CN103022945A - Method for mounting jumper wire of power transmission line tension-resisting tower - Google Patents
Method for mounting jumper wire of power transmission line tension-resisting tower Download PDFInfo
- Publication number
- CN103022945A CN103022945A CN2012104757473A CN201210475747A CN103022945A CN 103022945 A CN103022945 A CN 103022945A CN 2012104757473 A CN2012104757473 A CN 2012104757473A CN 201210475747 A CN201210475747 A CN 201210475747A CN 103022945 A CN103022945 A CN 103022945A
- Authority
- CN
- China
- Prior art keywords
- jumper
- length
- sag
- wire
- formula
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 33
- 230000005540 biological transmission Effects 0.000 title claims abstract description 15
- 238000012937 correction Methods 0.000 claims abstract description 33
- 238000009434 installation Methods 0.000 claims abstract description 22
- 238000002788 crimping Methods 0.000 claims abstract description 18
- 239000000725 suspension Substances 0.000 claims abstract description 14
- 239000012212 insulator Substances 0.000 claims description 18
- 230000009191 jumping Effects 0.000 claims description 6
- 239000004020 conductor Substances 0.000 description 18
- 238000013461 design Methods 0.000 description 14
- 238000010276 construction Methods 0.000 description 13
- 238000005259 measurement Methods 0.000 description 13
- 238000004364 calculation method Methods 0.000 description 12
- 238000010586 diagram Methods 0.000 description 8
- 125000006850 spacer group Chemical group 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 4
- 230000008569 process Effects 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 230000009286 beneficial effect Effects 0.000 description 3
- 238000011900 installation process Methods 0.000 description 3
- 238000009413 insulation Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000000630 rising effect Effects 0.000 description 2
- 238000012360 testing method Methods 0.000 description 2
- 239000004677 Nylon Substances 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 210000003811 finger Anatomy 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000000691 measurement method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 229920001778 nylon Polymers 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- 210000003813 thumb Anatomy 0.000 description 1
Images
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
- Electric Cable Installation (AREA)
Abstract
本发明提供一种输电线路耐张塔跳线安装方法,该方法包括:步骤1:测量跳线弦长l、跳线两悬挂点的高角差
及跳线调整弧垂f;步骤2:获取导线压接长度修正系数a及导线间距离调整值b;步骤3:将所述的l,f及a代入线长与弧垂之间的关系式(1)生成跳线长L,步骤4:根据跳线长L截取导线,在地面上压接截取的所述导线后进行塔上安装。本发明的输电线路耐张塔跳线安装方法通过进行压接修正、弧垂修正及线路转角修正处理,能够精确的测量跳线长,提高了跳线安装的效率。The invention provides a method for installing jumpers in tension towers of power transmission lines. The method includes: step 1: measuring the chord length l of the jumper and the height angle difference between two suspension points of the jumper
and the jumper to adjust the sag f; step 2: obtain the wire crimping length correction coefficient a and the distance adjustment value b between the wires; step 3: the above l, Substituting f and a into the relationship between line length and sag (1) generates jumper length L, Step 4: Cut the wire according to the length L of the jumper wire, crimp the cut wire on the ground and install it on the tower. The jumper installation method of the tension tower of the power transmission line of the present invention can accurately measure the length of the jumper through crimping correction, sag correction and line corner correction, and improves the efficiency of jumper installation.Description
技术领域 technical field
本发明是关于输电线路安装技术,特别是关于一种输电线路耐张塔跳线安装方法。 The invention relates to the installation technology of transmission lines, in particular to a method for installing jumpers of tension towers of transmission lines. the
背景技术 Background technique
输电线路的耐张塔跳线安装工艺,一直是影响施工质量和工作效率的一大技术难题。耐张塔上的跳线作为输电线路的一部分,其弧垂的大小直接影响着线路的安全稳定运行。当施工弧垂小于设计弧垂时,则引起导线与横担间的绝缘间隙不够;较大时,受风偏影响后,会导致塔身的绝缘间隙过小,引起线路绝缘水平的降低。因此,跳线长度的精度对输电线路施工的影响十分显著。 The installation process of jumpers for tension towers of transmission lines has always been a major technical problem that affects construction quality and work efficiency. The jumper on the strain tower is a part of the transmission line, and its sag directly affects the safe and stable operation of the line. When the construction sag is smaller than the design sag, the insulation gap between the conductor and the cross arm is insufficient; when it is large, the insulation gap of the tower body is too small after being affected by the wind deflection, resulting in a reduction in the insulation level of the line. Therefore, the accuracy of jumper length has a significant impact on transmission line construction. the
对于跨距在几米到二十多米之间的耐张塔上的跳线,其张力小,导线刚度对其弯曲的影响大,加之线夹(导线的起点)的角度、有无支持绝缘子、绝缘子串的倾斜度、线路的转角度数等众多因素的影响,引起跳线形态的变化,因此,尽管设计单位给出了跳线安装长度,而安装后测量出的实际跳线弧垂与设计弧垂间仍存在较大的误差。 For the jumper on the tension tower with a span of several meters to more than 20 meters, the tension is small, and the stiffness of the wire has a great influence on its bending. In addition, the angle of the clamp (the starting point of the wire), whether there is a supporting insulator, The inclination of the insulator string, the angle of rotation of the line, and many other factors cause changes in the shape of the jumper. Therefore, although the design unit has given the installation length of the jumper, the actual jumper sag measured after installation is consistent with the design. There is still a large error between sags. the
目前,对于跳线安装多数施工单位采取的是现场量比模拟法,它是先压接跳线的一端,将其悬挂至塔上,通过比对、划印确定线长,然后在地面截取导线,压接导线另一端,最后再安装成型。整个安装过程需要两次高空作业,工序繁琐,效率较低,而且还会造成一定量的导线浪费。 At present, most construction units adopt the on-site measurement ratio simulation method for jumper installation. It is to crimp one end of the jumper first, hang it on the tower, determine the length of the line through comparison and marking, and then intercept the wire on the ground. , Crimp the other end of the wire, and finally install and form. The whole installation process requires two high-altitude operations, the process is cumbersome, the efficiency is low, and a certain amount of wires will be wasted. the
为了简化施工过程、减少高空作业量、保证安全性、提高施工质量,亟待研究一种综合考虑现场各因素影响的装配式跳线安装方法,从而达到提高 施工效率、降低施工成本、提升技术水平、减轻施工人员劳动强度的目的。 In order to simplify the construction process, reduce the amount of high-altitude work, ensure safety, and improve construction quality, it is urgent to study a prefabricated jumper installation method that comprehensively considers the influence of various factors on the site, so as to improve construction efficiency, reduce construction costs, and improve the technical level. The purpose of reducing the labor intensity of construction personnel. the
发明内容 Contents of the invention
本发明提供一种输电线路耐张塔跳线安装方法,以精确测量跳线线长,准确高效的完成耐张塔跳线制作及安装工艺。 The invention provides a jumper wire installation method for a tension tower of a power transmission line, which can accurately measure the length of the jumper wire, and accurately and efficiently complete the production and installation process of the jumper wire for a tension tower. the
为了实现上述目的,本发明提供一种输电线路耐张塔跳线安装方法,该方法包括:步骤1:测量跳线弦长l、跳线两悬挂点的高角差及跳线调整弧垂f;步骤2:获取导线压接长度修正系数a及导线间距离调整值b;步骤3:将所述的l,f及a代入线长与弧垂之间的关系式(1)生成跳线长L, 步骤4:根据跳线长L截取导线,在地面上压接截取的所述导线后进行塔上安装。 In order to achieve the above object, the present invention provides a method for installing a wire jumper in a tension tower of a power transmission line, the method comprising: Step 1: measuring the chord length l of the wire jumper, and the height angle difference between the two suspension points of the wire jumper and the jumper to adjust the sag f; step 2: obtain the wire crimping length correction coefficient a and the distance adjustment value b between the wires; step 3: the above l, Substituting f and a into the relationship between line length and sag (1) generates jumper length L, Step 4: Cut the wire according to the length L of the jumper wire, crimp the cut wire on the ground and install it on the tower.
进一步地,对于耐张塔无跳串情况,在步骤3之后,所述的方法还包括:将关系式(1)中的弧垂按照下面公式(2)或者公式(3)进行修正, Further, for the case where the strain tower has no jumping strings, after step 3, the method further includes: modifying the sag in the relational expression (1) according to the following formula (2) or formula (3),
然后将修正值f*代入关系式(4)得到跳线长L,其中,fmax为跳线最大容许弧垂允许值,fmin为跳线最小容许弧垂允许值L=L1+L2+L3; Then substitute the correction value f* into the relation (4) to get the jumper length L, where f max is the maximum allowable sag value of the jumper, and f min is the minimum allowable sag value of the jumper L=L 1 +L 2 +L 3 ;
进一步地,对于耐张塔单跳串情况,测量引流板上挂点到跳串上导线挂孔的距离l1及l2,分别将l1及l2代入公式(2)或者公式(3)进行修正,分别得到第一跳线长L1及第二跳线长L2,L=L1+L2。 Further, for the case of a single jump string in the strain tower, measure the distance l 1 and l 2 from the hanging point on the drainage plate to the wire hanging hole on the jump string, and substitute l 1 and l 2 into formula (2) or formula (3) respectively Correction is performed to obtain the first jumper length L 1 and the second jumper length L 2 respectively, where L=L 1 +L 2 .
进一步地,对于耐张塔双跳串情况,测量引流板上挂点到跳串上导线挂孔的距离l1、l3及两跳串中间挂孔的距离l2,分别将l1及l3代入公式(2)或者 公式(3)进行修正,分别得到第一跳线长L1及第三跳线长L3,将l2代入下面关系式(4)得到第二跳线长L2,。 Further, for the case of double jump strings in the strain tower, measure the distances l 1 and l 3 from the hanging point on the drainage plate to the wire hanging holes on the jump strings and the distance l 2 between the hanging holes in the middle of the two jump strings, and take l 1 and l 3 Substituting formula (2) or formula (3) for correction, the first jumper length L 1 and the third jumper length L 3 are respectively obtained, and l 2 is substituted into the following relational formula (4) to get the second jumper length L 2 ,.
进一步地,当f/l<0.23时,将线长与弧垂之间的关系式中的弧垂按照公式(2)进行修正。 Further, when f/l<0.23, the sag in the relationship between the line length and the sag is corrected according to the formula (2). the
进一步地,当f/l>0.23时,将线长与弧垂之间的关系式中的弧垂按照公式(3)进行修正。 Further, when f/l>0.23, the sag in the relationship between the line length and the sag is corrected according to the formula (3). the
进一步地,对于耐张塔单跳串情况,
本发明实施例的有益效果在于,本发明的输电线路耐张塔跳线安装方法通过进行压接修正、弧垂修正及线路转角修正处理,能够精确的测量跳线长,提高了跳线安装的效率。 The beneficial effect of the embodiment of the present invention is that the jumper installation method of the tension tower of the transmission line of the present invention can accurately measure the length of the jumper by performing crimping correction, sag correction and line corner correction, and improves the installation efficiency of the jumper. efficiency. the
附图说明 Description of drawings
图1为本发明实施例的输电线路耐张塔跳线安装方法流程图; Fig. 1 is the flow chart of the installation method of the transmission line tension tower jumper of the embodiment of the present invention;
图2为本发明实施例的调整弧垂示意图; Fig. 2 is the adjustment sag schematic diagram of the embodiment of the present invention;
图3为本发明实施例的导线与引流管压接图; Fig. 3 is the wire and drainage tube crimping figure of the embodiment of the present invention;
图4为本发明实施例的无跳串不上扬的跳线示意图; Fig. 4 is the jumper schematic diagram that does not rise without jumping string in the embodiment of the present invention;
图5为本发明实施例的无跳串上扬的跳线示意图; Fig. 5 is the wire jumper schematic diagram that jumps up without string jumping according to the embodiment of the present invention;
图6为本发明实施例的单跳串的跳线示意图; Fig. 6 is the jumper schematic diagram of the single jump string of the embodiment of the present invention;
图7为本发明实施例的双跳串的跳线示意图; Fig. 7 is the jumper schematic diagram of the double jump string of the embodiment of the present invention;
图8为本发明实施例的跳线连接点空间关系图; Fig. 8 is the spatial relationship diagram of the jumper connection point of the embodiment of the present invention;
图9为本发明实施例的全站仪测量计算示意图。 Fig. 9 is a schematic diagram of the measurement and calculation of the total station according to the embodiment of the present invention. the
具体实施方式 Detailed ways
如图1所示,本发明提供一种输电线路耐张塔跳线安装方法,其特征在于,该方法包括: As shown in Figure 1, the present invention provides a kind of wire jumper installation method of transmission line strain tower, it is characterized in that, this method comprises:
步骤S301:测量跳线弦长l、跳线两悬挂点的高角差及跳线调整弧垂f。 Step S301: Measure the chord length l of the jumper and the height angle difference between the two suspension points of the jumper And jumper to adjust the sag f.
均匀荷载模型下的导线悬垂曲线悬链线方程式是表征导线力学特性的常用公式。但工程实际中,在满足计算精度要求的条件下,可以采用较简便的近似计算方法。下述悬垂曲线的抛物线方程式(5)是工程计算中常用的近似计算方法,在方程式(5)中,线长与弧垂之间满足: The catenary equation of the wire suspension curve under the uniform load model is a commonly used formula to characterize the mechanical properties of the wire. However, in engineering practice, a simpler approximate calculation method can be used under the condition that the calculation accuracy requirements are met. The parabolic equation (5) of the following sag curve is an approximate calculation method commonly used in engineering calculations. In equation (5), the relationship between the line length and the sag is satisfied:
式(5)中,L表示跳线长,l为跳线两边引流板两中心线交点间(或跳线引流板两中心线交点到跳线线夹挂点)的直线距离,简称跳线弦长,为两悬挂点间的高差角,f为跳线(调整)弧垂。导线弧垂是指自两悬挂点连线沿荷载方向到导线轴线间的距离。f如图2所示,图2中201代表横担,202代表跳线线夹,203代表引流管。 In formula (5), L represents the length of the jumper, and l is the straight-line distance between the intersection of the two centerlines of the diversion boards on both sides of the jumper (or the intersection of the two centerlines of the jumper diversion board to the hanging point of the jumper clamp), referred to as the jumper string long, is the height difference angle between the two suspension points, and f is the jumper (adjustment) sag. Conductor sag refers to the distance from the line connecting two suspension points along the load direction to the conductor axis. f As shown in Figure 2, 201 in Figure 2 represents the cross arm, 202 represents the jumper clip, and 203 represents the drainage tube.
步骤S302:获取导线压接长度修正系数a及导线间距离调整值b。 Step S302: Obtain the wire crimping length correction coefficient a and the wire-to-wire distance adjustment value b. the
本发明的优点之一在于引进了b进行修正。对于四分裂线路,设计给出的弧垂一般为两悬挂点连线到上、下导线中点间的距离。如果不对上、下子导线加以调整,计算结果会导致四根子导线间距略大于标准子导线间距。定义线间距离调整值b,b值的大小为导线间距值的一半。因此,在计算各子导线的线长时,上面两根子导线需加上一个调整值b,使其加长,下面两根子导线需减掉一个b,使其变短,从而使得四根子导线间距相同。 One of the advantages of the present invention is that b is introduced for correction. For the four-split line, the sag given by the design is generally the distance between the line connecting the two suspension points and the midpoint of the upper and lower conductors. If the upper and lower sub-conductors are not adjusted, the calculation result will cause the spacing of the four sub-conductors to be slightly larger than the standard sub-conductor spacing. Define the line distance adjustment value b, the size of the b value is half of the line spacing value. Therefore, when calculating the length of each sub-conductor, the upper two sub-conductors need to add an adjustment value b to make it longer, and the lower two sub-conductors need to subtract a b to make it shorter, so that the distance between the four sub-conductors is the same . the
另外,对于二分裂线路,b为0,对于六分裂及八分裂线路,b的计算方法与四分裂相似,不再赘述。 In addition, for the two-split line, b is 0, and for the six-split and eight-split lines, the calculation method of b is similar to that of the four-split line, and will not be repeated here. the
本发明的另一优点在于引进了a进行修正。导线与引流管压接时,导线压接长度并不等于引流管长度,其误差也会对弧垂造成一定的影响,因此,引入压接长度修正系数a,a是指引流管中心线交点到压接完毕后的导线断面的 距离,如图3所示。 Another advantage of the present invention is that a is introduced for correction. When the wire is crimped with the drainage tube, the crimping length of the wire is not equal to the length of the drainage tube, and its error will also have a certain impact on the sag. Therefore, the correction factor a of the crimping length is introduced. The distance of the wire section after crimping is shown in Figure 3. the
步骤S303:将所述的l,f及a代入线长与弧垂之间的关系式(1)生成跳线长L。 Step S303: the l, Substitute f and a into the relational expression (1) between the line length and sag to generate the jumper line length L.
计算跳线长度的方法就是在抛物线弧垂(调整弧垂)、弦长计算公式的基础上再增加两个调整值a及b,结果精确到厘米。 The method to calculate the jumper length is to add two adjustment values a and b on the basis of parabolic sag (adjustment sag) and chord length calculation formula, and the result is accurate to centimeters. the
跳线弦长l、跳线两悬挂点的高角差跳线调整弧垂f、导线压接长度修正系数a及导线间距离调整值b均需要通过测量得到。施工人员在上塔测量跳线弦长l、高角差时,测量点位置统一选择上挂点,使用钢性尺子,尺子一定要绷紧,减小尺子自身重力和风偏造成的测量误差。测量弧垂f时,在导线上的操作人员应使自己的重心位于两水平排列的子导线中间,否则可能会影响测量弧垂的准确性。 Jumper chord length l, height angle difference between the two suspension points of the jumper Jumper adjustment sag f, conductor crimping length correction coefficient a and distance adjustment value b between conductors all need to be obtained through measurement. Construction workers measure the chord length l and height angle difference of the jumper on the upper tower At the same time, the location of the measurement point is uniformly selected as the upper hanging point. When using a steel ruler, the ruler must be tightened to reduce the measurement error caused by the ruler's own gravity and wind deflection. When measuring the sag f, the operator on the wire should make his center of gravity in the middle of the two horizontally arranged sub-wires, otherwise the accuracy of the sag measurement may be affected.
步骤S304:根据跳线长L截取导线,在地面上压接截取的所述导线后进行塔上安装。 Step S304: Cutting the wire according to the length L of the jumper wire, crimping the cut wire on the ground and then installing it on the tower. the
通过步骤S303得到跳线长L进行导线截取后,在地面上可以将截取的长为L的导线的两端与引流管203压接在一起。导线的截取和压接需要注意下面内容:
After the length L of the jumper wire is obtained through step S303 and the wire is cut, the two ends of the cut wire with a length of L can be crimped together with the
导线截取长度量取时,需将导线从地面抬起,沿导线表面水平测量。跳线长度确定好之后,即可在未压接的跳线上进行画印(画出压接位置),然后放到地面进行压接。在地面压接引流连板时,应将跳线展开,不要使导线受力,两端的引流连板要在同一平面内。导线两端在地面压接完成后,放置在安装位置下方的地面上,地面要用苫布进行铺垫,防止导线损伤。 When measuring the intercepted length of the wire, it is necessary to lift the wire from the ground and measure horizontally along the surface of the wire. After the jumper length is determined, you can print on the uncrimped jumper (draw the crimping position), and then put it on the ground for crimping. When crimping the drain connecting plate on the ground, the jumper should be unfolded, and the wires should not be stressed, and the drain connecting plates at both ends should be in the same plane. After the two ends of the wires are crimped on the ground, place them on the ground below the installation location. The ground should be paved with tarpaulin to prevent damage to the wires. the
引流线全部安装完成后,安装间隔棒。间隔棒安装顺序是先安装两头,再安装中间。严禁施工人员直接攀爬在引流线上安装间隔棒。 After all the drainage lines are installed, install the spacer bars. The installation sequence of the spacer is to install the two ends first, and then install the middle. It is strictly forbidden for construction personnel to directly climb and install spacer bars on the drainage line. the
较佳地,为了使得跳线长L更准确,在步骤S303之后,还可以考虑对不同跳串形式下的弧垂进行修正处理,同时可以考虑对线路转角进行修正。下面逐一介绍: Preferably, in order to make the jumper length L more accurate, after step S303 , it may also be considered to correct the sag under different skipping forms, and at the same time, it may be considered to correct the line corner. Introduce one by one below:
1、耐张塔跳线长度计算分三种情况:无跳串、单跳串和双跳串,下面分别不同跳串形式下的弧垂修正处理。 1. There are three situations for calculating the length of jumper wires in tension towers: no jumper string, single jumper string and double jumper string. the
(1)无跳串 (1) No jump string
跳线为无跳串时,需要测量每根跳线弦长l(两边引流板上挂点之间的直线距离),以及横担下平面到跳线两边引流板上挂点连线的垂直距离f0,如图4所示,f1表示设计弧垂值。 When the jumper is without jumper strings, it is necessary to measure the chord length l of each jumper (the straight-line distance between the hanging points on the two sides of the drainage board), and the vertical distance from the lower plane of the cross arm to the hanging point on the two sides of the jumper. f 0 , as shown in Figure 4, f 1 represents the design sag value.
由于跳线跨度较小,受导线自身刚度的影响,线夹出口方向往往不在档距所成的垂直平面内,致使跳线可能产生上下、左右弯曲,很难呈规则的抛物线形状。为保证跳线对放电部分的间隙满足设计要求值,在采用关系式(1)1进行跳线长度计算时,需要调整设计弧垂值。 Due to the small span of the jumper, affected by the stiffness of the wire itself, the outlet direction of the clamp is often not in the vertical plane formed by the span, so that the jumper may bend up and down, left and right, and it is difficult to assume a regular parabolic shape. In order to ensure that the gap between the jumper and the discharge part meets the design requirements, the design sag value needs to be adjusted when using the relationship (1) 1 to calculate the length of the jumper. the
对于弧垂值的调整,根据现场试验的统计结果:弧垂误差随跳线弦长l的大小而变化。在f/l较小时,实测弧垂与设计弧垂误差为负,实测弧垂小于设计弧垂值;随着跨距的增大,f/l变大,当f/l增大到一定值时,实测弧垂与设计弧垂误差变为正,实测弧垂大于设计弧垂值。依据现场试验的统计f/l的分界点在0.23左右(本发明不限于0.23)。由于f/l的分界点受多种因素影响(耐张金具的长度、导线悬垂角、转角度数以及悬挂点高差等),并不是一固定值。因此,弧垂值的修正只能采用分段渐近修正法。 For the adjustment of the sag value, according to the statistical results of the field test: the sag error varies with the size of the jumper chord length l. When f/l is small, the error between the measured sag and the designed sag is negative, and the measured sag is smaller than the designed sag; as the span increases, f/l becomes larger, when f/l increases to a certain value When , the error between the measured sag and the design sag becomes positive, and the measured sag is greater than the design sag value. According to field test statistics, the cut-off point of f/l is around 0.23 (the present invention is not limited to 0.23). Since the cut-off point of f/l is affected by many factors (the length of the tension fitting, the suspension angle of the wire, the number of rotation angles, and the height difference of the suspension point, etc.), it is not a fixed value. Therefore, the correction of the sag value can only adopt the piecewise asymptotic correction method. the
当f/l<0.23时,弧垂修正值按下式计算 When f/l<0.23, the sag correction value is calculated according to the following formula
其中,fmax为跳线最大容许弧垂允许值,其大小为设计弧垂加上跳线弧垂最大允许误差值。 Among them, f max is the maximum allowable sag value of the jumper, and its size is the design sag plus the maximum allowable error value of the jumper sag.
当f/l>0.23时,弧垂调整值计算式为: When f/l>0.23, the calculation formula of sag adjustment value is:
其中,fmin为跳线最小容许弧垂允许值,其大小为设计弧垂减去跳线弧垂 最大允许误差值。 Among them, f min is the minimum allowable sag value of the jumper, and its size is the design sag minus the maximum allowable error value of the jumper sag.
对于耐张塔无跳串情况,需要将关系式(1)中的弧垂f按照公式(2)或者公式(3)进行修正。当f/l<0.23时,将线长与弧垂之间的关系式中的弧垂按照公式(2)进行修正。当f/l>0.23时,将线长与弧垂之间的关系式中的弧垂按照公式(3)进行修正。 For the case of no string jumping in the strain tower, the sag f in relation (1) needs to be corrected according to formula (2) or formula (3). When f/l<0.23, correct the sag in the relationship between line length and sag according to formula (2). When f/l>0.23, correct the sag in the relationship between line length and sag according to formula (3). the
修正之后,将修正值f*代入关系式(4)得到跳线长L,其中,fmax为跳线最大容许弧垂允许值,fmin为跳线最小容许弧垂允许值。关系式(4)如下: After the correction, substitute the correction value f* into the relation (4) to obtain the jumper length L, where f max is the maximum allowable sag value of the jumper, and f min is the minimum allowable sag value of the jumper. Relation (4) is as follows:
在关系式(4)中,由于无跳串的情况需减掉两端引流板上挂点到跳线端头的距离,所以修正值需要减掉2a。 In relation (4), since the distance from the hanging point on the drainage board at both ends to the end of the jumper wire needs to be subtracted in the case of no jumper string, the correction value needs to be subtracted by 2a. the
对于耐张绝缘子串无上扬的塔型,上横担和中横担由于要同时考虑上下两面放电部分的安全距离,调整弧垂一般比设计弧垂略小0.1m左右,下横担调整弧垂一般取设计弧垂值。 For the tower type with no rising tension insulator string, the upper cross arm and the middle cross arm should consider the safety distance of the discharge part on the upper and lower sides at the same time, the adjusted sag is generally about 0.1m smaller than the designed sag, and the lower cross arm adjusts the sag Generally take the design sag value. the
当耐张绝缘子串上扬时,如图5,为保证横担边缘满足放电间隙距离值,调整弧垂应适当增大,一般调整后的弧垂值比设计值大,上、中、下相调整值依次变大,见表1所示。 When the tension insulator string rises, as shown in Figure 5, in order to ensure that the edge of the cross-arm meets the distance value of the discharge gap, the adjusted sag should be increased appropriately. Generally, the adjusted sag value is larger than the design value, and the upper, middle and lower phases are adjusted. The values increase sequentially, as shown in Table 1. the
表1 Table 1
(2)单跳串 (2) Single hop string
对于耐张塔单跳串情况,测量引流板上挂点到跳串上导线挂孔的距离l1及l2(如图6所示),分别将l1及l2代入公式(2)或者公式(3)进行修正,分别得到第一跳线长L1及第二跳线长L2,L=L1+L2。耐张绝缘子上扬的情况与无跳 串的情况相同,但弧垂调整值比无跳串时的情况小,弧垂调整率一般在5%~10%左右。 For the case of a single jump string in a strain tower, measure the distance l 1 and l 2 from the hanging point on the drainage plate to the wire hanging hole on the jump string (as shown in Figure 6), and substitute l 1 and l 2 into the formula (2) or Formula (3) is corrected to obtain the length L 1 of the first jumper and the length L 2 of the second jumper respectively, where L=L 1 +L 2 . The rising situation of tension insulators is the same as that without skipping strings, but the sag adjustment value is smaller than that without skipping strings, and the sag adjustment rate is generally about 5% to 10%.
同无跳串时相同,当f/l<0.23时,将线长与弧垂之间的关系式中的弧垂按照公式(2)进行修正。当f/l>0.23时,将线长与弧垂之间的关系式中的弧垂按照公式(3)进行修正。 Same as when there is no string skipping, when f/l<0.23, correct the sag in the relationship between line length and sag according to formula (2). When f/l>0.23, correct the sag in the relationship between line length and sag according to formula (3). the
(3)双跳串 (3) double jump string
对于耐张塔双跳串情况,测量引流板上挂点到跳串上导线挂孔的距离l1、l3及两跳串中间挂孔的距离l2,如图7所示。两边调整弧垂的值l1、l3与单跳串、无跳串情况相同,l2对应的中间弧垂因两挂点等高不需要调整。分别将l1及l3代入公式(2)或者公式(3)进行修正,分别得到第一跳线长L1及第三跳线长L3,将l2代入关系式(4)得到第二跳线长L2,L=L1+L2+L3。 For the case of double jump strings in the strain tower, measure the distances l 1 , l 3 from the hanging point on the drainage plate to the wire hanging holes on the jump strings, and the distance l 2 between the hanging holes in the middle of the two jump strings, as shown in Figure 7. Adjusting the sag values l 1 and l 3 on both sides is the same as the case of single jump string and no jump string, and the middle sag corresponding to l 2 does not need to be adjusted because the two hanging points are of the same height. Substituting l 1 and l 3 into formula (2) or formula (3) for correction, the first jumper length L 1 and the third jumper length L 3 are respectively obtained, and l 2 is substituted into relational formula (4) to get the second Jumper length L 2 , L=L 1 +L 2 +L 3 .
同无跳串时相同,当f/l<0.23时,将线长与弧垂之间的关系式中的弧垂按照公式(2)进行修正。当f/l>0.23时,将线长与弧垂之间的关系式中的弧垂按照公式(3)进行修正。 Same as when there is no string skipping, when f/l<0.23, correct the sag in the relationship between line length and sag according to formula (2). When f/l>0.23, correct the sag in the relationship between line length and sag according to formula (3). the
2、对线路转角进行修正时,对于耐张塔单跳串情况下, 2. When correcting the corner of the line, in the case of a single jump string of the tension tower,
其中,M、N分别表示跳线在耐张绝缘子上的挂点,P为跳线安装前跳串绝缘子挂点位置,Q则表示跳线安装后的跳串绝缘子挂点位置。上述公式(6)、(7)的计算详细叙述如下: Among them, M and N represent the hanging point of the jumper on the tension insulator respectively, P is the hanging point position of the jumper insulator before the jumper is installed, and Q represents the hanging point of the jumper insulator after the jumper is installed. The calculation of the above formulas (6) and (7) is described in detail as follows:
由于跳线为空间曲线,在跳线为无跳串时,无论两悬挂点空间位置如何变化,跳线与两悬挂点始终处于同一平面内,线路转角不会对跳线精度造成影响。而对于单跳串和双跳串的情况,线路转角会使得跳线偏离档距所成的垂直平面,引起挂点空间位置的变化,从而造成挂点弦长的测量误差。图8 为考虑线路转角后的跳线连接点空间位置变化关系示意图,G点为横担悬挂点,M、N分别表示跳线在耐张绝缘子上的挂点,P为跳线安装前跳串绝缘子挂点位置,Q则表示跳线安装后的跳串绝缘子挂点位置。 Since the jumper is a space curve, when the jumper is a non-jump string, no matter how the spatial position of the two suspension points changes, the jumper and the two suspension points are always in the same plane, and the line corner will not affect the accuracy of the jumper. In the case of single-jump strings and double-jump strings, the corner of the line will cause the jumper to deviate from the vertical plane formed by the span, causing changes in the spatial position of the hanging point, thereby causing measurement errors in the chord length of the hanging point. Figure 8 is a schematic diagram of the spatial position change relationship of the jumper connection point after considering the line corner. Point G is the cross-arm suspension point, M and N respectively represent the hanging points of the jumper on the tension insulator, and P is the jumper string before installation The position of the hanging point of the insulator, and Q indicates the hanging point position of the jumper insulator after the jumper is installed. the
由于跳线安装前后平面GMP与GMQ,GNP与GNQ间存在夹角α,并不位于同一平面内,造成了测量的挂点弦长与安装后的实际挂点弦长并不一致,即MP≠MQ、NP≠NQ,长度l发生了偏差。 Because there is an included angle α between GMP and GMQ, GNP and GNQ before and after the installation of the jumper, they are not located in the same plane, resulting in a discrepancy between the measured chord length of the hanging point and the actual hanging point chord length after installation, that is, MP≠MQ , NP≠NQ, the length l deviates. the
由计算可知MP与MQ存在下列关系: It can be seen from the calculation that there is the following relationship between MP and MQ:
式中MP、NP为跳线安装前测量到的引流板上挂点到跳串上导线挂孔的距离。QP、∠MPN按下式计算: In the formula, MP and NP are the distances from the hanging point on the drainage plate to the wire hanging hole on the jumper string measured before the jumper is installed. QP and ∠MPN are calculated according to the following formula:
其中,d为跳串绝缘子长度,MN是引流板两上挂点间的距离。在考虑线路转角影响的情况下,线长计算公式中跳线弦长l应代入的是MQ、NQ的值,而不是MP、NP。通过多个工程应用,在偏角α<5°时,线路转角对跳线精度的影响很小,一般可忽略。 Among them, d is the length of the jump string insulator, and MN is the distance between the two hanging points of the diversion plate. In the case of considering the influence of the line corner, the jumper chord length l in the line length calculation formula should be substituted into the values of MQ and NQ instead of MP and NP. Through multiple engineering applications, when the deflection angle α<5°, the influence of the line rotation angle on the jumper accuracy is very small, which can generally be ignored. the
在上述弧垂修正处理及线路转角修正时,及得到修正后的跳线长之后,需要的数据测量方法如下: During the above-mentioned sag correction processing and line corner correction, and after obtaining the corrected jumper length, the required data measurement methods are as follows:
高空测量数据需要准备的工具有软梯和钢卷尺(误差小)。上塔测量尺寸,统一将钢尺的零点放在线路的大号侧,测量位置要放在挂点中心。对于无跳串的情况可以直接测量距离l,横担下平面到跳线两边引流板上挂点连线的垂直距离f0的测量可用绳索将两引流板的上挂点相连,在横担中点处放一把水 平尺,量取水平尺与左上子导线两挂点连线的垂直距离。单跳串的情况,为了方便塔上作业人员的操作可以先测出l1和l1+l2,再计算出l2。双跳串的情况,先量出l1、l1+l2和l1+l2+l3,再计算得出l2和l3,测量表格见附件。特别需要注意的是线号要确定准确,一般四根子导线中上面两根的弦长测量值相差不大,下面两根相差不大,测量时可用此原则初步确定测量值是否准确。 The tools that need to be prepared for high-altitude measurement data include a soft ladder and a steel tape measure (with small error). Go up the tower to measure the size, put the zero point of the steel ruler on the large side of the line uniformly, and place the measurement position at the center of the hanging point. For the case of no jumping string, the distance l can be directly measured, and the vertical distance f0 of the line between the lower plane of the cross-arm and the hanging point on the two sides of the jumper can be measured by using a rope to connect the upper hanging points of the two drainage plates, in the cross-arm Put a level ruler at the point, and measure the vertical distance between the level ruler and the line connecting the two hanging points of the upper left sub-conductor. In the case of a single jump string, l 1 and l 1 + l 2 can be measured first, and then l 2 can be calculated to facilitate the operation of the operators on the tower. In the case of double jump strings, first measure l 1 , l 1 +l 2 and l 1 +l 2 +l 3 , and then calculate l 2 and l 3 , see the attachment for the measurement table. Special attention should be paid to the accurate determination of the wire number. Generally, the measured values of the upper two chord lengths of the four sub-conductors are not much different, and the lower two are not much different. This principle can be used to preliminarily determine whether the measured values are accurate during measurement.
计算出跳线割线线长后,为避免测量引起的误差,导线量取方法需规范:应左手将钢卷尺紧压在导线上,右手大拇指在卷尺上,食指在卷尺下,捋着卷尺紧贴导线向前量取,同时量取者前后都需有人将卷尺和导线按在一起。 After calculating the length of the jumper secant line, in order to avoid errors caused by the measurement, the method of measuring the wire should be standardized: the steel tape should be pressed tightly on the wire with the left hand, the thumb of the right hand should be on the tape, and the index finger should be under the tape. Close to the wire and measure it forward, and at the same time, someone needs to press the tape measure and the wire together before and after the measurer. the
跳线量取完毕后画印,就地割线,然后可按照设计要求将间隔棒的安装位置在1号子导线上画印。跳线两端引流板压接完毕后上塔安装跳线,使用人力提升滑车(Φ15尼龙绳)进行导线起吊。在跳线安装整个过程中,要使用软梯作为施工人员承力工具,下端用小绳拽住调节与跳串及引流线的距离。按1号子导线上间隔棒的画印位置安装间隔棒,并使其垂直于其余三根子导线,这样可以大大缩短施工时间。 After the jumper is measured, draw and print, cut the line on the spot, and then draw and print the installation position of the spacer bar on the No. 1 sub-conductor according to the design requirements. After crimping the diversion plates at both ends of the jumper, install the jumper on the tower, and use the human lifting block (Φ15 nylon rope) to lift the wire. During the whole process of jumper installation, the soft ladder should be used as a load-bearing tool for construction personnel, and the lower end should be held by a small rope to adjust the distance from the jumper and the drainage line. Install the spacer bar according to the printed position of the spacer bar on the No. 1 sub-conductor, and make it perpendicular to the other three sub-conductors, which can greatly shorten the construction time. the
下面对耐张塔跳线装配式制作工艺扩展: The following is an expansion of the fabrication process of the tension tower jumper assembly:
跳线两挂点间的弦长、高差一般都是由高空作业人员上塔测量,效率相对较低。若利用全站仪来测量塔上两点间的距离,则可省去高空作业,既保证了安全性,也提高了工作效率,测量原理如图9所示。假设距离AD是塔上需要测量的两点距离,全站仪位于点O,点B、C分别是点A、D在水平面上的垂直投影,利用全站仪测出仰角∠AOB、∠DOC、水平角∠BOC以及全站仪与被测点的距离OA、OD。由图9所示的空间关系,过点A作AE∥BC交DC于点E,则AE﹦BC,AE⊥DC,点A与点D的高差DE可测。AD的长度可按下列公式计算得到。 The chord length and height difference between the two hanging points of the jumper are generally measured by workers working at heights on the tower, and the efficiency is relatively low. If a total station is used to measure the distance between two points on the tower, high-altitude operations can be omitted, which not only ensures safety, but also improves work efficiency. The measurement principle is shown in Figure 9. Assuming that the distance AD is the distance between two points to be measured on the tower, the total station is located at point O, and points B and C are the vertical projections of points A and D on the horizontal plane respectively. Use the total station to measure the elevation angles ∠AOB, ∠DOC, The horizontal angle ∠BOC and the distance OA and OD between the total station and the measured point. According to the spatial relationship shown in Figure 9, if AE∥BC passes through point A and intersects DC at point E, then AE﹦BC, AE⊥DC, and the height difference DE between point A and point D can be measured. The length of AD can be calculated according to the following formula. the
其中,OB=OA·cos∠AOB,OC=OD·cos ∠DOC。 Among them, OB=OA·cos∠AOB, OC=OD·cos∠DOC. the
本发明实施例的有益效果在于,本发明的输电线路耐张塔跳线安装方法通过进行压接修正、弧垂修正及线路转角修正处理,能够精确的测量跳线长,提高了跳线安装的效率。 The beneficial effect of the embodiment of the present invention is that the jumper installation method of the tension tower of the transmission line according to the present invention can accurately measure the length of the jumper by performing crimping correction, sag correction and line corner correction, and improves the installation efficiency of the jumper. efficiency. the
以上所述的具体实施例,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施例而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。 The specific embodiments described above have further described the purpose, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above descriptions are only specific embodiments of the present invention and are not intended to limit the scope of the present invention. Protection scope, within the spirit and principles of the present invention, any modification, equivalent replacement, improvement, etc., shall be included in the protection scope of the present invention. the
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210475747.3A CN103022945B (en) | 2012-11-21 | 2012-11-21 | Method for mounting jumper wire of power transmission line tension-resisting tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210475747.3A CN103022945B (en) | 2012-11-21 | 2012-11-21 | Method for mounting jumper wire of power transmission line tension-resisting tower |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103022945A true CN103022945A (en) | 2013-04-03 |
CN103022945B CN103022945B (en) | 2015-07-08 |
Family
ID=47971216
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210475747.3A Active CN103022945B (en) | 2012-11-21 | 2012-11-21 | Method for mounting jumper wire of power transmission line tension-resisting tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103022945B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107248711A (en) * | 2017-04-29 | 2017-10-13 | 中国能源建设集团安徽电力建设第工程有限公司 | One kind collection electric line ground wire erection method |
CN108471084A (en) * | 2018-03-08 | 2018-08-31 | 国网山东省电力公司经济技术研究院 | Assembled carbon-fibre wire erection method |
CN110727970A (en) * | 2019-10-22 | 2020-01-24 | 华北电力大学(保定) | Calculation method of wind deflection of jumper with large height difference under zero degree wind |
CN114172069A (en) * | 2021-09-26 | 2022-03-11 | 中国能源建设集团江苏省电力设计院有限公司 | Method for determining three-dimensional hard jumper scheme of strain tower |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4323722A (en) * | 1980-09-24 | 1982-04-06 | The United States Of America As Represented By The United States Department Of Energy | Overhead electric power transmission line jumpering system for bundles of five or more subconductors |
JPH06327113A (en) * | 1993-05-10 | 1994-11-25 | Chubu Electric Power Co Inc | Suspension type jumper and its wiring work method |
CN201536243U (en) * | 2009-07-06 | 2010-07-28 | 中国电力工程顾问集团公司 | Jumper device of ultrahigh-voltage voltage-resistant tower |
-
2012
- 2012-11-21 CN CN201210475747.3A patent/CN103022945B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4323722A (en) * | 1980-09-24 | 1982-04-06 | The United States Of America As Represented By The United States Department Of Energy | Overhead electric power transmission line jumpering system for bundles of five or more subconductors |
JPH06327113A (en) * | 1993-05-10 | 1994-11-25 | Chubu Electric Power Co Inc | Suspension type jumper and its wiring work method |
CN201536243U (en) * | 2009-07-06 | 2010-07-28 | 中国电力工程顾问集团公司 | Jumper device of ultrahigh-voltage voltage-resistant tower |
Non-Patent Citations (2)
Title |
---|
邹广平等: "考虑弯曲刚度影响的跳线长度计算", 《哈尔滨工程大学学报》, vol. 26, no. 4, 31 August 2005 (2005-08-31), pages 482 - 486 * |
黄成云: "500KV输电线路耐张塔4-4跳线长度的计算", 《电力建设》, no. 4, 30 April 1997 (1997-04-30), pages 57 - 63 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107248711A (en) * | 2017-04-29 | 2017-10-13 | 中国能源建设集团安徽电力建设第工程有限公司 | One kind collection electric line ground wire erection method |
CN108471084A (en) * | 2018-03-08 | 2018-08-31 | 国网山东省电力公司经济技术研究院 | Assembled carbon-fibre wire erection method |
CN110727970A (en) * | 2019-10-22 | 2020-01-24 | 华北电力大学(保定) | Calculation method of wind deflection of jumper with large height difference under zero degree wind |
CN110727970B (en) * | 2019-10-22 | 2023-05-26 | 华北电力大学(保定) | Zero-degree wind large-height-difference jumper wind deflection calculation method |
CN114172069A (en) * | 2021-09-26 | 2022-03-11 | 中国能源建设集团江苏省电力设计院有限公司 | Method for determining three-dimensional hard jumper scheme of strain tower |
CN114172069B (en) * | 2021-09-26 | 2024-04-30 | 中国能源建设集团江苏省电力设计院有限公司 | Method for determining three-dimensional hard jumper scheme of tension tower |
Also Published As
Publication number | Publication date |
---|---|
CN103022945B (en) | 2015-07-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101007503B1 (en) | Transmission Line Determination Method | |
CN103401183B (en) | A kind of assembly type overhead method | |
CN103022945B (en) | Method for mounting jumper wire of power transmission line tension-resisting tower | |
CN109458988B (en) | Holding pole inclination angle measuring method based on UWB wireless distance measuring technology | |
CN111222236A (en) | A method and analyzer for calculating the cutting length of flexible conductors in substations | |
CN105222737B (en) | Transmission line of electricity bow line sag measuring method | |
CN104201631A (en) | GIS (geographic information system) based three-dimensional jumper sag determination method | |
CN103268379A (en) | Precise Calculation Method for Interphase Distance of Spatial Sections at Arbitrary Positions of Overhead Transmission Conductors | |
CN106813585A (en) | A kind of conductor spacer range measurement and installation method | |
CN110906872B (en) | Method for observing and adjusting lead through high-efficiency gear side sag | |
CN204835411U (en) | Special high voltage direct current engineering polar line wall bushing arrangement structure | |
KR101543529B1 (en) | Dip measurement method | |
CN106570239B (en) | Calculation method and device for cutting length of soft busbar | |
CN101915566A (en) | A method for measuring the lightning shielding rate when the two ends of the overhead transmission line span are not equal in height | |
CN107179056A (en) | A kind of measuring method of the special isolated shelves conductor spacing of power circuit | |
CN202674539U (en) | Vertical diameter-changing height-adjusting device universally used for ocean platform bridge frames | |
CN202612860U (en) | Ocean platform bridge frame universal dextrorotatory elbow | |
CN110906871B (en) | Method for observing and adjusting lead through gear side sag | |
CN217947163U (en) | Corner unwrapping wire and measuring device of supplementary cable laying | |
CN114389222B (en) | Method for calculating length of isolated gear phase spacer of power transmission line | |
CN205333060U (en) | Simple and easy squareness measurement instrument | |
CN202674540U (en) | Tee transition device universally used for ocean platform bridge frames | |
CN104993418B (en) | A kind of supporting straightener of connecting tube used for large-section conducting wire protective device | |
CN117109514A (en) | Method and device for determining sag value of lead and electronic equipment | |
CN202674541U (en) | Narrow adjusting tee device universally used for ocean platforms |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |