CN103175405A - Reforming furnace with central burner nozzle - Google Patents

Reforming furnace with central burner nozzle Download PDF

Info

Publication number
CN103175405A
CN103175405A CN2011104547748A CN201110454774A CN103175405A CN 103175405 A CN103175405 A CN 103175405A CN 2011104547748 A CN2011104547748 A CN 2011104547748A CN 201110454774 A CN201110454774 A CN 201110454774A CN 103175405 A CN103175405 A CN 103175405A
Authority
CN
China
Prior art keywords
burner
burner nozzle
cooling water
magnetic valve
reforming furnace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011104547748A
Other languages
Chinese (zh)
Other versions
CN103175405B (en
Inventor
于晓亮
陈杰
祁宏图
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Aerospace Yuanzheng Fluid Control Co Ltd
Original Assignee
Xian Aerospace Yuanzheng Fluid Control Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Aerospace Yuanzheng Fluid Control Co Ltd filed Critical Xian Aerospace Yuanzheng Fluid Control Co Ltd
Priority to CN201110454774.8A priority Critical patent/CN103175405B/en
Publication of CN103175405A publication Critical patent/CN103175405A/en
Application granted granted Critical
Publication of CN103175405B publication Critical patent/CN103175405B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a reforming furnace with a central burner nozzle. The reforming furnace with the central burner nozzle comprises the central burner nozzle, a furnace head part, a combustion part, a catalytic conversion part and a converter outlet part. The central metal burner nozzle comprises an oxygen-steam inlet pipeline a, a cooling water inlet channel b and a cooling water outlet channel, wherein the cooling water inlet channel b and the cooling water outlet channel are arranged on a pipe wall of the oxygen-steam inlet pipeline. The reforming furnace with the central burner nozzle solves the technical problem that an existing reforming furnace with the metal burner nozzle is easily damaged by combustion, avoids partial combustion caused by uneven mixing of fuel and an oxidizing agent in an original reforming furnace, overcomes the defects that a high temperature region of the original reforming furnace is located around the furnace wall and then prolongs the service life. Under the normal operation, the service life of the reforming furnace with the central burner nozzle is 24-36 months, thereby greatly saving production and operation costs of enterprises.

Description

A kind of reforming furnace with central burner
Technical field
The present invention relates to a kind of metal burner reburner.
Background technology
Existing metal burner has the flow field, uniform temperature fields is reasonable, the advantage of long service life etc.Yet the operation of the efficient stable of burner needs continual the flowing of cooling water to take away 800~1400 ℃ of heat exchange amounts to burner in reburner, guarantees the normal operation of burner.But existing metal burner nozzle cooling water system can not be transported to cooling water in the metal burner when emergency episode occurring and cause power failure, and causes metal burner scaling loss.So, how to design the cooling water system that satisfies the cooling use of metal burner, safe and efficient stable operation in the future plays an important role for the metal burner.
Summary of the invention
In order to solve existing metal burner reburner burner easily by the technical problem of scaling loss, the invention provides a kind of reforming furnace with central burner.
Technical solution of the present invention:
A kind of central metal burner reburner, comprising central burner nozzle, burner part, combustion parts, catalytic conversion part and converter exit portion, described central metal burner comprises oxygen+steam inlet pipeline a, is arranged on oxygen+cooling water inlet passage b and coolant outlet passage c on the pipeline a tube wall of steam inlet; Its special character in: also comprise cooling water system, described cooling water system comprises the circulating water emergent water system of unifying, and described circulation comprises atmospheric water tank, pump group, import orifice plate, burner inlet channel, burner outlet conduit, the outlet orifice plate that connects successively and consist of water loop; Described emergent water system comprises high pressure nitrogen storage tank, nitrogen buffer tank, high-pressure water tank, high-pressure water inlet magnetic valve, High Pressure Drain magnetic valve; Described nitrogen buffer tank communicates with high-pressure water tank, and described high-pressure water tank communicates with the burner inlet channel after by the high-pressure water inlet magnetic valve, and described burner outlet conduit and High Pressure Drain magnetic valve join, the outlet ground connection ditch of described High Pressure Drain magnetic valve; The flowmeter of described outlet orifice plate and high-pressure water inlet electromagnetic valve linking.
The present invention has advantages of:
Central metal burner ejection of the present invention is effectively organized the oven gas in reburner (natural gas)+steam flow field up to oxygen+steam of 100-400m/s, has avoided former reburner fuel and oxidant to mix uneven and inclined to one side burning that cause; The former reburner high-temperature region drawback around in the furnace wall has been avoided in the high-temperature region of central metal burner of the present invention on center line in stove, and then improved reburner service life, under normal operating, the central metal burner reburner life-span is 24-36 month, has greatly saved the costs of production and operation of enterprise.
2, the present invention adopts the high-pressure water tank of nitrogen driving to provide emergency cooling water to burner, when gasification furnace cuts off the power supply for some reason, atmospheric water tank stop supplies cooling water, because high-pressure water inlet magnetic valve and High Pressure Drain magnetic valve are normally closed solenoid valve, all open this moment, and the water in high-pressure water tank under high pressure nitrogen drives, enters trench after high-pressure water inlet magnetic valve, import orifice plate, burner, outlet orifice plate and High Pressure Drain magnetic valve, guarantee the emergent cooling of burner, prevented the improper scaling loss of burner.
Description of drawings
Fig. 1 is the central metal burner structure of reborner schematic diagram that forms after the inventive method transformation;
In Fig. 1: 1,6-oven gas+steam inlet; 2-chuck coolant outlet; 3, the former oxygen+steam inlet of 7-; The 4-combustion space; 5-central metal burner; 8-corundum flame-proof sphere; The 9-corundum castable.
Fig. 2 is the pipeline structure schematic diagram of cooling water system of the present invention;
In Fig. 2: 11-high-pressure water inlet magnetic valve, 21-High Pressure Drain magnetic valve, 13-exports orifice plate, 14-import orifice plate, FC-flow control valve, PT-orifice plate flow transmitter, PG-Pressure gauge, PT-pressure transmitter, TT-temperature transmitter, LT-liquid level gauge.
The specific embodiment
Central metal burner reburner of the present invention comprises central burner nozzle, burner part, combustion parts, catalytic conversion part and converter exit portion, and furnace head divides and comprises the oven gas+steam inlet that is arranged on the furnace wall; Central burner nozzle partly comprises metal burner mounting flange d1 and the d2 that is arranged on body of heater end socket e centerline, the central metal burner that extend into the burner part from metal burner mounting flange centre bore; The central metal burner comprises oxygen+steam inlet pipeline a, is arranged on oxygen+cooling water inlet passage b and coolant outlet passage c on the pipeline a tube wall of steam inlet.
Metal burner nozzle cooling water system of the present invention comprises circulation under meet an urgent need under accident condition water system and normal condition.Circulation comprises atmospheric water tank, pump group, import orifice plate, burner inlet channel, burner outlet conduit, outlet orifice plate, the pressure release orifice plate group that connects successively and consist of water loop, and pressure release orifice plate group comprises a plurality of pressure release orifice plates; Emergent water system comprises high pressure nitrogen storage tank, nitrogen buffer tank, high-pressure water tank, high-pressure water inlet magnetic valve, High Pressure Drain magnetic valve; Nitrogen buffer tank communicates with high-pressure water tank, and high-pressure water tank communicates with the burner inlet channel after by the high-pressure water inlet magnetic valve, and burner outlet conduit and High Pressure Drain magnetic valve join, the outlet ground connection ditch of High Pressure Drain magnetic valve; Flowmeter and high-pressure water inlet magnetic valve and the High Pressure Drain electromagnetic valve linking of outlet orifice plate.High-pressure water inlet magnetic valve and High Pressure Drain magnetic valve are normally closed solenoid valve.
The normal condition circulation utilizes atmospheric water tank, pressure release orifice plate group, water pump, flow control valve etc. to guarantee the cooling water flow of at least 4 tons/hours of burners.
Under accident condition, emergent water system utilizes high pressure nitrogen storage tank and high-pressure water tank to guarantee the burner cooling water flow of at least 30 minutes, and then has sufficient time to stop, and reduces temperature in reburner.

Claims (1)

1. central metal burner reburner, comprising central burner nozzle, burner part, combustion parts, catalytic conversion part and converter exit portion, described central metal burner comprises oxygen+steam inlet pipeline a, is arranged on oxygen+cooling water inlet passage b and coolant outlet passage c on the pipeline a tube wall of steam inlet; It is characterized in that: also comprise cooling water system, described cooling water system comprises the circulating water emergent water system of unifying, and described circulation comprises atmospheric water tank, pump group, import orifice plate, burner inlet channel, burner outlet conduit, the outlet orifice plate that connects successively and consist of water loop; Described emergent water system comprises high pressure nitrogen storage tank, nitrogen buffer tank, high-pressure water tank, high-pressure water inlet magnetic valve, High Pressure Drain magnetic valve; Described nitrogen buffer tank communicates with high-pressure water tank, and described high-pressure water tank communicates with the burner inlet channel after by the high-pressure water inlet magnetic valve, and described burner outlet conduit and High Pressure Drain magnetic valve join, the outlet ground connection ditch of described High Pressure Drain magnetic valve; The flowmeter of described outlet orifice plate and high-pressure water inlet electromagnetic valve linking.
CN201110454774.8A 2011-12-20 2011-12-20 A kind of reforming furnace with central burner Expired - Fee Related CN103175405B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110454774.8A CN103175405B (en) 2011-12-20 2011-12-20 A kind of reforming furnace with central burner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110454774.8A CN103175405B (en) 2011-12-20 2011-12-20 A kind of reforming furnace with central burner

Publications (2)

Publication Number Publication Date
CN103175405A true CN103175405A (en) 2013-06-26
CN103175405B CN103175405B (en) 2016-09-14

Family

ID=48635442

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110454774.8A Expired - Fee Related CN103175405B (en) 2011-12-20 2011-12-20 A kind of reforming furnace with central burner

Country Status (1)

Country Link
CN (1) CN103175405B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0225523A (en) * 1988-07-14 1990-01-29 Kawasaki Steel Corp Direct heating type continuous heat-treatment furnace for metal strip
CN2245612Y (en) * 1995-11-23 1997-01-22 重庆市化工研究院 Hydrocarbon section thermal conversion furnace
CN101003358A (en) * 2006-12-12 2007-07-25 华东理工大学 Multi nozzle of gasification furnace by using feed in brei state or powder state
CN200999199Y (en) * 2007-01-09 2008-01-02 太原新唐科技有限公司 Metal burner for converter
CN202329212U (en) * 2011-12-20 2012-07-11 西安航天远征流体控制股份有限公司 Reforming furnace with central burner nozzle

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0225523A (en) * 1988-07-14 1990-01-29 Kawasaki Steel Corp Direct heating type continuous heat-treatment furnace for metal strip
CN2245612Y (en) * 1995-11-23 1997-01-22 重庆市化工研究院 Hydrocarbon section thermal conversion furnace
CN101003358A (en) * 2006-12-12 2007-07-25 华东理工大学 Multi nozzle of gasification furnace by using feed in brei state or powder state
CN200999199Y (en) * 2007-01-09 2008-01-02 太原新唐科技有限公司 Metal burner for converter
CN202329212U (en) * 2011-12-20 2012-07-11 西安航天远征流体控制股份有限公司 Reforming furnace with central burner nozzle

Also Published As

Publication number Publication date
CN103175405B (en) 2016-09-14

Similar Documents

Publication Publication Date Title
CN202329212U (en) Reforming furnace with central burner nozzle
CN102425794B (en) Burner nozzle cooling water system
CN202329213U (en) Conversion oven capable of realizing emergency cooling
CN103175405A (en) Reforming furnace with central burner nozzle
CN103175404A (en) Reforming furnace capable of achieving emergent cooling
CN103175404B (en) The reburner of emergent cooling can be realized
CN202415142U (en) Water cooling system for metal nozzle of reforming furnace
JP4962956B2 (en) Nuclear heat utilization equipment
CN206280969U (en) Force the three-dimensional mixing chamber of full premix
AU2011373507A1 (en) Burner nozzle and coal gasifier
CN107208885B (en) A kind of burner and related cooling circuit for synthesis gas production
CN103172020B (en) Cooling water system for reburner metal burner
CN103196227B (en) Conduction oil furnace capable of preventing conduction oil from coking in furnace tube and using method
JP6171893B2 (en) Coal fired biomass biomass burning method and equipment
CN202382247U (en) Burner cooling water system
CN103172020A (en) Cooling water system for reforming furnace metal burner
CN202719626U (en) External sighting type hearth flame monitoring structure
CN111607687A (en) Energy-saving device and method for improving steam quality of steelmaking RH refining furnace
CN212179206U (en) Semi-coke boiler
CN110671817A (en) Mine wellhead anti-freezing air heating device based on methanol nano catalytic oxidation
CN219588983U (en) Oxyhydrogen gas supply device suitable for kiln
CN204417438U (en) A kind of triple channel cross jet gasification burner tip device
CN204648657U (en) A kind of volumetric gas water heater of high efficiency low-loss
CN213416385U (en) Novel special water of combustion engine reforms transform equipment
CN219735304U (en) Cooling air system of micro-oil burner of coal-fired power plant

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914

Termination date: 20161220