CN103302251B - A kind of upper core box lazy-tongs of core making machine - Google Patents
A kind of upper core box lazy-tongs of core making machine Download PDFInfo
- Publication number
- CN103302251B CN103302251B CN201310282077.8A CN201310282077A CN103302251B CN 103302251 B CN103302251 B CN 103302251B CN 201310282077 A CN201310282077 A CN 201310282077A CN 103302251 B CN103302251 B CN 103302251B
- Authority
- CN
- China
- Prior art keywords
- core box
- upper core
- making machine
- tongs
- connecting plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Molds, Cores, And Manufacturing Methods Thereof (AREA)
Abstract
<b> the present invention relates to the upper core box lazy-tongs of a </b><bGreatT.Gre aT.GT core making machine, comprise core box lifting subassembly, upper core box Synchronization Component, described upper core box Synchronization Component comprises axle bed, synchronous connecting rod and small rod, described axle bed is fixed on the upper spider of core making machine, described synchronous connecting rod one end rotates with described axle bed and is connected, the other end rotates with described small rod one end and is connected, the other end of described small rod rotates with described upper core box lifting subassembly and is connected.</b><bGreatT.Gre aT.GT the present invention is by increasing upper core box Synchronization Component, and increase constraint and connect, the synchronism of core box lifting subassembly in enhancing, overcomes upper core box and be elevated asynchronous problem; When driver part action is asynchronous, guide post and fairlead resistance inconsistent time, when upper core box is laid particular stress on, by the effect of contraction of both sides synchronous connecting rod, overcome original cantilever design side force, overcome upper core box and be elevated asynchronous problem.</b>
Description
Technical field
the present invention relates to core making machine field, particularly relate to a kind of upper core box lazy-tongs of core making machine.
Background technology
upper core box hoisting mechanism is the important component part of core making machine, in shooting case of core maker sand and air blowing coremaking process, upper core box need with lower core box press seal, on most of type, core box and lower core box are due to the demand of device action, need upper and lower synchronization lifting; After core has solidified, core by after plunger tip effect ejects upper core box on equipment, need complete and got core.
core box hoisting mechanism on existing most of core making machine, mainly comprise left and right/former and later two hydraulic cylinders/air cylinder driven mechanism, four sides are guide post and fairlead, core box connecting plate on the bottom be connected with guide rod, the synchronous frame in top connected with driving mechanism and guide post.Fairlead and driving mechanism and core making machine upper spider are fixed, and guide post, upper core box connecting plate and synchronous frame oscilaltion realize upper core box lifting action.Wherein: 1, control mode: owing to adopting two independently driving mechanisms, action cannot Complete Synchronization; 2, process, the trueness error of assembling: four side guide posts and the fairlead resistance that leads is inconsistent; 3, core manufacturing craft demand: core is not arranged between two parties, or core profile size deviation, cause core box side to lay particular stress on.Above 3 main causes easily cause four side guide posts to go up and down with different paces and cause, the asynchronous problem of core box in generation.
the synchronous frame in the main top portion of existing structure overcomes above problem.The synchronous frame in top and guide post generally adopt guide post end screw to fix, or adopt guide post flange screw fixed form.The synchronous frame independent suspension in top, is not connected with other parts, this similar cantilever design.In actual use, although certain synchronous effect can be had, the asynchronous problem of synchronous frame itself cannot be overcome, cause core box to be elevated asynchronous.The asynchronous of synchronous frame itself also can be caused and guide post Joint failure, and synchronous frame synchronous effect was lost efficacy, and upper core box lifting is asynchronous more serious.About upper core box lifting or both sides, front and back are asynchronous, and upper and lower core box parting when easily causing core making machine to run, makes made core produce overlap, produces useless core.In addition, easily cause plunger tip effect unbalanced, core cannot be ejected upper core box or by bad for core top.
Summary of the invention
the object of this invention is to provide a kind of upper core box lazy-tongs of core making machine, mainly solve core box hoisting mechanism on core making machine, when lifting action, the problem of left and right or both sides, front and back poor synchronization.
for achieving the above object, the technical solution used in the present invention is:
a kind of upper core box lazy-tongs of core making machine, comprise core box lifting subassembly, upper core box Synchronization Component, described upper core box Synchronization Component comprises axle bed, synchronous connecting rod and small rod, described axle bed is fixed on the upper spider of core making machine, described synchronous connecting rod one end rotates with described axle bed and is connected, the other end rotates with described small rod one end and is connected, and the other end of described small rod rotates with described upper core box lifting subassembly and is connected.
preferably, described upper core box Synchronization Component is provided with a pair, and the upper core box Synchronization Component described in a pair is arranged on left and right or the side, front and back of described upper core box lifting subassembly.
preferably, be rotatably connected to gyroaxis between the axle bed described in a pair, an end of the synchronous connecting rod described in a pair is connected on described gyroaxis simultaneously.
preferably, described upper core box lifting subassembly comprises core box connecting plate, synchronized links plate, guide and driver part, the lower surface of described upper core box connecting plate is connected with upper core box, described guide is connected between described upper core box connecting plate and synchronized links plate, described driver part is fixed on the upper spider of core making machine, and acting on described upper core box connecting plate, the other end of described small rod rotates with described synchronized links plate and is connected.
further preferably, described guide is be arranged on described upper core box connecting plate, the guide post on synchronized links plate four limit, the fairlead be disposed on described guide post, and the upper and lower end of described guide post is by locating hole, end face screw or fixed by flange screw and described synchronized links plate, upper core box connecting plate.
further preferably, described driver part is connected with described upper core box connecting plate with bearing pin or connector flange screw by oil cylinder articulated joint.
further preferably, described driver part is provided with two groups.
further preferably, described driver part is hydraulic cylinder or cylinder.
because technique scheme is used, the present invention compared with prior art has following advantages:
the present invention is by increasing upper core box Synchronization Component, and increase constraint and connect, the synchronism of core box lifting subassembly in enhancing, overcomes upper core box and be elevated asynchronous problem; When driver part action is asynchronous, guide post and fairlead resistance inconsistent time, when upper core box is laid particular stress on, by the effect of contraction of both sides synchronous connecting rod, overcome original cantilever design side force, overcome upper core box and be elevated asynchronous problem.
Accompanying drawing explanation
accompanying drawing 1 is structural representation of the present invention (front view);
accompanying drawing 2 is structural representation of the present invention (side view);
accompanying drawing 3 is the principle sketch of lazy-tongs in the present invention.
wherein: 10, upper core box connecting plate; 11, synchronized links plate; 12, guide post; 13, fairlead; 14, driver part; 20, axle bed; 21, synchronous connecting rod; 22, small rod; 23, gyroaxis; 3, upper core box; 4, upper spider.
Detailed description of the invention
below in conjunction with drawings and Examples, the invention will be further described:
the upper core box lazy-tongs of a kind of core making machine as Figure 1-3, comprise core box lifting subassembly, upper core box Synchronization Component.Wherein:
upper core box lifting subassembly comprises core box connecting plate 10, synchronized links plate 11, guide 12, fairlead 13 and driver part 14.The lower surface of upper core box connecting plate 10 and upper core box 3 are connected by retaining mechanism and fix; The upper end of guide post 12 is fixed by locating hole, end face screw and synchronized links plate 11, the lower end of guide post 12 is fixed by core box connecting plate 10 on locating hole, end face screw, can certainly be fixed by flange screw, guide post 12 is arranged on four limits of core box connecting plate 10 and synchronized links plate 11; Driver part 14 is fixed on the upper spider 4 of core making machine, is connected with bearing pin or connector flange screw by oil cylinder articulated joint with upper core box connecting plate 10.Driver part 12(is as hydraulic cylinder, cylinder) lifting of core box connecting plate 10 in control, in drive, core box 3 is elevated, guide post 12 and synchronized links plate 11 synchronization lifting, the oscilaltion action dependence guide post 12 of guide post 12 leads with fairlead 13 and coordinates positioning action, and in guarantee, core box 3 is accurate with lower core box die-closed position.
upper core box Synchronization Component comprises axle bed 20, synchronous connecting rod 21 and small rod 22, and upper core box Synchronization Component is provided with a pair, and on a pair, core box Synchronization Component is arranged on left and right or the side, front and back of core box lifting subassembly.Axle bed 20 is fixed on the upper spider 4 of core making machine, gyroaxis 23 is rotatably connected between a pair axle bed 20, gyroaxis 23 is fixed with the bearing in axle bed 20, one end of a pair synchronous connecting rod 21 is connected on gyroaxis 23 simultaneously, the other end and small rod 22 1 end are rotated by bearing pin and are connected, and 22 the other end of small rod to be rotated with synchronized links plate 11 by bearing pin and are connected.
the driver part 14 of upper core box lifting subassembly is elevated, drive synchronized links plate 11 synchronization lifting, small rod 22 and synchronous connecting rod 21 synchronous axial system, the effect of upper core box Synchronization Component to be retrained with upper spider 4 by synchronous connecting rod 21 by synchronized links plate 11 to be connected, when upper core box 3 is elevated, overcome the nonsynchronous problem of upper core box lifting subassembly.
above-described embodiment, only for technical conceive of the present invention and feature are described, its object is to person skilled in the art can be understood content of the present invention and implement according to this, can not limit the scope of the invention with this.All equivalences done according to Spirit Essence of the present invention change or modify, and all should be encompassed within protection scope of the present invention.
Claims (5)
1. the upper core box lazy-tongs of a core making machine, it is characterized in that: comprise core box lifting subassembly, upper core box Synchronization Component, described upper core box Synchronization Component comprises axle bed, synchronous connecting rod and small rod, described axle bed is fixed on the upper spider of core making machine, described upper core box Synchronization Component is provided with a pair, gyroaxis is rotatably connected between axle bed described in a pair, one end of the synchronous connecting rod described in a pair is connected on described gyroaxis simultaneously, synchronous connecting rod the other end described in a pair rotates with described small rod one end and is connected, upper core box Synchronization Component described in a pair is arranged on left and right or the side, front and back of described upper core box lifting subassembly,
Described upper core box lifting subassembly comprises core box connecting plate, synchronized links plate, guide and driver part, the lower surface of described upper core box connecting plate is connected with upper core box, described guide is connected between described upper core box connecting plate and synchronized links plate, described driver part is fixed on the upper spider of core making machine, and acting on described upper core box connecting plate, the other end of described small rod rotates with the synchronized links plate of described upper core box Synchronization Component and is connected.
2. the upper core box lazy-tongs of a kind of core making machine according to claim 1, it is characterized in that: described guide is be arranged on described upper core box connecting plate, the guide post on synchronized links plate four limit, the fairlead be disposed on described guide post, the upper and lower end of described guide post is by locating hole, end face screw or fixed by flange screw and described synchronized links plate, upper core box connecting plate.
3. the upper core box lazy-tongs of a kind of core making machine according to claim 1, is characterized in that: described driver part is connected with described upper core box connecting plate with connector flange screw by oil cylinder articulated joint with bearing pin or described driver part by oil cylinder articulated joint.
4. the upper core box lazy-tongs of a kind of core making machine according to claim 1, is characterized in that: described driver part is provided with two groups.
5. the upper core box lazy-tongs of a kind of core making machine according to claim 1, is characterized in that: described driver part is hydraulic cylinder or cylinder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310282077.8A CN103302251B (en) | 2013-07-05 | 2013-07-05 | A kind of upper core box lazy-tongs of core making machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310282077.8A CN103302251B (en) | 2013-07-05 | 2013-07-05 | A kind of upper core box lazy-tongs of core making machine |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103302251A CN103302251A (en) | 2013-09-18 |
CN103302251B true CN103302251B (en) | 2015-12-23 |
Family
ID=49128219
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310282077.8A Active CN103302251B (en) | 2013-07-05 | 2013-07-05 | A kind of upper core box lazy-tongs of core making machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103302251B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108262452A (en) * | 2018-03-12 | 2018-07-10 | 苏州明志科技有限公司 | A kind of electricity drives molding core making machine |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3496988A (en) * | 1968-03-14 | 1970-02-24 | Woodward Corp | Process of making green sand cores |
CN1556025A (en) * | 2003-12-31 | 2004-12-22 | 深圳市汇银实业开发有限公司 | Swing type lifter for assembling four link torsional force axial type synchro |
CN201244666Y (en) * | 2008-08-01 | 2009-05-27 | 苏州明志科技有限公司 | Lifting mechanism for upper core box |
CN201284138Y (en) * | 2008-08-30 | 2009-08-05 | 江苏天奇物流系统工程股份有限公司 | Synchronous jacking conveying appliance |
CN201720392U (en) * | 2010-07-09 | 2011-01-26 | 宁波凯利机械模具有限公司 | Die with long water jacket core |
CN202752541U (en) * | 2012-06-15 | 2013-02-27 | 苏州三信机器制造有限公司 | Upper core box mechanism of cold core machine |
CN202752549U (en) * | 2012-08-10 | 2013-02-27 | 河北欧耐机械模具有限公司 | Cooler core box core shooting machine |
CN203343381U (en) * | 2013-07-05 | 2013-12-18 | 苏州明志科技有限公司 | Upper core box synchronizing mechanism of core manufacturing machine |
-
2013
- 2013-07-05 CN CN201310282077.8A patent/CN103302251B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3496988A (en) * | 1968-03-14 | 1970-02-24 | Woodward Corp | Process of making green sand cores |
CN1556025A (en) * | 2003-12-31 | 2004-12-22 | 深圳市汇银实业开发有限公司 | Swing type lifter for assembling four link torsional force axial type synchro |
CN201244666Y (en) * | 2008-08-01 | 2009-05-27 | 苏州明志科技有限公司 | Lifting mechanism for upper core box |
CN201284138Y (en) * | 2008-08-30 | 2009-08-05 | 江苏天奇物流系统工程股份有限公司 | Synchronous jacking conveying appliance |
CN201720392U (en) * | 2010-07-09 | 2011-01-26 | 宁波凯利机械模具有限公司 | Die with long water jacket core |
CN202752541U (en) * | 2012-06-15 | 2013-02-27 | 苏州三信机器制造有限公司 | Upper core box mechanism of cold core machine |
CN202752549U (en) * | 2012-08-10 | 2013-02-27 | 河北欧耐机械模具有限公司 | Cooler core box core shooting machine |
CN203343381U (en) * | 2013-07-05 | 2013-12-18 | 苏州明志科技有限公司 | Upper core box synchronizing mechanism of core manufacturing machine |
Also Published As
Publication number | Publication date |
---|---|
CN103302251A (en) | 2013-09-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203804168U (en) | Floating-type sand-core clamping mechanism | |
CN204686279U (en) | A kind of hold down gag for the flat docking laser welding equipment of thin plate | |
CN103302251B (en) | A kind of upper core box lazy-tongs of core making machine | |
CN203343381U (en) | Upper core box synchronizing mechanism of core manufacturing machine | |
CN105386425A (en) | Hydraulic dam supporting mechanism capable of being limited in folded mode | |
CN204475187U (en) | A kind of bridge formwork separating mechanism | |
CN202701039U (en) | Car frame assembly straightness correcting device | |
CN203212246U (en) | Connecting structure of telescopic oil cylinder and basic arm | |
CN105382517A (en) | Rolling wheel assembly device | |
CN103722039B (en) | A kind of large-tonnage stress balance formula drawing machine | |
CN202530258U (en) | Driving mechanism for hanging head and joint pin press leg of flat knitting machine | |
CN205152908U (en) | Collapsible spacing hydraulic pressure dam supporting mechanism | |
CN103522737B (en) | Fire extinguisher screen printer | |
CN203496424U (en) | Fire extinguisher screen printer | |
CN202867390U (en) | Single cylinder inserted pin type crane and extensible oil cylinder therefore and cylinder head thereof | |
CN204435370U (en) | A kind of shoe of new structure | |
CN204605112U (en) | Semi-automatic steel disc stiffening plate make-up machine | |
CN203976312U (en) | Draw bench take-up cabin hydraulic elevating platform with stopper | |
CN104265342B (en) | A kind of back timber side guard board and front-axle beam side guard board syndeton | |
CN202937283U (en) | Mining horizontal stand column assembling machine | |
CN102788060B (en) | The cylinder head of single cylinder bolt-type hoist and telescopic oil cylinder thereof, telescopic oil cylinder | |
CN105672214A (en) | Hydraulic lifting dam | |
CN204321089U (en) | A kind of retaining mechanism of mould | |
CN204773382U (en) | Injection mold thimble canceling release mechanical system | |
CN205969836U (en) | Aircraft nose board of moulding plastics |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 215217 No. 1, No. 1 highway, Tongli Town, Suzhou City, Jiangsu, Wujiang Patentee after: Suzhou Mingzhi Technology Co., Ltd Address before: 215217 No. 1, No. 1 highway, Tongli Town, Suzhou City, Jiangsu, Wujiang Patentee before: SUZHOU MINGZHI TECHNOLOGY Co.,Ltd. |
|
CP01 | Change in the name or title of a patent holder |