CN103003507A - 混凝土提升锚具 - Google Patents
混凝土提升锚具 Download PDFInfo
- Publication number
- CN103003507A CN103003507A CN2010800678359A CN201080067835A CN103003507A CN 103003507 A CN103003507 A CN 103003507A CN 2010800678359 A CN2010800678359 A CN 2010800678359A CN 201080067835 A CN201080067835 A CN 201080067835A CN 103003507 A CN103003507 A CN 103003507A
- Authority
- CN
- China
- Prior art keywords
- bar
- shearing bar
- ground tackle
- concrete
- shank
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/142—Means in or on the elements for connecting same to handling apparatus
- E04G21/147—Means in or on the elements for connecting same to handling apparatus specific for prefabricated masonry wall elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/142—Means in or on the elements for connecting same to handling apparatus
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Road Paving Structures (AREA)
Abstract
一种用于混凝土板用边缘提升锚具的剪力杆,该剪力杆是成形为提供中部和腿部的杆,该中部用于在安装到板中时接合提升锚具的上边缘,腿部从中部的每一端向下倾斜,每个腿部的下侧被成型为锁定在周围混凝土中,型面由一系列纵向间隔的形成物形成,这些形成物中的每一个一般为锯齿形,每个形成物的前缘面朝中部,使得在将剪切荷载施加到剪力杆时,腿部将利用在两个腿部之间的区域中施加到混凝土的大体压缩的荷载锁定在混凝土内。
Description
本发明涉及用于在架设期间提升诸如墙板的浇注混凝土产品的过程中使用的锚具。更具体地,本发明涉及用于与边缘提升锚具一起使用的剪力杆。
在现场外预制场或现场进行的预制混凝土墙板的制造过程中,需要将墙板从其被浇注的水平构型提升到用于运输和/或架设的竖直构型。对于现场外浇注和某些现场浇注情况来说,板的提升从板的边缘进行,该边缘为处于架设状态的板的上边缘。为此,所谓的边缘提升锚具在浇注之前被并入板的加强结构中。在浇注期间,锚具的头部包封在可移除或一次性的空模具内以在板的边缘表面内形成凹部,锚具的头部处于该凹部内以便可释放地联接到起重设备。
目前可得到各种形式的边缘提升锚具。在当板处于其浇注之后的水平构型时边缘提升开始时,锚具在横向于板的上表面的方向上经受相当大的剪切荷载。为了抵抗这种剪切荷载,锚具与接合锚具主体上边缘的剪力杆相关联。常规地,剪力杆由一段加强杆形成,并且因此具有基本上圆形的横截面,该横截面适当地弯曲以上覆锚具主体的上边缘并进一步伸入板的深度内。剪力杆必须具有足够的尺寸以承载和分布荷载。就这一点而言,常规剪力杆的潜在失效模式是所谓的混凝土的失效锥的失效模式,其从杆的外边缘延伸至板的上表面。杆正下方的混凝土区基本上受拉伸荷载,并且因此不有助于剪力杆和板之间的荷载分布。换言之,杆不锁定在其下面的混凝土中,并且杆借助于其形状以及混凝土和杆表面之间的摩擦粘结强度而与其上面的混凝土互锁。在提升开始时,用于抑制杆的向上移动的杆上方的混凝土被置于张力中且不提供高抵抗力。剪力杆的尺寸需要允许实现这一目的。
本发明涉及一种剪力杆,其以相比常规剪力杆更有效的方式锁定在混凝土中。
根据本发明,提供了一种用于混凝土板用边缘提升锚具的剪力杆,该剪力杆是成形为提供中部和腿部的杆,该中部用于在安装到板中时接合提升锚具的上边缘,腿部从中部的每一端向下倾斜,每个腿部的下侧被成型为锁定在周围混凝土中,型面由一系列纵向间隔的形成物形成,这些形成物中的每一个一般为锯齿形,每个形成物的前缘面朝中部,使得在将剪切荷载施加到剪力杆时,腿部将利用在两个腿部之间的区域中施加到混凝土的大体压缩的荷载锁定在混凝土内。
在一个优选的实施例中,杆具有大体平坦的横截面,该横截面被构造成使得杆的大面积表面向上面向在提升板之前处于安装位置的板的上表面。
现在将仅以举例方式结合附图描述本发明的各实施例,在附图中:
图1是透视图,示出了其上安装有根据本发明的剪力杆的边缘提升锚具;
图2是端视图;
图3是平面图;
图4是侧视图;
图5是类似于图2的片段端视图,并且处于放大的比例以更好示出剪力杆的锁定形成物的细节;
图6是类似于图1的视图,但具有形成为不同构型的剪力杆;以及
图7是端视图。
图1至图4示出了处于其安装后的位置的边缘提升锚具2,该锚具用于将板从其中板的上表面为水平的浇注构型提升。锚具具有用于联接到起重装置的头部4和具有一对基本上平行的腿部6的形式的锚固部分,腿部6从头部4延伸。所示特定头部4设计用于与环形离合器形式的起重离合器以及接纳在头部的眼内的弓形锁定螺栓配合,但应当理解,头部可具有不同的详细设计以与其它类型的起重装置一起使用。腿部6沿其内边缘成型有锯齿轮廓,以便锁定在周围的混凝土中,但应当理解,腿部可具有用于实现该目的的任何其它形式的轮廓,并且锚固部分可以甚至具有不使用平行腿部的形式。
在其中腿部6沿其内边缘成型有锯齿轮廓的所示实施例中,优选的是详细的轮廓如专利申请2006201337中所描述的那样,该申请的公开内容以引用方式并入本文中。如在该申请中所公开的,型面由具有锯齿状形状的一系列形成物形成,该形成物的前表面表示面朝锚具的头部的锁定部分。该前表面朝头部倾斜,使得在将拉伸荷载施加到头部时,形成物将导致以增加的荷载将腿部更紧密地锁定在混凝土中,并且在承受荷载时作用于形成物上的力的影响之下不会侧向向外偏转。在实践中,锯齿状形成物的前缘的倾斜将施加侧向向内力到两个腿部中的每一个,从而使两个腿部之间的混凝土将承受压缩荷载。
显示为带有平行腿部的一般类型或不带平行腿部的其它形式的锚具通过本领域的技术人员充分理解的切削和/或挤压技术而由厚金属板形成。锚具在其浇注构型中在板中取向为上边缘基本上平行于板的上表面。在所示实施例中,锚具的头部4相对于锚固部分向内成阶梯状,阶梯在附图中标以4a。金属剪力杆8在阶梯4a附近接合头部4的上边缘,如图1和图4中清楚地示出的,但在替代形式中,锚具的边缘可以在头部的基部处设有合适形状的凹部,以接纳和定位剪力杆。
剪力杆8大体上具有平坦横截面,并且成形为在头部4的上边缘上延伸,然后在头部4的每一侧处向下延伸以形成更深地埋入板的厚度内的向下倾斜的部分或腿部8a。杆的外部8b侧向向外(水平地)延伸,以便基本上平行于板的表面平放。其大面积表面向上面向板的上表面的这种形式的平杆的使用提供了大的表面积,这样能比圆形横截面的等同剪力杆更好地承载剪切荷载。
应当指出,向下倾斜的腿部8a中的每一个的下侧形成有锯齿型面,该型面类似于锚具的腿部6的型面,并且被构造成以基本上相同的方式操作。特别地且参照图5,带锯齿的形成物中的每一个具有朝剪力杆8的中部8c倾斜的前缘10,其中杆接合锚具2的边缘,使得当在板从其在浇注期间呈现的水平构型升起时将剪切荷载施加到杆8时,带锯齿的形成物将更牢固地锁定在混凝土中。由于在腿部8a的下侧上的这些形成物所导致的在腿部8a和混凝土之间的内部作用产生侧向向内的力,从而使在两个腿部8a之间的区域中的混凝土经受压缩荷载。由于这种压缩荷载,在剪力杆8的腿部8a和下面的混凝土之间实现强锚固,并且这种锚固对由向上面向板的上表面的杆的大表面积提供的效应提供了显著的补充。因此,由剪力杆提供的承载力显著大于等同的常规剪力杆的承载力。这提供了显著的优点。对于所需承载能力来说,剪力杆可以比当使用常规剪力杆时本来需要的更小,从而降低材料成本。此外,虽然常规剪力杆使板能够在其固化到满强度之前被提升,优选实施例的剪力杆借助于压缩荷载而使板能够在较低的部分固化强度下被提升;因此板能在浇注之后更早地提升,从而为现场外和现场浇注两者提供提高的效率。
图6和图7示出了腿部8a比此前的实施例中更陡峭地倾斜的剪力杆8,该剪力杆可以主要地适用于提升承载力要求降低时的较小部件。应当理解,图6和7的杆使用比此前的实施例更少的材料。
各实施例仅以举例方式描述,并且在本发明的范围内可以进行修改。
Claims (6)
1.一种用于混凝土板用边缘提升锚具的剪力杆,所述剪力杆是成形为提供中部和腿部的杆,所述中部用于在安装到所述板中时接合所述提升锚具的上边缘,所述腿部从所述中部的每一端向下倾斜,每个腿部的下侧被成型为锁定在周围混凝土中,型面由一系列纵向间隔的形成物形成,所述形成物中的每一个一般为锯齿形,每个形成物的前缘面朝所述中部,使得在将剪切荷载施加到所述剪力杆时,所述腿部将利用在所述两个腿部之间的区域中施加到所述混凝土的大体压缩的荷载锁定在所述混凝土内。
2.根据权利要求1所述的剪力杆,其中,所述腿部中的每一个具有基本上水平地延伸的外端部。
3.根据权利要求1或权利要求2所述的剪力杆,其中,所述剪力杆具有矩形横截面,所述横截面具有相对的大面积表面和相对的较小面积表面,并且被构造成使得所述中部用其大面积表面中的一个接合所述边缘提升锚具。
4.具有用来联接到提升装置的头部和从所述头部延伸的锚固部分的边缘提升锚具和根据权利要求1至3中的任一项所述的剪力杆的组合,所述剪力杆的所述中部可与所述锚具的上边缘接合。
5.根据权利要求4所述的组合,其中,所述锚具的所述上边缘具有可由所述剪力杆的所述中部接合的平面部分。
6.根据权利要求4所述的组合,其中,所述锚具的所述上边缘被成形用于定位所述剪力杆。
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2009903351A AU2009903351A0 (en) | 2009-07-17 | Concrete lifting anchors | |
PCT/AU2010/000830 WO2011006188A1 (en) | 2009-07-17 | 2010-06-30 | Concrete lifting anchors |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103003507A true CN103003507A (zh) | 2013-03-27 |
Family
ID=43448789
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010800678359A Pending CN103003507A (zh) | 2009-07-17 | 2010-06-30 | 混凝土提升锚具 |
Country Status (5)
Country | Link |
---|---|
US (1) | US20130091785A1 (zh) |
EP (1) | EP2588679B1 (zh) |
CN (1) | CN103003507A (zh) |
CA (1) | CA2803406A1 (zh) |
WO (1) | WO2011006188A1 (zh) |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2803410A1 (en) * | 2009-07-17 | 2011-01-20 | Casne Verige Pty Ltd | Concrete lifting anchors |
CN103025980A (zh) * | 2009-07-17 | 2013-04-03 | 卡斯内维里奇股份有限公司 | 混凝土提升锚具 |
AU2013203970B2 (en) * | 2012-04-26 | 2015-06-04 | Illinois Tool Works Inc. | Lifting anchors |
US10066406B2 (en) * | 2016-08-25 | 2018-09-04 | Midwest Concrete & Masonry Supply, Inc. | Erection anchor for precast insulated concrete wall panels |
US11421431B1 (en) * | 2019-02-21 | 2022-08-23 | ALP Supply, Inc. | Erection anchor with coil legs |
CN110043046A (zh) * | 2019-05-27 | 2019-07-23 | 沈阳建筑大学 | 一种预制构件专用预埋吊件及安装方法 |
USD1022259S1 (en) * | 2021-06-07 | 2024-04-09 | Illinois Tool Works Inc. | Anchor |
AU2021205063A1 (en) | 2021-07-14 | 2023-02-02 | Illinois Tool Works Inc. | Anchor |
USD1010160S1 (en) * | 2021-07-14 | 2024-01-02 | Illinois Tool Works Inc. | Anchor |
USD1009583S1 (en) * | 2022-06-06 | 2024-01-02 | ALP Supply, Inc. | Fish tail lift anchor for precast concrete |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2518398A1 (de) * | 1975-04-25 | 1976-11-04 | Juergen Goldberg | Einrichtung zum heben und transportieren von betonfertigteilen o.dgl. |
US5094047A (en) * | 1989-03-22 | 1992-03-10 | The Burke Company | Apparatus and method for lifting tilt-up wall constructions |
CN1299334A (zh) * | 1998-05-04 | 2001-06-13 | 伊恩·亚历山大·佩特森 | 关于混凝土板类预制体提升的改进 |
US20060248813A1 (en) * | 2005-04-07 | 2006-11-09 | Goeff Fletcher | Cast-in anchors |
CN200958032Y (zh) * | 2006-09-28 | 2007-10-10 | 马勇 | 多功能张拉拔管机 |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2920477A (en) * | 1956-06-11 | 1960-01-12 | Harry F Shaw | Plate masonry clamp |
FR2649738B1 (fr) * | 1989-07-17 | 1993-06-11 | Marcel Arteon | Ancre notamment pour panneau de beton |
US5402616A (en) * | 1992-12-28 | 1995-04-04 | Jw Peters & Sons, Inc. | Concrete weldment and method of manufacture |
US5899043A (en) * | 1995-12-18 | 1999-05-04 | Engineering Certifiers Ltd. | Ductile-failure anchors for concrete elements |
AU752353B2 (en) * | 1999-04-20 | 2002-09-19 | Hilbert Superannuation Management Pty Ltd | Lifting system |
IT1319375B1 (it) * | 2000-12-11 | 2003-10-10 | Sergio Zambelli | Inserto di sollevamento per manufatti cementizi prefabbricati constaffatura per incrementarne la resistenza a taglio |
US6769663B2 (en) * | 2001-06-25 | 2004-08-03 | Meadow Burke Products | Void forming and anchor positioning apparatus and method for concrete structures |
US8413400B2 (en) * | 2006-06-13 | 2013-04-09 | Woodstock Percussion Pty Ltd. | Recess former for concrete panels |
CN103025980A (zh) * | 2009-07-17 | 2013-04-03 | 卡斯内维里奇股份有限公司 | 混凝土提升锚具 |
-
2010
- 2010-06-30 CN CN2010800678359A patent/CN103003507A/zh active Pending
- 2010-06-30 WO PCT/AU2010/000830 patent/WO2011006188A1/en active Application Filing
- 2010-06-30 US US13/806,185 patent/US20130091785A1/en not_active Abandoned
- 2010-06-30 EP EP10799271.1A patent/EP2588679B1/en not_active Not-in-force
- 2010-06-30 CA CA2803406A patent/CA2803406A1/en not_active Abandoned
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2518398A1 (de) * | 1975-04-25 | 1976-11-04 | Juergen Goldberg | Einrichtung zum heben und transportieren von betonfertigteilen o.dgl. |
US5094047A (en) * | 1989-03-22 | 1992-03-10 | The Burke Company | Apparatus and method for lifting tilt-up wall constructions |
CN1299334A (zh) * | 1998-05-04 | 2001-06-13 | 伊恩·亚历山大·佩特森 | 关于混凝土板类预制体提升的改进 |
US20060248813A1 (en) * | 2005-04-07 | 2006-11-09 | Goeff Fletcher | Cast-in anchors |
CN200958032Y (zh) * | 2006-09-28 | 2007-10-10 | 马勇 | 多功能张拉拔管机 |
Also Published As
Publication number | Publication date |
---|---|
CA2803406A1 (en) | 2011-01-20 |
EP2588679A4 (en) | 2014-05-14 |
WO2011006188A1 (en) | 2011-01-20 |
EP2588679B1 (en) | 2015-08-12 |
EP2588679A1 (en) | 2013-05-08 |
US20130091785A1 (en) | 2013-04-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103003507A (zh) | 混凝土提升锚具 | |
US9217256B2 (en) | Concrete lifting anchors | |
CA2542032C (en) | Cast-in anchors | |
CN103038429A (zh) | 混凝土提升锚具 | |
CN103025980A (zh) | 混凝土提升锚具 | |
CN106320530A (zh) | 一种层间连接节点 | |
CN106121050A (zh) | 一种层间连接节点 | |
KR101590026B1 (ko) | 연결앵커가 형성된 프리캐스트 블록 및 그 시공방법 | |
AU2006201337A1 (en) | Cast-in anchors | |
AU2010273162B2 (en) | Concrete lifting anchors | |
AU2012261677B2 (en) | Concrete lifting anchors | |
AU2010273164B2 (en) | Concrete lifting anchors | |
KR200364617Y1 (ko) | 매입 말뚝 지지력 증대 기구 | |
CN106121051A (zh) | 一种层间连接节点 | |
CN205558036U (zh) | 一种带柱帽叠合宽扁梁结构 | |
CN107299719A (zh) | 一种带柱帽叠合宽扁梁结构 | |
AU2010273161A1 (en) | Concrete lifting anchors | |
AU2010273163A1 (en) | Concrete lifting anchors | |
AU2007209790A1 (en) | Frameless glazing panel system | |
CN106223473A (zh) | 一种预制钢筋混凝土构件连接方法 | |
CN106223485A (zh) | 一种预制混凝土构件连接方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C05 | Deemed withdrawal (patent law before 1993) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130327 |