CN103322580B - Water-cooling dry-type slag discharge device of pulverized coal boiler - Google Patents

Water-cooling dry-type slag discharge device of pulverized coal boiler Download PDF

Info

Publication number
CN103322580B
CN103322580B CN201310278631.5A CN201310278631A CN103322580B CN 103322580 B CN103322580 B CN 103322580B CN 201310278631 A CN201310278631 A CN 201310278631A CN 103322580 B CN103322580 B CN 103322580B
Authority
CN
China
Prior art keywords
slag
water
transfer roller
cooler
breaker
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310278631.5A
Other languages
Chinese (zh)
Other versions
CN103322580A (en
Inventor
陈亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jinglong Alloy Steel Machinery Manufacturing Co., Ltd.
Original Assignee
陈亮
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 陈亮 filed Critical 陈亮
Priority to CN201310278631.5A priority Critical patent/CN103322580B/en
Publication of CN103322580A publication Critical patent/CN103322580A/en
Application granted granted Critical
Publication of CN103322580B publication Critical patent/CN103322580B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)
  • Crushing And Grinding (AREA)

Abstract

The invention provides a water-cooling dry-type slag discharge device of a pulverized coal boiler. The water-cooling dry-type slag discharge device comprises a drum slag cooler and a slag conveyor, a slag crushing device is arranged between a boiler slag well and the drum slag cooler, an outlet of the slag crushing device is communicated with a feed port of the drum slag cooler, a discharge port of the drum slag cooler is communicated with the slag conveyor, the slag crushing device is a high-temperature double-roll slag crusher which comprises two rotary rolls driven to rotate oppositely by a transmission mechanism a plurality of slag crushing teeth are distributed on the surface of each rotary roll along the axial direction of the rotary roll, the rotary rolls are arranged in a water jacket case, and auxiliary slag crushing teeth corresponding to the slag crushing teeth on the surfaces of the rotary rolls are distributed on the inner wall face of the water jacket case. A cooling chamber for supplying cooling water is formed in each of the rotary rolls and the water jacket case to cool parts in contact with slag blocks. The water-cooling dry-type slag discharge device of the pulverized coal boiler can crush coal slag to the required size and store the crushed slag as well as achieve heat recycling.

Description

Pulverized-coal fired boiler water-cooled dry slag-draining device
Technical field
The present invention relates to the boiler slag removal device that the industrial circles such as the energy, metallurgy, petrochemical industry take fine coal as fuel, particularly a kind of pulverized-coal fired boiler water-cooled dry slag-draining device.
Background technology
The industrial circles such as current China energy, metallurgy, petrochemical industry take fine coal as the dreg removing system that the steam generator system of fuel uses, substantially in the majority with wet type deslagging.Ye You minority enterprise uses wire mesh conveyor belt and supporting scraper plate jointly to use, and cooling source adopts air-cooled Dry Slag Removal System.Although two kinds of cold slags can cool deslagging temperature, the disadvantage existed is a lot of, and it is excessive that two kinds of cold slag systems of form all exist capital expenditure, wastes the major defect that recyclable resource, serious environment pollution, floor space are excessive in a large number.Also there are the serious problems such as waste water treatmentntrol difficult, water consumption is large, the disposable input of capital constructive fund is excessive in wet type deslagging.
Application number be 201220383646.9 utility model patent disclose a kind of dried slag removing waste-heat recovery device of coal-powder boiler, this device comprises coal-powder boiler, furnace hopper, slag charge monitor, level-sensing device, tremie pipe, push-pull valve, lag cooler, furnace hopper is arranged on the bottom of Pulverized Fuel Boiler Furnace, is connected with burner hearth by expansion joint, double-edged fine-toothed comb is arranged at the bottom of furnace hopper, hydraulic pressure plate breaker is arranged at double-edged fine-toothed comb top, and hopper is arranged at double-edged fine-toothed comb bottom, and hopper is connected with lag cooler by tremie pipe.This device, by hydraulic cylinder band hydrodynamic pressure plate breaker, extrudes slag by the extrusion head of indentation, makes slag broken, and uses lag cooler to cool lime-ash, to realize dried slag removing.Extruding break cannot meet the uniform requirement of discharging-material size, and when bulk lime-ash drops, breaker is disposed and easily caused double-edged fine-toothed comb to be impacted not in time and damaged.
Summary of the invention
For solving prior art Problems existing, the invention provides a kind of pulverized-coal fired boiler water-cooled dry slag-draining device, substantially eliminating environmental pollution, save floor occupying area, energy-saving and emission-reduction, the available heat circulation of recovery use, solving the disadvantage that original deslagging mode exists.
Pulverized-coal fired boiler water-cooled dry slag-draining device provided by the invention, comprise barrel slag cooler and defeated slag device, slag charge breaker is set between boiler slag well and described barrel slag cooler, the described outlet of slag charge breaker is communicated with the charging aperture of barrel slag cooler, the discharging opening of described barrel slag cooler is communicated with described defeated slag device, described slag charge breaker is the two roller slag breaker of high temperature, the two roller slag breaker of this high temperature comprises two are driven opposite direction rotating transfer roller by transmission mechanism, roll surface axially lays some disintegrating slag teeth along transfer roller, described transfer roller is arranged in a water jacket cabinet, the disintegrating slag tooth internal face of described water jacket cabinet corresponding to roll surface is laid with auxiliary disintegrating slag tooth, transfer roller and water jacket cabinet are provided with the cooling chamber of Cooling Water, cool the parts of contact clinker.
Further, described water jacket cabinet arranges described cooling chamber along its four peripheral wall surfaces, described cooling chamber and inlet header water tank with export header tank and be communicated with; The cooling chamber of described transfer roller is that hollow shaft form is arranged, and arranges swivel joint implement cooling for, draining near described transfer roller end,
During for preventing from running in the state of accident, produce the bulk coke button that scabs and fall and impact destruction to the two roller slag breaker of high temperature, arrange broken cone in the junction of the two roller slag breaker of boiler slag well and high temperature, the pointed portion that this fragmentation is bored upward.
Two transfer rollers of the two roller slag breaker of described high temperature are respectively initiatively transfer roller and passive transfer roller, and wherein, initiatively transfer roller directly transmits rotary power by the driving shaft of transmission mechanism, and initiatively power transmission is given passive transfer roller by gear train by transfer roller simultaneously.This kind of kind of drive can not change the normal meshing relation in transmission mechanism between each travelling gear because transfer roller centre-to-centre spacing changes, and fully ensures that two transfer rollers do synchronous opposite direction rotating all the time.
For making the particle size after cracking of cinder correspond to actual needs, the tooth front space of described disintegrating slag tooth is 1.3 times of maximum slag charge discharging-material size; Along described transfer roller radial direction, the spacing of adjacent disintegrating slag tooth is 1.1-1.4 times of maximum slag charge discharging-material size, and the tooth top arc length of adjacent disintegrating slag tooth is 1.9-2.3 times of maximum slag charge discharging-material size.
Further, along the axial direction of described transfer roller, the spacing of adjacent disintegrating slag tooth is the 2/3-3/4 of maximum slag charge discharging-material size.
Further, the diameter of described transfer roller is 2.5-4.5 times of maximum slag charge discharging-material size.
Transformation at present pulverized-coal fired boiler dreg removing system, generally, elevation is all difficult to the size reaching apparatus arrangement, can according to the real space at scene, adopt water-cooling spiral lag cooler as the pipeline promoting lime-ash elevation, enter pre-cooled section before barrel slag cooler and changeover portion as lime-ash.That is, described high temperature is two is provided with water-cooling spiral lag cooler between roller slag breaker and described barrel slag cooler, and namely the outlet of the two roller slag breaker of described high temperature is connected with described water-cooling spiral lag cooler, and the outlet of described water-cooling spiral lag cooler is connected with described barrel slag cooler.
Pulverized-coal fired boiler water-cooled dry slag-draining device provided by the present invention has the following advantages: after (1) pulverized-coal fired boiler water-cooled provided by the present invention dry slag-draining device adopts water-cooled dried slag removing, save a large amount of land occupation areas, significantly reduce construction funds invested.(2) eliminate buck settling tank, eliminate the pathogeny of strong wind sand, effectively prevent dust from flying contaminated environment, have positive role to the particle reduced in air.(3) eliminate washing slag water, substantially reduce the discharge capacity of sewage in boiler operatiopn, reduce the pressure of effluent from boiler process, strong ensure that the safety of water source.(4) pulverized-coal fired boiler water-cooled dry slag-draining device provided by the present invention employs barrel slag cooler, water-cooling spiral lag cooler, heat exchange mode is solid phase and liquid phase indirect heat exchange, obtain Lowlevel thermal energy, can, as the soft water pre-heating device entering stokehold, heat energy 757MJ can be utilized to calculate by ton slag, be equivalent to reduce mark coal 25.8Kg, equal to reduce discharging CO2-67.6Kg, SO2-0.22Kg, oxynitrides-0.19Kg, have the positive role of energy-saving and emission-reduction.(5) adopt closed conveying mode, prevent dust from flying contaminated environment, improve deslagging post labour health condition, alleviate field worker labour intensity.
Accompanying drawing explanation
Fig. 1 is the embodiment of the present invention one structural representation;
Fig. 2 is the two roller slag breaker A-A direction view of high temperature of the present invention;
Fig. 3 is I place enlarged drawing in Fig. 2;
Fig. 4 is that dregs breaking tooth of the present invention is at transfer roller axial distribution schematic diagram;
Fig. 5 is the embodiment of the present invention two structural representation.
In figure: 1-fragmentation cone; The two roller slag breaker of 2-high temperature; 3-barrel slag cooler; The defeated slag device of 4-; 5-slag storehouse; 6-slag well; 7-water-cooling spiral lag cooler; 2.1-is transfer roller initiatively; 2.2-water jacket cabinet; 2.3-cooling chamber; 2.4-transmission mechanism; 2.5-gear train; 2.6-disintegrating slag tooth; 2.7-assists disintegrating slag tooth; The passive transfer roller of 2.8-.
Detailed description of the invention
Embodiment one:
As shown in Figure 1, 2, pulverized-coal fired boiler water-cooled dry slag-draining device provided by the present invention, comprises barrel slag cooler 3, defeated slag device 4.Defeated slag device can be made up of high angle belt conveyer or bucket chain conveyor.Slag charge breaker is set between boiler slag well 6 and barrel slag cooler 3, the slag charge breaker that the present embodiment provides is the two roller slag breaker 2 of high temperature, the outlet of the two roller slag breaker 2 of high temperature is communicated with the charging aperture of barrel slag cooler 3, and the discharging opening of barrel slag cooler 3 is communicated with defeated slag device 4.The two roller slag breaker of high temperature comprises two are driven opposite direction rotating transfer roller (2.1,2,8) by transmission mechanism 2.4, and roll surface axially lays some dregs breaking tooths 2.6 along transfer roller.Transfer roller (2.1,2.8) is arranged in water jacket cabinet 2.2, and the dregs breaking tooth 2.6 internal face of water jacket cabinet corresponding to transfer roller 2.1 surface is laid with auxiliary dregs breaking tooth 2.7.Transfer roller (2.1,2.8) and water jacket cabinet 2.2 are provided with the cooling chamber 2.3 of Cooling Water, and for cooling the parts of contact clinker, cooled by continuous water flowing, the temperature rise ensureing crusher members in allowed limits, guarantees to have good intensity all the time.
Two transfer rollers of the two roller slag breaker 2 of high temperature are respectively initiatively transfer roller 2.1 and passive transfer roller 2.8, wherein, initiatively transfer roller 2.1 directly transmits rotary power by the driving shaft of transmission mechanism, and initiatively power transmission is given passive transfer roller 2.8 by gear train 2.5 by transfer roller 2.1 simultaneously.
The cooling chamber of water jacket cabinet 2.2 can be arranged along its four peripheral wall surfaces, described cooling chamber and inlet header water tank with export header tank and be communicated with; The cooling chamber of described transfer roller (2.1,2.8) is that hollow shaft form is arranged, and arranges swivel joint implement cooling for, draining near described transfer roller end.
During for effectively preventing from running in the state of accident, producing the bulk coke button that scabs and falling and impact destruction to the two roller slag breaker of high temperature, arrange in the junction of the two roller slag breaker 2 of boiler slag well 6 and high temperature and brokenly bore 1, its pointed portion upward.Broken cone 1 is made up of special alloy steel that is high temperature resistant, rub resistance, and shape conically or triangle.
As shown in Figure 2,3, 4, for making the particle size after cracking of cinder correspond to actual needs, the tooth front space L of dregs breaking tooth is 1.3 times of maximum slag charge discharging-material size; Transfer roller radial direction, the space D of adjacent dregs breaking tooth is 1.1-1.4 times of maximum slag charge discharging-material size; Transfer roller radial direction, the tooth top arc length H of adjacent dregs breaking tooth is 1.9-2.3 times of maximum slag charge discharging-material size.Along transfer roller axial direction, the spacing W of adjacent dregs breaking tooth is the 2/3-3/4 of maximum slag charge discharging-material size.In pulverized-coal fired boiler tapping process, usually cinder will be broken into the disintegrating slag of < 50mm, namely maximum slag charge discharging-material size diameter is 50mm.So in maximum slag charge discharging-material size 50mm situation, tooth front space L is 65mm; Along transfer roller radial direction, the space D of adjacent dregs breaking tooth is 55-70mm, and the tooth top arc length H of adjacent dregs breaking tooth is 95-115mm; Along transfer roller axial direction, the spacing W of adjacent dregs breaking tooth is 33-37mm.Doubly, this scope, can obtain comparatively ideal crushing effect to the 2.5-4.5 typically having a diameter from maximum slag charge discharging-material size of transfer roller.
Embodiment two:
As shown in Figure 5, to pulverized-coal fired boiler transform time, need the real space determination modification scheme according to scene.When height dimension is not enough, can adopts and increase a water-cooling spiral lag cooler 7 between roller slag breaker 2 and barrel slag cooler 3 and improve the elevation cooling lime-ash high temperature is two, carry out relay cooling.
By pulverized-coal fired boiler water-cooled dry slag-draining device provided by the present invention, lime-ash can be broken into the disintegrating slag of < 50mm, and utilize boiler feedwater indirectly to be cooled by warm sludge, reclaim heat to recycle, ash temperature is down to≤100 DEG C, be beneficial to use inclined angle belt or bucket chain conveyor to be delivered to slag warehousing and deposit.The Lowlevel thermal energy that wet type Quench is lost is reclaimed, effectively avoids a large amount of waste water resource and produce sewage, meeting the state basic policy of energy-saving and emission-reduction.This device has the effect of high-performance heat exchanger, and heat exchange mode is the indirect heat exchange of solid phase and liquid phase, and heat exchange area equilibrium, characteristics of compact layout, heat exchange efficiency are high.The continuity of defeated slag, can with the change of boiler load and coal and at any time long-range or Field adjustment.Lime-ash adopts closed conveying mode, prevents dust from flying contaminated environment, improves deslagging post labour health condition, have the positive role of energy-saving and emission-reduction.Slag-draining device adopts the manufacture of antiwear heat resisting alloy steel material, and the oxidation effectively can offsetting high-temperature ash is washed away and weares and teares, the service life of extension fixture.This plant running is steady, maintenance is few and convenient and easy, long service life, can meet the requirement of matched with devices, meanwhile, also has to the industry such as petrochemical industry, metallurgy of other solid shape material cooling the value promoted the use of.

Claims (8)

1. a pulverized-coal fired boiler water-cooled dry slag-draining device, comprise barrel slag cooler and defeated slag device, slag charge breaker is set between boiler slag well and described barrel slag cooler, the described outlet of slag charge breaker is communicated with the charging aperture of barrel slag cooler, the discharging opening of described barrel slag cooler is communicated with described defeated slag device, it is characterized in that: described slag charge breaker is the two roller slag breaker of high temperature, the two roller slag breaker of this high temperature comprises two are driven opposite direction rotating transfer roller by transmission mechanism, roll surface axially lays some disintegrating slag teeth along transfer roller, described transfer roller is arranged in a water jacket cabinet, the disintegrating slag tooth internal face of described water jacket cabinet corresponding to roll surface is laid with auxiliary disintegrating slag tooth, transfer roller and water jacket cabinet are provided with the cooling chamber of Cooling Water, cool the parts of contact clinker.
2. pulverized-coal fired boiler water-cooled dry slag-draining device as claimed in claim 1, is characterized in that: described water jacket cabinet arranges described cooling chamber along its four peripheral wall surfaces, described cooling chamber and inlet header water tank with export header tank and be communicated with; The cooling chamber of described transfer roller is that hollow shaft form is arranged, and arranges swivel joint implement cooling for, draining near described transfer roller end.
3. pulverized-coal fired boiler water-cooled dry slag-draining device as claimed in claim 1, is characterized in that: arrange broken cone in the junction of boiler slag well and the two roller slag breaker of high temperature, the pointed portion of this fragmentation cone upward.
4. pulverized-coal fired boiler water-cooled dry slag-draining device as claimed in claim 1, it is characterized in that: two transfer rollers of the two roller slag breaker of described high temperature are respectively initiatively transfer roller and passive transfer roller, wherein, initiatively transfer roller directly transmits rotary power by the driving shaft of transmission mechanism, and initiatively power transmission is given passive transfer roller by gear train by transfer roller simultaneously.
5. pulverized-coal fired boiler water-cooled dry slag-draining device as claimed in claim 1, is characterized in that: the tooth front space of described disintegrating slag tooth is 1.3 times of maximum slag charge discharging-material size; Along described transfer roller radial direction, the spacing of adjacent disintegrating slag tooth is 1.1-1.4 times of maximum slag charge discharging-material size, and the tooth top arc length of adjacent disintegrating slag tooth is 1.9-2.3 times of maximum slag charge discharging-material size.
6. pulverized-coal fired boiler water-cooled dry slag-draining device as claimed in claim 5, it is characterized in that: along the axial direction of described transfer roller, the spacing of adjacent disintegrating slag tooth is the 2/3-3/4 of maximum slag charge discharging-material size.
7. pulverized-coal fired boiler water-cooled dry slag-draining device as claimed in claim 1, is characterized in that: the diameter of described transfer roller is 2.5-4.5 times of maximum slag charge discharging-material size.
8. the pulverized-coal fired boiler water-cooled dry slag-draining device as described in claim 1-7 any one claim, it is characterized in that: described high temperature is two is provided with water-cooling spiral lag cooler between roller slag breaker and described barrel slag cooler, namely the outlet of the two roller slag breaker of described high temperature is connected with described water-cooling spiral lag cooler, and the outlet of described water-cooling spiral lag cooler is connected with described barrel slag cooler.
CN201310278631.5A 2013-07-03 2013-07-03 Water-cooling dry-type slag discharge device of pulverized coal boiler Active CN103322580B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310278631.5A CN103322580B (en) 2013-07-03 2013-07-03 Water-cooling dry-type slag discharge device of pulverized coal boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310278631.5A CN103322580B (en) 2013-07-03 2013-07-03 Water-cooling dry-type slag discharge device of pulverized coal boiler

Publications (2)

Publication Number Publication Date
CN103322580A CN103322580A (en) 2013-09-25
CN103322580B true CN103322580B (en) 2015-04-08

Family

ID=49191496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310278631.5A Active CN103322580B (en) 2013-07-03 2013-07-03 Water-cooling dry-type slag discharge device of pulverized coal boiler

Country Status (1)

Country Link
CN (1) CN103322580B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103615732B (en) * 2013-11-26 2015-12-02 东南大学 A kind of device strengthening the heat transfer of power station boiler dry slag discharge machine
CN103884017A (en) * 2014-02-26 2014-06-25 青岛松灵电力环保设备有限公司 Spiral conveying slag cooler
CN104165354B (en) * 2014-06-09 2016-09-07 章云 A kind of coal cinder burner
CN108731007B (en) * 2018-06-28 2023-07-25 西安交通大学 Boiler fire extinguishing device for preventing boiler from being burnt by ash bucket of power station boiler
CN110440269A (en) * 2019-07-15 2019-11-12 南通九洲环保科技有限公司 A kind of solid waste burning dry-type pulverizing slag-tapping system
CN113446612B (en) * 2021-07-28 2022-10-14 中材节能股份有限公司 Boiler slagging waste heat recovery device
CN115888892B (en) * 2022-12-21 2023-08-15 山东鲁泰热电有限公司 Dust-free slag crusher for thermal power plant

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4463686A (en) * 1982-10-05 1984-08-07 L. & C. Steinmuller Gmbh Apparatus for removal of ash and slag
CN2252291Y (en) * 1996-05-06 1997-04-16 李清临 Inner-cooled roll slag crusher
CN101008492A (en) * 2006-01-24 2007-08-01 北京国电富通科技发展有限责任公司 Dry slag-draining device of coal boiler
CN101632951A (en) * 2009-07-27 2010-01-27 常州市通力机电设备制造有限公司 Vertical shakeout crusher
CN201476032U (en) * 2009-08-21 2010-05-19 北京国电龙源环保工程有限公司 Mechanical slag removal device of pulverized-coal boiler
CN202902309U (en) * 2012-03-13 2013-04-24 尹华雷 Boiler slag cooling, crushing and dry-discharging combination device
CN203431889U (en) * 2013-07-03 2014-02-12 陈亮 Water-cooled dry type slagging device of pulverized coal boiler

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4463686A (en) * 1982-10-05 1984-08-07 L. & C. Steinmuller Gmbh Apparatus for removal of ash and slag
CN2252291Y (en) * 1996-05-06 1997-04-16 李清临 Inner-cooled roll slag crusher
CN101008492A (en) * 2006-01-24 2007-08-01 北京国电富通科技发展有限责任公司 Dry slag-draining device of coal boiler
CN101632951A (en) * 2009-07-27 2010-01-27 常州市通力机电设备制造有限公司 Vertical shakeout crusher
CN201476032U (en) * 2009-08-21 2010-05-19 北京国电龙源环保工程有限公司 Mechanical slag removal device of pulverized-coal boiler
CN202902309U (en) * 2012-03-13 2013-04-24 尹华雷 Boiler slag cooling, crushing and dry-discharging combination device
CN203431889U (en) * 2013-07-03 2014-02-12 陈亮 Water-cooled dry type slagging device of pulverized coal boiler

Also Published As

Publication number Publication date
CN103322580A (en) 2013-09-25

Similar Documents

Publication Publication Date Title
CN103322580B (en) Water-cooling dry-type slag discharge device of pulverized coal boiler
CN102645105B (en) High-temperature material heat recovery system
CN102748955B (en) Heat-energy recovery system of high-temperature material
CN104748134A (en) Double-spiral slag cooler
CN206219613U (en) A kind of dry type blast-furnace cement sensible heat recovery system
CN203431889U (en) Water-cooled dry type slagging device of pulverized coal boiler
CN113061673A (en) Device and method for recycling crushing waste heat of high-temperature steel slag rotating bed
CN209909892U (en) Slag crusher
CN202709144U (en) Dry-type slag discharging waste heat recovery device of coal-powder boiler
CN103307616A (en) Boiler cold slag broken coke dry discharging aggregate unit (machine)
CN105276595A (en) Water-cooled dry ash discharging device of pulverized coal boiler
CN104197365A (en) Preheating combustion air device for recovering waste heat of high-temperature slag in stepped mode
CN202902309U (en) Boiler slag cooling, crushing and dry-discharging combination device
CN209877660U (en) Equipment suitable for cooling high-temperature molten material and recovering waste heat
CN203784972U (en) Double-spiral slag cooler
CN109295298A (en) A kind of revolution kiln tail vertical preheater
CN104713372B (en) Can significantly lower consumption can the method for work of Heat-energy recovery system of high-temperature material
CN104713374A (en) Working method for high temperature material heat energy recovery system with high waste heat recovery rate
CN212237525U (en) High-temperature industrial slag grinding waste heat utilization system
CN201748451U (en) Dry-type slag discharging machine
CN101659522B (en) Calcined dolomite production machine
CN104634125A (en) Working method of high-temperature material thermal energy recovering system
CN201277805Y (en) Returning type multiple hearth rotary kiln
CN104296541B (en) Heat-energy recovery system of high-temperature material
CN217578945U (en) Device for preheating scrap steel by utilizing waste heat of steel slag

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170602

Address after: 214532, Jiangsu, Taizhou, Dongxing Town, Jingjiang Hui Feng head dam East

Patentee after: Jiangsu Jinglong Alloy Steel Machinery Manufacturing Co., Ltd.

Address before: 214500, Huimin road 28, Dongxing Town, Taizhou, Jiangsu, Jingjiang

Patentee before: Chen Liang

TR01 Transfer of patent right