CN103139885B - Mobile Poewr control method and device based on VAMOS pairing user - Google Patents

Mobile Poewr control method and device based on VAMOS pairing user Download PDF

Info

Publication number
CN103139885B
CN103139885B CN201110386552.7A CN201110386552A CN103139885B CN 103139885 B CN103139885 B CN 103139885B CN 201110386552 A CN201110386552 A CN 201110386552A CN 103139885 B CN103139885 B CN 103139885B
Authority
CN
China
Prior art keywords
power
power grade
user
ascending
grade
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110386552.7A
Other languages
Chinese (zh)
Other versions
CN103139885A (en
Inventor
龚婷
张维
庄建伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Zhongxing Communication Technology Service Co., Ltd.
Original Assignee
ZTE Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZTE Corp filed Critical ZTE Corp
Priority to CN201110386552.7A priority Critical patent/CN103139885B/en
Publication of CN103139885A publication Critical patent/CN103139885A/en
Application granted granted Critical
Publication of CN103139885B publication Critical patent/CN103139885B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Mobile Radio Communication Systems (AREA)

Abstract

A kind of mobile Poewr control method based on VAMOS pairing user of disclosure and device, the method comprises the following steps: VAMOS pairing user each carries out uplink power control judgement, it is determined that VAMOS power adjusts mode, it is thus achieved that ascending power grade;Judge whether the ascending power grade of two pairing users meets sub-channel power and limit than SCPIR;If so, then the ascending power grade that two match user is issued to mobile platform;If it is not, then according to the ascending power grade obtained, carry out corresponding VAMOS power adjustment.Present invention achieves the purpose of the ascending power grade that the VAMOS pairing user how finding power difference excessive is suitable for, when not increasing frequency resource, successfully pairing user is multiplexed on the same time slot of same frequency, the voice capacity making each ambulatory transceiver letter platform and whole system is improved, and improves frequency spectrum resource utilization rate.

Description

Mobile Poewr control method and device based on VAMOS pairing user
Technical field
The present invention relates to mobile platform power control field, particularly relate to a kind of mobile the Poewr control method of user and device of matching based on VAMOS (VoiceServicesOverAdaptiveMulti-userChannelsOnOneSlot carries the voice service of adaptive multiple subscriber channel on one time slot).
Background technology
Along with being continuously increased of wireless telecommunication system number of users, speech business is consequently increased, huge pressure is brought to existing network, growing GSM (GlobalSystemForMobileCommunications, global system for mobile communications) user is more and more prominent to the contradiction between requirement and the limited frequency utilization resource of existing network capacity.
In order to alleviate the frequency spectrum pressure of GSM, improve frequency spectrum resource utilization rate, it is proposed that VAMOS technology.VAMOS technology is at a TDMA (TimeDivisionMultipleAccess, time division multiple acess) two users are multiplexed on the same time slot of same frequency in frame, thus the availability of frequency spectrum being promoted one times when not increasing frequency resource, the voice capacity of each base transceiver station and whole system is made to be improved.Two users sharing a time slot are called pairing user.Adopting the mobile phone that VAMOS technology participates in multiplexing pairing user can be the VAMOS mobile phone of traditional non-SAIC (SingleAntennaInterferenceCancellation, single antenna interference cancellation) mobile phone, SAIC mobile phone or new definition.
Owing to there is SCPIR (SubChannelsPowerImbalanceRatio between two pairing user power grades, sub-channel power ratio) constraint, therefore, VAMOS two matches can exist the problem that power difference is excessive between user, thus being unfavorable for that same time slot matches.
Summary of the invention
The main purpose of the present invention is to provide a kind of mobile Poewr control method based on VAMOS pairing user, it is intended to reaches to find out the purpose of the ascending power grade of applicable two pairing users' pairings, improves frequency spectrum resource utilization rate.
The invention provides a kind of mobile Poewr control method based on VAMOS pairing user, comprise the following steps:
VAMOS pairing user each carries out uplink power control judgement, it is determined that ascending power adjusts step-length, it is thus achieved that ascending power grade;
Judge whether the ascending power grade of two pairing users meets SCPIR restriction;
If so, then the ascending power grade that two match user is issued to mobile platform;
If it is not, then according to the ascending power grade obtained, carry out corresponding VAMOS power adjustment.
Preferably, described according to the ascending power grade obtained, the step carrying out corresponding VAMOS power adjustment includes:
If wherein a user is in the user that power increases or subtracts state, and its ascending power grade is MS1;Another user is the user being in power invariant state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1new meeting SCPIR restriction mated with MS2 in [MS1, MS1old] scope;MS1old is in power increase or subtract the ascending power grade that the user of state is currently in use;
If so, then the ascending power grade MS1new after ascending power grade MS2 and VAMOS power control is handed down to mobile platform.
Preferably, described according to the ascending power grade obtained, the step carrying out corresponding VAMOS power adjustment includes:
If wherein a user is in power to increase the strong user of state, and its ascending power grade is MS1;Another user is in power to increase the weak user of state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1 ' meeting SCPIR restriction mated with MS2 in [MS1, MS1old] scope;
If there is the ascending power grade MS1 ' meeting SCPIR restriction mated with MS2, then the ascending power grade MS1 ' after ascending power grade MS2 and VAMOS power control is handed down to mobile platform;
If being absent from the ascending power grade MS1 ' meeting SCPIR restriction mated with MS2, then judging [MS1, preset minimum power level] exist in scope mate with MS2 meet the SCPIR ascending power grade MS1 limited " time, the ascending power grade MS1 after ascending power grade MS2 and VAMOS power control " is handed down to mobile platform;
If being absent from the ascending power grade MS1 meeting SCPIR restriction mated with MS2 "; the ascending power grade then progressively adjusting weak user is MS2 '; and again find in [MS2 '; MS2old] scope; and with the ascending power grade MS1 ' or MS1 of MS2 ' pairing ", then it is handed down to mobile platform;Wherein MS2old is the ascending power grade that weak user is currently in use.
Preferably, described according to the ascending power grade obtained, the step carrying out corresponding VAMOS power adjustment includes:
If wherein a user is in power to subtract the strong user of state, and its ascending power grade is MS1;Another user is in power to subtract the weak user of state, and its ascending power grade is MS2;
With up power grade MS1 for adjusting benchmark, it is judged that whether there is the ascending power grade MS2new meeting SCPIR restriction mated with MS1 in [MS2, preset minimum power level] scope;
If so, then the ascending power grade MS2new after ascending power grade MS1 and VAMOS power control is handed down to mobile platform.
Preferably, described according to the ascending power grade obtained, the step carrying out corresponding VAMOS power adjustment includes:
If wherein a user is in power to subtract the user of state, and its ascending power grade is MS1;Another user is in power to increase the user of state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1 ' meeting SCPIR restriction mated with MS2 in [MS1, preset minimum power level] scope;
If so, then the ascending power grade MS1 ' after ascending power grade MS2 and VAMOS power control is handed down to mobile platform;
If not, then at [MS2old, MS2] scope interior increase ascending power grade MS2 to MS2 ', and with MS2 ' for benchmark, judging [MS1, preset minimum power level] exist in scope mate with MS2 ' meet the SCPIR ascending power grade MS1 limited " time, ascending power grade MS2 ' and the MS1 after VAMOS power control " is handed down to mobile platform;MS2old is in power to increase the up ascending power grade that the user of state is currently in use.
Preferably, described VAMOS matches and also includes before the step that user each carries out uplink power control judgement:
VAMOS pairing user power controls initial synchronisation.
Present invention also offers a kind of mobile output control device based on VAMOS pairing user, including with lower module:
Power judging module: each carry out uplink power control judgement for VAMOS pairing user, it is determined that ascending power adjusts step-length, it is thus achieved that ascending power grade;
Power control module: for according to the ascending power grade obtained, it is judged that whether the ascending power grade of two pairing users meets SCPIR restriction;
If so, then the ascending power grade that two match user is issued to mobile platform;
If it is not, then according to the ascending power grade obtained, carry out corresponding VAMOS power and control.
Preferably, described power control module specifically for:
If wherein a user is in the user that power increases or subtracts state, and its ascending power grade is MS1;Another user is the user being in power invariant state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1new meeting SCPIR restriction mated with MS2 in [MS1, MS1old] scope;MS1old is in power increase or subtract the ascending power grade that the user of state is currently in use;
If so, then the ascending power grade MS1new after ascending power grade MS2 and VAMOS power control is handed down to mobile platform.
Preferably, described power control module is additionally operable to:
If wherein a user is in power to increase the strong user of state, and its ascending power grade is MS1;Another user is in power to increase the weak user of state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1 ' meeting SCPIR restriction mated with MS2 in [MS1, MS1old] scope;
If there is the ascending power grade MS1 ' meeting SCPIR restriction mated with MS2, then the ascending power grade MS1 ' after ascending power grade MS2 and VAMOS power control is handed down to mobile platform;
If being absent from the ascending power grade MS1 ' meeting SCPIR restriction mated with MS2, then judging [MS1, preset minimum power level] exist in scope mate with MS2 meet the SCPIR ascending power grade MS1 limited " time, the ascending power grade MS1 after ascending power grade MS2 and VAMOS power control " is handed down to mobile platform;
If being absent from the ascending power grade MS1 meeting SCPIR restriction mated with MS2 "; then progressively adjust the ascending power grade MS2 ' of weak user, and again find in [MS2 ', MS2old] scope; with the ascending power grade MS1 ' or MS1 of MS2 ' pairing ", then it is handed down to mobile platform;Wherein MS2old is the ascending power grade that weak user is currently in use.
Preferably, described power control module is additionally operable to:
If wherein a user is in power to subtract the strong user of state, and its ascending power grade is MS1;Another user is in power to subtract the weak user of state, and its ascending power grade is MS2;
With up power grade MS1 for adjusting benchmark, it is judged that whether there is the ascending power grade MS2new meeting SCPIR restriction mated with MS1 in [MS2, preset minimum power level] scope;
If so, then the ascending power grade MS2new after ascending power grade MS1 and VAMOS power control is handed down to mobile platform.
Preferably, described power control module is additionally operable to:
If wherein a user is in power to subtract the user of state, and its ascending power grade is MS1;Another user is in power to increase the user of state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1 ' meeting SCPIR restriction mated with MS2 in [MS1, preset minimum power level] scope;
If so, then ascending power grade MS2 and the MS1 ' after VAMOS power control is handed down to mobile platform;
If not, then at [MS2old, MS2] scope interior increase ascending power grade MS2 to MS2 ', and with MS2 ' for benchmark, judging [MS1, preset minimum power level] exist in scope mate with MS2 ' meet the SCPIR ascending power grade MS1 limited " time, ascending power grade MS2 ' and the MS1 after VAMOS power control " is handed down to mobile platform;MS2old is in power to increase the up ascending power grade that the user of state is currently in use.
Preferably, described mobile the output control device based on VAMOS pairing user, it is characterised in that also include:
Initial synchronization module: control initial synchronisation for VAMOS pairing user power.
Mobile the Poewr control method based on VAMOS pairing user disclosed by the invention and device, it is achieved that the purpose of the ascending power grade that the VAMOS pairing user how finding power difference excessive is suitable for, improve frequency spectrum resource utilization rate.
Accompanying drawing explanation
Fig. 1 is the present invention mobile the Poewr control method first embodiment schematic flow sheet based on VAMOS pairing user;
Fig. 2 is in the present invention mobile the Poewr control method first embodiment based on VAMOS pairing user, when a user power increases or subtracts, another user power is constant, and the schematic flow sheet that VAMOS power controls;
Fig. 3 is in the present invention mobile the Poewr control method first embodiment based on VAMOS pairing user, when two users are power increasing, and the schematic flow sheet that VAMOS power controls;
Fig. 4 is the present invention based on VAMOS match user mobile Poewr control method first embodiment in, two users are power when subtracting, the schematic flow sheet that VAMOS power controls;
Fig. 5 is in the present invention mobile the Poewr control method first embodiment based on VAMOS pairing user, when a user power increases, another user power subtracts, and the schematic flow sheet that VAMOS power controls;
Fig. 6 is the present invention mobile Poewr control method the second embodiment schematic flow sheet based on VAMOS pairing user;
Fig. 7 is that in the present invention mobile Poewr control method the second embodiment based on VAMOS pairing user, VAMOS power controls the schematic flow sheet of initial synchronisation;
Fig. 8 is the present invention mobile the output control device first embodiment structural representation based on VAMOS pairing user;
Fig. 9 is the present invention mobile output control device the second example structure schematic diagram based on VAMOS pairing user.
The realization of the object of the invention, functional characteristics and advantage will in conjunction with the embodiments, are described further with reference to accompanying drawing.
Detailed description of the invention
Technical scheme is further illustrated below in conjunction with Figure of description and specific embodiment.Should be appreciated that specific embodiment described herein is only in order to explain the present invention, is not intended to limit the present invention.
Fig. 1 is the present invention mobile the Poewr control method first embodiment schematic flow sheet based on VAMOS pairing user;The present invention includes step based on mobile the Poewr control method of VAMOS pairing user:
Step S01, VAMOS pairing user each carries out uplink power control judgement, it is determined that ascending power adjusts step-length, it is thus achieved that ascending power grade;
After a time slot is re-used, two users each carry out uplink power control judgement, calculate power adjustment step size, it is thus achieved that power grade;Adjust step-length to arrange according to concrete condition, in embodiments of the present invention, it is preferred to 2dB.The ascending power court verdict of each user can have state three kinds different: power remains unchanged, power increases and power subtracts.
Step S02, judge two pairing users ascending power grades whether meet SCPIR restriction;
According to the ascending power grade obtained, it is judged that whether uplink receiving level MS1level and the MS2level of two pairing users meets SCPIR restriction:
| MS1level (dB)-MS2level (dB) | <=| SCPIR (dB) |;
Wherein, uplink receiving level MS1level, according to ascending power grade MS1, carries out estimating and obtaining;Uplink receiving level MS2level, according to ascending power grade MS2, carries out estimating and obtaining.
If so, step S03 is then performed;
If it is not, then perform step S04;
Step S03, by two match users ascending power grade be issued to mobile platform;
Step S04, according to obtain ascending power grade, carry out corresponding VAMOS power control.
Owing to the ascending power court verdict of each user can have state three kinds different: power remains unchanged, power increases and power subtracts;Owing to there is SCPIR constraint between two pairing user uplink power grades, except the combinations of states that two pairing user uplink power all remain unchanged, other power ratings combination of two pairing users all would be likely to occur the problem that power difference is excessive;For the situation that the power difference of two pairing other power ratings of user combination existence is excessive, correspondingly four kinds of various combination modes of four kinds of modes difference correspondence two pairing user power states that VAMOS power controls:
Mode one: wherein a user uplink power increases or subtracts, and another user uplink power remains unchanged;
Mode two: two users are ascending power and increase;
Mode three: two users are ascending power and subtract;
Mode four: wherein a user uplink power increases, and another user uplink power subtracts.
The present invention is by judging whether the ascending power grades of two pairing users meet SCPIR and limit and carry out corresponding VAMOS power according to different situations and control this technical scheme, solve the problem that two pairing user power have big difference, reach the beneficial effect of the ascending power grade finding out applicable two pairing user's pairings.
If wherein a user is in the user that power increases or subtracts state, and its ascending power grade is MS1;Another user is the user being in power invariant state, and its ascending power grade is MS2;
Increase with reference to a user power in mobile the Poewr control method first embodiment of Fig. 2, Fig. 2 to be the present invention based on VAMOS match user or subtract, another user power constant time the schematic flow sheet that controls of VAMOS power, step S04 farther includes:
Step S041a, with up power grade MS2 for adjust benchmark, it is judged that whether exist in [MS1, MS1old] scope mate with ascending power grade MS2 meet SCPIR limit ascending power grade MS1new;If so, step S041b is then performed;If it is not, then perform step S041c;
Specifically, first judge whether ascending power grade MS1 and MS2 meets SCPIR restriction, be that ascending power grade MS1 and MS2 is issued to mobile platform.Otherwise, with up power grade MS2 for adjusting benchmark, and to adjust in units of step-length, by ascending power grade MS1, progressively adjusting ascending power grade is MS1 ', and judge whether the ascending power grade MS1 ' adjusted and ascending power grade MS2 meets SCPIR restriction, until ascending power grade MS1 ' is equal to ascending power grade MS1old;If the ascending power grade MS1 ' after adjusting meets SCPIR restriction, then perform step S041b;If the ascending power grade MS1 ' after adjusting is unsatisfactory for, then perform step S041c.Wherein, MS1old is the ascending power grade that power grade is in that the user of variable condition is currently in use, and adjusting step-length can be arranged according to concrete condition, in embodiments of the present invention, it is preferred to 2dB;Judge whether uplink receiving level MS1newlevel and uplink receiving level MS2level meets SCPIR restriction:
| MS1newlevel (dB)-MS2level (dB) | <=| SCPIR (dB) |;
Wherein, uplink receiving level MS1newlevel, according to ascending power grade MS1new, carries out estimating and obtaining;Uplink receiving level MS2level, according to ascending power grade MS2, carries out estimating and obtaining.
Here it should be noted that, if a user is in the state that power increases, another user is constant, then incrementally increase ascending power grade MS1 ', and judge whether the ascending power grade MS1 ' adjusted and ascending power grade MS2 meets SCPIR restriction, until ascending power grade MS1 ' is equal to ascending power grade MS1old;If a user is in the state that power subtracts, another user is constant, then gradually reduce ascending power grade MS1 ', and judge whether the ascending power grade MS1 ' adjusted and ascending power grade MS2 meets SCPIR restriction, until ascending power grade MS1 ' is equal to ascending power grade MS1old.
Step S041b, the ascending power grade MS1new after ascending power grade MS2 and VAMOS power control is handed down to mobile platform;
Step S041c, it is not operated, keeps existing power grade.
If wherein a user is in power to increase the strong user of state, and its ascending power grade is MS1;Another user is in power to increase the weak user of state, and its ascending power grade is MS2;
Weak user in two users can judge according to concrete condition, it is judged that the priority of weak user is: first compare uplink receiving level, if two users' incoming level is consistent;Then judge uplink receiving quality, if both the same;Then arbitrarily select.In embodiments of the present invention, it is preferable that MS2 is the ascending power grade of weak user;
Being that the present invention is, based on two users in mobile the Poewr control method first embodiment of VAMOS pairing user, the schematic flow sheet that when power increases, VAMOS power controls with reference to Fig. 3, Fig. 3, step S04 farther includes:
Step S042a, with up power grade MS2 for adjust benchmark, it is judged that whether exist in [MS1, MS1old] scope mate with MS2 meet SCPIR limit ascending power grade MS1 ';If so, step S042b is then performed;If it is not, then perform step S042c;
Specifically, first judge whether ascending power grade MS1 and MS2 meets SCPIR restriction, it is that ascending power grade MS1 and MS2 is issued to mobile platform, otherwise, with up power grade MS2 for adjusting benchmark, and to adjust in units of step-length, by ascending power grade MS1, incrementally increasing ascending power grade is MS1 ', and judge whether the ascending power grade MS1 ' adjusted and ascending power grade MS2 meets SCPIR restriction, until ascending power grade MS1 ' is equal to ascending power grade MS1old;If the ascending power grade MS1 ' after adjusting meets SCPIR restriction, then perform step S42b;If the ascending power grade MS1 ' after adjusting is unsatisfactory for SCPIR restriction, then perform step S042c.Wherein, MS1old is the ascending power grade that another user is currently in use, and adjusting step-length can be arranged according to concrete condition, in embodiments of the present invention, it is preferred to 2dB;Judge whether uplink receiving level MS1 ' level and uplink receiving level MS2level meets SCPIR restriction:
| MS1 ' level (dB)-MS2level (dB) | <=| SCPIR (dB) |;
Wherein, uplink receiving level MS1 ' level, according to ascending power grade MS1 ', carries out estimating and obtaining;Uplink receiving level MS2level, according to ascending power grade MS2, carries out estimating and obtaining.
Step S042b, the ascending power grade MS1 ' after ascending power grade MS2 and VAMOS power control is handed down to mobile platform;
Step S042c, in [MS1, preset minimum power level] scope, it may be judged whether exist mate with MS2 meet SCPIR restriction ascending power grade MS1 ";If so, step S042d is then performed;If it is not, then perform step S042e;
Specifically, with up power grade MS2 for adjusting benchmark, and to adjust in units of step-length, by ascending power grade MS1, gradually reduce ascending power grade MS1 "; and judge the ascending power grade MS1 adjusted " with whether ascending power grade MS2 meets SCPIR restriction, until ascending power grade MS1 is " equal to preset minimum power level;If the ascending power grade MS1 adjusted " meets SCPIR restriction, then performs step S042d;If the ascending power grade MS1 adjusted " is unsatisfactory for SCPIR restriction, then performs step S042e.Preset minimum power level is the minimum power level that backstage is arranged, it is possible to arrange according to concrete condition, in embodiments of the present invention, it is preferred to 5;Adjust step-length to arrange according to concrete condition, in embodiments of the present invention, it is preferred to 2dB;Judge uplink receiving level MS1 " whether level and uplink receiving level MS2level meets SCPIR restriction:
| MS1 " level (dB)-MS2level (dB) | <=| SCPIR (dB) |;
Wherein, uplink receiving level MS1 " level is according to ascending power grade MS1 ", carry out estimating and obtaining;Uplink receiving level MS2level, according to ascending power grade MS2, carries out estimating and obtaining.
Step S042d, the ascending power grade MS1 after ascending power grade MS2 and VAMOS power control " is handed down to mobile platform;
Step S042e, the ascending power grade progressively adjusting weak user are MS2 ', and judge that whether MS2 ' is equal to MS2old;If then returning and performing step S042a;Then perform step S042f if not;
According to adjusting step-length, by the ascending power grade MS2 of weak user, the ascending power grade incrementally increasing weak user is MS2 ', and returns execution step S042a, until ascending power grade MS2 ' is equal to ascending power grade MS2old.Wherein, MS2old is the ascending power grade that weak user is currently in use, and adjusting step-length can be arranged according to concrete condition.
Step S042f, it is not operated, keeps existing power grade.
If wherein a user is in power to subtract the strong user of state, and its ascending power grade is MS1;Another user is in power to subtract the weak user of state, and its ascending power grade is MS2.
In embodiments of the present invention, it is preferable that MS1 is the ascending power grade of strong user, MS2 is the ascending power grade of weak user;
Being that the present invention is, based on two users in mobile the Poewr control method first embodiment of VAMOS pairing user, the schematic flow sheet that when power subtracts, VAMOS power controls with reference to Fig. 4, Fig. 4, step S04 farther includes:
Step S043a, with up power grade MS1 for adjust benchmark, it is judged that whether exist in [MS2, preset minimum power level] scope mate with MS1 meet SCPIR limit ascending power grade MS2new;If so, step S043b is then performed;If it is not, then perform step S043c;
Specifically, first judge whether ascending power grade MS1 and MS2 meets SCPIR restriction, be that ascending power grade MS1 and MS2 is issued to mobile platform.Otherwise, with up power grade MS1 for adjusting benchmark, and to adjust in units of step-length, by ascending power grade MS2, gradually reducing ascending power grade is MS2 ', and judge whether the ascending power grade MS2 ' adjusted and ascending power grade meet SCPIR restriction, until ascending power grade MS2new is equal to preset minimum power level;If the ascending power grade MS2 ' after adjusting meets SCPIR restriction, then perform step S043b;If the ascending power grade MS2 ' after adjusting is unsatisfactory for, then perform step S043c.Preset minimum power level can be arranged according to concrete condition, in embodiments of the present invention, it is preferred to 5;Adjust step-length to arrange according to concrete condition, in embodiments of the present invention, it is preferred to 2dB;Judge whether uplink receiving level MS2newlevel and uplink receiving level MS1level meets SCPIR restriction:
| MS1level (dB)-MS2newlevel (dB) | <=| SCPIR (dB) |;
Wherein, uplink receiving level MS1level, according to ascending power grade MS1, carries out estimating and obtaining;Uplink receiving level MS2newlevel, according to ascending power grade MS2new, carries out estimating and obtaining.
Step S043b, the ascending power grade MS2new after ascending power grade MS1 and VAMOS power control is handed down to mobile platform;
Step S043c, it is not operated, keeps existing power grade.
If wherein a user is in power to subtract the user of state, and its ascending power grade is MS1;Another user is in power to increase the user of state, and its ascending power grade is MS2.
Being the schematic flow sheet that the present invention controls based on VAMOS power when a user power increasing, another user power subtract in mobile the Poewr control method first embodiment of VAMOS pairing user with reference to Fig. 5, Fig. 5, step S04 farther includes:
Step S044a, with up power grade MS2 for adjust benchmark, it is judged that whether exist in [MS1, preset minimum power level] scope mate with MS2 meet SCPIR limit ascending power grade MS1 ';If so, step S044b is then performed;If it is not, then perform step S044c;
Specifically, first judge whether ascending power grade MS1 and MS2 meets SCPIR restriction, be that ascending power grade MS1 and MS2 is issued to mobile platform.Otherwise, with up power grade MS2 for adjusting benchmark, and to adjust in units of step-length, by ascending power grade MS1, gradually reducing ascending power grade is MS1 ', and judge whether the ascending power grade MS1 ' adjusted and ascending power grade MS2 meets SCPIR restriction, until ascending power grade MS1 ' is equal to preset minimum power level;If the ascending power grade MS1 ' after adjusting meets SCPIR restriction, then perform step S044b, if the ascending power grade MS1 ' after adjusting is unsatisfactory for SCPIR restriction, then perform step S044c.Preset minimum power level can be arranged according to concrete condition, in embodiments of the present invention, it is preferred to 5;Adjust step-length to arrange according to concrete condition, in embodiments of the present invention, it is preferred to 2dB;Judge whether uplink receiving level MS1 ' level and uplink receiving level MS2level meets SCPIR restriction:
| MS1 ' level (dB)-MS2level (dB) | <=| SCPIR (dB) |;
Wherein, uplink receiving level MS1 ' level, according to ascending power grade MS1 ', carries out estimating and obtaining;Uplink receiving level MS2level, according to ascending power grade MS2, carries out estimating and obtaining.
Step S044b, the ascending power grade MS1 ' after ascending power grade MS2 and VAMOS power control is handed down to mobile platform;
Step S044c, at [MS2old, MS2] incrementally increase ascending power grade MS2 to MS2 ' in scope, and with MS2 ' for benchmark, it is judged that whether there is the ascending power grade MS1 meeting SCPIR restriction mated with MS2 ' in [MS1, preset minimum power level] scope ";If so, step S044d is then performed;If it is not, then perform step S044e;
At [MS2old, MS2] incrementally increase ascending power grade MS2 to MS2 ' in scope, until ascending power grade MS2 ' is equal to ascending power grade MS2old, MS2old is in power to increase the ascending power grade that the user of state is currently in use, and adjusting step-length can be arranged according to concrete condition.With MS2 ' for benchmark, judging in [MS1, preset minimum power level] scope, whether there is the ascending power grade MS1 meeting SCPIR restriction mated with MS2 ' ":
| MS1 " level (dB)-MS2 ' level (dB) | <=| SCPIR (dB) |;
Wherein, uplink receiving level MS1 " level is according to ascending power grade MS1 ", carry out estimating and obtaining;Uplink receiving level MS2 ' level, according to ascending power grade MS2 ', carries out estimating and obtaining.
Step S044d, ascending power grade MS2 ' and the MS1 after VAMOS power control " is handed down to mobile platform;
Step S044e, it is not operated, keeps existing power grade.
Being the present invention mobile Poewr control method the second embodiment schematic flow sheet based on VAMOS pairing user with reference to Fig. 6, Fig. 6, on the basis of above-described embodiment, the present embodiment further comprised the steps of: before step S01
Step S05, VAMOS pairing user power controls initial synchronisation;
Owing to the mobility of VAMOS pairing user itself and the polytropy of residing wireless signal are inconsistent, also can not estimate;And pairing user is that the independent wireless environment according to self carries out power control judgement, calculates power adjustment step size, obtains ascending power grade, adjudicates duration due to power control and there will be situation about causing different in size, it is easy to make power adjustment that mistake to occur.
VAMOS matches user power and controls initial synchronisation and can obtain the up-to-date power judgement of two pairing users simultaneously, then carries out the power adjustment between two users, has reached to reduce power and has adjusted error probability, realizes pairing user power and control the beneficial effect of synchronicity.
Being that the present invention controls the schematic flow sheet of initial synchronisation based on VAMOS power in mobile Poewr control method second embodiment of VAMOS pairing user with reference to Fig. 7, Fig. 7, VAMOS pairing user power controls initial synchronisation and farther includes:
Step S051, judge current time slots whether multiplexing;If so, step S052 is then performed;If it is not, then perform step S053;
Base station is after Channel Activation or when receiving measurement report, all needs to judge current time slots whether multiplexing;
Step S052, judge whether VAMOS match user;If so, step S054 is then performed;If it is not, then perform step S055;
Step S053, carry out common power control;
If step S054, VAMOS pairing user initially matches, then remove the related data for uplink power control that the two user preserves, keep power control synchronization;Put flag bit simultaneously.
Step S055, VAMOS pairing user each carries out uplink power control judgement, it is determined that ascending power adjusts step-length, it is thus achieved that ascending power grade.
Being the present invention mobile the output control device first embodiment structural representation based on VAMOS pairing user with reference to Fig. 8, Fig. 8, the present invention includes based on mobile the output control device of VAMOS pairing user:
Power judging module 01, each carries out uplink power control judgement for VAMOS pairing user, it is determined that ascending power adjusts step-length, it is thus achieved that ascending power grade;
Power control module 02, for according to the ascending power grade obtained, it is judged that whether the ascending power grade of two pairing users meets SCPIR restriction;If so, then the ascending power grade that two match user is issued to mobile platform;If it is not, then according to the ascending power grade obtained, carry out corresponding VAMOS power and control.
When there is VAMOS user and matching, in power judging module 01, VAMOS pairing user each carries out uplink power control judgement, it is determined that ascending power adjusts step-length, it is thus achieved that ascending power grade;According to power control court verdict, power control module 02 judges whether the ascending power grade of the two user meets SCPIR restriction.If meeting SCPIR restriction, then directly it is handed down to mobile platform;If being unsatisfactory for SCPIR restriction, the power control module 02 different conditions according to the concrete up power grade of two users, different control models is adopted to find the power adjustment direction meeting each user and be suitable for the ascending power grade of two pairing user's pairings.
Owing to the ascending power court verdict of each user can have state three kinds different: power remains unchanged, power increases and power subtracts;Owing to there is SCPIR constraint between two pairing user uplink power grades, except the combinations of states that two pairing user uplink power all remain unchanged, other power ratings combination of two pairing users all would be likely to occur the problem that power difference is excessive;For the situation that the power difference of two pairing other power ratings of user combination existence is excessive, correspondingly four kinds of various combination modes of four kinds of modes difference correspondence two pairing user power states that VAMOS power controls:
Mode one: wherein a user uplink power increases or subtracts, and another user uplink power remains unchanged;
Mode two: two users are ascending power and increase;
Mode three: two users are ascending power and subtract;
Mode four: wherein a user uplink power increases, and another user uplink power subtracts.
For four kinds of various combination modes of two pairing user power states, power control module 02 is to there being VAMOS power control mode four kinds different;Four kinds of different modes that VAMOS power controls have described its concrete enforcement step in embodiment above, do not repeat them here.
The present invention can select different power control modes according to the different capacity state of pairing user based on mobile the output control device of VAMOS pairing user, has reached to find out the beneficial effect of the ascending power grade being suitable for pairing user's pairing.
Being the present invention mobile output control device the second example structure schematic diagram based on VAMOS pairing user with reference to Fig. 9, Fig. 9, the present invention also includes based on mobile the output control device of VAMOS pairing user:
Initial synchronization module 03, controls initial synchronisation for VAMOS pairing user power;
The initial module 03 that controls is when base station receives measurement report or after the channel of base station is activated, it is judged that whether current time slots exists VAMOS user's pairing;If time slot exists users multiplexing, and is initial pairing, then remove the related data for uplink power control that the two user preserves, keep power control synchronization, put flag bit simultaneously;If current time slots is absent from users multiplexing, then carry out common power control.
Initially control module 03 by VAMOS pairing user power is controlled initial synchronisation, reached minimizing pairing user power and adjusted the beneficial effect of error probability, maintenance pairing user power control synchronicity.
The foregoing is only the preferred embodiments of the present invention; not thereby its scope of the claims is limited; every equivalent structure utilizing description of the present invention and accompanying drawing content to make or equivalence flow process conversion; directly or indirectly it is used in other relevant technical fields, all in like manner includes in the scope of patent protection of the present invention.

Claims (12)

1. a mobile Poewr control method based on VAMOS pairing user, it is characterised in that comprise the following steps:
The voice service VAMOS pairing user carrying adaptive multiple subscriber channel on one time slot each carries out uplink power control judgement, it is determined that ascending power adjusts step-length, it is thus achieved that ascending power grade;
Judge whether the uplink receiving level corresponding to ascending power grade of two pairing users meets sub-channel power and limit than SCPIR;
If so, then the ascending power grade that two match user is issued to mobile platform;
If it is not, then according to the ascending power grade obtained, carry out corresponding VAMOS power adjustment.
2. mobile the Poewr control method based on VAMOS pairing user according to claim 1, it is characterised in that described according to the ascending power grade obtained, the step carrying out corresponding VAMOS power adjustment includes:
If wherein a user is in the user that power increases or subtracts state, and its ascending power grade is MS1;Another user is the user being in power invariant state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1new meeting SCPIR restriction mated with MS2 in [MS1, MS1old] scope;MS1old is in power increase or subtract the ascending power grade that the user of state is currently in use;
If so, then the ascending power grade MS1new after ascending power grade MS2 and VAMOS power control is handed down to mobile platform.
3. mobile the Poewr control method based on VAMOS pairing user according to claim 1, it is characterised in that described according to the ascending power grade obtained, the step carrying out corresponding VAMOS power adjustment includes:
If wherein a user is in power to increase the strong user of state, and its ascending power grade is MS1;Another user is in power to increase the weak user of state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1' meeting SCPIR restriction mated with MS2 in [MS1, MS1old] scope;
If there is the ascending power grade MS1' meeting SCPIR restriction mated with MS2, then the ascending power grade MS1' after ascending power grade MS2 and VAMOS power control is handed down to mobile platform;
If being absent from the ascending power grade MS1' meeting SCPIR restriction mated with MS2, then judging [MS1, preset minimum power level] exist in scope mate with MS2 meet the SCPIR ascending power grade MS1 limited " time, the ascending power grade MS1 after ascending power grade MS2 and VAMOS power control " is handed down to mobile platform;
If the ascending power grade MS1 meeting SCPIR restriction being absent from mating with MS2 "; the ascending power grade then progressively adjusting weak user is MS2'; again find in existences [MS2', MS2old] scope and with the MS2' ascending power grade MS1' matched or MS1 ", be then handed down to mobile platform.
4. mobile the Poewr control method based on VAMOS pairing user according to claim 1, it is characterised in that described according to the ascending power grade obtained, the step carrying out corresponding VAMOS power adjustment includes:
If wherein a user is in power to subtract the strong user of state, and its ascending power grade is MS1;Another user is in power to subtract the weak user of state, and its ascending power grade is MS2;
With up power grade MS1 for adjusting benchmark, it is judged that whether there is the ascending power grade MS2new meeting SCPIR restriction mated with MS1 in [MS2, preset minimum power level] scope;
If so, then the ascending power grade MS2new after ascending power grade MS1 and VAMOS power control is handed down to mobile platform.
5. mobile the Poewr control method based on VAMOS pairing user according to claim 1, it is characterised in that described according to the ascending power grade obtained, the step carrying out corresponding VAMOS power adjustment includes:
If wherein a user is in power to subtract the user of state, and its ascending power grade is MS1;Another user is in power to increase the user of state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1' meeting SCPIR restriction mated with MS2 in [MS1, preset minimum power level] scope;
If so, then ascending power grade MS2 and the MS1' after VAMOS power control is handed down to mobile platform;
If not, then at [MS2old, MS2] scope interior increase ascending power grade MS2 to MS2', and with MS2' for benchmark, judge [MS1, preset minimum power level] exist in scope mate with MS2' meet the SCPIR ascending power grade MS1 limited " time, ascending power grade MS2' and the MS1 after VAMOS power control " is handed down to mobile platform;MS2old is in power to increase the ascending power grade that the user of state is currently in use.
6. mobile the Poewr control method matching user based on VAMOS according to any one of claim 1 to 5, it is characterised in that described VAMOS matches and also includes before the step that user each carries out uplink power control judgement:
VAMOS pairing user power controls initial synchronisation.
7. a mobile output control device based on VAMOS pairing user, it is characterised in that include with lower module:
Power judging module: each carry out uplink power control judgement for VAMOS pairing user, it is determined that ascending power adjusts step-length, it is thus achieved that ascending power grade;
Power control module: for according to the ascending power grade obtained, it is judged that whether the uplink receiving level that the ascending power grade of two pairing users is corresponding meets SCPIR restriction;If so, then the ascending power grade that two match user is issued to mobile platform;If it is not, then according to the ascending power grade obtained, carry out corresponding VAMOS power and control.
8. according to claim 7 based on VAMOS match user mobile output control device, it is characterised in that described power control module specifically for:
If wherein a user is in the user that power increases or subtracts state, and its ascending power grade is MS1;Another user is the user being in power invariant state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1new meeting SCPIR restriction mated with MS2 in [MS1, MS1old] scope;MS1old is in power increase or subtract the ascending power grade that the user of state is currently in use;
If so, then the ascending power grade MS1new after ascending power grade MS2 and VAMOS power control is handed down to mobile platform.
9. mobile the output control device based on VAMOS pairing user according to claim 7, it is characterised in that described power control module is additionally operable to:
If wherein a user is in power to increase the strong user of state, and its ascending power grade is MS1;Another user is in power to increase the weak user of state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1' meeting SCPIR restriction mated with MS2 in [MS1, MS1old] scope;
If there is the ascending power grade MS1' meeting SCPIR restriction mated with MS2, then the ascending power grade MS1' after ascending power grade MS2 and VAMOS power control is handed down to mobile platform;
If being absent from the ascending power grade MS1' meeting SCPIR restriction mated with MS2, then judging [MS1, preset minimum power level] exist in scope mate with MS2 meet the SCPIR ascending power grade MS1 limited " time, the ascending power grade MS1 after ascending power grade MS2 and VAMOS power control " is handed down to mobile platform;
If being absent from the ascending power grade MS1 meeting SCPIR restriction mated with MS2 "; then progressively adjust the ascending power grade MS2' of weak user, and again find in [MS2', MS2old] scope; with the ascending power grade MS1' or MS1 of MS2' pairing ", then it is handed down to mobile platform;Wherein MS2old is the ascending power grade that weak user is currently in use.
10. mobile the output control device based on VAMOS pairing user according to claim 7, it is characterised in that described power control module is additionally operable to:
If wherein a user is in power to subtract the strong user of state, and its ascending power grade is MS1;Another user is in power to subtract the weak user of state, and its ascending power grade is MS2;
With up power grade MS1 for adjusting benchmark, it is judged that whether there is the ascending power grade MS2new meeting SCPIR restriction mated with MS1 in [MS2, preset minimum power level] scope;
If so, then the ascending power grade MS2new after ascending power grade MS1 and VAMOS power control is handed down to mobile platform.
11. mobile the output control device based on VAMOS pairing user according to claim 7, it is characterised in that described power control module is additionally operable to:
If wherein a user is in power to subtract the user of state, and its ascending power grade is MS1;Another user is in power to increase the user of state, and its ascending power grade is MS2;
With up power grade MS2 for adjusting benchmark, it is judged that whether there is the ascending power grade MS1' meeting SCPIR restriction mated with MS2 in [MS1, preset minimum power level] scope;
If so, then ascending power grade MS2 and the MS1' after VAMOS power control is handed down to mobile platform;
If not, then at [MS2old, MS2] scope interior increase ascending power grade MS2 to MS2', and with MS2' for benchmark, judge [MS1, preset minimum power level] exist in scope mate with MS2' meet the SCPIR ascending power grade MS1 limited " time, ascending power grade MS2' and the MS1 after VAMOS power control " is handed down to mobile platform;MS2old is in power to increase the ascending power grade that the user of state is currently in use.
12. mobile the output control device based on VAMOS pairing user according to any one of claim 7 to 11, it is characterised in that also include:
Initial synchronization module: control initial synchronisation for VAMOS pairing user power.
CN201110386552.7A 2011-11-29 2011-11-29 Mobile Poewr control method and device based on VAMOS pairing user Active CN103139885B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110386552.7A CN103139885B (en) 2011-11-29 2011-11-29 Mobile Poewr control method and device based on VAMOS pairing user

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110386552.7A CN103139885B (en) 2011-11-29 2011-11-29 Mobile Poewr control method and device based on VAMOS pairing user

Publications (2)

Publication Number Publication Date
CN103139885A CN103139885A (en) 2013-06-05
CN103139885B true CN103139885B (en) 2016-06-29

Family

ID=48499057

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110386552.7A Active CN103139885B (en) 2011-11-29 2011-11-29 Mobile Poewr control method and device based on VAMOS pairing user

Country Status (1)

Country Link
CN (1) CN103139885B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105282834A (en) * 2014-05-30 2016-01-27 中兴通讯股份有限公司 Power allocation method and device
CN106034353B (en) * 2015-03-10 2019-11-15 中兴通讯股份有限公司 The circule power control method and device of single time slot adaptive multiuser voice service VAMOS user pairing
CN110062412B (en) * 2019-04-09 2022-01-04 惠州Tcl移动通信有限公司 Wireless pairing method, system, storage medium and mobile terminal
CN115221903B (en) * 2022-09-19 2022-11-29 东集技术股份有限公司 RFID (radio frequency identification) reading method and device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010125459A2 (en) * 2009-04-30 2010-11-04 Telefonaktiebolaget L M Ericsson (Publ) Integrated power control and link adaptation
CN102036321A (en) * 2009-09-25 2011-04-27 上海华为技术有限公司 Switching controlling method for multiplexing time slot user and wireless communication base station
CN102143569A (en) * 2010-02-02 2011-08-03 华为技术有限公司 Communication control method, communication control device and communication control system
CN102196545A (en) * 2010-03-10 2011-09-21 中兴通讯股份有限公司 Method and device for controlling downlink power of multi-user multiplexing single-time-slot mobile station

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010125459A2 (en) * 2009-04-30 2010-11-04 Telefonaktiebolaget L M Ericsson (Publ) Integrated power control and link adaptation
CN102036321A (en) * 2009-09-25 2011-04-27 上海华为技术有限公司 Switching controlling method for multiplexing time slot user and wireless communication base station
CN102143569A (en) * 2010-02-02 2011-08-03 华为技术有限公司 Communication control method, communication control device and communication control system
CN102196545A (en) * 2010-03-10 2011-09-21 中兴通讯股份有限公司 Method and device for controlling downlink power of multi-user multiplexing single-time-slot mobile station

Also Published As

Publication number Publication date
CN103139885A (en) 2013-06-05

Similar Documents

Publication Publication Date Title
EP2078343B1 (en) Methods and apparatus related to power control and/or interference management in a mixed wireless communications system supporting wan signaling and peer to peer signaling
CN102647777B (en) Power control method and device
US11252673B2 (en) Communication method, terminal, and network device
CN103582099B (en) A kind of ascending power control method, terminal and base station
US7974352B2 (en) Wireless transmitter, wireless receiver and wireless communication system
US20100062799A1 (en) Mobile communication system, base station, mobile station, and communication control method
US20060084459A1 (en) Outer loop power control of user equipment in wireless communication
KR20100138723A (en) Device and method for controlling uplink transmission power in wireless communication system
KR101411245B1 (en) An uplink power control scheme
CN103596258A (en) A power control method and a base station
CN106455083A (en) D2D communication resource multiplex selection method, base station and terminal
CN101998415A (en) Interference self-avoidance substation site selection method of TD-LTE (TD-SCDMA Long Term Evolution) system
CN103139885B (en) Mobile Poewr control method and device based on VAMOS pairing user
EP2982192A1 (en) Method and apparatus for uplink transmission power control of multi-link connections
KR101593238B1 (en) Apparatus and method for controlling transmission power in wireless communication system
WO2021162613A1 (en) Systems and methods for supporting coherent transmissions in a non-terrestrial network
CN118118991A (en) Uplink power control for multi-slot transport block transmission
CN102577533B (en) Method and device for controlling transmission power of subscriber terminal equipment
US10091735B2 (en) Systems and methods for power control in wireless networks
CN110896559B (en) Reporting method and device of power headroom and computer readable storage medium
WO2018059009A1 (en) Uplink signal quality compensation method and device
CN110868756B (en) Power distribution method and device in NOMA system
CN110476464B (en) Uplink synchronization method and device
CN106028348B (en) The resource allocation methods of phone user are used in a kind of D2D communication system
CN105407536B (en) It is a kind of to communicate the method and device for determining access frequency range based on D2D

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170509

Address after: 518057 Nanshan District high tech Industrial Park, Guangdong,, ZTE A3-01, A3-02

Patentee after: Shenzhen Zhongxing Communication Technology Service Co., Ltd.

Address before: 518057 Nanshan District Guangdong high tech Industrial Park, South Road, science and technology, ZTE building, Ministry of Justice

Patentee before: ZTE Corporation

TR01 Transfer of patent right