CN103324572A - Operating system performance test method and device for power secondary system - Google Patents

Operating system performance test method and device for power secondary system Download PDF

Info

Publication number
CN103324572A
CN103324572A CN2013102705746A CN201310270574A CN103324572A CN 103324572 A CN103324572 A CN 103324572A CN 2013102705746 A CN2013102705746 A CN 2013102705746A CN 201310270574 A CN201310270574 A CN 201310270574A CN 103324572 A CN103324572 A CN 103324572A
Authority
CN
China
Prior art keywords
performance
test
operating system
electric power
power secondary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102705746A
Other languages
Chinese (zh)
Other versions
CN103324572B (en
Inventor
江泽鑫
梁智强
胡朝辉
黄岳峰
梁志宏
刘菲
孙建伟
顾博川
唐升卫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Guangdong Power Grid Co Ltd
Original Assignee
Electric Power Research Institute of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of Guangdong Power Grid Co Ltd filed Critical Electric Power Research Institute of Guangdong Power Grid Co Ltd
Priority to CN201310270574.6A priority Critical patent/CN103324572B/en
Publication of CN103324572A publication Critical patent/CN103324572A/en
Application granted granted Critical
Publication of CN103324572B publication Critical patent/CN103324572B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses an operating system performance test method for a power secondary system. The method includes: a recognizing a performance item to be tested for the operating system of the power secondary system according the information of the performance item selected by a use; acquiring a test script file corresponding to the performance item to be tested from a test script library; and executing the acquired test script file to obtain test data. Test item files corresponding to test performance items of the operating system of the power secondary system are pre-stored in the test script library. In addition, the invention discloses an operating system performance test device for the power secondary system. The test script files can be customized according to the performances of the operating system, so that the comprehensive test can be realized and the testing is not limited to one specific performance. Compared with manual item-by-tem testing, the method and the device have the advantages that automatic testing can be achieved to the maximum extent and efficiency of testing the operating system is improved.

Description

Operating system performance method of testing and the device of electric power secondary system
Technical field
The present invention relates to electric power operation systems technology field, relate in particular to a kind of operating system performance method of testing of electric power secondary system and a kind of operating system performance proving installation of electric power secondary system.
Background technology
Electric power secondary system is to comprise private data network that electric power monitoring system, the power dispctching MIS, power communication and dispatching data network, electric power secondary system use etc.All these security of system stable operations are for ensureing that power network safety operation is most important.
The operation of electric power secondary system needs a basic software and hardware platform, and wherein basic software platform is exactly operating system, particularly the operating system of server version.The operating system of perfect performance, high-performance, high stability and high security has vital role for the normal stable operation of safety that guarantees electric power secondary system.Thereby whether the performance test of operating system is satisfied the power business demand for the performance of decision operation system is necessary and urgent.
Under the present circumstances, mainly there is following problem in the performance test of electric power secondary system operating system: only test for a certain specific targets of operating system; Substantially be to rely on manually to check, waste time and energy, and accuracy is not enough.In addition, the test of operating system performance is not carried out for the power business characteristics, failed according to power business the demand of operating system to be tested targetedly.Thereby under present case, be badly in need of a kind of not only general but also the efficient operating system performance method of testing of electric power secondary system.
Summary of the invention
Based on this, the invention provides a kind of operating system performance method of testing of electric power secondary system and a kind of operating system performance proving installation of electric power secondary system.
A kind of operating system performance method of testing of electric power secondary system may further comprise the steps:
Test performance item according to the user is selected information, identifies the performance item to be tested of electric power secondary system operating system;
From test script library, obtain the test script file corresponding with described performance item to be tested; Wherein, prestore the test script file corresponding with each test performance item of electric power secondary system operating system in the described test script library;
The described test script file that execution is obtained obtains test data.
Compare with general technology, the operating system performance method of testing of electric power secondary system of the present invention is by being pre-stored in the test script file of each test performance item correspondence in the test script library, can test the operating system performance of electric power secondary system quantitatively, thereby provide foundation for the operation of operating system in electric power networks.Because each performance that test script file can be directed to operating system customizes, so the present invention can realize full test, and is not limited to certain specific performance.Than artificial manual test item by item, degree of the present invention can farthest be realized automatic test, thereby has improved the testing efficiency of operating system.In addition, customize because test script file can be directed to the performance of operating system, therefore, test can be carried out for the power business characteristics, can test targetedly the demand of operating system according to power business.The present invention has testing efficiency height and the objective advantage of test result.
A kind of operating system performance proving installation of electric power secondary system comprises identification module, acquisition module and test module;
Described identification module is used for selecting information according to user's test performance item, identifies the performance item to be tested of electric power secondary system operating system;
Described acquisition module is used for obtaining the test script file corresponding with described performance item to be tested from test script library; Wherein, prestore the test script file corresponding with each test performance item of electric power secondary system operating system in the described test script library;
Described test module is used for carrying out the described test script file that obtains, and obtains test data.
Compare with general technology, the operating system performance proving installation of electric power secondary system of the present invention is by being pre-stored in the test script file of each test performance item correspondence in the test script library, can test the operating system performance of electric power secondary system quantitatively, thereby provide foundation for the operation of operating system in electric power networks.Because each performance that test script file can be directed to operating system customizes, so the present invention can realize full test, and is not limited to certain specific performance.Than artificial manual test item by item, degree of the present invention can farthest be realized automatic test, thereby has improved the testing efficiency of operating system.In addition, customize because test script file can be directed to the performance of operating system, therefore, test can be carried out for the power business characteristics, can test targetedly the demand of operating system according to power business.The present invention has testing efficiency height and the objective advantage of test result.
Description of drawings
Fig. 1 is the schematic flow sheet of the operating system performance method of testing of electric power secondary system of the present invention;
Fig. 2 is that embodiment is towards the structural representation of the operating system performance test macro of power business;
Fig. 3 is the structural representation of the operating system performance proving installation of electric power secondary system of the present invention.
Embodiment
For further setting forth the technological means that the present invention takes and the effect that obtains, below in conjunction with accompanying drawing and preferred embodiment, to technical scheme of the present invention, know and complete description.
See also Fig. 1, be the schematic flow sheet of the operating system performance method of testing of electric power secondary system of the present invention.
The operating system performance method of testing of electric power secondary system of the present invention may further comprise the steps:
S101 selects information according to user's test performance item, identifies the performance item to be tested of electric power secondary system operating system;
S102 obtains the test script file corresponding with described performance item to be tested from test script library; Wherein, prestore the test script file corresponding with each test performance item of electric power secondary system operating system in the described test script library;
S103 carries out the described test script file that obtains, and obtains test data.
In step S101, operating system testing performance item comprises following particularly: the aspect performances such as the Dhrystone benchmark test of operating system, Whetstone benchmark test, file copy performance, pipeline throughput performance, process creation performance, shell script execution performance, integer arithmetic performance, floating point arithmetic performance, context performance of handoffs, local communication performance, local communication bandwidth performance and internal memory operation time-delay.
Test performance item according to user's input is selected information, can select.
As one of them embodiment, in the step of the described performance item to be tested that identifies electric power secondary system operating system, described test performance item comprises: the aspect performances such as the Dhrystone benchmark test of operating system, Whetstone benchmark test, file copy performance, pipeline throughput performance, process creation performance, shell script execution performance, integer arithmetic performance, floating point arithmetic performance, context performance of handoffs, local communication performance, local communication bandwidth performance and internal memory operation time-delay.
The test performance item can be according to the actual conditions setting, has both satisfied comprehensively, has also increased dirigibility.
In step S102, from test script library, obtain the test script file corresponding with described performance item to be tested; Wherein, prestore the test script file corresponding with each test performance item of electric power secondary system operating system in the described test script library.
Wherein, test script file corresponding to each test performance item.Wherein, but Dhrystone benchmark test, Whetstone benchmark test, file copy performance, pipeline throughput performance, process creation performance test script called after UB.sh; But shell script execution performance, integer arithmetic performance, floating point arithmetic performance, context performance of handoffs, local communication performance, local communication bandwidth performance and internal memory operation delay test script called after lm.sh.
In step S103, as one of them embodiment, before the step of the described test script file that described execution is obtained, may further comprise the steps:
According to the described test script file that obtains, configuration testing script argument; Wherein, described test script parameter comprises the record path of test data and procedure file.
The configuration testing script argument can guarantee expeditiously execution of test.
As one of them embodiment, the described test script file that described execution is obtained obtains the step of test data, may further comprise the steps:
Main frame in electric power secondary system operating system is carried out described test and appraisal script file, obtains and carries out the test data of returning behind the described test script file.
Main frame in operating system is carried out described test and appraisal script file, can guarantee accuracy and the objectivity of test result.
As one of them embodiment, after the described step of obtaining test data, may further comprise the steps:
Described test data and the preset range obtained are compared;
If described test data surpasses described preset range, then send alarm signal.
Preset range can be set according to practical experience, has guaranteed like this can in time pinpoint the problems and alarm or early warning when operating system breaks down or is unusual.
As one of them embodiment, after the described step of obtaining test data, may further comprise the steps:
Generate the test result file of electric power secondary system operating system according to described test data.
Generate test result file, can keep historical information for the user, as user during to the inquiry test result, only need to consult test result file and get final product.
As a preferred embodiment, can be according to the present invention the operating system performance method of testing of electric power secondary system set up one towards the operating system performance test macro of power business, comprise function scheduler module, test result and procedure file memory module, GUI human-computer interaction interface module, operation capture unit, performance test module and security test module.As shown in Figure 2, be the structural representation of embodiment towards the operating system performance test macro of power business.
The described function scheduler module of the present embodiment, refer to by the operation response capture unit the mouse of GUI human-computer interaction interface module and the operation of keyboard, carry out the module of each operating system testing module, simultaneously its test result and test process file are stored, and testing progress is fed back to GUI human-computer interaction interface module to show.
Described performance test module refers to a series of test scripts for the Test Operating System performance, mainly comprises the various operating system performances of power business needs; Comprise particularly the aspect performances such as Dhrystone benchmark test, Whetstone benchmark test, file copy performance, pipeline throughput performance, process creation performance, shell script execution performance, integer arithmetic performance, floating point arithmetic performance, context performance of handoffs, local communication performance, local communication bandwidth performance and internal memory operation time-delay to operating system.
Described security test module refers to the security for Test Operating System, mainly comprises the various operating system safety protecting abilities of power business needs; The identity that comprises particularly operating system differentiates security performance test, autonomous access control safety performance test, the test of safety label security performance, protection security performance test and operating-system resources utilize the security performance test when forcing access control safety performance test, security audit performance test, data integrity and the test of confidentiality security performance, the test of trusted path security performance, operation.
Described test result and procedure file memory module, finger is used for the information such as the intermediate record of each test script implementation of operating system and final testing result are stored, after being completed, the tester can carry out quantitative comprehensive evaluation to operating system according to these test results and test record.
Described GUI human-computer interaction interface module refers to the friendly human-machine interface of operating system integrated test system, is used for selecting to carry out corresponding test module according to user's mouse, and monitors the aspect such as the complete process situation of current test script.
Described operation capture unit refers to monitor the script of mouse and keyboard operation, and the input according to monitoring mouse and keyboard sends information to the performance scheduling module, thereby carries out each test module.
Running face is after the operating system performance test macro of power business, select " operating system security test " test item from the GUI human-computer interaction interface, when selecting this test item, integrated test system will be carried out a series of test subitems of corresponding performance test item correspondence;
The parameter that configuration operation security of system property testing relates to mainly comprises the parameter that test result and procedure file record path and test subitem relate to;
" test " button of clicking on the GUI human-computer interaction interface is tested;
After all test subitems are completed, complete operation security of system property testing.
Wherein, the operating system security test item comprises following particularly: identity is differentiated when access control safety performance test, security audit performance test, data integrity and the test of confidentiality security performance, the test of trusted path security performance, operation are tested, forced to security performance test, autonomous access control safety performance test, safety label security performance and is protected security performance test and operating-system resources to utilize the security performance test.
Wherein, test script corresponding to each test subitem; But identity is differentiated security performance test script called after IDAuthTest.sh; But autonomous access control safety performance test script called after AACtrolTest.sh; But safety label security performance test script called after SecTagTest.sh; But force access control safety performance test script called after SACTest.sh; But security audit performance test script called after SecAuditTest.sh; But data integrity and confidentiality security performance test script called after DataInteAndSecTest.sh; But trusted path security performance test script called after RelPathTest.sh; But the test of protection security performance and operating-system resources utilize security performance test script called after RunTimeSecAndResourceTest.sh during operation.
Compare with general technology, the operating system performance method of testing of electric power secondary system of the present invention is by being pre-stored in the test script file of each test performance item correspondence in the test script library, can test the operating system performance of electric power secondary system quantitatively, thereby provide foundation for the operation of operating system in electric power networks.Because each performance that test script file can be directed to operating system customizes, so the present invention can realize full test, and is not limited to certain specific performance.Than artificial manual test item by item, degree of the present invention can farthest be realized automatic test, thereby has improved the testing efficiency of operating system.In addition, customize because test script file can be directed to the performance of operating system, therefore, test can be carried out for the power business characteristics, can test targetedly the demand of operating system according to power business.The present invention has testing efficiency height and the objective advantage of test result.
See also Fig. 3, be the structural representation of the operating system performance proving installation of electric power secondary system of the present invention.
The operating system performance proving installation of electric power secondary system of the present invention comprises identification module 301, acquisition module 302 and test module 303;
Described identification module 301 is used for selecting information according to user's test performance item, identifies the performance item to be tested of electric power secondary system operating system;
Described acquisition module 302 is used for obtaining the test script file corresponding with described performance item to be tested from test script library; Wherein, prestore the test script file corresponding with each test performance item of electric power secondary system operating system in the described test script library;
Described test module 303 is used for carrying out the described test script file that obtains, and obtains test data.
As one of them embodiment, described test performance item comprises: the aspect performances such as the Dhrystone benchmark test of operating system, Whetstone benchmark test, file copy performance, pipeline throughput performance, process creation performance, shell script execution performance, integer arithmetic performance, floating point arithmetic performance, context performance of handoffs, local communication performance, local communication bandwidth performance and internal memory operation time-delay.
The test performance item can be according to the actual conditions setting, has both satisfied comprehensively, has also increased dirigibility.
As one of them embodiment, also comprise configuration module;
Described configuration module is used for before the described test script file that execution is obtained, according to the described test script file that obtains, configuration testing script argument; Wherein, described test script parameter comprises the record path of test data and procedure file.
The configuration testing script argument can guarantee expeditiously execution of test.
As one of them embodiment, also comprise alarm modules;
Described alarm modules, the described test data and the preset range that are used for obtaining compare;
And when described test data surpasses described preset range, send alarm signal.
Preset range can be set according to practical experience, has guaranteed like this can in time pinpoint the problems and alarm or early warning when operating system breaks down or is unusual.
Compare with general technology, the operating system performance proving installation of electric power secondary system of the present invention is by being pre-stored in the test script file of each test performance item correspondence in the test script library, can test the operating system performance of electric power secondary system quantitatively, thereby provide foundation for the operation of operating system in electric power networks.Because each performance that test script file can be directed to operating system customizes, so the present invention can realize full test, and is not limited to certain specific performance.Than artificial manual test item by item, degree of the present invention can farthest be realized automatic test, thereby has improved the testing efficiency of operating system.In addition, customize because test script file can be directed to the performance of operating system, therefore, test can be carried out for the power business characteristics, can test targetedly the demand of operating system according to power business.The present invention has testing efficiency height and the objective advantage of test result.
The above embodiment has only expressed several embodiment of the present invention, and it describes comparatively concrete and detailed, but can not therefore be interpreted as the restriction to claim of the present invention.Should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.

Claims (10)

1. the operating system performance method of testing of an electric power secondary system is characterized in that, may further comprise the steps:
Test performance item according to the user is selected information, identifies the performance item to be tested of electric power secondary system operating system;
From test script library, obtain the test script file corresponding with described performance item to be tested; Wherein, prestore the test script file corresponding with each test performance item of electric power secondary system operating system in the described test script library;
The described test script file that execution is obtained obtains test data.
2. the operating system performance method of testing of electric power secondary system according to claim 1, it is characterized in that, in the step of the described performance item to be tested that identifies electric power secondary system operating system, described test performance item comprises: operating system Dhrystone benchmark test, Whetstone benchmark test, the file copy performance, the pipeline throughput performance, the process creation performance, shell script execution performance, the integer arithmetic performance, the floating point arithmetic performance, the context performance of handoffs, the local communication performance, local communication bandwidth performance and/or internal memory operation delay performance.
3. the operating system performance method of testing of electric power secondary system according to claim 1 is characterized in that, before the step of the described test script file that described execution is obtained, may further comprise the steps:
According to the described test script file that obtains, configuration testing script argument; Wherein, described test script parameter comprises the record path of test data and procedure file.
4. the operating system performance method of testing of electric power secondary system according to claim 1 is characterized in that, the described test script file that described execution is obtained obtains the step of test data, may further comprise the steps:
Main frame in electric power secondary system operating system is carried out described test and appraisal script file, obtains and carries out the test data of returning behind the described test script file.
5. the operating system performance method of testing of electric power secondary system according to claim 1 is characterized in that, after the described step of obtaining test data, may further comprise the steps:
Described test data and the preset range obtained are compared;
If described test data surpasses described preset range, then send alarm signal.
6. the operating system performance method of testing of electric power secondary system according to claim 1 is characterized in that, after the described step of obtaining test data, may further comprise the steps:
Generate the test result file of electric power secondary system operating system according to described test data.
7. the operating system performance proving installation of an electric power secondary system is characterized in that, comprises identification module, acquisition module and test module;
Described identification module is used for selecting information according to user's test performance item, identifies the performance item to be tested of electric power secondary system operating system;
Described acquisition module is used for obtaining the test script file corresponding with described performance item to be tested from test script library; Wherein, prestore the test script file corresponding with each test performance item of electric power secondary system operating system in the described test script library;
Described test module is used for carrying out the described test script file that obtains, and obtains test data.
8. the operating system performance proving installation of electric power secondary system according to claim 7, it is characterized in that, described test performance item comprises: operating system Dhrystone benchmark test, Whetstone benchmark test, file copy performance, pipeline throughput performance, process creation performance, shell script execution performance, integer arithmetic performance, floating point arithmetic performance, context performance of handoffs, local communication performance, local communication bandwidth performance and/or internal memory operation delay performance.
9. the operating system performance proving installation of electric power secondary system according to claim 7 is characterized in that, also comprises configuration module;
Described configuration module is used for before the described test script file that execution is obtained, according to the described test script file that obtains, configuration testing script argument; Wherein, described test script parameter comprises the record path of test data and procedure file.
10. the operating system performance proving installation of electric power secondary system according to claim 7 is characterized in that, also comprises alarm modules;
Described alarm modules, the described test data and the preset range that are used for obtaining compare;
And when described test data surpasses described preset range, send alarm signal.
CN201310270574.6A 2013-06-28 2013-06-28 The operating system performance method of testing of electric power secondary system and device Active CN103324572B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310270574.6A CN103324572B (en) 2013-06-28 2013-06-28 The operating system performance method of testing of electric power secondary system and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310270574.6A CN103324572B (en) 2013-06-28 2013-06-28 The operating system performance method of testing of electric power secondary system and device

Publications (2)

Publication Number Publication Date
CN103324572A true CN103324572A (en) 2013-09-25
CN103324572B CN103324572B (en) 2016-12-28

Family

ID=49193331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310270574.6A Active CN103324572B (en) 2013-06-28 2013-06-28 The operating system performance method of testing of electric power secondary system and device

Country Status (1)

Country Link
CN (1) CN103324572B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103678130A (en) * 2013-12-17 2014-03-26 中国联合网络通信集团有限公司 Automated performance test method and platform
CN104516814A (en) * 2013-09-29 2015-04-15 腾讯科技(深圳)有限公司 Automatic test method and device of terminal software
CN105183605A (en) * 2015-10-29 2015-12-23 浪潮(北京)电子信息产业有限公司 Server performance test method and device
CN106201856A (en) * 2015-05-04 2016-12-07 阿里巴巴集团控股有限公司 A kind of multi version performance test methods and device
CN111581084A (en) * 2020-04-28 2020-08-25 南方电网数字电网研究院有限公司 Process testing method and device based on intelligent electric meter operating system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1503136A (en) * 2002-11-21 2004-06-09 深圳市中兴通讯股份有限公司 Embedded software test method
CN1601483A (en) * 2004-10-22 2005-03-30 中国工商银行 Automation software testing system based on script explanatory tool
CN101079004A (en) * 2007-06-22 2007-11-28 中兴通讯股份有限公司 Method and device for implementing test script management and distribution
CN101145964A (en) * 2007-07-27 2008-03-19 中兴通讯股份有限公司 An automatic smoke testing method and system for network management system
CN101174240A (en) * 2006-11-03 2008-05-07 凌阳科技股份有限公司 Software testing management method and system thereof
US20080126867A1 (en) * 2006-08-30 2008-05-29 Vinod Pandarinathan Method and system for selective regression testing
US7783927B2 (en) * 2007-03-09 2010-08-24 International Business Machines Corporation Intelligent processing tools

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1503136A (en) * 2002-11-21 2004-06-09 深圳市中兴通讯股份有限公司 Embedded software test method
CN1601483A (en) * 2004-10-22 2005-03-30 中国工商银行 Automation software testing system based on script explanatory tool
US20080126867A1 (en) * 2006-08-30 2008-05-29 Vinod Pandarinathan Method and system for selective regression testing
CN101174240A (en) * 2006-11-03 2008-05-07 凌阳科技股份有限公司 Software testing management method and system thereof
US7783927B2 (en) * 2007-03-09 2010-08-24 International Business Machines Corporation Intelligent processing tools
CN101079004A (en) * 2007-06-22 2007-11-28 中兴通讯股份有限公司 Method and device for implementing test script management and distribution
CN101145964A (en) * 2007-07-27 2008-03-19 中兴通讯股份有限公司 An automatic smoke testing method and system for network management system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104516814A (en) * 2013-09-29 2015-04-15 腾讯科技(深圳)有限公司 Automatic test method and device of terminal software
CN103678130A (en) * 2013-12-17 2014-03-26 中国联合网络通信集团有限公司 Automated performance test method and platform
CN106201856A (en) * 2015-05-04 2016-12-07 阿里巴巴集团控股有限公司 A kind of multi version performance test methods and device
CN105183605A (en) * 2015-10-29 2015-12-23 浪潮(北京)电子信息产业有限公司 Server performance test method and device
CN111581084A (en) * 2020-04-28 2020-08-25 南方电网数字电网研究院有限公司 Process testing method and device based on intelligent electric meter operating system

Also Published As

Publication number Publication date
CN103324572B (en) 2016-12-28

Similar Documents

Publication Publication Date Title
Liu et al. A two-layered permission-based android malware detection scheme
US9400887B2 (en) Program analysis/verification service provision system, control method for same, computer readable non-transitory storage medium, program analysis/verification device, program analysis/verification tool management device
TWI461952B (en) Method and system for detecting malware applications
Beccuti et al. Quantification of dependencies between electrical and information infrastructures
WO2018196559A1 (en) Method and apparatus for dealing with abnormality of application program, and storage medium
CN103324572A (en) Operating system performance test method and device for power secondary system
Jauhar et al. Model-based cybersecurity assessment with nescor smart grid failure scenarios
CN106533724B (en) Method, device and system for monitoring and optimizing Network Function Virtualization (NFV) network
CN104462970A (en) Android application program permission abuse detecting method based on process communication
CN112685682B (en) Method, device, equipment and medium for identifying forbidden object of attack event
US20150220417A1 (en) Monitoring user activity and performance of computerized devices
EP3084672A1 (en) Protection system including machine learning snapshot evaluation
CN103336740A (en) Comprehensive test method and device for operation system of power secondary system
CN103345444A (en) Method and device for testing operating system function of power secondary system
CN104346279A (en) Method and device for software testing
CN102306119A (en) System for capturing global exception and method
CN104461888A (en) Application testing method and system
KR101256468B1 (en) Apparatus and method for detecting malicious file
US20170017561A1 (en) Software detection method and device
CN113792341A (en) Privacy compliance automation detection method, device, equipment and medium for application program
CN103336741A (en) Method and device for testing stability of operation system of power secondary system
CN103279708A (en) Method and system for monitoring and analyzing mobile terminal malicious code behaviors
CN113961465A (en) Method, device and program product for processing reproduction of program crash scene
KR102231648B1 (en) Method, apparatus and computer-readable medium for managing inspection history information of fire fighting facility
CN110795330A (en) Monkey pressure testing method and device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8

Patentee after: ELECTRIC POWER RESEARCH INSTITUTE, GUANGDONG POWER GRID CO., LTD.

Address before: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8

Patentee before: Electrical Power Research Institute of Guangdong Power Grid Corporation