CN103050999A - 一种基于agc模式下同型机组负荷调度排序方法 - Google Patents

一种基于agc模式下同型机组负荷调度排序方法 Download PDF

Info

Publication number
CN103050999A
CN103050999A CN2012105428859A CN201210542885A CN103050999A CN 103050999 A CN103050999 A CN 103050999A CN 2012105428859 A CN2012105428859 A CN 2012105428859A CN 201210542885 A CN201210542885 A CN 201210542885A CN 103050999 A CN103050999 A CN 103050999A
Authority
CN
China
Prior art keywords
load
unit
agc
units
mode
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012105428859A
Other languages
English (en)
Inventor
郭江龙
侯双林
姚力强
王兴国
李琼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hebei Electric Power Co Ltd
Hebei Electric Power Construction Adjustment Test Institute
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hebei Electric Power Co Ltd
Hebei Electric Power Construction Adjustment Test Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Hebei Electric Power Co Ltd, Hebei Electric Power Construction Adjustment Test Institute filed Critical State Grid Corp of China SGCC
Priority to CN2012105428859A priority Critical patent/CN103050999A/zh
Publication of CN103050999A publication Critical patent/CN103050999A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Control Of Eletrric Generators (AREA)

Abstract

本发明公开了一种基于AGC模式下同型机组负荷调度排序方法,其包括以下步骤:在电网调度负荷允许的情况下,将所比较的同型机组负荷通过AGC调整成一致;要求将所比较机组的主蒸汽压力定值统一设定,并切换为定压调节模式,维持主蒸汽压力定值一定,在该定压调节方式下,机组调门开度与负荷一一对应;通过AGC增减各机组负荷,使调门开度保持一致;然后进行判断,判断标准:负荷增加大的机组,能耗较低,排序优先。本发明在机组定压调节时,根据AGC微调机组出力增量的变化值,确定同型机组调度排序,判断方法比较简便,容易操作。本发明方法方法简单易行,通过负荷增量变化可直观表征机组能效。

Description

一种基于AGC模式下同型机组负荷调度排序方法
 
技术领域
本发明涉及一种基于AGC模式下同型机组负荷调度排序确定方法,适用于《节能发电调度办法(试行)》中以能耗作为同类电厂调度排序的依据。
背景技术
改革现行发电调度方式,开展节能发电调度,对于减少能源消耗和污染物排放,推动国民经济又快又好发展,具有重要意义。根据国家发展改革委、环保总局、电监会和能源办共同制定的《节能发电调度办法(试行)》规定,同类型火力发电机组按照能耗水平由低到高排序,节能优先。
一般而言,同类型火力发电机组中参数高、容量大的机组能耗要低于参数低、容量小的机组,调度排序优先是没有疑问的。但是对于参数、容量完全一致的机组,如何判断其能耗高低,确定调度排序是非常复杂的,目前并没有简便的判断方法。
发明内容
本发明要解决的技术问题是提供一种判断方便、快捷的基于AGC模式下同型机组负荷调度排序方法。
为解决上述技术问题,本发明所采取的技术方案是:一种基于AGC模式下同型机组负荷调度排序方法,其包括以下步骤:
1) 在电网调度负荷允许的情况下,将所比较的同型机组负荷通过AGC调整成一致;
2) 要求将所比较机组的主蒸汽压力定值统一设定,并切换为定压调节模式,维持主蒸汽压力定值一定,在该定压调节方式下,机组调门开度与负荷一一对应;
3) 通过AGC增减各机组负荷,使调门开度保持一致;
4) 然后进行判断,判断标准:负荷增加大的机组,能耗较低,排序优先。
本发明解决其技术问题的理论依据在于:滑压运行方式下滑压参数与主蒸汽流量具有较强的映射性:机组能耗较低时,同样主蒸汽流量发出的电负荷较高。文中同型机组是指容量、参数等级完全一致的汽轮发电机组;AGC是自动发电控制(Automatic Generation Control)的英文简称。
采用上述技术方案所产生的有益效果在于:本发明在机组定压调节时,根据AGC微调机组出力增量的变化值,确定同型机组调度排序,判断方法比较简便,容易操作。本发明方法方法简单易行,通过负荷增量变化可直观表征机组能效。
具体实施方式
下面结合具体实施方式对本发明作进一步详细的说明。
以网内某3台300MW亚临界机组为例,机组调门控制顺序均为GV1(GV2)→GV3→GV4,即GV1、GV2同时开启,然后是GV3,最后是GV4。AGC调度负荷在150MW时,3台机组压力定值均设定为10.5MPa,此时调门开度分别为:
机组A:GV1、GV2开度34%,GV3、GV4开度均为0;
机组B:GV1、GV2开度27%,GV3、GV4开度均为0;
机组C:GV1、GV2开度31%,GV3、GV4开度均为0;
通过AGC,增加机组B、C出力,使机组B、C的阀门开度与机组A完全一致。调整结果为机组B增加出力2.3MW,机组C增加出力1.5MW。根据评价标准,三台机组能耗由低到高排序为:机组B、机组C、机组A。在节能调度排序中,按照能耗指标优先调度顺序依次为机组B→机组C→机组A。
本发明全面考虑了汽轮机组主、辅设备及各设备连接间压损、温降等对机组能耗的综合影响,效果比较好。

Claims (1)

1.一种基于AGC模式下同型机组负荷调度排序方法,其特征在于:其包括以下步骤:
1) 在电网调度负荷允许的情况下,将所比较的同型机组负荷通过AGC调整成一致;
2) 要求电厂将所比较机组的主蒸汽压力定值统一设定,并切换为定压调节模式,维持主蒸汽压力定值一定,在该定压调节方式下,机组调门开度与负荷一一对应;
3) 通过AGC增减各机组负荷,使调门开度保持一致;
4) 然后进行判断,判断标准:负荷增加大的机组,能耗较低,排序优先。
CN2012105428859A 2012-12-15 2012-12-15 一种基于agc模式下同型机组负荷调度排序方法 Pending CN103050999A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012105428859A CN103050999A (zh) 2012-12-15 2012-12-15 一种基于agc模式下同型机组负荷调度排序方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012105428859A CN103050999A (zh) 2012-12-15 2012-12-15 一种基于agc模式下同型机组负荷调度排序方法

Publications (1)

Publication Number Publication Date
CN103050999A true CN103050999A (zh) 2013-04-17

Family

ID=48063550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012105428859A Pending CN103050999A (zh) 2012-12-15 2012-12-15 一种基于agc模式下同型机组负荷调度排序方法

Country Status (1)

Country Link
CN (1) CN103050999A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104750973A (zh) * 2015-02-28 2015-07-01 河北省电力建设调整试验所 基于数据平滑度函数的火电机组负荷(准)稳态工况聚类算法
CN111668880A (zh) * 2020-06-16 2020-09-15 聊城信源集团有限公司 一种基于区域电网稳控系统的发电机组协调控制装置及方法
CN114151207A (zh) * 2021-11-03 2022-03-08 中山嘉明电力有限公司 一种燃机机组快速变负荷控制方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104750973A (zh) * 2015-02-28 2015-07-01 河北省电力建设调整试验所 基于数据平滑度函数的火电机组负荷(准)稳态工况聚类算法
CN104750973B (zh) * 2015-02-28 2019-01-29 国网河北能源技术服务有限公司 基于数据平滑度函数的机组负荷(准)稳态工况聚类算法
CN111668880A (zh) * 2020-06-16 2020-09-15 聊城信源集团有限公司 一种基于区域电网稳控系统的发电机组协调控制装置及方法
CN111668880B (zh) * 2020-06-16 2024-01-30 聊城信源集团有限公司 一种基于区域电网稳控系统的发电机组协调控制装置及方法
CN114151207A (zh) * 2021-11-03 2022-03-08 中山嘉明电力有限公司 一种燃机机组快速变负荷控制方法
CN114151207B (zh) * 2021-11-03 2023-12-22 中山嘉明电力有限公司 一种燃机机组快速变负荷控制方法

Similar Documents

Publication Publication Date Title
CN105006846A (zh) 一种风电场场站级有功功率优化方法
CN105811472B (zh) 一种基于风电场经济性的有功功率调节方法及系统
CN104467030B (zh) 一种基于风电与火电联合发电的功率分配方法
US11378025B2 (en) Gaseous fuel consuming engine controlling systems
CN102518560B (zh) 一种风电场有功功率调节方法
CN107732941B (zh) 一种电池储能电源参与电网一次调频的控制方法
CN104124714B (zh) 一种分布式电源并网功率控制方法、装置及系统
CN107834564B (zh) 一种微电网系统的小干扰电压稳定性的控制方法
CN106487024B (zh) 风电场无功补偿装置和风电机组的无功置换方法及装置
CN112838603B (zh) 一种风光储抽多源能源agc协调互补控制方法和装置
CN204615404U (zh) 自动功率因数调节的乏风瓦斯/光伏发电系统
CN106773644B (zh) 一种基于供热抽汽量变化的agc控制系统及其方法
CN103354365B (zh) 光伏电站智能功率调节方法
CN105529720A (zh) 动态无功优先调节的风电场电容器自动投切方法
CN103050999A (zh) 一种基于agc模式下同型机组负荷调度排序方法
CN107154645B (zh) 一种余压余热发电机组参与发电厂agc调节的方法
CN107069797B (zh) 一种含双馈型风力发电机的分散式风电场并网方法
CN110716425B (zh) 一种热电联产机组电热协调控制方法
CN103545817B (zh) 一种梯级水电站自动发电控制方法
Ilo et al. Uncontrolled reactive power flow due to local control of distributed generators
CN107273673B (zh) 一种考虑平抑风电波动的空调冷水机组群控方法
CN104300547A (zh) 风电场动态无功补偿装置与风机的无功置换方法
CN204497753U (zh) 一种综合能源的发电系统
CN108155675B (zh) 基于预测信息与运行状态的风电场群功率优化调度方法
Ma et al. Parameter setting of new energy sources generator rapid frequency response in northwest power grid based on multi-frequency regulation resources coordinated controlling

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130417