For the purpose of advance.
6. station according to claim 5, is characterized in that, when yarn under working loses, related station (2) is switched to red Lamp.
7. station according to claim 2, is characterized in that, each winding layer of cross winding bobbin (6) (19a, 19b, 19c, 19d...) the length of thread material can be according to subsequently will be with the corresponding winding layer of the cross winding bobbin (6) (19a, 19b, 19c, 19d...) carrys out the length of woven each piece goods and comes precisely predetermined.
8. station according to claim 7, is characterized in that, be provided with for the operation of auxiliary initialization station computer (18) Mechanism (31), by means of the operating mechanism can make a reservation for exactly respectively the cross winding bobbin (6) each winding layer (19a, 19b, 19c, 19d...) thread material length of yarn.
9. station according to claim 7, is characterized in that, each winding layer of cross winding bobbin (6) (19a, 19b, 19c, 19d...) thread material length of yarn can by the central control unit (30) of automatic cross-winding bobbin winder come It is accurately predetermined respectively.
10. station according to claim 5, is characterized in that, because of yarn breakage or the cut-out of yarn cleaner spinning is interrupted.
CN201310126383.2A 2012-04-13 2013-04-12 Method for preparing cross-wound bobbin and station for implementing method Expired - Fee Related CN103373639B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE102012007467.0 2012-04-13
DE102012007467A DE102012007467A1 (en) 2012-04-13 2012-04-13 Method for producing a cross-wound bobbin

Publications (2)

Publication Number Publication Date
CN103373639A CN103373639A (en) 2013-10-30
CN103373639B true CN103373639B (en) 2017-05-10

Family

ID=49231958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310126383.2A Expired - Fee Related CN103373639B (en) 2012-04-13 2013-04-12 Method for preparing cross-wound bobbin and station for implementing method

Country Status (4)

Country Link
JP (1) JP2013220945A (en)
CN (1) CN103373639B (en)
DE (1) DE102012007467A1 (en)
IT (1) ITMI20130431A1 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5925260B2 (en) 2013-10-24 2016-05-25 株式会社シマノ Gradient calculation device
DE102014011938A1 (en) * 2014-08-12 2016-02-18 Saurer Germany Gmbh & Co. Kg Method and device for avoiding image windings when winding a cross-wound bobbin
CN108529317B (en) * 2018-05-03 2020-11-13 绍兴市德帏纺织科技有限公司 Method for improving winding efficiency of wire harness in spinning process
CN108792784B (en) * 2018-05-03 2020-11-13 嘉兴市鑫锋纺织有限公司 Bobbin winder for spinning
CN111620196B (en) * 2020-06-10 2021-12-07 福建浔兴拉链科技股份有限公司 Constant tensiometer length device of nylon zipper sewing machine
CN115009928A (en) * 2022-06-27 2022-09-06 张家港扬子纺纱有限公司 Yarn production system capable of reducing yarn damage through flexible logistics in winding

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3624904A1 (en) * 1986-07-23 1988-01-28 Schlafhorst & Co W AUTOMATIC CROSS REEL WINDING MACHINE
DE4225842A1 (en) 1992-08-05 1994-02-10 Schlafhorst & Co W Device for measuring the speed of textile threads on a winding device
DE19539762B4 (en) * 1995-10-26 2004-07-15 Saurer Gmbh & Co. Kg Textile machine producing cross-wound bobbins
DE10118659A1 (en) 2001-04-14 2002-10-17 Schlafhorst & Co W Bobbin of a textile machine
JP4408619B2 (en) * 2002-11-11 2010-02-03 東洋紡績株式会社 Opening synthetic fiber
DE102005045789A1 (en) * 2005-09-24 2007-03-29 Saurer Gmbh & Co. Kg Method for operating a workstation of a textile machine producing cross-wound bobbins
DE102007040184A1 (en) * 2007-08-25 2009-02-26 Oerlikon Textile Gmbh & Co. Kg Textile machine comprises a yarn sensor integrated in an electronic unit and an individual control unit to evaluate measuring signals from the sensor and to control actuators at the operating site depending on the measuring signals

Also Published As

Publication number Publication date
CN103373639A (en) 2013-10-30
JP2013220945A (en) 2013-10-28
ITMI20130431A1 (en) 2013-10-14
DE102012007467A1 (en) 2013-10-17

Similar Documents

Publication Publication Date Title
CN103373639B (en) Method for preparing cross-wound bobbin and station for implementing method
JP6080153B2 (en) Spinning machine and method for interrupting the production of yarn in a spinning machine
CN103848273B (en) For the method for accelerating control to bobbin driven roller
WO2011040545A1 (en) Yarn winder
CN105177774A (en) Semi-automatic opening rotor spinning machine
Gandhi Yarn preparation for weaving: winding
CN1188334C (en) Method winding continuous yarn to one working position of spinning hobbin machine cone winding
CN102190211A (en) Spinning-winding apparatus and spinning-in method therein
EP1764333B1 (en) Method and device for spooling a yarn and wound body thus achieved
JPH0274645A (en) Method for feeding weft yarn in weaving carbon fiber cloth
JP7346200B2 (en) Method and apparatus for detecting yarn loops in a working unit of a textile machine producing wound packages
JP2008510671A (en) Method and apparatus for optimizing work parameters at the work site of a textile machine that manufactures a traverse package
CN102249120A (en) Method for manufacturing spinning cops
US10907278B2 (en) Method for automatically piecing a thread at a workstation of a textile machine, and textile machine
CS226715B2 (en) Method of and apparatus for attaining predetermined precise yarn lengths on cross-wound packages
CN105398880A (en) Yarn Storage Device And Yarn Winding Device Equipped With Yarn Storage Device
JP2017517653A (en) Textile machine and method of driving a textile machine
JP2017115290A (en) Yarn splicing device
CN105366425B (en) Yarn take-up device and fiber are mechanical
EP1422179A2 (en) Method and device to prepare a wound package of a succession of different yarns and package obtained with said method and device
US20190360130A1 (en) Core yarn comprising core thread with variant drawing, and fabric that is obtained from this core yarn
CN1643194B (en) Centrifugal spinning device
JPS6013943B2 (en) Spun yarn splicing device
CN103373642B (en) Operation method of winding machine and winding machine thereof
JP3944727B2 (en) Yarn splicing device for different types of yarn

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: SAURER GERMANY GMBH + CO. KG

Free format text: FORMER OWNER: OERLIKON TEXTILE GMBH + CO. KG

Effective date: 20131104

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20131104

Address after: The German city of Remscheid

Applicant after: Saurer Germany GmbH & Co KG

Address before: The German city of Remscheid leiwo Guselu No. 65

Applicant before: Oerlikon Textile GmbH & Co. KG

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170510