CN103008972A - Blade replacing and installing method of wind generating set - Google Patents

Blade replacing and installing method of wind generating set Download PDF

Info

Publication number
CN103008972A
CN103008972A CN2012105789005A CN201210578900A CN103008972A CN 103008972 A CN103008972 A CN 103008972A CN 2012105789005 A CN2012105789005 A CN 2012105789005A CN 201210578900 A CN201210578900 A CN 201210578900A CN 103008972 A CN103008972 A CN 103008972A
Authority
CN
China
Prior art keywords
blade
mounting method
lifting
generating set
impeller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012105789005A
Other languages
Chinese (zh)
Inventor
陈若旺
陈金龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Original Assignee
Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Goldwind Science and Creation Windpower Equipment Co Ltd filed Critical Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Priority to CN2012105789005A priority Critical patent/CN103008972A/en
Publication of CN103008972A publication Critical patent/CN103008972A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Wind Motors (AREA)

Abstract

The invention discloses a blade replacing and installing method of a wind generating set. The blade mounting method of the wind generating set comprises the following steps: vertically upward or downward of a blade mounting position; hoisting the blades and adjusting the blades to be in a vertical state; and vertically installing the hoisted blade to the one blade installation position. The installation method provided by the invention is efficient, environment-friendly and cost-saving, and an impeller driving device is not required.

Description

The blade exchanging of wind power generating set and installation method
Technical field
The present invention relates to the wind power generating set field, more particularly, relate to a kind of blade exchanging method and installation method of wind power generating set.
Background technology
Be prone to leaf destruction after the blade of traditional wind power generating set is struck by lightning, need this moment to change new blade to recover normal operation.The method that tradition is changed blade is the impeller integral demounting that bad blade will be arranged first, and impeller after being put into ground is extractd damaged blade, loads onto new blade, then impeller integral body is installed.
The reason of damaging owing to wind generator set blade is struck by lightning and leaf destruction occurred, thus blade damage after impeller can disequilibrium.Be affected by gravity, impeller can pick up poised state automatically, that is, impeller can become " people " word state usually, and broken blade vertically up.
Therefore, the replacing method of existing wind power generating set damaged blade is as follows:
Step 1: the supporting suspender belt of the suspension hook of crane is hung on the wind power generating set outer rotor hanger, so that the power that makes vane rotary to be provided.
Step 2: make vane rotary 180 degree by the crane lifting force, make broken blade vertically down, in this process hoist lifting hook and wind power generating set outer rotor hanger are broken away from, and be locked into just " Y " state, because the impeller of hanging belt blade need three blades be " Y " shape (be impeller vertically up direction blade can not be arranged) just make things convenient for hanging hook and suspender, if and rotate 60 degree or 120 degree can cause impeller and blade integral deviation of gravity center (because having broken blade), so can only the Rotate 180 degree.
Step 3: by crane with the impeller of damaged blade pluck from, and impeller put to ground.
Step 4: on ground the broken blade on the impeller is removed, and new blade is assembled, then impeller integral body is lifted, so far, blade exchanging is finished.
The method of this replacing blade promotes by crane and orders about vane rotary 180 degree, and this work progress operation is many, have a big risk, long construction period, cost height.In addition, the impeller demolition process construction risk of broken blade is large, difficulty of construction is large.And it is many that dismounting impeller process is scrapped spare part, and can bring the hidden failures source to the wind power generating set miscellaneous part.
In addition, when the impeller of traditional wind power generating set was installed, its conventional way was first wheel hub to be lifted to tower top, then with wheel hub locking be a blades installation position towards level, level lifts first blade and attaches it to the position afterwards.Then unclamp wheel hub and adjust its position, again with wheel hub locking be another blades installation position towards level, then lift and install second blade.Lift after the same method at last and install the 3rd blade, thereby form the assembly of three blades and wheel hub, thereby finish the installation of impeller.
In this impeller installation method, because the angle that in the individual blade hoisting process, needs to regulate impeller, so wind power generating set need to possess the vane rotary driving mechanism, and many, the long construction period of hoisting process construction procedure.
Therefore, be necessary to propose a kind of new blade exchanging and installation method effectively to overcome the above problems.
Summary of the invention
The object of the present invention is to provide the blade exchanging method of the simple wind power generating set of a kind of arrangement and method for construction.
Another object of the present invention is to provide the mounting method for blade of the wind power generating set that a kind of construction site reduces.
Another object of the present invention is to provide a kind of blade exchanging method and installation method of wind power generating set, and need not impeller driving device.
According to an aspect of the present invention, provide a kind of blade exchanging method of wind power generating set, comprise the steps: to make the blade that needs to change to keep vertically up; Unload the blade that needs replacing; Lift new blade and new blade is adjusted into vertical state; The new blade of lifting is in place vertically.
The mode that lifts new blade can lift for level.
Can utilize crane and suspender to carry out lifting and the adjustment of new blade.
The blade that needs to change is kept vertically up.
According to a further aspect in the invention, provide a kind of mounting method for blade of wind power generating set, comprise the steps: to make a blades installation position to keep vertically down; Hoisting blade also is adjusted into vertical state with blade; The blade of lifting is installed to a described blades installation position vertically; Continue to install two other blade.
A described blades installation position is kept vertically down.
Continuing to install two other blade can keep carrying out under the vertical state down at a blade of having installed.
Two other blade continue to be installed can carry out under the locked state of the wheel hub of impeller.
Can carry out the step that two other blade is installed in described continuation by the position that successively installation site of two other blade is adjusted to vertically down.
The mode of hoisting blade can be the level lifting.
Can utilize crane and suspender to carry out lifting and the adjustment of blade.
According to a further aspect in the invention, provide a kind of mounting method for blade of wind power generating set, comprise the steps: to make a blades installation position vertically or vertically down up; Hoisting blade also is adjusted into vertical state with blade; The blade of lifting is installed to a described blades installation position vertically.
The mode of hoisting blade can be the level lifting.
Can utilize crane and suspender to carry out the lifting of blade.
Described blades installation position is kept vertically up or vertically down.
Blades installation or replacing method are preferentially changed or are installed the blades installation position that is in vertical state under the natural balanced state of impeller according to an embodiment of the invention, not only technique is simple, and need not impeller driving device, greatly reduced construction cost.In addition, said method takes up an area little, and high-efficiency environment friendly is with a wide range of applications.
Description of drawings
By the description of carrying out below in conjunction with accompanying drawing, above and other purpose of the present invention and characteristics will become apparent, wherein:
Fig. 1 to Fig. 5 is the schematic diagram that illustrates according to the method for the damaged blade of the replacing wind power generating set of the first embodiment of the present invention.
Fig. 6 to Fig. 8 is the schematic diagram that the blade of installation wind power generating set according to a second embodiment of the present invention is shown.
The specific embodiment
Below, describe embodiments of the invention in detail with reference to accompanying drawing.
The below is with reference to the method for Fig. 1 to Fig. 5 description according to the damaged blade of the replacing wind power generating set of the first embodiment of the present invention.
When leaf destruction or when damaging, the quality of blade can change (that is, reducing).As shown in Figure 1, the impeller that is supported by the tower cylinder 40 of wind-driven generator is owing to be subjected to the impact of Gravity changer, and the blade 10 of usually fracture can be vertically up.In according to an embodiment of the invention replacing method, impeller need to be locked into " people " font or inverted Y-shaped state, namely, all the time (blade vertically up the meaning is the blade 10 that makes fracture vertically up, blade tip blade root vertically directly over, be blade tip up, blade root is down), then utilize crane 1 and suspender 2 with the fracture blade 10 disassemble.In this process, the certain pulling force of the essential maintenance of the suspension hook of crane 1, suspender should keep certain clamping force, with the blade landing that prevents from rupturing.
Then, as shown in Figure 2, the blade 10 of fracture is disassembled from wheel hub, so that blade 10 can break away from fully with wheel hub, then cooperate with suspender 2 by crane 1, the suspension hook of crane 1 is promoted, suitable place can be plucked from and be placed on to vertical broken blade 10 up.
Then, as shown in Figure 3 and Figure 4, utilize crane 1 and suspender 2, first new blade 11 levels are risen and winch to aerial correct position, then level is worked winching to aerial new blade 11 and be rotated 90 degree, the root that makes new blade 11 down and blade tip up, thereby new blade 11 is adjusted into vertical state.Wherein, can utilize many known modes such as two crane cooperations, special hanger, manpower are auxiliary to carry out the adjustment of Leaf orientation, be not described in detail at this.
At last, as shown in Figure 5, the new blade 11 that crane 1 will be in vertical state promotes, and its position of mounting hole that lifts to the wheel hub of the impeller of wind power generating set is assembled, and can finish the replacing of blade.
According to top aspect, not only reduced the blade exchanging construction procedure, and reduced the risk of blade exchanging process, and reduced therefrom the blade exchanging cost.In addition, owing to do not need to adjust the attitude of impeller, therefore need not impeller drive in the said method.
The below describes the mounting method for blade of wind power generating set according to a second embodiment of the present invention in detail with reference to Fig. 6 to Fig. 8.
As shown in Figure 6, lift at first separately wheel hub 50, and three blades installation locking positions on the wheel hub 50 are become positive Y shape shape.
Then, as shown in Figure 7, vertical blade (being so-called slipping tail blade) 110 down is assembled on the wheel hub 50, forms the new impeller of a blade 110 and wheel hub 50 assemblys.
The method of the mode of hoisting blade 110 and hoisting blade 11 is similar, mainly comprise the steps: to utilize crane 1 and suspender 2, first new blade 110 levels are risen and winch to aerial correct position, then level is risen winch to aerial new blade 110 be rotated 90 the degree, the root that makes new blade 110 up and blade tip down, thereby new blade 110 is adjusted into vertical state, wherein, can utilize many known modes such as two crane cooperations, special hanger, manpower are auxiliary to carry out the adjustment of Leaf orientation, be not described in detail at this.
Security consideration for construction technology; the blade parallel with tower cylinder 40 is installed first down at first can be reduced wind area and avoid the scene to blow causing impeller to rock the risk brought; next is the problem of having considered the impeller gravity balance; because fill first towards lower blade 110 relatively steadily reliable; and this moment, the stop pin of impeller hub did not need work, and rationed marketing is a kind of protection to impeller lock.
Then, keep the attitude of new impeller constant, again utilize crane 1 and suspender 2 that two other blade 120 and 130 is installed successively, thereby finish the installation of impeller, as shown in Figure 8.
Yet, the invention is not restricted to this, for blade 120 and 130, also can carry out successively according to the installation method of prior art level and install, be not described in detail at this.
By utilizing top mounting method for blade, have at least following advantage:
(1) reduces installation wind power generating set construction site usable floor area, reduced wind energy turbine set vegetation deterioration area, reduced owner's construction cost;
(2) solved can not single leaf blade hanging without the wind power generating set of vane rotary driving mechanism problem;
(3) reduce wind power generating set impeller installation procedure, raised labour efficiency reducing construction cost.
By top detailed description, can be clear that, blades installation or replacing method are preferentially changed or are installed the blades installation position that is in vertical state under the natural balanced state of impeller according to an embodiment of the invention, not only technique is simple, and need not impeller driving device, greatly reduced construction cost.In addition, said method takes up an area little, and high-efficiency environment friendly is with a wide range of applications.
Although illustrated in conjunction with the embodiments and described the present invention, it will be apparent to one skilled in the art that and in the situation that does not break away from the spirit and scope of the present invention that are defined by the claims, can make amendment and modification.

Claims (15)

1. the blade exchanging method of a wind power generating set comprises the steps:
The blade that needs to change is kept vertically up;
Unload the blade that needs replacing;
Lift new blade and new blade is adjusted into vertical state;
The new blade of lifting is in place vertically.
2. blade exchanging method as claimed in claim 1, wherein, the mode that lifts new blade is the level lifting.
3. blade exchanging method as claimed in claim 1 wherein, utilizes crane and suspender to carry out lifting and the adjustment of new blade.
4. blade exchanging method as claimed in claim 1, wherein, the wheel hub by locked impeller keeps vertically up the blade that needs to change.
5. the mounting method for blade of a wind power generating set comprises the steps:
Wheel hub is in place;
A blades installation position is kept vertically down;
Hoisting blade also is adjusted into vertical state with blade;
The blade of lifting is installed to a described blades installation position vertically;
Continue to install two other blade.
6. mounting method for blade as claimed in claim 5, wherein, the wheel hub by locked impeller keeps vertically down a described blades installation position.
7. mounting method for blade as claimed in claim 6 wherein, continues to install two other blade and keeps carrying out under the vertical state down at a blade of having installed.
8. mounting method for blade as claimed in claim 7 wherein, continues to install two other blade and carries out under the locked state of the wheel hub of impeller.
9. mounting method for blade as claimed in claim 5 wherein, is carried out the step that two other blade is installed in described continuation by the position that successively installation site of two other blade is adjusted to vertically down.
10. mounting method for blade as claimed in claim 5, wherein, the mode of hoisting blade is the level lifting.
11. mounting method for blade as claimed in claim 5 wherein, utilizes crane and suspender to carry out lifting and the adjustment of blade.
12. the mounting method for blade of a wind power generating set comprises the steps:
Make a blades installation position vertically or vertically down up;
Hoisting blade also is adjusted into vertical state with blade;
The blade of lifting is installed to a described blades installation position vertically.
13. mounting method for blade as claimed in claim 12, wherein, the mode of hoisting blade is the level lifting.
14. mounting method for blade as claimed in claim 12 wherein, utilizes crane and suspender to carry out the lifting of blade.
15. mounting method for blade as claimed in claim 12, wherein, the wheel hub by locked impeller keeps vertically up a described blades installation position or vertically down.
CN2012105789005A 2012-12-27 2012-12-27 Blade replacing and installing method of wind generating set Pending CN103008972A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012105789005A CN103008972A (en) 2012-12-27 2012-12-27 Blade replacing and installing method of wind generating set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012105789005A CN103008972A (en) 2012-12-27 2012-12-27 Blade replacing and installing method of wind generating set

Publications (1)

Publication Number Publication Date
CN103008972A true CN103008972A (en) 2013-04-03

Family

ID=47958376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012105789005A Pending CN103008972A (en) 2012-12-27 2012-12-27 Blade replacing and installing method of wind generating set

Country Status (1)

Country Link
CN (1) CN103008972A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104625562A (en) * 2014-12-23 2015-05-20 新疆金风科技股份有限公司 Method of correcting blade dislocation of wind generating set
CN104646918A (en) * 2015-01-16 2015-05-27 南车株洲电力机车研究所有限公司 Replacing method for blade of wind generating set
CN105883602A (en) * 2016-06-24 2016-08-24 成都世唯科技有限公司 Fan blade hanger support with clamp mechanism
CN107150946A (en) * 2017-06-29 2017-09-12 湖北三江航天江河化工科技有限公司 A kind of wing plate boom hoisting and its hanging method
CN111765049A (en) * 2020-07-10 2020-10-13 大连理工大学 Structure for replacing wind driven generator of reservoir or lake and using method thereof
CN114837895A (en) * 2022-03-30 2022-08-02 国能思达科技有限公司 Method for replacing variable-pitch bearing of wind generating set

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1688808A (en) * 2002-05-27 2005-10-26 威斯塔斯风力系统公开有限公司 Methods of handling wind turbing blades and mounting said blades a wind turbine, system and gripping unit for handling a wind turbine blade
CN101823672A (en) * 2009-02-25 2010-09-08 通用电气公司 Fall and rise single wind turbine rotor blade from six-o ' clock position
CN101929443A (en) * 2009-10-26 2010-12-29 华锐风电科技(集团)股份有限公司 Blade self-replacement device of wind driven generator set and working method thereof
CN102400862A (en) * 2011-09-29 2012-04-04 江苏金风风电设备制造有限公司 Method for assembling impeller of wind power generator unit
CN102438932A (en) * 2009-04-29 2012-05-02 西门子公司 Blade lifting system with saloon doors
US20120141280A1 (en) * 2010-12-03 2012-06-07 AVAILON GmbH Method and apparatus for turning a rotor blade bearing on wind turbines without using a mobile crane
EP2481912A1 (en) * 2011-01-28 2012-08-01 LM Wind Power A/S Method of attaching a repair platform to a wind turbine
CN202390071U (en) * 2011-12-02 2012-08-22 新疆金风科技股份有限公司 Blade change auxiliary system of wind-power generator set
CN102650261A (en) * 2012-05-18 2012-08-29 中国十七冶集团有限公司 Segmental lifting method for impeller of high-power wind driven generator

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1688808A (en) * 2002-05-27 2005-10-26 威斯塔斯风力系统公开有限公司 Methods of handling wind turbing blades and mounting said blades a wind turbine, system and gripping unit for handling a wind turbine blade
CN101823672A (en) * 2009-02-25 2010-09-08 通用电气公司 Fall and rise single wind turbine rotor blade from six-o ' clock position
CN102438932A (en) * 2009-04-29 2012-05-02 西门子公司 Blade lifting system with saloon doors
CN101929443A (en) * 2009-10-26 2010-12-29 华锐风电科技(集团)股份有限公司 Blade self-replacement device of wind driven generator set and working method thereof
US20120141280A1 (en) * 2010-12-03 2012-06-07 AVAILON GmbH Method and apparatus for turning a rotor blade bearing on wind turbines without using a mobile crane
EP2481912A1 (en) * 2011-01-28 2012-08-01 LM Wind Power A/S Method of attaching a repair platform to a wind turbine
CN102400862A (en) * 2011-09-29 2012-04-04 江苏金风风电设备制造有限公司 Method for assembling impeller of wind power generator unit
CN202390071U (en) * 2011-12-02 2012-08-22 新疆金风科技股份有限公司 Blade change auxiliary system of wind-power generator set
CN102650261A (en) * 2012-05-18 2012-08-29 中国十七冶集团有限公司 Segmental lifting method for impeller of high-power wind driven generator

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104625562A (en) * 2014-12-23 2015-05-20 新疆金风科技股份有限公司 Method of correcting blade dislocation of wind generating set
CN104646918A (en) * 2015-01-16 2015-05-27 南车株洲电力机车研究所有限公司 Replacing method for blade of wind generating set
CN105883602A (en) * 2016-06-24 2016-08-24 成都世唯科技有限公司 Fan blade hanger support with clamp mechanism
CN105883602B (en) * 2016-06-24 2017-07-14 成都世唯科技有限公司 The fan blade suspender support of tape clamp mechanism
CN107150946A (en) * 2017-06-29 2017-09-12 湖北三江航天江河化工科技有限公司 A kind of wing plate boom hoisting and its hanging method
CN111765049A (en) * 2020-07-10 2020-10-13 大连理工大学 Structure for replacing wind driven generator of reservoir or lake and using method thereof
CN114837895A (en) * 2022-03-30 2022-08-02 国能思达科技有限公司 Method for replacing variable-pitch bearing of wind generating set

Similar Documents

Publication Publication Date Title
CN103008972A (en) Blade replacing and installing method of wind generating set
KR101094475B1 (en) Method of mounting rotor for wind-driven generator and method of constructing wind-driven generator
EP2369174B1 (en) A method of craneless mounting or demounting of a wind turbine blade
EP2224126A2 (en) Lowering and raising a single wind turbine rotor blade from six-o'clock position
ES2322000B1 (en) A METHOD FOR MOUNTING THE ROTOR OF AN AIRBRUSHER.
CN102192111B (en) Installation method of blades of offshore wind turbine
US10508645B2 (en) System and method for suspending a rotor blade of a wind turbine uptower
CN101858308A (en) Wind power generator
NZ583572A (en) Method to install wind-turbine blades where the blades are transported to site attached to the tower
GB2487083A (en) Wind turbine blade bearing removal apparatus and method
CN203128000U (en) Hoisting device for direct-driven wind power generator set
CN105129629B (en) Large component lifting system, disassembling method thereof and large component lifting method
CN103133267B (en) The blade exchanging method of wind power generating set and blade exchanging auxiliary system
CN117105107B (en) Overturning and hoisting system for crane on tower of wind generating set
CN201362955Y (en) Angle self-regulating mounting frame of hoister
CN104646918B (en) Replacing method for blade of wind generating set
CN108105037A (en) Simulated blade device and blade replacement method
CN202483781U (en) Water turbine rotating wheel supporting device
CN102423847B (en) Method for assembling axial-flow movable-blade type hydraulic turbine and support device adopted by axial-flow movable-blade hydraulic turbine
CN108190765A (en) A kind of high tower Wind turbines lifting tire chassis derrick crane
CN206955502U (en) A kind of high tower wind-powered electricity generation lifts crawler body derrick crane
CN110914532B (en) Lifting system for torque bearing of wind driven generator
CN219509756U (en) Wind driven generator blade replacement equipment based on multiple guide units
JP7063977B1 (en) How to remove the blade, how to attach the blade and hanging jig
CN219412790U (en) Wind driven generator blade replacement equipment based on multiple pulley blocks

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130403