CN103031852A - 方形钢筋混凝土预制井壁及安装法 - Google Patents

方形钢筋混凝土预制井壁及安装法 Download PDF

Info

Publication number
CN103031852A
CN103031852A CN2012105172185A CN201210517218A CN103031852A CN 103031852 A CN103031852 A CN 103031852A CN 2012105172185 A CN2012105172185 A CN 2012105172185A CN 201210517218 A CN201210517218 A CN 201210517218A CN 103031852 A CN103031852 A CN 103031852A
Authority
CN
China
Prior art keywords
reinforced concrete
concrete prefabricated
shaft wall
square reinforced
prefabricated shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012105172185A
Other languages
English (en)
Inventor
邱惠民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2012105172185A priority Critical patent/CN103031852A/zh
Publication of CN103031852A publication Critical patent/CN103031852A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本人所写的隐藏在地下的停车轿厢(申请号201210347492.3)在具体施工中会碰到挖地下时一边挖一边塌的情景,特别在软土和沙土地方更是如此,为了解决这个问题,所以发明了方形钢筋混凝土预制井壁及安装法。本发明是用方形钢筋混凝土预制井壁并把它运到施工现埸,一边开挖地基当挖到第一个方形钢筋混凝土预制井壁高度的深度时,就把第一个方形钢筋混凝土预制井壁吊装到位,然后再挖去方形钢筋混凝土预制井壁中间的泥土,当挖到一定深度方形钢筋混凝土预制井壁由于它的自重对已挖空的地方的压力就自然下沉,当第一个方形钢筋混凝土预制井壁沉到于地面一样平时再吊第二个压在第一个上面,这样依次类推就能方便地安全地完成整个工程的施工。

Description

方形钢筋混凝土预制井壁及安装法
技术领域;
本发明涉及方形钢筋混凝土预制井壁及安装法,尤其是涉及隐藏在地下的停车轿厢的方形钢背景技术; 
本人所写的隐藏在地下的停车轿厢(申请号201210347492.3)在具体施工中会碰到挖地下时一边挖一边塌的情景,特别在软土和沙土地方更是如此,为了解决这个问题,所以发明了方形钢筋混凝土预制井壁及安装法。 
本发明是用方形钢筋混凝土预制井壁并把它运到施工现埸,一边开挖地基当挖到第一个方形钢筋混凝土预制井壁高度的深度时,就把第一个方形钢筋混凝土预制井壁吊装到位,然后再挖去方形钢筋混凝土预制井壁中间的泥土,当挖到一定深度方形钢筋混凝土预制井壁由于它的自重对已挖空的地方的压力就自然下沉,当第一个方形钢筋混凝土预制井壁沉到于地面一样平时再吊第二个压在第一个上面,这样依次类推就能方便地安全地完成整个工程的施工。 
发明内容;
制作方形钢筋混凝土预制井壁一般的水泥混凝土预制车间都能制造,工序也一样,按规定规格做好产品后放过钢筋混凝土预制品保质期后再拉到施工现埸就可使用。(施工方法参照背景技术后部份)。 
附图说明;
图1为本发明的正面示意图; 
图2为本发明的侧面示意图; 
图3左侧本发明的俯视示意图,右侧为剖面示意图; 
图4为本发明的施工示意图。 
具体实施方式;
以下结合附图实施例对本发明作进一步详细描述。 
如图所示,方形钢筋混凝土预制井壁及安装法,它包括主钢筋1,箍钢筋2是固定捆扎主钢筋的,3是混凝土,4是橡胶条是起到隔水作用的,5是下内凸边,它的作用是在吊装时嵌入下的方6上外凸边内侧,7是挖土机,8是吊机。 

Claims (2)

1.方形钢筋混凝土预制井壁及安装法,它包括钢筋架构和水泥混凝土,所述的方形钢筋混凝土预制井壁上口有外凸边,外凸边的内的根部槽内有一橡胶条,所述的方形钢筋混凝土预制井壁的下口有内凸边,内凸边的根部槽内也有一条橡胶条。
2.如权利要求1所述的方形钢筋混凝土预制井壁及安装法,其特征在于上下凸边的根部槽内的橡胶条,它是在吊装后在方形钢筋混凝土预制井壁自重力的压力下起到隔水作用。
CN2012105172185A 2012-11-05 2012-11-05 方形钢筋混凝土预制井壁及安装法 Pending CN103031852A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012105172185A CN103031852A (zh) 2012-11-05 2012-11-05 方形钢筋混凝土预制井壁及安装法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012105172185A CN103031852A (zh) 2012-11-05 2012-11-05 方形钢筋混凝土预制井壁及安装法

Publications (1)

Publication Number Publication Date
CN103031852A true CN103031852A (zh) 2013-04-10

Family

ID=48019211

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012105172185A Pending CN103031852A (zh) 2012-11-05 2012-11-05 方形钢筋混凝土预制井壁及安装法

Country Status (1)

Country Link
CN (1) CN103031852A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958258A (zh) * 2017-03-21 2017-07-18 国网冀北电力有限公司唐山供电公司 一种杆塔基础开挖防塌陷结构的施工方法
CN109630128A (zh) * 2019-02-19 2019-04-16 广东华方工程设计有限公司 一种预制钢筋混凝土装配式自重下沉竖井

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2644316B1 (de) * 1976-10-01 1977-07-07 Franz Dipl-Ing Bauer Raumzelle, fertiggarage o.dgl. aus stahlbeton
JPS6452922A (en) * 1987-08-21 1989-03-01 Toa Harbor Works Co Ltd Construction of cut-off wall of caisson and its reuse
DE4307396A1 (en) * 1992-03-16 1993-09-23 Georg Thalmeier Method of lining of shaft with concrete sections - has sections cast in-situ in circular forms which are re-used as lower sections harden and are driven down
CN201169940Y (zh) * 2008-03-17 2008-12-24 马坤业 一种地下停车装置
JP4230618B2 (ja) * 1999-06-23 2009-02-25 早川ゴム株式会社 止水目地構造体
CN102168431A (zh) * 2011-03-15 2011-08-31 浙江双环塑胶阀门有限公司 检查井
CN102400577A (zh) * 2011-04-01 2012-04-04 卢丹 一种地下车库
CN102635124A (zh) * 2012-04-23 2012-08-15 浙江省建工集团有限责任公司 一种针对软土地区大型沉井的施工方法
CN102720381A (zh) * 2012-06-27 2012-10-10 郑治中 一种电梯式地下立体车库井筒及其建造方法

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2644316B1 (de) * 1976-10-01 1977-07-07 Franz Dipl-Ing Bauer Raumzelle, fertiggarage o.dgl. aus stahlbeton
JPS6452922A (en) * 1987-08-21 1989-03-01 Toa Harbor Works Co Ltd Construction of cut-off wall of caisson and its reuse
DE4307396A1 (en) * 1992-03-16 1993-09-23 Georg Thalmeier Method of lining of shaft with concrete sections - has sections cast in-situ in circular forms which are re-used as lower sections harden and are driven down
JP4230618B2 (ja) * 1999-06-23 2009-02-25 早川ゴム株式会社 止水目地構造体
CN201169940Y (zh) * 2008-03-17 2008-12-24 马坤业 一种地下停车装置
CN102168431A (zh) * 2011-03-15 2011-08-31 浙江双环塑胶阀门有限公司 检查井
CN102400577A (zh) * 2011-04-01 2012-04-04 卢丹 一种地下车库
CN102635124A (zh) * 2012-04-23 2012-08-15 浙江省建工集团有限责任公司 一种针对软土地区大型沉井的施工方法
CN102720381A (zh) * 2012-06-27 2012-10-10 郑治中 一种电梯式地下立体车库井筒及其建造方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958258A (zh) * 2017-03-21 2017-07-18 国网冀北电力有限公司唐山供电公司 一种杆塔基础开挖防塌陷结构的施工方法
CN109630128A (zh) * 2019-02-19 2019-04-16 广东华方工程设计有限公司 一种预制钢筋混凝土装配式自重下沉竖井
CN109630128B (zh) * 2019-02-19 2024-02-06 广东华方工程设计有限公司 一种预制钢筋混凝土装配式自重下沉竖井

Similar Documents

Publication Publication Date Title
CN108442382B (zh) 横穿深基坑的压力管线原位保护及围护挡土结构及施工方法
CN106567717B (zh) 一种利用地铁出入口兼作施工斜通道结构及施工方法
CN108547639B (zh) 隧道临近既有构筑物的超前同孔多导管分层注浆施工方法
CN101922302A (zh) 高压富水区域断层处理方法
CN205876348U (zh) 一种复杂地质条件下横通道拱顶多层次超前支护结构
CN102505704A (zh) 软弱地质竖井中大型沉井施工方法
CN104294769B (zh) 一种补桩与增大台帽组合加固已建桥台结构的施工方法
CN104373128A (zh) 一种富水隧道超大断面双侧下导坑超前降水施工方法
CN104806251A (zh) 一种用于复杂环境下城市地铁车站附属仰挖施工方法
CN105239598A (zh) 井式全自动立体车库的整体下沉施工方法
CN103696784A (zh) 一种浅埋大跨隧道下穿建构筑物的大直径长管幕施工方法
CN103924602A (zh) 深厚软土基坑施工方法
CN102116030A (zh) 一种组合基坑支护结构及其施工方法
JP2015183364A (ja) ジオセル固定用施工補助体による土構造物ののり面表層すべり対策工法
CN103993885A (zh) 一种暗挖隧道侧向开洞支撑体系构建方法
CN104563147B (zh) 适用于岩溶区的组合结构桩基础及其施工方法
CN107237332A (zh) 一种采用复合型土钉墙的含流砂层基坑边坡支护方法
CN104695457B (zh) 一种新型竖井水平旋喷桩基坑封底隔水层的施工方法
CN104480929A (zh) 一种将咬合桩应用于永久地下室外墙的桩墙合一施工方法
CN112576265A (zh) 一种盾构下穿老旧村庄沉降控制方法
CN104131566B (zh) 一种地下室无水平支撑基坑的施工方法
CN107975040A (zh) 圆形顶管工作坑深基坑支护技术施工方法
CN101994314A (zh) 深孔矩形联排抗滑桩不跳桩开挖施工
CN204097889U (zh) 一种补桩与增大台帽组合加固已建桥台结构
CN103031852A (zh) 方形钢筋混凝土预制井壁及安装法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130410