CN103277129B - 一种防止采煤工作面上隅角瓦斯超限技术 - Google Patents

一种防止采煤工作面上隅角瓦斯超限技术 Download PDF

Info

Publication number
CN103277129B
CN103277129B CN201310140116.0A CN201310140116A CN103277129B CN 103277129 B CN103277129 B CN 103277129B CN 201310140116 A CN201310140116 A CN 201310140116A CN 103277129 B CN103277129 B CN 103277129B
Authority
CN
China
Prior art keywords
sealing
hole
drilling
extraction
arrange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310140116.0A
Other languages
English (en)
Other versions
CN103277129A (zh
Inventor
何俊
郭魏魏
王安虎
匡帅
陈新生
敬复兴
翟培杰
刘林兵
牛帅
唐一举
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Technology
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201310140116.0A priority Critical patent/CN103277129B/zh
Publication of CN103277129A publication Critical patent/CN103277129A/zh
Application granted granted Critical
Publication of CN103277129B publication Critical patent/CN103277129B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

一种防止采煤工作面上隅角瓦斯超限的方法,所述方法包括下述步骤:a、从采煤工作面回风上隅角位置开始在回风巷道顶板每隔2.5m布置一排钻孔,钻孔垂直于顶板,每排根据巷道具体尺寸布置2—3个钻孔,钻孔长度6--10m,钻孔施工采用MQT—130型锚索钻机并扩孔,扩孔后钻孔直径为50mm。b、钻孔封孔:钻孔施工完毕后孔内使用管径40mm的PVC管作为抽采管,两PVC管的连接处进行密封处理并且及时的封孔,封孔直接用1m长的铁接头裹涂抹聚氨酯棉质布袋封孔,封孔长度为1m。c、联网抽采:封孔后用直径42mm的高压胶管把顶板钻孔并网到回风顺槽的瓦斯抽采管路上进行抽采。

Description

一种防止采煤工作面上隅角瓦斯超限技术
技术领域
本发明涉及一种治理采煤工作面上隅角瓦斯超限的方法。
背景技术
采煤工作面上隅角是指回采工作面中的回风流与回风巷交汇处靠近采空区侧的端头位置。由于主风流方向的改变和边界几何条件的限制,在上隅角处形成涡流区,造成靠近采空区的回风流拐角处上隅角位置风速较小;由于瓦斯密度比空气密度小,瓦斯向上积聚富集,加之采空区瓦斯随着顶板周期来压规律性的涌入上隅角,极易造成采煤工作面上隅角的瓦斯浓度超限。
上隅角瓦斯浓度的积聚直至超限会给矿井的安全生产带来极其严重的影响。上隅角与采空区瓦斯事故的时有发生会造成人员的伤亡和财产的损失,因此上隅角是煤矿回采工作面防止瓦斯事故的重点监控和治理位置。目前防止上隅角瓦斯超限的直接方式主要以通过增加风量的方式驱散瓦斯涡流为主,其中增加风量的方式以局部挂风障、安装风射流引射器为主。
上述防止上隅角瓦斯超限的不足之处在于:
一、挂风障的主要目的是为了增加上隅角位置的通风量驱散涡流,但是由于井下机械设备的复杂性,挂设风障管理困难,影响生产进度。
二、安装风(水)射流引射器的成本太高,加之引射器的供风量有限,大部分矿井不予采用。
发明内容
本发明的目的正是针对上述现有技术中所存在的不足之处而提供一种新的防止采煤工作面上隅角超限的方法。该方法可以及时高效的抽采采煤工作面上隅角形成的积聚瓦斯,确保工作面生产安全。
本发明的目的可通过下述技术措施来实现:
本发明的方法包括下述步骤:
a、从采煤工作面回风上隅角位置开始在回风巷道顶板每隔2.5m布置一排钻孔,钻孔方位垂直于回风巷略偏向于采空区方向,每排根据巷道具体尺寸布置2—3个钻孔,钻孔长度6--10m,钻孔施工采用MQT—130型锚索钻机并扩孔,扩孔后钻孔直径为50mm。
b、钻孔封孔:钻孔施工完毕后孔内使用管径40mm的PVC管作为抽采管,两PVC管的连接处进行密封处理并且及时的封孔,封孔直接用1m长的铁接头裹涂抹聚氨酯棉质布袋封孔,封孔长度为1m。
c、联网抽采:封孔后用直径42mm的高压胶管把顶板钻孔插管并网到回风顺槽的瓦斯抽采管路上进行抽采。
本发明的有益效果如下:
1、通过布置抽采钻孔,在工作面上隅角位置形成一个负压区域,可以利用抽采系统及时高效的抽采上隅角因涡流而形成的积聚瓦斯。
2、抽采系统与增加通风设备比较,管理简单,且效率较高,经济效益好。
附图说明
图1是本发明使用地点的平面图,图2、图3分别为侧视图和剖面图。图4是上隅角顶板插管钻孔封孔及连接抽采管路局部示意图。
图中序号:1'—顶板钻孔2'—连接管路3'—抽采管路4'—采空区
图中的序号:1—高压胶管2—抽采管路3—聚氨酯封孔段4—1m长的铁接头5—PVC管6—顶板钻孔
具体实施方式
本发明以下将结合实施列(附图)做进一步描述:
如附图所示,本发明的方法包括下述步骤:
a、如附图1所示,从采煤工作面回风上隅角位置开始在回风巷道顶板每隔2.5m布置一排钻孔,钻孔方位垂直于回风巷略偏向于采空区方向,每排根据巷道具体尺寸布置2—3个钻孔,钻孔长度6--10m,钻孔施工采用MQT—130型锚索钻机并扩孔,扩孔后钻孔直径为50mm,钻孔终孔位置如图2和图3所示。
b、钻孔封孔:钻孔施工完毕后孔内使用管径40mm的PVC管5作为抽采管,如附图4所示,末端使用1m长的铁接头4连接PVC管,封孔时铁接头4裹涂抹聚氨酯棉质布袋封孔,封孔长度3为1m。
c、联网抽采:封孔后用直径42mm的高压胶管1把顶板插管并网到回风顺槽的瓦斯抽采管路2上进行抽采。

Claims (1)

1.一种防止采煤工作面上隅角瓦斯超限的方法,所述的方法包括下述具体步骤:
a、从采煤工作面回风上隅角位置开始在回风巷道顶板每隔2.5m布置一排钻孔,钻孔方位垂直于回风巷顶板略偏向于采空区方向,每排根据巷道具体尺寸布置2-3个钻孔,钻孔长度6-10m,钻孔施工采用MQT—130型锚索钻机并扩孔,扩孔后钻孔直径为50mm;
b、钻孔封孔:钻孔施工完毕后孔内使用管径40mm的PVC管作为抽采管,两PVC管的连接处进行密封处理并且及时的封孔,封孔直接用1m长的铁接头裹涂抹聚氨酯棉质布袋封孔,封孔长度为1m;
c、联网抽采:封孔后用直径42mm的高压胶管把顶板钻孔并网到回风顺槽的瓦斯抽采管路上进行抽采,在工作面上隅角位置形成一个负压区域,可以利用抽采系统及时抽采上隅角因涡流而形成的积聚瓦斯。
CN201310140116.0A 2013-04-22 2013-04-22 一种防止采煤工作面上隅角瓦斯超限技术 Expired - Fee Related CN103277129B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310140116.0A CN103277129B (zh) 2013-04-22 2013-04-22 一种防止采煤工作面上隅角瓦斯超限技术

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310140116.0A CN103277129B (zh) 2013-04-22 2013-04-22 一种防止采煤工作面上隅角瓦斯超限技术

Publications (2)

Publication Number Publication Date
CN103277129A CN103277129A (zh) 2013-09-04
CN103277129B true CN103277129B (zh) 2016-04-06

Family

ID=49059733

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310140116.0A Expired - Fee Related CN103277129B (zh) 2013-04-22 2013-04-22 一种防止采煤工作面上隅角瓦斯超限技术

Country Status (1)

Country Link
CN (1) CN103277129B (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103557026B (zh) * 2013-10-28 2015-12-30 煤科集团沈阳研究院有限公司 一种基于顶管掘进装置解决上隅角瓦斯的方法
CN104481540A (zh) * 2014-10-08 2015-04-01 六盘水师范学院 一种利用高位钻孔注浆控制多种煤矿开采灾害的方法
CN105697048A (zh) * 2016-03-03 2016-06-22 华北科技学院 一种控制炮掘巷道有毒有害物质超限的方法
CN106337695B (zh) * 2016-09-23 2018-06-05 河南理工大学 一种采空区遗煤自燃及上隅角瓦斯超限的综合治理方法
CN106761580B (zh) * 2017-01-23 2019-02-22 中国矿业大学 一种软围岩综放工作面瓦斯抽采方法
CN107503789B (zh) * 2017-07-31 2019-07-02 山西晋城无烟煤矿业集团有限责任公司 低瓦斯矿井高产高效工作面瓦斯地面抽采方法
CN111911220A (zh) * 2020-08-14 2020-11-10 辽宁工程技术大学 一种自动监测去除工作面上隅角一氧化碳的方法
CN113685225A (zh) * 2021-09-27 2021-11-23 太原理工大学 一种y型通风工作面采空区顶管瓦斯抽采方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1731964A1 (ru) * 1990-01-10 1992-05-07 Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела Способ дегазации газоносных и пожароопасных пластов
RU2086773C1 (ru) * 1995-04-24 1997-08-10 Государственный научно-исследовательский, проектно-конструкторский и проектный угольный институт с экспериментальным заводом "Печорниипроект" Способ дегазации надрабатываемого пласта-спутника
CN101082283A (zh) * 2007-06-29 2007-12-05 淮南矿业(集团)有限责任公司 沿空留巷y型通风采空区顶板卸压瓦斯抽采的方法
CN102003201A (zh) * 2010-12-21 2011-04-06 山西晋城无烟煤矿业集团有限责任公司 煤矿采空区瓦斯抽放方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1731964A1 (ru) * 1990-01-10 1992-05-07 Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела Способ дегазации газоносных и пожароопасных пластов
RU2086773C1 (ru) * 1995-04-24 1997-08-10 Государственный научно-исследовательский, проектно-конструкторский и проектный угольный институт с экспериментальным заводом "Печорниипроект" Способ дегазации надрабатываемого пласта-спутника
CN101082283A (zh) * 2007-06-29 2007-12-05 淮南矿业(集团)有限责任公司 沿空留巷y型通风采空区顶板卸压瓦斯抽采的方法
CN102003201A (zh) * 2010-12-21 2011-04-06 山西晋城无烟煤矿业集团有限责任公司 煤矿采空区瓦斯抽放方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
低透气性煤层瓦斯综合治理技术实践;薛德平等;《矿业安全与环保》;20130109;第40卷(第1期);第81-84页 *
八连城煤矿瓦斯抽放技术实践;史首业;《山东煤炭科技》;20100215(第01期);第167页,第169页 *

Also Published As

Publication number Publication date
CN103277129A (zh) 2013-09-04

Similar Documents

Publication Publication Date Title
CN103277129B (zh) 一种防止采煤工作面上隅角瓦斯超限技术
CN107083988B (zh) 基于千米定向钻孔的采动裂隙带瓦斯抽采技术方法
CN103924945B (zh) 煤矿用厚松散层下富水风化裂隙岩层的高压注浆工艺
CN103775127B (zh) 一种低透气性高瓦斯煤层群保护层瓦斯综合治理方法
WO2018171255A1 (zh) 一种网络化优势瓦斯运移通道构建及瓦斯导流抽采方法
CN111561297B (zh) 基于断层导水裂隙带的煤-地热水协同开采方法
CN103883350B (zh) 一种间隔跳采的充填采煤方法
CN103883304B (zh) 一种构建气化炉通道的地下煤炭气化方法
WO2013102309A1 (zh) 一种长壁工作面无煤柱开采方法
CN102226413A (zh) 瓦斯排放巷穿层钻孔区域瓦斯抽采方法
WO2015103861A1 (zh) 沿空留巷y型通风高位回风巷钻孔抽采瓦斯方法
CN103306657B (zh) 一种煤层割缝卸压增透和缝槽保持装置及方法
CN104975868A (zh) 基于定向钻进的顶板高位走向大直径长钻孔瓦斯抽采方法
CN104989339A (zh) 一种老空区抽采煤层气的系统及方法
CN102748064A (zh) 一种大采高综放工作面瓦斯治理方法
CN113803104B (zh) 上采区埋管与下向钻孔一体化布置及全周期瓦斯抽采方法
CN205089360U (zh) 大孔径采空区埋管瓦斯抽采装置
CN106437825A (zh) 一种高瓦斯矿井综放工作面高位钻孔的瓦斯抽采方法
CN106014345B (zh) 一种下部垮落法开采形成的复合老空区煤层气的抽采方法
CN105971563B (zh) 一种下部刀柱法开采形成的复合老空区煤层气的抽采方法
CN103557026B (zh) 一种基于顶管掘进装置解决上隅角瓦斯的方法
CN109915198B (zh) 采煤工作面超前钻孔全风压瓦斯排放方法
CN201696048U (zh) 煤层采空区裂隙带注水观测系统
CN104121036B (zh) 一种用于连通上下煤层中的地下水库的连接装置及连接方法
CN103758483B (zh) 一种处理穿层钻孔抽后破碎区域的二次封孔方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160406

Termination date: 20200422

CF01 Termination of patent right due to non-payment of annual fee