CN103195194B - Mounting method of glass curtain wall with vertical-hidden frames and horizontal-exposed frames - Google Patents

Mounting method of glass curtain wall with vertical-hidden frames and horizontal-exposed frames Download PDF

Info

Publication number
CN103195194B
CN103195194B CN201310101767.9A CN201310101767A CN103195194B CN 103195194 B CN103195194 B CN 103195194B CN 201310101767 A CN201310101767 A CN 201310101767A CN 103195194 B CN103195194 B CN 103195194B
Authority
CN
China
Prior art keywords
glass
curtain wall
hidden
mounting
sash system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310101767.9A
Other languages
Chinese (zh)
Other versions
CN103195194A (en
Inventor
廖健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHENGDU SUNSHINE ALUMINIUM CO LTD
Original Assignee
CHENGDU SUNSHINE ALUMINIUM CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU SUNSHINE ALUMINIUM CO LTD filed Critical CHENGDU SUNSHINE ALUMINIUM CO LTD
Priority to CN201310101767.9A priority Critical patent/CN103195194B/en
Publication of CN103195194A publication Critical patent/CN103195194A/en
Application granted granted Critical
Publication of CN103195194B publication Critical patent/CN103195194B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Securing Of Glass Panes Or The Like (AREA)
  • Special Wing (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention discloses a mounting method of a glass curtain wall with vertical-hidden frames and horizontal-exposed frames. Two methods are included. Method A: glass is fixedly pasted on a glass frame, then the glass frame is mounted on a bar system to mount the glass curtain wall; and the method A includes the steps of producing the glass frame, pasting the glass, mounting the bar system, mounting the glass frame, reinforcing cross edges and sealing. Method B: the glass is mounted in inlay slots at the top and bottom of the bar system directly to install the glass curtain wall; and the method B includes the steps of mounting the bar system, fixing the glass, adjusting the glass, pouring glue and sealing. According to the mounting method, a silicone sealant is adopted to paste, fix and closely combine the glass, the glass frame and the aluminum alloy bar system, fireproof thermal-insulating materials are filled between the glass curtain wall and a building main structure, and the inner and outer surfaces of the glass curtain wall are connected and sealed through a sealant; and the glass curtain wall is rainproof, windproof, fireproof, thermal-insulated and high in safety and reliability.

Description

The mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke
Technical field
The present invention relates to a kind of mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke.
Background technology
Curtain wall is rolled into metal edge frame with aluminium alloys or other light-weight metals, is prefabricated into module, is then fixedly mounted in the braced structures of building external, the building external structure of formation or decorating structure together with functional glass.Curtain wall forms the continuous body of wall of smooth large area at building external, due to be coated glass, so can't see from the outside after glass, the Large Surface Mirror effect that whole body of wall is formed can only be seen, form a zingy large mirror, the scenery of sky and surrounding environment is mirrored wherein, during light change, colors of image is bright-colored, with countless changes, novelty very attractive in appearance, under the reflection of light, indoor are not by strong illumination, vision is soft, it is by the architectural aesthetics, building function, the factors such as building structure are organically united, it is the notable feature in modernism highrise building epoch.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art, there is provided a kind of employing silicone sealant that glass is pasted fixing compact with instrument bezel and aluminium alloys sash system to be combined, fill with fire-retardant heat-insulation material between curtain wall and major structure of construction, with fluid sealant, curtain wall surfaces externally and internally is connected sealing, flashing, wind proofing is prevented fires, heat-insulation and heat-preservation, the mounting method of the not hidden curtain wall of the perpendicular hidden horizontal stroke that safety reliability is strong.
The object of the invention is to be achieved through the following technical solutions: the mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke, it comprises following two kinds of modes:
Method A: by glass is fixedly pasted onto on instrument bezel, then instrument bezel is arranged on sash system upper type mounting glass curtain wall, it comprises the following steps:
S1: make instrument bezel: aluminium alloy cast ingot is whittled into pole, pole homogenising preheat temperature 560 DEG C is kept 4.5h, and then extrude on extruding unit, extrusion speed is 0.2 ~ 0.4m/s, recipient temperature is 410 ~ 430 DEG C, and making two vertical edges has installation groove;
S2: sticking glass: by structure glue, coated glass being pasted onto two vertical edges has on the instrument bezel of installation groove, and installs rubber strip in glass surrounding, rubber strip length should than frame notch long 1.5% to 2%;
S3: install sash system: install aluminium alloys sash system at building external;
S4: mounting glass frame: be fixed on the montant of aluminium alloys sash system by instrument bezel vertical edge stator, ensures that conplane glass flatness will control within 3mm, and the width error of filleting also controls within 2mm;
S5: reinforce horizontal edge: be fixed on by upper and lower for glass widthwise edge in the embedding groove of aluminium alloys sash body groove beam;
S6: sealing: with the gap between fire-retardant heat-insulation material filling curtain wall surrounding and agent structure, and with fluid sealant, surfaces externally and internally is connected sealing;
Method B: glass is directly installed in the embedding groove of sash system top and bottom, then fill in the mode mounting glass curtain wall of the seam dead slot between glass and sash system montant by structure glue, it comprises the following steps:
S1: install sash system: install aluminium alloys sash system at building external, wherein sash system top and bottom are provided with embedding groove;
S2: fixing glass: coated glass is fixed in the embedding groove of aluminium alloys sash frame body sectional material top and bottom;
S3: adjustment glass: adjustment glass surface, ensure that conplane glass flatness will control within 3mm, the width error of filleting also controls within 2mm;
S4: encapsulating: fill in glass and the surperficial seam dead slot formed of montant by structure glue;
S5: sealing: with the gap between fire-retardant heat-insulation material filling curtain wall surrounding and agent structure, and with fluid sealant, surfaces externally and internally is connected sealing.
Described structure glue is silicone sealant, and described fire-retardant heat-insulation material is glass wool, and described fluid sealant is silicone sealant.
The invention has the beneficial effects as follows:
The present invention adopts silicone sealant that glass is pasted fixing compact with instrument bezel and aluminium alloys sash system and is combined, and safety factor is high; Fill with fire-retardant heat-insulation material between curtain wall and major structure of construction, the good safety factor high reliability of fireproof insulation effect is strong; With fluid sealant, curtain wall surfaces externally and internally is connected sealing, water proof wind proof, and further increase the safety reliability of curtain wall, secure is reliable more to make curtain wall.
Detailed description of the invention
Below in conjunction with specific embodiment, technical scheme of the present invention is described in further detail:
[embodiment 1]
The mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke, it comprises the following steps:
S1: make instrument bezel: aluminium alloy cast ingot is whittled into pole, keeps 4.5h by pole homogenising preheat temperature 560 DEG C, and then extrude on extruding unit, extrusion speed is 0.2m/s, and recipient temperature is 430 DEG C, and making two vertical edges has installation groove;
S2: sticking glass: with silicone sealant, coated glass being pasted onto two vertical edges has on the instrument bezel of installation groove, and installs rubber strip in glass surrounding, rubber strip length should than frame notch long 1.5%;
S3: install sash system: install aluminium alloys sash system at building external;
S4: mounting glass frame: be fixed on the montant of aluminium alloys sash system by instrument bezel vertical edge stator, ensures that conplane glass flatness will control within 3mm, and the width error of filleting also controls within 2mm;
S5: reinforce horizontal edge: be fixed on by upper and lower for glass widthwise edge in the embedding groove of aluminium alloys sash body groove beam;
S6: sealing: with the gap between fire-retardant heat-insulation material glass wool filling curtain wall surrounding and agent structure, and with silicone sealant, surfaces externally and internally is connected sealing.
[embodiment 2]
The mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke, it comprises the following steps:
S1: make instrument bezel: aluminium alloy cast ingot is whittled into pole, keeps 4.5h by pole homogenising preheat temperature 560 DEG C, and then extrude on extruding unit, extrusion speed is 0.4m/s, and recipient temperature is 410 DEG C, and making two vertical edges has installation groove;
S2: sticking glass: with silicone sealant, coated glass being pasted onto two vertical edges has on the instrument bezel of installation groove, and installs rubber strip in glass surrounding, rubber strip length should than frame notch long 2%;
S3: install sash system: install aluminium alloys sash system at building external;
S4: mounting glass frame: be fixed on the montant of aluminium alloys sash system by instrument bezel vertical edge stator, ensures that conplane glass flatness will control within 3mm, and the width error of filleting also controls within 2mm;
S5: reinforce horizontal edge: be fixed on by upper and lower for glass widthwise edge in the embedding groove of aluminium alloys sash body groove beam;
S6: sealing: with the gap between fire-retardant heat-insulation material glass wool filling curtain wall surrounding and agent structure, and with silicone sealant, surfaces externally and internally is connected sealing.
[embodiment 3]
The mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke, it comprises the following steps:
S1: make instrument bezel: aluminium alloy cast ingot is whittled into pole, keeps 4.5h by pole homogenising preheat temperature 560 DEG C, and then extrude on extruding unit, extrusion speed is 0.3m/s, and recipient temperature is 420 DEG C, and making two vertical edges has installation groove;
S2: sticking glass: with silicone sealant, coated glass being pasted onto two vertical edges has on the instrument bezel of installation groove, and installs rubber strip in glass surrounding, rubber strip length should than frame notch long 1.8%;
S3: install sash system: install aluminium alloys sash system at building external;
S4: mounting glass frame: be fixed on the montant of aluminium alloys sash system by instrument bezel vertical edge stator, ensures that conplane glass flatness will control within 3mm, and the width error of filleting also controls within 2mm;
S5: reinforce horizontal edge: be fixed on by upper and lower for glass widthwise edge in the embedding groove of aluminium alloys sash body groove beam;
S6: sealing: with the gap between fire-retardant heat-insulation material glass wool filling curtain wall surrounding and agent structure, and with silicone sealant, surfaces externally and internally is connected sealing.
[embodiment 4]
The mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke, it comprises the following steps:
S1: install sash system: install aluminium alloys sash system at building external, wherein sash system top and bottom are provided with embedding groove;
S2: fixing glass: coated glass is fixed in the embedding groove of aluminium alloys sash frame body sectional material top and bottom;
S3: adjustment glass: adjustment glass surface, ensure that conplane glass flatness will control within 3mm, the width error of filleting also controls within 2mm;
S4: encapsulating: fill in glass and the surperficial seam dead slot formed of montant with silicone sealant;
S5: sealing: with the gap between fire-retardant heat-insulation material glass wool filling curtain wall surrounding and agent structure, and with silicone sealant, surfaces externally and internally is connected sealing.

Claims (3)

1. the mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke, is characterized in that: it comprises following two kinds of modes:
Method A: by glass is fixedly pasted onto on instrument bezel, then instrument bezel is arranged on sash system upper type mounting glass curtain wall, it comprises the following steps:
S1: make instrument bezel: aluminium alloy cast ingot is whittled into pole, pole homogenising preheat temperature 560 DEG C is kept 4.5h, and then extrude on extruding unit, extrusion speed is 0.2 ~ 0.4m/s, recipient temperature is 410 ~ 430 DEG C, and making two vertical edges has installation groove;
S2: sticking glass: by structure glue, coated glass being pasted onto two vertical edges has on the instrument bezel of installation groove, and installs rubber strip in glass surrounding, rubber strip length should than frame notch long 1.5% to 2%;
S3: install sash system: install aluminium alloys sash system at building external;
S4: mounting glass frame: be fixed on the montant of aluminium alloys sash system by instrument bezel vertical edge stator, ensures that conplane glass flatness will control within 3mm, and the width error of filleting also controls within 2mm;
S5: reinforce horizontal edge: be fixed on by upper and lower for glass widthwise edge in the embedding groove of aluminium alloys sash body groove beam;
S6: sealing: with the gap between fire-retardant heat-insulation material filling curtain wall surrounding and agent structure, and with fluid sealant, surfaces externally and internally is connected sealing;
Method B: glass is directly installed in the embedding groove of sash system top and bottom, then fill in the mode mounting glass curtain wall of the seam dead slot between glass and sash system montant by structure glue, it comprises the following steps:
S1: install sash system: install aluminium alloys sash system at building external, wherein sash system top and bottom are provided with embedding groove;
S2: fixing glass: coated glass is fixed in the embedding groove of aluminium alloys sash frame body sectional material top and bottom;
S3: adjustment glass: adjustment glass surface, ensure that conplane glass flatness will control within 3mm, the width error of filleting also controls within 2mm;
S4: encapsulating: fill in glass and the surperficial seam dead slot formed of montant by structure glue;
S5: sealing: with the gap between fire-retardant heat-insulation material filling curtain wall surrounding and agent structure, and with fluid sealant, surfaces externally and internally is connected sealing; Described fire-retardant heat-insulation material is glass wool, and the good safety factor high reliability of fireproof insulation effect is strong.
2. the mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke according to claim 1, is characterized in that: described structure glue is silicone sealant.
3. the mounting method of the perpendicular not hidden curtain wall of hidden horizontal stroke according to claim 1, is characterized in that: described fluid sealant is silicone sealant.
CN201310101767.9A 2013-03-27 2013-03-27 Mounting method of glass curtain wall with vertical-hidden frames and horizontal-exposed frames Active CN103195194B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310101767.9A CN103195194B (en) 2013-03-27 2013-03-27 Mounting method of glass curtain wall with vertical-hidden frames and horizontal-exposed frames

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310101767.9A CN103195194B (en) 2013-03-27 2013-03-27 Mounting method of glass curtain wall with vertical-hidden frames and horizontal-exposed frames

Publications (2)

Publication Number Publication Date
CN103195194A CN103195194A (en) 2013-07-10
CN103195194B true CN103195194B (en) 2015-07-22

Family

ID=48717997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310101767.9A Active CN103195194B (en) 2013-03-27 2013-03-27 Mounting method of glass curtain wall with vertical-hidden frames and horizontal-exposed frames

Country Status (1)

Country Link
CN (1) CN103195194B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58135269A (en) * 1981-10-15 1983-08-11 ヨ−ゼフ・ガルトナ−・アンド・カンパニ− Method of installing curtain wall and wall element used therein
CN2367735Y (en) * 1999-04-28 2000-03-08 谢增厚 Aluminium alloy curtain wall
CN2389944Y (en) * 1998-09-25 2000-08-02 郑永康 Glass curtain wall structure
JP2001066137A (en) * 1999-08-30 2001-03-16 Taisei Corp Positioning method of curtain wall
CN101392569A (en) * 2008-11-10 2009-03-25 广东金刚幕墙工程有限公司 Angle adjustable corner section bar system for curtain wall
CN201377137Y (en) * 2009-06-12 2010-01-06 北京东方泰洋装饰工程有限公司 Hidden frame curtain wall
CN101936073A (en) * 2010-08-24 2011-01-05 龙信建设集团有限公司 Construction method of combined hidden frame curtain wall of glass and corrugated aluminum sheet
CN202164725U (en) * 2011-07-07 2012-03-14 北京江河幕墙股份有限公司 Steel keel glass curtain wall system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58135269A (en) * 1981-10-15 1983-08-11 ヨ−ゼフ・ガルトナ−・アンド・カンパニ− Method of installing curtain wall and wall element used therein
CN2389944Y (en) * 1998-09-25 2000-08-02 郑永康 Glass curtain wall structure
CN2367735Y (en) * 1999-04-28 2000-03-08 谢增厚 Aluminium alloy curtain wall
JP2001066137A (en) * 1999-08-30 2001-03-16 Taisei Corp Positioning method of curtain wall
CN101392569A (en) * 2008-11-10 2009-03-25 广东金刚幕墙工程有限公司 Angle adjustable corner section bar system for curtain wall
CN201377137Y (en) * 2009-06-12 2010-01-06 北京东方泰洋装饰工程有限公司 Hidden frame curtain wall
CN101936073A (en) * 2010-08-24 2011-01-05 龙信建设集团有限公司 Construction method of combined hidden frame curtain wall of glass and corrugated aluminum sheet
CN202164725U (en) * 2011-07-07 2012-03-14 北京江河幕墙股份有限公司 Steel keel glass curtain wall system

Also Published As

Publication number Publication date
CN103195194A (en) 2013-07-10

Similar Documents

Publication Publication Date Title
CN202689269U (en) Glass curtain wall suitable for exposed frame, hidden frame and half hidden frame
CN209799101U (en) Perforated aluminum plate and aluminum alloy window combined energy-saving decoration integrated curtain wall
CN203891277U (en) Steel structure solar glass curtain wall
CN207048135U (en) The general expansion joint system of curtain wall indoor and outdoor
CN204001315U (en) One aluminium Baogang curtain wall profiles structure
CN102182329A (en) Aluminum sheathed wood sunlight house
CN205314321U (en) Full -color some accuse formula video photoelectricity glass frame system
CN106760090A (en) A kind of perpendicular bright horizontal hidden curtain wall of the adjustable transverse direction ornamental strip of band
CN202081662U (en) Aluminium cladding wooden solar house
CN104499662A (en) Continuously and gradually varied free-form surface aluminum alloy plate sun-shading system
CN103195194B (en) Mounting method of glass curtain wall with vertical-hidden frames and horizontal-exposed frames
CN103206034B (en) Method for mounting transversely hidden and vertically unhidden glass curtain wall
CN205369625U (en) Hidden frame curtain wall with LED lamp area
CN204551839U (en) A kind of curtain wall with ornamental glass rib
CN209703722U (en) Glass curtain wall expanded joint structure
CN209620302U (en) A kind of layering type frame curtain wall
CN207568016U (en) A kind of U-shaped glass curtain wall system of achievable super-span
CN204081826U (en) A kind of aluminum alloy fixed window
CN108049534B (en) Energy-saving and environment-friendly type public building horizontal and vertical hidden glass curtain wall
CN103628601B (en) A kind of mounting method of full concealed frame glass curtain wall
CN203412498U (en) Built-in electric louver system of existing glass curtain wall
CN202359944U (en) Vertically-hinged inward-tilt window structure of exposed frame glass curtain wall
CN214302461U (en) Heat-insulating full-exposed frame glass curtain wall structure
CN203669162U (en) Exposed-frame glass curtain wall
CN209308234U (en) A kind of fixed structure of bright frame glass curtain wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant