CN103235838B - A kind of figure for power distribution network is across figure automatic connection method - Google Patents

A kind of figure for power distribution network is across figure automatic connection method Download PDF

Info

Publication number
CN103235838B
CN103235838B CN201210359617.3A CN201210359617A CN103235838B CN 103235838 B CN103235838 B CN 103235838B CN 201210359617 A CN201210359617 A CN 201210359617A CN 103235838 B CN103235838 B CN 103235838B
Authority
CN
China
Prior art keywords
line chart
tie point
attachment points
rear end
power distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210359617.3A
Other languages
Chinese (zh)
Other versions
CN103235838A (en
Inventor
韩武
王琳
陆耀平
李卫
康林春
肖啸
赵玺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Ruiying Technology Co ltd
Yunnan Power Grid Co Ltd
Original Assignee
Suzhou Ruiying Technology Co ltd
Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Ruiying Technology Co ltd, Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd filed Critical Suzhou Ruiying Technology Co ltd
Priority to CN201210359617.3A priority Critical patent/CN103235838B/en
Publication of CN103235838A publication Critical patent/CN103235838A/en
Application granted granted Critical
Publication of CN103235838B publication Critical patent/CN103235838B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Abstract

The invention discloses a kind of figure for power distribution network across figure automatic connection method, described method carries out certainly being dynamically connected across figure to the figure of power distribution network by the computing machine containing load module, Network topology module and output module, said method comprising the steps of: (1) reads graph data; (2) search of figure tie point; The connection of figure tie point; (4) export new graph data, the present invention can be to provide a convenience when yardman carries out dispatching of power netwoks, dispatch picture clearly, operation is implemented very convenient, can decrease the trouble that yardman switches drawing back and forth, greatly improve the work efficiency of yardman.

Description

A kind of figure for power distribution network is across figure automatic connection method
Technical field
The present invention relates to a kind of figure across figure automatic connection method, be specifically related to a kind of figure for power distribution network across figure automatic connection method.
Background technology
The network of power distribution network originally individual complexity in electric power dispatching system, and compass of competency is larger, existing technology only has dependence CAD drawing to check, CAD drawing is for single, drawing without link on the contrary can be dealt with problems, but when drawing is trans-regional, specifying information can only be checked by ceaselessly switching drawing, repeatedly switching drawing and checking that information causes a lot of troubles to yardman.
Summary of the invention
For solving the problem, the invention provides one and drawing information is combined effectively, user is clearly seen under the prerequisite that need not switch drawing, and the figure of the power distribution network of complete drawing information is across figure automatic connection method.
For achieving the above object, the invention provides following technical scheme: a kind of figure for power distribution network is across figure automatic connection method, described method carries out certainly being dynamically connected across figure to the figure of power distribution network by the computing machine containing load module, Network topology module and output module, said method comprising the steps of:
(1) read graph data, read the line chart that will carry out in the graphic data base of power distribution network connecting across figure by load module;
(2) search of figure tie point, carry out the following step by Network topology module:
There is connectionless point in line chart described in a, automatic search, if do not had, then terminate search; If had, then record the property value of described tie point, and enter next step;
B, the adjacent line chart of adjacent attachment points and described adjacent attachment points place matched with it according to the property value search of described tie point, and record the property value of described adjacent attachment points;
(3) connection of figure tie point, forms a new line chart by line chart described in Network topology module automatic Mosaic and adjacent line chart;
(4) export new graph data, read described new line chart by output module.
Preferably, the coordinate figure recording described tie point and the coordinate figure recording described adjacent attachment points is also comprised respectively in step a, the b of described step (2).
Preferably, described step (3) comprises the following steps:
Whether tie point described in c, automatic decision is identical with the coordinate figure of adjacent attachment points, if identical, then line chart described in automatic Mosaic and adjacent line chart form a new line chart; If not identical, then enter next step;
The coordinate figure of d, the figure paper size according to described line chart and adjacent line chart, described tie point and adjacent attachment points cuts described line chart and/or adjacent line chart, and line chart after cutting described in automatic Mosaic and adjacent line chart form a new line chart.
Preferably, described load module and output module are dispatching simulation screen system.
Preferably, described tie point comprises front end tie point and rear end tie point; Described adjacent attachment points comprises the front end adjacent attachment points matched with described front end tie point and the rear end adjacent attachment points matched with described rear end tie point; Described adjacent line chart comprises front end line chart and rear end line chart; Described front end adjacent attachment points is located on the line chart of described front end; Described rear end adjacent attachment points is located on the line chart of described rear end.
Adopt the beneficial effect of above technical scheme to be: the present invention can effectively realize being certainly dynamically connected between drawing, and the drawing of zones of different is shown on same drawing, and yardman seems very clear, reduce the problem that yardman switches drawing.Substantially increase the work efficiency of yardman.
Accompanying drawing explanation
Fig. 1 is the workflow block scheme of a kind of figure for power distribution network of the present invention across figure automatic connection method;
To be a kind of figure for power distribution network of the present invention connect original state schematic diagram across the figure of figure automatic connection method embodiment 1 to Fig. 2;
To be a kind of figure for power distribution network of the present invention complete schematic diagram across the graphic joining of figure automatic connection method embodiment 1 to Fig. 3;
To be a kind of figure for power distribution network of the present invention connect original state schematic diagram across the figure of figure automatic connection method embodiment 2 to Fig. 4;
To be a kind of figure for power distribution network of the present invention cut view across the figure of figure automatic connection method embodiment 2 to Fig. 5;
Fig. 6 is the graphic joining completion status schematic diagram of a kind of figure for power distribution network of the present invention across figure automatic connection method embodiment 2;
To be a kind of figure for power distribution network of the present invention connect original state schematic diagram across the figure of figure automatic connection method embodiment 3 to Fig. 7;
To be a kind of figure for power distribution network of the present invention complete schematic diagram across the graphic joining of figure automatic connection method embodiment 3 to Fig. 8.
Wherein, single line Figure 21 that 11. adjacent attachment points 13. front end, adjacent attachment points 131. front end, line chart 121. rear end, tie point 12. rear end, tie point 112. front end, line chart 111. rear end line charts 2. are new, the splice point of 22. tie points and adjacent attachment points.
Embodiment
The preferred embodiment of the present invention is described in detail below in conjunction with accompanying drawing.
Embodiment 1
See Fig. 1, Fig. 2 and Fig. 3, as shown in legend wherein, a kind of figure for power distribution network, across figure automatic connection method, comprises the following steps:
(1) entered in the graphic data base of power distribution network by mapping software, and enter in the single line Figure 11 that will carry out connecting across figure;
(2) search in single line Figure 11 and have rear end tie point 111;
(3) information of rear end tie point 111 is recorded, and according to the rear end adjacent attachment points 121 in information searching rear end single line Figure 12 of rear end tie point 111, and record the information of rear end adjacent attachment points 121;
(4) judge that rear end tie point 111 and rear end adjacent attachment points 121 can dock, splice single line Figure 11 and adjacent single line Figure 12 thus form a new line chart 2;
(6) information of rear end tie point 111 and rear end adjacent attachment points 121 docking point 21 is recorded.
Network Topology Discovery algorithm is adopted automatically to search respectively in described single line Figure 11 with or without rear end tie point 111 and the rear end adjacent attachment points 121 automatically searched in the single line Figure 12 of rear end in step (2) and step (3).
Network topology method automatic Mosaic single line Figure 11 and adjacent single line Figure 12 is adopted in described step (4).
In step (3), the information of rear end tie point 111 comprises coordinate figure and the property value of rear end tie point 111; In step (3), the information of rear end adjacent attachment points 121 comprises coordinate figure and the property value of rear end adjacent attachment points 12.
In described step (1), the graphic data base of power distribution network comprises the information of the information of described single line Figure 11, the information of rear end single line Figure 12 and new line chart 2.
Figure for power distribution network is as follows across figure automatic connection method detailed process:
1. first log in paint program, navigate to the position will carrying out connecting across figure;
2. use in the position will carrying out connecting across figure line tail symbol pel to connect, and name (so-and-so and so-and-so get in touch with);
3. navigate to the position will carrying out another point connected across figure, use line tail symbol pel to connect, and name (consistent with the title of another tie point);
4. double-click the setting that line tail symbol carries out same connection;
5. start intelligent dispatch management system and carry out drawing renewal.
Embodiment 2
See Fig. 1, Fig. 4, Fig. 5 and Fig. 6, as shown in legend wherein, a kind of figure for power distribution network, across figure automatic connection method, comprises the following steps:
(1) entered in the graphic data base of power distribution network by mapping software, and enter in the single line Figure 11 that will carry out connecting across figure;
(2) the rear end tie point 111 in single line Figure 11 is found;
(3) information of rear end tie point 111 is recorded, and according to the rear end adjacent attachment points 121 in information searching rear end single line Figure 12 of rear end tie point 111, and record the information of rear end adjacent attachment points 121;
(4) judge that rear end tie point 111 and rear end adjacent attachment points 121 can not dock;
(5) single line Figure 11 and rear end single line Figure 12 is cut according to the information of the figure paper size of single line Figure 11 and adjacent single line Figure 12, rear end tie point 111 and rear end adjacent attachment points 121, and single line Figure 11 after cutting described in splicing and rear end single line Figure 12 thus the new line chart 2 of composition one, and record the information of institute's rear end tie point 111 and rear end adjacent attachment points 121 docking point 21.
Network Topology Discovery algorithm is adopted automatically to search respectively in single line Figure 11 with or without rear end tie point 111 and the rear end adjacent attachment points 121 automatically searched in the single line Figure 12 of rear end in step (2) and step (3).
Network topology method automatic Mosaic single line Figure 11 and rear end single line Figure 12 is adopted in step (4).
Adopt in step (5) Network topology method automatically to cut line chart 11 and rear end single line Figure 12, and automatic Mosaic cut after single line Figure 11 and rear end single line Figure 12.
In step (3), the information of rear end tie point 111 comprises coordinate figure and the property value of rear end tie point 111; In step (3), the information of rear end adjacent attachment points 121 comprises coordinate figure and the property value of described rear end adjacent attachment points 121.
In step (1), the graphic data base of power distribution network comprises the information of the information of single line Figure 11, the information of rear end single line Figure 12 and new line chart 2.
Figure for power distribution network is as follows across figure automatic connection method detailed process:
1. first log in paint program, navigate to the position will carrying out connecting across figure;
2. use in the position will carrying out connecting across figure line tail symbol pel to connect, and name (so-and-so and so-and-so get in touch with);
3. navigate to the position will carrying out another point connected across figure, use line tail symbol pel to connect, and name (consistent with the title of another tie point);
4. double-click the setting that line tail symbol carries out same connection;
5. start intelligent dispatch management system and carry out drawing renewal;
6. navigate to across drawing connect more how, double-click this circuit, system can carry out splicing and the cutting of figure automatically according to algorithm.
Embodiment 3
See Fig. 1, Fig. 7 and Fig. 8, as shown in legend wherein, a kind of figure for power distribution network, across figure automatic connection method, comprises the following steps:
(1) entered in the graphic data base of power distribution network by mapping software, and enter in the single line Figure 11 that will carry out connecting across figure;
(2) find in single line Figure 11 and have rear end tie point 111 and front end tie point 112;
(3) information of rear end tie point 111 and front end tie point 112 is recorded, and according to the rear end adjacent attachment points 121 in information searching rear end single line Figure 12 of rear end tie point 111, and record the information of rear end adjacent attachment points 121; Simultaneously according to the front end adjacent attachment points 131 in information searching front end single line Figure 13 of front end tie point 112, and record the information of front end adjacent attachment points 131;
(4) judge that rear end tie point 111 and rear end adjacent attachment points 121 can dock; Front end tie point 112 and front end adjacent attachment points 131 can dock; Respectively rear end single line Figure 12 and front end single line Figure 13 is spliced to the rear end of single line Figure 11 and front end thus the new line chart 2 of composition one, and records the information of rear end adjacent attachment points 121 and rear end tie point 111 docking point 21; The information of record front end adjacent attachment points 131 and front end tie point 112 docking point 22.
Network Topology Discovery algorithm is adopted automatically to search respectively with or without rear end tie point 111 and front end tie point 112 in single line Figure 11 in step (2) and step (3), and the front end adjacent attachment points 131 in the rear end adjacent attachment points 121 automatically searched in the single line Figure 12 of rear end and front end single line Figure 13.
Network topology method is adopted automatically rear end single line Figure 12 and front end single line Figure 13 to be spliced to rear end and the front end of single line Figure 11 in step (4).
In step (3), the information of rear end tie point 111 comprises coordinate figure and the property value of rear end tie point 111, and the information of front end tie point 112 comprises coordinate figure and the property value of front end tie point 112;
In step (3), the information of rear end adjacent attachment points 121 comprises coordinate figure and the property value of rear end adjacent attachment points 121; The information of front end adjacent attachment points 131 comprises coordinate figure and the property value of front end adjacent attachment points 131.
The graphic data base of power distribution network comprises the information of the information of single line Figure 11, the information of rear end single line Figure 12, the information of front end single line Figure 13 and new line chart 2 in step (1).
Figure for power distribution network is as follows across figure automatic connection method detailed process:
1. first log in paint program, navigate to the position will carrying out connecting across figure;
2. use in the position will carrying out connecting across figure line tail symbol pel to connect, and name (so-and-so and so-and-so get in touch with);
3. navigate to the position will carrying out another point connected across figure, use line tail symbol pel to connect, and name (consistent with the title of another tie point);
4. double-click the setting that line tail symbol carries out same connection;
5. start intelligent dispatch management system and carry out drawing renewal.
Adopt the beneficial effect of above technical scheme to be: the present invention can effectively realize being certainly dynamically connected between drawing, and the drawing of zones of different is shown on same drawing, and yardman seems very clear, reduce the problem that yardman switches drawing.Substantially increase the work efficiency of yardman.
Above-described is only the preferred embodiment of the present invention, it should be pointed out that for the person of ordinary skill of the art, and without departing from the concept of the premise of the invention, can also make some distortion and improvement, these all belong to protection scope of the present invention.

Claims (4)

1. one kind for the figure of power distribution network across figure automatic connection method, it is characterized in that, described method carries out certainly being dynamically connected across figure to the figure of power distribution network by the computing machine containing load module, Network topology module and output module, said method comprising the steps of:
(1) read graph data, read the line chart that will carry out in the graphic data base of power distribution network connecting across figure by load module;
(2) search of figure tie point, carry out the following step by Network topology module:
There is connectionless point in line chart described in a, automatic search, if do not had, then terminate search; If had, then record the property value of described tie point, and enter next step;
B, the adjacent line chart of adjacent attachment points and described adjacent attachment points place matched with it according to the property value search of described tie point, and record the property value of described adjacent attachment points;
(3) connection of figure tie point, forms a new line chart by line chart described in Network topology module automatic Mosaic and adjacent line chart, comprises the following steps:
Whether tie point described in c, automatic decision is identical with the coordinate figure of adjacent attachment points, if identical, then line chart described in automatic Mosaic and adjacent line chart form a new line chart; If not identical, then enter next step;
The coordinate figure of d, the figure paper size according to described line chart and adjacent line chart, described tie point and adjacent attachment points cuts described line chart and/or adjacent line chart, and line chart after cutting described in automatic Mosaic and adjacent line chart form a new line chart;
(4) export new graph data, export described new line chart by output module.
2. the figure for power distribution network according to claim 1 is across figure automatic connection method, it is characterized in that, also comprises the coordinate figure recording described tie point and the coordinate figure recording described adjacent attachment points respectively in step a, the b of described step (2).
3. the figure for power distribution network according to claim 1 is across figure automatic connection method, it is characterized in that, described load module and output module are dispatching simulation screen system.
4. the figure for power distribution network according to claim 1 is across figure automatic connection method, it is characterized in that, described tie point comprises front end tie point and rear end tie point; Described adjacent attachment points comprises the front end adjacent attachment points matched with described front end tie point and the rear end adjacent attachment points matched with described rear end tie point; Described adjacent line chart comprises front end line chart and rear end line chart; Described front end adjacent attachment points is located on the line chart of described front end; Described rear end adjacent attachment points is located on the line chart of described rear end.
CN201210359617.3A 2012-09-25 2012-09-25 A kind of figure for power distribution network is across figure automatic connection method Active CN103235838B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210359617.3A CN103235838B (en) 2012-09-25 2012-09-25 A kind of figure for power distribution network is across figure automatic connection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210359617.3A CN103235838B (en) 2012-09-25 2012-09-25 A kind of figure for power distribution network is across figure automatic connection method

Publications (2)

Publication Number Publication Date
CN103235838A CN103235838A (en) 2013-08-07
CN103235838B true CN103235838B (en) 2015-09-09

Family

ID=48883879

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210359617.3A Active CN103235838B (en) 2012-09-25 2012-09-25 A kind of figure for power distribution network is across figure automatic connection method

Country Status (1)

Country Link
CN (1) CN103235838B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104361617B (en) * 2014-11-07 2017-06-16 广州市科创电脑技术开发有限公司 A kind of method and apparatus spliced with combination view
CN105046032B (en) * 2015-09-11 2018-08-31 国网山东庆云县供电公司 The method and system of distribution network line are drawn based on CAD
CN113626961B (en) * 2021-08-05 2024-05-07 国网山东省电力公司青岛市黄岛区供电公司 Automatic mapping method for power supply path

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101661527A (en) * 2009-09-25 2010-03-03 江西九江供电公司 Automatic switching system from geographical wiring diagram of distribution network to single line diagram

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080125984A1 (en) * 2006-09-25 2008-05-29 Veselin Skendzic Spatially Assisted Fault Reporting Method, System and Apparatus

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101661527A (en) * 2009-09-25 2010-03-03 江西九江供电公司 Automatic switching system from geographical wiring diagram of distribution network to single line diagram

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
基于CIM/SVG和面向对象的配电单线图自动生成;章坚民 等;《电力系统自动化》;20081125;第32卷(第22期);第61-65页 *
基于图数模统一设计的变电站图数识别和自动成图的研究;徐冠华;《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》;20110915;第2011年卷(第09期);第C042-360页 *
无重叠交叉的配电网单线图自动生成算法;陈勇 等;《电力自动化设备》;20101130;第30卷(第11期);第90-93页 *
辛华.配电网单线图自动成图的算法研究.《2010年云南电力技术论坛》.2010,全文. *

Also Published As

Publication number Publication date
CN103235838A (en) 2013-08-07

Similar Documents

Publication Publication Date Title
CN102932062B (en) Intelligent optical fiber connects distribution system and adapter port state information identification method
CN103997079B (en) A kind of electric vehicle alternating-current charging pile and using method thereof
CN103235838B (en) A kind of figure for power distribution network is across figure automatic connection method
CN103441861A (en) Method and device for generating data records
CN204156542U (en) A kind of electric vehicle alternating-current charging pile
CN104967534B (en) A kind of Grid Central and distribution substation's cable resource unified management and planing method
CN102937948B (en) A kind of image, text and data edit methods of mobile terminal
CN107562372A (en) A kind of electronic equipment and its data managing method, computer-readable recording medium
CN202453889U (en) Portable terminal of electronic manual for military vehicle maintenance
CN207731322U (en) One kind managing system for auto parts flow line production
CN100438521C (en) Information management method in data communication equipment
CN102457498A (en) Method and device for switching instant messaging session
CN104506597A (en) Method, device and system for acquiring information of electricity customers
CN108052245A (en) A kind of data processing method and device of battery management system
CN105225169A (en) A kind of data management system of transformer platform area
CN102868222A (en) Port configuration-based naming method of optical fiber secondary circuit of intelligent substation
CN105117305A (en) Data management apparatus for intelligent device of intelligent substation
CN204926057U (en) Tiled display system of cell -phone screen
CN103297631B (en) A kind of synchronizing telephone directory method and cloud server
CN107580070B (en) A kind of method, system and the relevant apparatus of the transmission of computer remote file
CN101345386B (en) Method and structure for wiring indication of electric wire and cable
CN105930952A (en) Energy consumption analysis and evaluation system for power distribution equipment
CN204256778U (en) A kind of library intelligent label read-write equipment
CN102629284B (en) Design method for intelligent substation communication based on intelligent device physical port modeling
CN103546320B (en) A kind of docking calculation of the cross-linked data of transmission network based on SDH

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: Suzhou City, Jiangsu province 215000 Suzhou Industrial Park Loufeng District Yang Fu Road No. 60

Co-patentee after: Yunnan Power Grid Corporation

Patentee after: SUZHOU RUIYING TECHNOLOGY Co.,Ltd.

Address before: Suzhou City, Jiangsu province 215000 Suzhou Industrial Park Loufeng District Yang Fu Road No. 60

Co-patentee before: KUNMING POWER SUPPLY BUREAU, YUNNAN POWER GRID Corp.

Patentee before: SUZHOU RUIYING TECHNOLOGY Co.,Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20191010

Address after: 650011 No. 63 East extension Road, Yunnan, Kunming

Patentee after: Yunnan Power Grid Corporation

Address before: Suzhou City, Jiangsu province 215000 Suzhou Industrial Park Loufeng District Yang Fu Road No. 60

Co-patentee before: Yunnan Power Grid Corporation

Patentee before: SUZHOU RUIYING TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right