CN103036404A - Timing sequence design method of dicycle information acquisition and processing execution in turns - Google Patents

Timing sequence design method of dicycle information acquisition and processing execution in turns Download PDF

Info

Publication number
CN103036404A
CN103036404A CN2012105355063A CN201210535506A CN103036404A CN 103036404 A CN103036404 A CN 103036404A CN 2012105355063 A CN2012105355063 A CN 2012105355063A CN 201210535506 A CN201210535506 A CN 201210535506A CN 103036404 A CN103036404 A CN 103036404A
Authority
CN
China
Prior art keywords
information
bridge arm
control unit
period
processing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012105355063A
Other languages
Chinese (zh)
Other versions
CN103036404B (en
Inventor
姜喜瑞
谢敏华
高阳
王韧秋
汤广福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
China EPRI Electric Power Engineering Co Ltd
State Grid Smart Grid Research Institute of SGCC
Original Assignee
DALIAN POWER SUPPLY Co OF LIAONING ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
China EPRI Electric Power Engineering Co Ltd
State Grid Smart Grid Research Institute of SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DALIAN POWER SUPPLY Co OF LIAONING ELECTRIC POWER Co Ltd, State Grid Corp of China SGCC, China EPRI Electric Power Engineering Co Ltd, State Grid Smart Grid Research Institute of SGCC filed Critical DALIAN POWER SUPPLY Co OF LIAONING ELECTRIC POWER Co Ltd
Priority to CN201210535506.3A priority Critical patent/CN103036404B/en
Publication of CN103036404A publication Critical patent/CN103036404A/en
Application granted granted Critical
Publication of CN103036404B publication Critical patent/CN103036404B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Control Of Electrical Variables (AREA)
  • Electrically Driven Valve-Operating Means (AREA)

Abstract

本发明提供一种双周期信息采集与处理轮流执行的时序设计方法,包括以下步骤:采集T1周期内桥臂分段控制单元上送的分段阀信息;在T2周期内对所采集的分段阀信息进行处理和综合排序。本发明中分层分段式的采集处理结构解决了阀基控制设备对大规模子模块信息的采集和处理能力限制的问题,双周期轮流进行采集和处理思想,保证了庞大采集信息和处理的微秒级决策形成;采取双周期实现,采集周期和处理计算周期轮流运行方式,使桥臂汇总控制整体桥臂的电压平衡效果更为宏观合理。

Figure 201210535506

The invention provides a timing design method for double-period information collection and processing in turn, comprising the following steps: collecting segment valve information sent by the bridge arm segment control unit in the T1 cycle; Valve information is processed and comprehensively sorted. The layered and segmented acquisition and processing structure in the present invention solves the problem that the valve base control equipment can limit the collection and processing capacity of large-scale sub-module information, and the idea of collecting and processing in two cycles in turn ensures the efficiency of huge collection of information and processing Microsecond-level decision-making; adopting double-cycle implementation, the acquisition cycle and processing calculation cycle operate in turn, making the voltage balance effect of the bridge arm summary control of the overall bridge arm more macroscopic and reasonable.

Figure 201210535506

Description

The time sequence design method that a kind of binary cycle information gathering and processing are carried out in turn
Technical field
The invention belongs to electric and electronic technical field, be specifically related to a kind of binary cycle information gathering and process the time sequence design method of carrying out in turn.
Background technology
Current, be applied to more and more the fields such as electric power system, locomotive traction, Aero-Space based on the various Power Electronic Circuit of all-controlling power electronics device IGBT.Along with the development of power electronic technology and material, manufacturing process, the through-current capability of IGBT device is also more and more stronger, makes it also obtain important performance space in the direct current transportation field, has directly promoted birth and the development of Technology of HVDC based Voltage Source Converter.Different from traditional high voltage dc transmission technology, the flexible DC power transmission converter has substituted the Thyristors in series converter valve with the high-voltage commutation valve that is made of the IGBT series connection, has formed the flexible direct current converter of voltage-source type.Flexible DC power transmission can be realized powering to remote middle-size and small-size isolated, weak load; Can carry out independent, accurately, meritorious/Reactive Power Control flexibly, improve economy and the stability of system load flow transmission; Direct voltage polarity is constant when trend is reversed, and conveniently consists of the multi-terminal HVDC transmission system; When linking system short-circuit, do not increase the capacity of short circuit of system, be conducive to limiting short-circuit current, stop the fault pervasion of system; Reactive power support and FREQUENCY CONTROL can be provided, be used for the regenerative resources such as wind energy turbine set and the distributed power generation special advantage that is incorporated into the power networks; Behind the electric network fault that links, can provide the black power supply that starts, the fast restoration capabilities behind the quickening electric network fault; The current conversion station floor space greatly reduces with respect to conventional DC.
The abundant performance advantage of Technology of HVDC based Voltage Source Converter has attracted numerous scientific research technical staff to put into relevant research and has put into practice in the work, its flexibly control performance also so that the control guard method of flexible direct current and control protective unit become the study hotspot of flexible direct current technology.In the control based on the flexible direct current of modularization multi-level converter topological structure, be very important link in the whole control protection system to the control protection of converter submodule inside.
Summary of the invention
In order to overcome above-mentioned the deficiencies in the prior art, the invention provides a kind of binary cycle information gathering and process the time sequence design method of carrying out in turn, the acquisition process structure of layer and section formula has solved the problem of valve base control appliance to the acquisition and processing capabilities limits of extensive submodule information, binary cycle carries out acquisition and processing thought in turn, has guaranteed that the Microsecond grade decision-making of huge Information Monitoring and processing forms; Take binary cycle to realize, collection period and process in turn operational mode of computing cycle, the balance of voltage effect that brachium pontis is gathered control whole brachium pontis is more macroscopical reasonable.
In order to realize the foregoing invention purpose, the present invention takes following technical scheme:
A kind of binary cycle information gathering is provided and processes the time sequence design method of carrying out in turn, said method comprising the steps of:
Step 1: gather the sectioning valve information of sending on the brachium pontis segmentation control unit in the T1 cycle;
Step 2: in the cycle sectioning valve information that gathers is processed with integrated ordered at T2.
Described sectioning valve information comprise these all submodules of segmentation voltage and, bypass count, operation information and error protection information.
The described T1 cycle is divided into t1~t2 time period and t2~t3 time period; The described T2 cycle is divided into t3~t4 time period and t4~t5 time period.
Described step 1 may further comprise the steps:
Step 1-1:t1~t2 is in the time period, and the modulation intelligence according to the circulation control unit issues adopts the bridge arm voltage balanced algorithm, forms the modulation voltage information that each brachium pontis segmentation control unit needs, and sends to each brachium pontis segmentation control unit;
Step 1-2:t2~t3 is in the time period, and brachium pontis gathers control unit and gathers respectively the sectioning valve information of sending on each brachium pontis segmentation control unit, guarantees all to gather complete; Arrangement sectioning valve information gathers and uploads the sectioning valve information of whole brachium pontis and control protection information to the circulation control unit.
Brachium pontis gathers control unit by the mode of poll and flag bit mark, gathers the sectioning valve information of sending on each brachium pontis segmentation control unit, guarantees to receive the information that has gathered and does not repeat to receive, and does not accept and believe breath and does not miss.
Described step 2 may further comprise the steps:
Step 2-1:t3~t4 is in the time period, and the modulation intelligence according to the circulation control unit issues adopts the bridge arm voltage balanced algorithm, forms the modulation voltage information that each segmentation control unit of brachium pontis needs, and sends to each brachium pontis segmentation control unit;
Step 2-2:t4~t5 sorted by the average voltage of bubbling method to each brachium pontis segmentation control unit in the time period, and arrangement sectioning valve information, gathered and uploaded the sectioning valve information of whole brachium pontis and control protection information to the circulation control unit.
Described bridge arm voltage balanced algorithm is that the average voltage to whole each segmentation of brachium pontis carries out macro-control, and each segmentation submodule average voltage is consistent as much as possible; Obtain the information that each brachium pontis segmentation control unit current period need to be modulated by the bridge arm voltage balanced algorithm, send to respectively each brachium pontis segmentation control unit.
Compared with prior art, beneficial effect of the present invention is:
1. the acquisition process structure of layer and section formula has solved the problem of valve base control appliance to the acquisition and processing capabilities limits of extensive submodule information, binary cycle carries out acquisition and processing thought in turn, has guaranteed that the Microsecond grade decision-making of huge Information Monitoring and processing forms;
2. take binary cycle to realize, collection period and process in turn operational mode of computing cycle, the balance of voltage effect that brachium pontis is gathered control whole brachium pontis is more macroscopical reasonable;
3. ordered pair switching time, system sequence without any restriction, and have greatly strengthened reliability and the fault tolerant of system to balance of voltage effect and system protection etc. without any impact during binary cycle;
4. in large capacity MMC flexible DC power transmission system, converter valve brachium pontis cascade number is large, and the acquisition process structure of layer and section formula has guaranteed that the Microsecond grade decision-making of huge Information Monitoring and processing forms;
5. brachium pontis gathers control unit the information of voltage of each brachium pontis segmentation control unit is collected, and can't form ordered sequence within the monocycle, and binary cycle carries out acquisition and processing thought in turn, makes that to gather the balance of voltage effect of control whole brachium pontis more macroscopical reasonable.
Description of drawings
Fig. 1 is the modularization multi-level converter topology diagram;
Fig. 2 is that brachium pontis gathers the processing collection calculating of control unit monocycle and processing procedure schematic diagram;
Fig. 3 is that brachium pontis gathers the information gathering of control unit binary cycle and schematic diagram is carried out in processing in turn.
Embodiment
Below in conjunction with accompanying drawing the present invention is described in further detail.
Such as Fig. 1, valve base control appliance structured flowchart as shown in Figure 1, it is processor DSP+ programmable device FPGA that brachium pontis wherein gathers the control unit core, interface comprises the information communication with protocol communication and a plurality of brachium pontis segmentation control units of circulation unit, the valve information of a plurality of brachium pontis segmenting units is unified to gather, adopt the balance of voltage strategy of whole brachium pontis, make whole brachium pontis submodule capacitance voltage balance movement.
Such as Fig. 2, brachium pontis gathers the control unit monocycle and processes collection calculating and processing procedure, and step is as follows,
The t1-t2 time period:
● according to the modulation intelligence that electric current current control unit issues, adopt bridge arm voltage balanced algorithm strategy, form the modulation voltage information that each segmentation control unit of brachium pontis needs, send to each segmentation control unit;
The t2-t3 time period:
● wait for each segmentation control feedback valve information of brachium pontis;
The t3-t4 time period
● gather respectively the valve information of sending in each brachium pontis segmentation that receives, guarantee all to gather to receive
● each bridge arm voltage ordering is processed;
● arrangement valve information, gather the control protection information, upwards send current control unit;
● each segment information arrangement is sent to current control unit;
● brachium pontis gathers control unit and sorts according to the submodule information of voltage that upper each segmentation of cycle brachium pontis issues;
The above t1-t4 time period is one-period T, in one-period, above task is all finished, then the processing time needs to be less than 70% of the whole cycle at least, and 30% free time in whole like this cycle can be satisfied the stability requirement of system's high reliability and the emergency case processing requirements of high fault tolerance.By test as can be known, the length of this time period depends on the processing time of brachium pontis segmentation control unit feeding-back valve information feedback, and segmentation is more, and the time is longer, even the situation that can't be disposed in the cycle may occur.
Such as Fig. 3, the invention provides a kind of binary cycle information gathering and process the time sequence design method of carrying out in turn, said method comprising the steps of:
Step 1: gather the sectioning valve information of sending on the brachium pontis segmentation control unit in the T1 cycle;
Step 2: in the cycle sectioning valve information that gathers is processed with integrated ordered at T2.
Described sectioning valve information comprise these all submodules of segmentation voltage and, bypass count, operation information and error protection information.
The described T1 cycle is divided into t1~t2 time period and t2~t3 time period; The described T2 cycle is divided into t3~t4 time period and t4~t5 time period.
Described step 1 may further comprise the steps:
Step 1-1:t1~t2 is in the time period, and the modulation intelligence according to the circulation control unit issues adopts the bridge arm voltage balanced algorithm, forms the modulation voltage information that each brachium pontis segmentation control unit needs, and sends to each brachium pontis segmentation control unit;
Step 1-2:t2~t3 is in the time period, and brachium pontis gathers control unit and gathers respectively the sectioning valve information of sending on each brachium pontis segmentation control unit, guarantees all to gather complete; Arrangement sectioning valve information gathers and uploads the sectioning valve information of whole brachium pontis and control protection information to the circulation control unit.
Brachium pontis gathers control unit by the mode of poll and flag bit mark, gathers the sectioning valve information of sending on each brachium pontis segmentation control unit, guarantees to receive the information that has gathered and does not repeat to receive, and does not accept and believe breath and does not miss.
Described step 2 may further comprise the steps:
Step 2-1:t3~t4 is in the time period, and the modulation intelligence according to the circulation control unit issues adopts the bridge arm voltage balanced algorithm, forms the modulation voltage information that each segmentation control unit of brachium pontis needs, and sends to each brachium pontis segmentation control unit;
Step 2-2:t4~t5 sorted by the average voltage of bubbling method to each brachium pontis segmentation control unit in the time period, and arrangement sectioning valve information, gathered and uploaded the sectioning valve information of whole brachium pontis and control protection information to the circulation control unit.
Described bridge arm voltage balanced algorithm is that the average voltage to whole each segmentation of brachium pontis carries out macro-control, and each segmentation submodule average voltage is consistent as much as possible; Obtain the information that each brachium pontis segmentation control unit current period need to be modulated by the bridge arm voltage balanced algorithm, send to respectively each brachium pontis segmentation control unit.
Per cycle of current control unit (100 microseconds or still less) gathers control unit to brachium pontis and sends modulation intelligence and other relevant informations, among the figure from t1 constantly, the balance of voltage strategy that brachium pontis gathers control unit then to be needed to carry out whole brachium pontis is realized, reach the work such as control information processing, afterwards the switching decision-making is sent to each brachium pontis segmentation control unit, then, received the information feedback of the brachium pontis segmentation control unit transmission in a upper cycle; Afterwards, in next cycle, namely t3 is constantly among the figure, the balance of voltage strategy that brachium pontis gathers control unit then to be needed to carry out whole brachium pontis is realized, and the work such as control information processing, the processing of sorting of the voltage that will collect afterwards is the t3~t4 time period among the figure during this period of time; Like this, finished respectively process to gather and computing at binary cycle, thereby avoided both to coexist in the one-period, it is excessive that the formed processing time accounts for cycle proportion, maybe can't finish the work, and reduces the correlated performances such as System Error-tolerance Property and reliability.
Should be noted that at last: above embodiment is only in order to illustrate that technical scheme of the present invention is not intended to limit, although with reference to above-described embodiment the present invention is had been described in detail, those of ordinary skill in the field are to be understood that: still can make amendment or be equal to replacement the specific embodiment of the present invention, and do not break away from any modification of spirit and scope of the invention or be equal to replacement, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (7)

1.一种双周期信息采集与处理轮流执行的时序设计方法,其特征在于:所述方法包括以下步骤:1. A sequential design method for double-period information acquisition and processing performed in turn, characterized in that: the method may further comprise the steps: 步骤1:采集T1周期内桥臂分段控制单元上送的分段阀信息;Step 1: Collect the section valve information sent by the bridge arm section control unit in the T1 cycle; 步骤2:在T2周期内对所采集的分段阀信息进行处理和综合排序。Step 2: Process and comprehensively sort the collected segmented valve information within the T2 period. 2.根据权利要求1所述的双周期信息采集与处理轮流执行的时序设计方法,其特征在于:所述分段阀信息包括该分段所有子模块的电压和、旁路数、运行信息以及故障保护信息。2. The sequential design method of double-period information acquisition and processing in turn according to claim 1, characterized in that: the segmented valve information includes the voltage sum of all sub-modules in the segment, the number of bypasses, operating information and Failsafe information. 3.根据权利要求1所述的双周期信息采集与处理轮流执行的时序设计方法,其特征在于:所述T1周期分为t1~t2时间段和t2~t3时间段;所述T2周期分为t3~t4时间段和t4~t5时间段。3. The timing design method for double-period information collection and processing performed in turn according to claim 1, characterized in that: the T1 period is divided into t1~t2 time period and t2~t3 time period; the T2 period is divided into t3~t4 time period and t4~t5 time period. 4.根据权利要求1所述的双周期信息采集与处理轮流执行的时序设计方法,其特征在于:所述步骤1包括以下步骤:4. The sequence design method for double-period information collection and processing performed in turn according to claim 1, characterized in that: said step 1 comprises the following steps: 步骤1-1:t1~t2时间段内,根据环流控制单元下发的调制信息,采用桥臂电压平衡算法,形成各桥臂分段控制单元需要的调制量信息,并发送给各桥臂分段控制单元;Step 1-1: During the time period from t1 to t2, according to the modulation information issued by the circulating current control unit, the bridge arm voltage balance algorithm is used to form the modulation amount information required by each bridge arm segment control unit, and send it to each bridge arm branch segment control unit; 步骤1-2:t2~t3时间段内,桥臂汇总控制单元分别采集各桥臂分段控制单元上送的分段阀信息,保证全部采集完毕;整理分段阀信息,汇总并上传整个桥臂的分段阀信息和控制保护信息至环流控制单元。Step 1-2: During the time period from t2 to t3, the bridge arm summary control unit separately collects the section valve information sent by each bridge arm section control unit to ensure that all the collection is completed; sort out the section valve information, summarize and upload the entire bridge Arm section valve information and control protection information to the circulation control unit. 5.根据权利要求4所述的双周期信息采集与处理轮流执行的时序设计方法,其特征在于:桥臂汇总控制单元通过轮询和标志位标注的方式,采集各桥臂分段控制单元上送的分段阀信息,确保收已采集的信息不重复接收,未采信息不漏掉。5. according to claim 4 two-period information collection and the sequential design method that processing is carried out in turn, it is characterized in that: the bridge arm summary control unit is by the mode of polling and mark position mark, collects on each bridge arm subsection control unit The section valve information sent to ensure that the collected information is not received repeatedly, and the uncollected information is not missed. 6.根据权利要求1所述的双周期信息采集与处理轮流执行的时序设计方法,其特征在于:所述步骤2包括以下步骤:6. The sequential design method for double-period information collection and processing in turn according to claim 1, characterized in that: said step 2 comprises the following steps: 步骤2-1:t3~t4时间段内,根据环流控制单元下发的调制信息,采用桥臂电压平衡算法,形成桥臂各分段控制单元需要的调制量信息,发送给各桥臂分段控制单元;Step 2-1: During the time period from t3 to t4, according to the modulation information issued by the circulating current control unit, the bridge arm voltage balance algorithm is used to form the modulation amount information required by the control units of each segment of the bridge arm and sent to each segment of the bridge arm control unit; 步骤2-2:t4~t5时间段内,通过冒泡法对各桥臂分段控制单元的平均电压进行排序,并整理分段阀信息,汇总并上传整个桥臂的分段阀信息和控制保护信息至环流控制单元。Step 2-2: During the time period from t4 to t5, sort the average voltage of the segment control units of each bridge arm through the bubbling method, sort out the segment valve information, summarize and upload the segment valve information and control of the entire bridge arm Protection information to the circulation control unit. 7.根据权利要求4或6所述的双周期信息采集与处理轮流执行的时序设计方法,其特征在于:所述桥臂电压平衡算法是对整个桥臂各分段的平均电压进行宏观控制,使各分段子模块平均电压尽可能的保持一致;通过桥臂电压平衡算法得到各桥臂分段控制单元当前周期需要调制的信息,分别发送给各桥臂分段控制单元。7. according to claim 4 or 6 described two-period information acquisition and processing sequence design method that is carried out in turn, it is characterized in that: described bridge arm voltage balance algorithm is to carry out macroscopical control to the average voltage of each subsection of whole bridge arm, Keep the average voltage of each segment sub-module as consistent as possible; obtain the current period modulation information of each bridge arm segment control unit through the bridge arm voltage balance algorithm, and send it to each bridge arm segment control unit respectively.
CN201210535506.3A 2012-12-12 2012-12-12 Timing sequence design method of dicycle information acquisition and processing execution in turns Active CN103036404B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210535506.3A CN103036404B (en) 2012-12-12 2012-12-12 Timing sequence design method of dicycle information acquisition and processing execution in turns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210535506.3A CN103036404B (en) 2012-12-12 2012-12-12 Timing sequence design method of dicycle information acquisition and processing execution in turns

Publications (2)

Publication Number Publication Date
CN103036404A true CN103036404A (en) 2013-04-10
CN103036404B CN103036404B (en) 2015-07-08

Family

ID=48022980

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210535506.3A Active CN103036404B (en) 2012-12-12 2012-12-12 Timing sequence design method of dicycle information acquisition and processing execution in turns

Country Status (1)

Country Link
CN (1) CN103036404B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116526638A (en) * 2023-07-04 2023-08-01 宁德时代新能源科技股份有限公司 Modulation method and modulation device of cascade energy storage system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101726640A (en) * 2009-12-23 2010-06-09 中国电力科学研究院 Control and protection system of converter valve operating test device
CN102170123A (en) * 2011-03-16 2011-08-31 中国电力科学研究院 Valve base control equipment sequential method of modularization multilevel flexible DC transmission system
CN102222901A (en) * 2011-06-16 2011-10-19 中国电力科学研究院 Sequence control process for modular multi-level flexible direct-current transmission system control equipment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101726640A (en) * 2009-12-23 2010-06-09 中国电力科学研究院 Control and protection system of converter valve operating test device
CN102170123A (en) * 2011-03-16 2011-08-31 中国电力科学研究院 Valve base control equipment sequential method of modularization multilevel flexible DC transmission system
CN102222901A (en) * 2011-06-16 2011-10-19 中国电力科学研究院 Sequence control process for modular multi-level flexible direct-current transmission system control equipment

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
吴亚楠等: "模块化多电平VSC-HVDC换流阀的运行试验方法", 《中国电机工程学报》, vol. 32, no. 30, 25 October 2012 (2012-10-25) *
董文杰等: "模块化多电平变流器均压策略研究", 《电力电子技术》, vol. 46, no. 2, 29 February 2012 (2012-02-29) *
赵岩等: "模块化多电平变流器HVDC输电系统控制策略", 《中国电机工程学报》, vol. 31, no. 25, 5 September 2011 (2011-09-05) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116526638A (en) * 2023-07-04 2023-08-01 宁德时代新能源科技股份有限公司 Modulation method and modulation device of cascade energy storage system
CN116526638B (en) * 2023-07-04 2023-11-21 宁德时代新能源科技股份有限公司 Modulation method and modulation device of cascade energy storage system

Also Published As

Publication number Publication date
CN103036404B (en) 2015-07-08

Similar Documents

Publication Publication Date Title
CN103066805B (en) Capacitor voltage balance control method based on bundling type switching of multiple sub modules
CN103078400B (en) Bridge arm collecting protection system suitable for high-capacity MMC (Multi Media Controller) flexible direct-current power transmission system
CN103354427B (en) Single-phase inverter and three-phase inverter
CN113938037B (en) Modular multilevel converter, fault ride-through method and electronic equipment
CN107134935A (en) It is a kind of to reduce the modulator approach of current-type PWM converter switching loss
CN102035402A (en) Integrated gate-commutated thyristor (IGCT)-based hybrid cascaded H-bridge multi-level high-voltage inverter
CN104617803A (en) Multi-level converter submodule as well as inverter circuit and MMC topology both manufactured from such submodule
CN104914746A (en) MMC converter valve control device based on flexible DC power transmission and control method
CN204206015U (en) The mixing module combination multi-level converter of AC cascaded H-bridges
CN203399013U (en) Static synchronous compensator based on three-level H bridge cascade and voltage source inversion module
CN103066567A (en) Hierarchical sectional capacity balance control method based on switching number
CN201726334U (en) Photovoltaic grid-connected inverter
CN103036210B (en) Layering sectional type capacitive balance control method based on look-up table
CN103929076A (en) Novel topology for photovoltaic inverter
CN103312210A (en) Three-phase four-wire type three-level photovoltaic grid-connected inverter
CN208046465U (en) An Improved Double Clamp Submodule and Modular Multilevel Converter
CN102901889A (en) Operation testing device for voltage source type converter sub-module and testing method thereof
CN103036404A (en) Timing sequence design method of dicycle information acquisition and processing execution in turns
CN204089635U (en) High-frequency electrical pulses plating power supply
CN203151392U (en) High-efficiency low-leakage-current inverter topology
CN205104918U (en) Big power convertor principal and subordinate control system
CN102185491A (en) Serial and parallel connection electrical bridge type impedance network power converter
CN105406743A (en) Hybrid modular multi-level converter with asymmetric bridge arms
CN106329927A (en) A Quasi-Zero-Current Switching DC/DC Converter Based on Modular Multilevel Converter
CN107017798B (en) A kind of modular multi-level converter topology with energy-storage function

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 102211 Beijing city Changping District Xiaotangshan town big East Village Road No. 270 (future technology city)

Co-patentee after: CHINA-EPRI ELECTRIC POWER ENGINEERING Co.,Ltd.

Patentee after: STATE GRID SMART GRID Research Institute

Co-patentee after: DALIAN POWER SUPPLY COMPANY, STATE GRID LIAONING ELECTRIC POWER Co.,Ltd.

Co-patentee after: State Grid Corporation of China

Address before: 102211 Beijing city Changping District Xiaotangshan town big East Village Road No. 270 (future technology city)

Co-patentee before: CHINA-EPRI ELECTRIC POWER ENGINEERING Co.,Ltd.

Patentee before: STATE GRID SMART GRID Research Institute

Co-patentee before: DALIAN POWER SUPPLY COMPANY OF LIAONING ELECTRIC POWER Co.,Ltd.

Co-patentee before: State Grid Corporation of China

TR01 Transfer of patent right

Effective date of registration: 20170531

Address after: 102211 Beijing city Changping District Xiaotangshan town big East Village Road No. 270 (future technology city)

Co-patentee after: DALIAN POWER SUPPLY COMPANY, STATE GRID LIAONING ELECTRIC POWER Co.,Ltd.

Patentee after: STATE GRID SMART GRID Research Institute

Co-patentee after: State Grid Corporation of China

Address before: 102211 Beijing city Changping District Xiaotangshan town big East Village Road No. 270 (future technology city)

Co-patentee before: CHINA-EPRI ELECTRIC POWER ENGINEERING Co.,Ltd.

Patentee before: STATE GRID SMART GRID Research Institute

Co-patentee before: DALIAN POWER SUPPLY COMPANY, STATE GRID LIAONING ELECTRIC POWER Co.,Ltd.

Co-patentee before: State Grid Corporation of China

CI01 Publication of corrected invention patent application

Correction item: Patentee|Address|Patentee

Correct: China-EPRI Electric Power Engineering Co., Ltd.|102200 Beijing city Changping District South Shao Zhen Nan Road No. 16|Dalian Power Supply Company, State Grid Liaoning Electric Power Co., Ltd.|State Grid Corporation of China

False: State Grid Smart Grid Institute|102211 Beijing city Changping District Xiaotangshan town big East Village Road No. 270 (future technology city)|Dalian Power Supply Company, State Grid Liaoning Electric Power Co., Ltd.|State Grid Corporation of China

Number: 24-02

Volume: 33